U. S. Nuclear Regulatory Commission Serial No. 09-003
by user
Comments
Transcript
U. S. Nuclear Regulatory Commission Serial No. 09-003
VIRGINIA ELECTRIC AND POWER COMPANY RICHMOND, VIRGINIA 23261 February 27, U. S. Nuclear Regulatory Commission Attention: Document Control Desk One White Flint North 11555 Rockville Pike Rockville, MD 20852 2009 Serial No. NLOS/GDM Docket Nos. License Nos. 09-003 R1 50-338/339 NPF-4/7 VIRGINIA ELECTRIC AND POWER COMPANY NORTH ANNA POWER STATION UNITS 1 AND 2 UPDATED SUPPLEMENTAL RESPONSE TO NRC GENERIC LETTER 2004-02 POTENTIAL IMPACT OF DEBRIS BLOCKAGE ON EMERGENCY RECIRCULATION DURING DESIGN BASIS ACCIDENTS AT PRESSURIZED-WATER REACTORS By letter dated February 29, 2008 (ADAMS ML080650563), Virginia Electric and Power Company (Dominion) submitted supplemental detailed information concerning corrective actions taken in response to NRC Generic Letter (GL) 2004-02 for North Anna Power Station (North Anna) Units 1 and 2. That letter fully detailed the corrective actions that had been performed for GL 2004-02 at that time and specified the corrective actions that were ongoing including: 1) downstream effects evaluations for Emergency Core Cooling System (ECCS) and Recirculation Spray System (RSS) pump seal performance and component wear, and 2) chemical effects testing and evaluation. The required date for completion of the outstanding corrective actions for North Anna Units 1 and 2 was extended from the original due date of December 31, 2007 to November 30, 2008. [Reference NRC letter dated September 29, 2008 (ADAMS ML082730022).] Attachment 1 to this letter provides Dominion's updated supplemental response to GL 2004-02 for North Anna Units 1 and 2 and includes the necessary information to appropriately address the analyses performed and corrective actions taken that were not complete at the time of Dominion's previous supplemental response. These corrective actions were completed for North Anna Units 1 and 2 by the November 30, 2008 due date. Final resolution of potential chemical and downstream effects on the reactor core and flowpaths is pending the issuance of WCAP-16793-NP and the associated NRC Safety Evaluation Report (SER). Corrective actions will be identified, if required for resolution of this item, within 90 days of issuance of the NRC SER. The content and level of detail provided in Attachment 1 are consistent with the guidance included in NRC letter dated November 21, 2007 (ADAMS ML073110389) and March 28, 2008 (ADAMS ML080230112) to the Nuclear Energy Institute. vpi Serial No. 09-003 Docket Nos. 50-338/339 Page 2 of 3 Attachment 2 provides responses to the remaining open items from the North Anna Units 1 and 2 NRC GL 2004-02 Audit. Should you have any questions or require additional information, please contact Mr. Gary D. Miller at (804) 273-2771. Sincerely, ean Price President - Nuclear Engineering Commitment: 1. Corrective actions for resolution of potential chemical and downstream effects on the reactor core and flowpaths will be determined and reported to the NRC within 90 days following the issuance of revised WCAP-16793-NP and the associated NRC Safety Evaluation Report (SER). Attachments: 1. Updated Supplemental Response to Generic Letter 2004-02, North Anna Power Station Units 1 and 2 2. Response to Generic Letter 2004-02 Audit Open Items, North Anna Power Station Units 1 and 2 COMMONWEALTH OF VIRGINIA ) COUNTY OF HENRICO ) ) The foregoing document was acknowledged before me, in and for the County and Commonwealth aforesaid, today by Mr. J. Alan Price, who is Vice President - Nuclear Engineering, of Virginia Electric and Power Company. He has affirmed before me that he is duly authorized to execute and file the foregoing document in behalf of that company, and that the statements in the document are true to the best of his knowledge and belief. Acknowledged before me this 2iI My Commission Expires: CwmumuPWMu W fr1VASM ,2009. 4I'O) 1 Notary Public1 6m•( L MOM ¶GSW day of 1 Serial No. 09-003 Docket Nos. 50-338/339 Page 3 of 3 cc: U.S. Nuclear Regulatory Commission Region II Sam Nunn Atlanta Federal Center 61 Forsyth Street, SW Suite 23T85 Atlanta, Georgia 30303 NRC Senior Resident Inspector North Anna Power Station Mr. J. F. Stang, Jr. NRC Project Manager U. S. Nuclear Regulatory Commission One White Flint North Mail Stop 8G9A 11555 Rockville Pike Rockville, Maryland 20852 Ms. D. N. Wright NRC Project Manager U. S. Nuclear Regulatory Commission One White Flint North Mail Stop 8H4A 11555 Rockville Pike Rockville, Maryland 20852 Mr. J. E. Reasor, Jr. Old Dominion Electric Cooperative Innsbrook Corporate Center 4201 Dominion Blvd. Suite 300 Glen Allen, Virginia 23060 Serial No. 09-003 Docket Nos. 50-338 and 50-339 ATTACHMENT I UPDATED SUPPLEMENTAL RESPONSE TO GENERIC LETTER 2004-02 NORTH ANNA POWER STATION UNITS i AND 2 VIRGINIA ELECTRIC AND POWER COMPANY (DOMINION) Serial No. 09-003 Docket Nos. 50-338 and 50-339 Attachment 1 Page 1 of 42 UPDATED SUPPLEMENTAL RESPONSE TO GL 2004-02 NORTH ANNA POWER STATION UNITS I AND 2 1.0 Description of Approach for Overall Compliance This information supplements the Overall Compliance information included in the supplemental response to GL 2004-02 dated February29, 2008. By letter dated February 29, 2008, Serial No. 08-0019, Dominion provided a supplemental response to Generic Letter (GL) 2004-02, "Potential Impact of Debris Blockage on Emergency Recirculation during Design Basis Accidents at Pressurized-Water Reactors," for North Anna Power Station (North Anna) Units 1 and 2. This attachment updates the information that was previously provided. The balance of this attachment provides the following items: 1.a 1.b 2.0 3.f 3.g 3.j 3.m 3.n 3.o 3.p 1.a Conservatisms Summary General Description of and Schedule for Corrective Actions Head Loss and Vortexing Net Positive Suction Head (NPSH) Screen Modification Downstream Effects - Components and Systems Downstream Effects - Fuel and Vessel Chemical Effects Licensing Basis Conservatisms Detailed analyses of debris generation and transport ensure that a bounding quantity and a limiting mix of debris are assumed at the containment sump strainer following a design basis accident (DBA). Using the results of the analyses, conservative evaluations were performed to determine worst-case strainer head loss and downstream effects. Chemical effects bench-top tests conservatively assessed the solubilities and behaviors of precipitates and applicability of industry data on the dissolution and precipitation tests of station-specific conditions and materials. Reduced-scale testing was performed by Atomic Energy of Canada Limited (AECL) using two separate test facilities: Test Rig 33, a single-loop test rig and multi-loop Test Rig 89. The reduced-scale testing established the influence of chemical products on head loss across the strainer surfaces by simulating the plant-specific chemical environment present in the water of the containment sump after a Loss-of-Coolant-Accident (LOCA). These analyses included the conservatisms discussed in the balance of this section. Serial No. 09-003 Docket Nos. 50-338 and 50-339 Attachment 1 Page 2 of 42 1. Test evaluations demonstrate that a fully formed thin-bed of debris takes significant time (hours) to form and that formation of a thin-bed is dependent upon disturbing settled debris throughout the test tank. Consequently, a worst-case thin-bed of debris would be difficult to form and would not be expected to form until several hours after sump recirculation is initiated. Significant debris settling and sump water subcooling occurs during the formation of a debris-bed so additional net positive suction head (NPSH) margin is present for chemical effects head loss. However, as a conservative measure, chemical effects testing began with an established debris thin-bed on the strainer fin and was conducted for the 30-day mission time. 2. The debris load in head loss testing was taken from the debris transport calculation, which conservatively credits no particulate settling. 3. Debris introduction procedures in chemical effects testing ensured minimum near-field settling and resulted in conservatively high debris bed head losses. 4. Debris introduction was accomplished in a carefully controlled manner to result in the highest possible head loss. Particulate was introduced initially, which was followed by discrete fiber additions after the particulate debris had fully circulated. 5. Only fines of fibrous debris were used in head loss testing as if all the fibrous debris erosion, which is expected to take a considerable amount of time, occurred at recirculation start. 6. Debris bed formation during testing included agitating (or "stirring") the settled debris to ensure maximum debris on the strainer. However, any turbulence in post-LOCA containment sump water is expected to be localized to limited areas of the strainers. Consequently, much of the sump water will be quiescent, which would promote debris settling. 7. Particulate settling in head loss testing was conservatively minimized through use of a lower density walnut shell particulate as a surrogate for the higher density epoxy coating particulate that may be present in postLOCA sump water. 8. Downstream wear analysis used the Large Break LOCA particulate load to determine abrasive and erosive wear. This is a conservative particulate loading, in view of the following: • Much of the particulate included in analysis is unqualified coating that is outside the break zone of influence (ZOI). This unqualified coating Serial No. 09-003 Docket Nos. 50-338 and 50-339 Attachment 1 Page 3 of 42 is assumed to dislodge due to exposure to the containment environment. However, such dislodgement is likely only after many hours, if at all. The low velocity of the sump water column and the significant number of surfaces throughout containment promote significant settling of particulate in containment. Settled coating will not be drawn through the sump strainer since the Recirculation Spray (RS) strainer is located approximately six inches, and the Low Head Safety Injection (LHSI) strainer is approximately 19 inches, above the containment floor. " The analysis assumes 100% strainer bypass of particulate conservatively maximizing the effects of downstream wear. 9. Chemical effects testing results were conservative based upon several conditions: * Aluminum corrosion amounts were calculated at high pH, where aluminum corrosion and release rates are high. Testing was performed at neutral pH, where aluminum solubility is low to encourage aluminum compound precipitation. Sump water pH is expected to be approximately 8 in the long-term. * The minimum sump water volume at specified times post-LOCA were used to maximize the calculated sump aluminum concentrations. " The analysis of aluminum load conservatively does not account for the possible inhibitory effect of silicate or other species on aluminum corrosion. * The rate of corrosion is maximized by analysis that does not assume development of passive films, i.e., no aluminum oxides remain adhered to aluminum surfaces. The formation of passive films could be credited to decrease the corrosion and release rates at long exposure times. Consequently, it is conservative to assume that all aluminum released by corrosion enters the solution. " All aluminum released into the solution is conservatively assumed to transport to the debris-bed instead of plating out on the multiple surfaces throughout containment. During bench-top testing, aluminum plated out on glass beakers and, during reduced-scale testing, aluminum plated out on fiber. It is reasonable to expect that a portion of the aluminum ions released into solution will plate out on Serial No. 09-003 Docket Nos. 50-338 and 50-339 Attachment 1 Page 4 of 42 some of the multiple surfaces in containment prior to arriving at the debris-bed on the strainer. Chemical effects test evaluations conservatively neglect the effect of the presence of oxygen in the sump water. The corrosion rate of aluminum in aerated pH 10 alkaline water can be a factor of two lower than that measured in nitrogen-deaerated water. This data is in NUREG/CR-6873, "Corrosion Rate Measurements and Chemical Speciation of Corrosion Products Using Thermodynamic Modeling of Debris Components to Support GSI-191." 10. NPSH margins were determined with the following conservatisms: No credit was taken for additional NPSH margin in the short-term due to subcooling of the sump water combined with the several hours required to form the limiting thin-bed of debris. Our analyses conservatively assume transport to the strainer following the break occurs much sooner. 0 There is conservatism in scaling from test temperatures to higher specified sump temperatures. The debris bed will expand slightly when head loss is lower, i.e., at the higher sump temperature, the bed would be expected to be slightly more porous than at the lower test temperature. The assumption of a purely linear relationship between head loss and viscosity when scaling to higher temperatures is, therefore, conservative. 0 The NPSH calculations were guided by the observation that the minimum margin would likely occur for the combination of parameters that would minimize the containment pressure and maximize the sump water temperature (and, hence the vapor pressure of this fluid), thereby conservatively minimizing the contribution of containment accident pressure to the calculated NPSH margin. 1.b Summary The corrective actions associated with GL 2004-02 to resolve NRC Generic Safety Issue (GSI) 191, "Assessment of DebrisAccumulation on PWR Sump Performance,"have been completed for North Anna Units 1 and 2. Downstream effects analyses (components) have been completed consistent with WCAP-1 6406-P, Rev. 1, "Evaluation of Downstream Sump Debris Effects in Support of GSI [Generic Safety Issue]-1 91," to identify any wear, blockage or vibration concerns with components and systems due to debris-laden fluids. Significant conservatisms are inherent in these Serial No. 09-003 Docket Nos. 50-338 and 50-339 Attachment 1 Page 5 of 42 analyses, which provide reasonable assurance that downstream component clogging will not occur, and downstream component wear will not significantly affect component or system performance. The results of these analyses are detailed in Section 3.m below. Downstream effects analyses for the fuel and vessel -were previously performed consistent with the methodology of WCAP-16793-NP, Rev. 0, "Evaluation of Long-Term Cooling Considering Particulate, Fibrous and Chemical Debris in the Recirculating Fluid," May 2007. However, since that time, in response to concerns raised by the Advisory Committee on Reactor Safeguards regarding WCAP-16793-NP, Rev. 0, the Pressurized Water Reactor Owners' Group (PWROG) is performing additional testing and analyses to more realistically determine the potential downstream and chemical effects on the reactor core and the vessel/components. Corrective actions will be identified, if required for resolution of this item, and submitted to the NRC within 90 days following the issuance of the revised WCAP16793-NP and the associated NRC Safety Evaluation Report (SER). Chemical effects testing and analyses have been completed for the LHSI and RS strainers. AECL has performed various hydraulic tests that simulated the actual debris loading and chemical conditions specific to North Anna Units 1 and 2 based on debris generation, debris transport, and chemical effects evaluationsi. Fibrous and particulate debris and chemicals were added to a test rig to simulate the plant-specific chemical environment present in the water of the containment sump following a DBA. Each test was operated for more than 30 days after the formation of the debris bed and initial chemical addition at specified temperatures and flow rates to assess chemical precipitate formation and head loss change. These tests verified that adequate NPSH is available to support the operation of the LHSI and RS pumps during the post-LOCA recirculation mode. The description of the analysis methodology, as well as the analysis and testing results, are provided in Section 3.o below. The completion of the evaluation of downstream effects on systems and components and chemical effects testing resulted in changes-to information submitted in Dominion's previous supplemental response dated February 29, 2008. Therefore, updated information is provided in Sections 3.f, 3.g, and 3.j below. Based on the methodology, modifications, and conservatisms described herein, as well as the detailed information provided in Dominion's previous supplemental response dated February 29, 2008, there is reasonable assurance that long-term core cooling will successfully remove decay heat for at least 30 days following a DBA. Serial No. 09-003 Docket Nos. 50-338 and 50-339 Attachment 1 Page 6 of 42 2.0 Description of and Schedule for Corrective Actions This information supplements the Descriptionof and Schedule for Corrective Actions information included in the supplemental response to GL 2004-02 dated February29, 2008. By letter dated February 29, 2008, Dominion indicated that the following actions were on-going, and that an update would be provided: 1. Chemical and downstream effects testing evaluation. 2. Chemical effects bench-top testing. 3. Chemical effects reduced-scale testing. 4. Downstream wear evaluation for components. 5. Downstream wear evaluation for fuel and vessel. Previously approved extension requests for North Anna Units 1 and 2 permitted the completion of these actions by November 30, 2008. Component downstream effects analyses have been completed using the methodology described in WCAP-16406-P, Rev. 1, and those analyses and relevant results are discussed in Section 3.m below. Information previously provided on downstream effects for components and systems in the supplemental response letter dated February 29, 2008 remains valid. In-vessel downstream effects have been evaluated using WCAP-16406-P, Rev. 1, and WCAP-16793-NP, Rev. 0, with acceptable results as described in Section 3.n below. The NRC SER for WCAP-1 6793-NP has not been issued and may contain staff conditions and limitations to be addressed. Dominion will review the results of the staff SER when issued to determine if additional analyses and corrective actions are required. If necessary, Dominion will submit its plan to address any changes to the analysis of the in-vessel downstream effects issue within 90 days of issuance of the final NRC staff SER on WCAP-16793. Chemical effects testing and analyses have also been completed. The testing and analyses were completed using a methodology and testing protocol developed with AECL at their Chalk River facility and observed, in part, by the NRC staff. The description of the analysis methodology, as well as the testing and analysis results, is discussed in Section 3.o below. Information previously Serial No. 09-003 Docket Nos. 50-338 and 50-339 Attachment 1 Page 7 of 42 provided on chemical effects in the supplemental response letter dated February 29, 2008 remains valid. 3.0 Additional Information for Head Loss and Vortexing (3.f), Net Positive Suction Head (NPSH) (3.g), Screen Modification (3.j), Downstream Effects Components and Systems (3.m), Downstream Effects - Fuel and Vessel (3.n), Chemical Effects (3.o), and Licensing Basis (3.p) - The Dominion supplemental response to GL 2004-02 dated February 29, 2008 indicated in the response to RAIs 2, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, and 31 from NRC letter dated February 9, 2006 (ADAMS ML060370463) that additional information related to these requests would be provided when the downstream effects and chemical effects evaluations were complete. Sections 3.m and 3.o below provide additional information relevant to these RAIs. 3.f Head Loss and Vortexing This information supplements the Head Loss and Vortexing information included in the supplementalresponse to GL 2004-02 dated February29, 2008. The Dominion GL 2004-02 supplemental response dated February 29, 2008 provided containment sump strainer head loss information based on testing without chemical effects. Chemical effects testing has been completed (see Section 3.o) and revised allowable head loss values were determined for input to the final strainer hydraulic analyses. The hydraulic analyses are performed to identify NPSH margins for pumps taking suction from the containment sump (Section 3.g) and to evaluate the effect of any predicted sump fluid flashing or dissolved air released from solution in the strainer or at the pump suctions. Containment sump strainer head loss is evaluated for two distinct time periods short-term and long-term. The short-term is defined as the time period from event initiation to the point at which stable containment pressure, sump temperature, and sump water level are achieved, which occurs within 6 hours. During this initial period of the accident response, chemical effects are not required to be considered in the determination of strainer head loss since chemical debris would not have begun to influence the debris bed head loss for several hours or days. The long-term considers containment conditions from 6 hours to 30 days and conservatively includes the maximum effect of aluminum precipitation in the debris bed for the entire period. The RS strainer flowrate for the short-term is defined by the operation of all four RS pumps. Post-LOCA containment conditions stabilize below atmospheric pressure within 6 hours and emergency operating procedures direct operators to stop two of the four RS pumps. Therefore, for the long-term period, the RS strainer flowrate is defined by the limiting set of two RS pumps in operation. Serial No. 09-003 Docket Nos. 50-338 and 50-339 Attachment 1 Page 8 of 42 Containment sump conditions and required pump flowrates were considered for each time period, and the limiting condition for strainer head loss requirements was determined for use in this evaluation. Final design and testing criteria for the containment sump strainers are provided in Table 3.f-1. Table 3.f-1: Final Design and Testing Acceptance Criteria for Sump Strainers Total Strainer Allowable Water Level Head Loss (ft Flow Rate Temperature (ft.) above H20) (gpm) (OF) floor Recirculation Spray RS Short Terma 5.0 12,620 180 1.8 RS Long Terma 8.0 7500 104 6.7 Low Head Safety Injection LHSI RMT Initiation 1.0 4050 113 5.0 (No Debris) LHSI Short Terma (after 2 Sump 5.0Q 4050 113 5.0 Turnovers) LHSI Long Terma 8.5 4050 104 6.7 a. Short Term is defined as the time period from event initiation to the point at which stable containment pressure, sump temperature, and sump water level are achieved (less than 6 hours). Long Term considers containment conditions from 6 hours to 30 days and includes the maximum effect of aluminum precipitation in the debris bed. Strainer Flashing The potential for sump liquid flashing into vapor in the strainer system was reevaluated. The methods of analysis were the same as described in the Dominion GL 2004-02 supplemental response dated February 29, 2008. The analysis revealed that the onset of flashing is predicted for the North Anna Unit 2 RS strainer (the worst-case RS strainer) when the debris bed on the fins reached a pressure loss of 1.56 ft H2 0 or about 50% of the allowable debris pressure loss of 3.11 ft H 2 0 at the bulk water temperature used in the flashing analysis. If the pressure loss of the debris bed increases above this level, then flashing is predicted in the strainer internal piping. The condition for which the possibility of flashing was evaluated is a worst-case low margin scenario occurring approximately 5 - 10 minutes after the RS system is put in service. At this time a debris bed is'only just beginning to form on the strainer fins. Testing performed by AECL has shown that several hours to days Serial No. 09-003 Docket Nos. 50-338 and 50-339 Attachment 1 Page 9 of 42 are required for the full debris bed to form and to reach the point where maximum debris pressure loss occurs. At the time the transient low margin condition occurs, the pressure loss due to debris will be well below 50% of the full debris pressure loss, and flashing will not occur within the strainer system. The flashing analysis for the LHSI strainer concluded that there is significant margin to flashing considering the maximum allowable strainer head loss. Therefore, there is no concern for flashing in the LHSI strainer. Air Inqestion The potential for air ingestion was re-evaluated considering the results of chemical effects testing. (There is no change to the vortexing evaluation results provided with the Dominion GL 2004-02 supplemental response dated February 29, 2008.)'The analytical evaluation-for the allowable head loss limit shows a small amount of voiding within the strainer system, and no voiding at the inlets to the pumps, for the RS system. The LHSI strainer evaluation shows less than 1% voiding in the strainer system, and a potential for up to 0.27% voiding at the pump inlet for the short-term case and up to 0.47% voiding at the pump inlet for the long-term case. Since there is no void formation at the RS pump inlet due to air ingestion, no adjustment to required NPSH is necessary. Adjustment for voiding was made for the LHSI pump in accordance with NRC Regulatory Guide (RG) 1.82, Rev. 3, Appendix A methodology for void fraction less than 2%. Consequently, the factor P3 1 + 0.5 * (void fraction) from RG 1.82 was'applied to the required NPSH for the LHSI pumps (see Table 3.g-1). This small void fraction would have insignificant impact on LHSI pump total developed head and therefore, the delivered flowrate. Hydraulic Analysis Results The total allowable strainer head loss compared to the test results from chemical effects head loss testing (described in Section 3.o) is provided in Table 3.f-2. To encompass the effects of dissolved chemicals on the viscosity of sump water, the calculations for strainer debris bed head-loss and internal head-loss include a 12% increase in water viscosity over that of clean water. This value is supported by the chemical effects testing performed by AECL and the data from NUREG/CR-6914, Vol. 1. Serial No. 09-003 Docket Nos. 50-338 and 50-339 Attachment 1 Page 10 of 42 Table 3.f-2: Hydraulic Analysis Results Total Strainer Strainer Allowable Internal Head Loss, HUt Head Loss, Debris Bed Head Loss, HLt > HLs + HLd HLS (ft H20) HLd (ft H 2 0)a ? 1.50 1.00 0.71 6.28 YES YES 0.97 -- YES 0.93 1.72 YES 0.93 7.44 YES (ft H20) Recirculation Spray Strainer RS Short Term 5.0 RS Long Term 8.0 Low Head Safety Injection Strainer LHSI RMT Initiation. 1.0 (No Debris) LHSI Short Term (after 2 Sump 5.0 Turnovers) LHSI Long Term 8.5 a. These debris bed head loss results in ft H20 are equivalent to the debris bed head loss results reported in Section 3.o in psi. The debris head loss includes the fin loss. 3.g Net Positive Suction Head (NPSH) This information supplements the Net Positive Suction Head (NPSH) information included in the supplemental response to GL 2004-02 dated February29, 2008. The Dominion GL 2004-02 supplemental response dated February 29, 2008 provided NPSH information based on containment sump strainer testing without chemical effects. Chemical effects testing has been completed (see Section 3.o) and hydraulic analyses have been performed incorporating the results of chemical effects testing. Revised NPSH margins were determined for the RS and LHSI pumps drawing from the containment sump following a LOCA. NPSH margins were determined at the time after a LOCA corresponding to lowest available NPSH for the shortterm and long-term cases. The NPSH margin was determined by subtracting the total strainer allowable head loss and the required NPSH (NPSHr) from the available NPSH (NPSHa), which was determined from the worst-case North Anna GOTHIC containment analysis result and does not include the strainer head loss. The total strainer allowable head loss establishes the design requirement for the sump strainer. In most cases, containment analysis results provided an NPSHa' value at a containment sump temperature that was greater than the head loss test temperature. Conservatively, the allowable strainer head loss was specified at test temperature without temperature correction, which provides an additional unquantified margin in the head loss results. Serial No. 09-003 Docket Nos. 50-338 and 50-339 Attachment 1 Page 11 of 42 North Anna UFSAR Figures 6.2-66, 6.2-70, and 6.3-7 illustrate the trend of available NPSH (without strainer losses) over time after an accident for the Inside RS (IRS), Outside RS (ORS), and LHSI pumps, respectively. As stated in Section 3.f, there is no void fraction at the RS pump inlets; therefore, there is no adjustment required to the NPSHr for the RS pumps. A void fraction of 0.27% short-term and 0.47% long-term is predicted at the LHSI pump inlets, and the NPSHr was adjusted by the factor P3 from RG 1.82, Appendix A for less than 2% void fraction. NPSH margin calculation results based on maximum allowable strainer head loss are provided in Table 3.g-1. Note that information in this table supersedes the information in Table 3g-1 included in the February 29, 2008 supplemental response. The total allowable strainer head loss was compared to the test results from chemical effects head loss testing (described in Section 3.o) in Table 3.f-2. All sump strainer test results satisfactorily met the allowable head loss criteria. The difference between the test results and the allowable head loss is not included in the Minimum Margin values identified in Table 3.g-1 ,as an additional conservatism. Serial No. 09-003 Docket Nos. 50-338 and 50-339 Attachment 1 Page 12 of 42 Table 3.g-1: Summary of RS and LHSI Pum Margins Pump Total Strainer NPSHr (ft H20) Allowable Head at Maximum Minimum Margin Min. NPSHa (ft Loss, HL (ft H2 0)a H20)b Flowrate (gpm) (ft H20) = NPSHa - HL - NPSHr 18.1 @ 193.2-F 5.0 @ 1800Fd 11.3 @ 3750 1.8 27.1 @ 104°F 8.0 @ 104°F 11.3 @ 3750 7.8 14.6 @ 204.3°F 5.0 @ 180°Fd 9.6 @ 3400 0.09 15.3 @ 198.4 0F 5.0 @ 180°Fd 9.6 @ 3400 0.7 28.0 @ 151.1°F 8.0 @ 104°Fd 9.6 @ 3400 10.4 14.7 @168 0 F 1.0 at 113oFd 13.4 @ 4050 0.3 22.4 @ 139.8°F 5.0 @ 113°Fd 15.21' @ 4050 2.19 26.6 @ 1040 F 8.5 @ 1040 F 16.55'@ 4050 1.55 ORSc - Short Terme ORS Long Terme IRSc Short Terme,f IRS Short Term ,h IRS Long Terme LHSI RMT LHSI - Short Terme LHSI - Long Terme a. This value is from the North Anna GOTHIC containment analysis and does not include strainer head loss. b. This value includes the debris bed and strainer internals head loss at the strainer flowrates identified in Table 3.f-1. c. ORS - Outside Recirculation Spray, IRS - Inside Recirculation Spray d. Conservatively, no temperature correction has been made from NPSHa specified temperature. e. Short Term is defined as the time period from event initiation to the point at which stable containment pressure, sump temperature, and sump water level are achieved (less than 6 hours). Long Term considers containment conditions from 6 hours to 30 days and includes the maximum effect of aluminum precipitation in the debris bed. f. Two RS pumps in operation. g. Although there is no margin available when compared to the specification for total strainer head loss (5.0 ft H2 0), there is margin available to the test result of 2.21 ft H2 0 at 180OF - see Table 3Jf-2. h. Four RS pumps in operation. i. NPSHr is adjusted by P = 1 + 0.5 * (void fraction), i.e., NPSHr = 13.4 * 13.See Section 3.f for discussion of void fractions predicted. Serial No. 09-003 Docket Nos. 50-338 and 50-339 Attachment 1 Page 13 of 42 3.j Screen Modification This information supplements the Screen Modification information included in the supplemental response to GL 2004-02 dated February29, 2008. Although the maximum opening size in the North Anna Units 1 and 2 sump strainer fins is a 0.0625 inch diameter hole, the possibility exists for larger 'gaps' in the strainer assembly due to fit-up inconsistencies. The potential for gaps up to 0.125 inch wide for a total of 1% of strainer total flow area, and a limited number of 0.1875 inch wide and 1 inch long gaps, was evaluated for its affect on the downstream effects analysis described in Section 3.m. Five areas of the downstream effects analysis that could be affected by increased debris resulting from increased gap size were evaluated: (1) bypass fraction and debris size, (2) downstream component wear, (3) downstream component blockage, (4) fuels blockage, and (5) strainer hydraulics. The evaluation concluded that the presence of 0.125 inch wide gaps for 1% of strainer flow area, and 0.1875 inch wide by 1 inch long gaps limited to four on the LHSI strainer and eight on the RS strainer, would have no significant effect on the results of the downstream effects analyses for systems and components or the fuel and vessel. 3.m Downstream Effects - Components and Systems This information supplements the Downstream Effects - Components and Systems information included in the supplemental response to GL 2004-02 dated February29, 2008. The methodology used for downstream effects analysis was consistent with WCAP-16406-P, Rev. 1, and the limitations and conditions described in the accompanying NRC SER dated December 20, 2007 (ADAMS ML073520295). No design or operational changes were required as a result of the downstream effects evaluations. This update of the downstream effects analysis addresses: * Wear of the High Head Safety Injection (HHSI) pumps (Charging pumps), ORS pumps, IRS pumps, LHSI pumps, manually throttled valves, motor operated valves, orifices, flow venturis, recirculation spray nozzles, and heat exchangers, and an analysis of the wear effects on the performance of these components, Serial No. 09-003 Docket Nos. 50-338 and 50-339 Attachment 1 Page 14 of 42 * Pressure relief which could potentially open and piston check valves which will open during recirculation to determine if there is a possibility that the valves will not reseat properly due to debris in the fluid potentially resulting in an undesirable flow path for the recirculation fluid, and * Blockage of downstream components, including instrumentation, due to the presence of debris. Debris from the LOCA may pass through the containment sump LHSI and RS strainers and enter the Emergency Core Cooling System (ECCS) and RS System (RSS) causing abrasion and/or erosion on the surfaces of components. Wear models were developed in accordance with the methodology provided in WCAP-16406-P, Rev. 1, to assess the amount of wear in ECCS and RSS components based on the initial debris concentration in the pumped fluid, the debris concentration depletion due to settling and depletion, the hardness of the, wear surfaces, and the mission time. The results for all downstream components were determined to be acceptable per the criteria set forth in WCAP-16406-P, Rev. 1.1 Wear Models * Abrasive Wear Models Two abrasive wear models have been considered: the "free flow" type and the "packing (or Archard's)" type. Free flow wear is the removal of material due to hard or sharp particles that flow with the fluid between two closeproximity surfaces in relative motion to each other. In the Archard's model, particles carried by the fluid adhere to the stationary surface by forming a packing that wears the moving surface. These types of wear affect, in particular, pump components such as wear rings, impeller hubs, bushings, and diffuser rings. The wear rate of Archard's model is constant and does not depend on the debris concentration and its depletion over time. Once packing is established in the close running clearances, debris depletion in the bulk fluid does not affect the rate of wear. For the free flowing abrasive wear model, the rate of wear is a direct result of the debris concentration in the fluid at any time during the pump (or other component) duty cycle. Archard's wear is single sided since only the moving surface is worn out, whereas the free flow model wears both the rotating and the stationary surface individually and independently. * Erosive Model Erosive wear is caused by particles impinging on a component surface or edge and removing material from that surface due to momentum effects. This Serial No. 09-003 Docket Nos. 50-338 and 50-339 Attachment 1 Page 15 of 42 type of wear can occur in components with high velocity flows such as throttling valves, orifices, heat exchanger tubes, and pump components. The wear rate model includes the capability to calculate the initial debris concentration, the debris concentration as a function of time, and the rate of debris settlement. In addition to being captured by the sump strainer, debris heavier than the recirculation fluid tends to settle out in the low velocity regions, such as the reactor lower plenum. Therefore, the concentration of debris in the recirculation flow will diminish with time. The time-dependent concentrations of particulate and fibrous debris were used as inputs to complete the evaluation of the effects of debris ingestion on ECCS and RSS pumps, safety-related valves, heat exchangers, orifices, recirculation spray nozzles, piping, and instrumentation tubing. Pumps The evaluation of pump hydraulic performance and mechanical dynamic performance was based on design performance characteristics as a starting point. This approach is supported by a review of approximately ten years of inservice testing data that concludes that there has been no statistically significant degradation of the performance of the HHSI, LHSI, IRS, and ORS pumps over this time period. Hydraulic Performance Abrasive and erosive wear of pump internal subcomponents resulting from pumping debris-laden water can cause an increase in the flow clearances of the pump, which can result in increases in internal leakages and an overall decrease in pump performance. ECCS and RSS pump wear was conservatively calculated and the "worn" condition pump hydraulic performance was evaluated for its effect on system minimum performance requirements. This overall system performance evaluation also included a review of cumulative system resistance changes due to wear in system piping and components to determine the impact on system maximum flow to assess pump runout potential. The review of component wear concluded that all system components pass the WCAP-1 6406P, Rev. 1, criteria. In addition, the system performance evaluation concluded that there is no significant effect on system resistance or flowrates. The overall system performance evaluation concluded that the ECCS and RSS pumps meet their hydraulic performance requirements at the end of the 30 day mission time. Serial No. 09-003 Docket Nos. 50-338 and 50-339 Attachment 1 Page 16 of 42 * Mechanical Seal Wear/Performance The impact of abrasive debris on the performance of pump mechanical shaft seals has been evaluated for the LHSI, HHSI, and ORS pumps (IRS pumps do not utilize a mechanical seal). The conclusion of the evaluation is that the debrisladen recirculation fluid would not adversely impact the performance of the mechanical seals. For the LHSI and ORS pumps with a tandem seal design, the inboard seal is cooled by pump discharge water. The evaluation conservatively assumed that the inboard seal failed due to wear from the debris-laden pumpage, and shaft sealing was accomplished solely by the outboard seal. The evaluation concluded that, since there is no significant convection of fluid to bring debris into the outer seal and diffusion of debris is not credible due to the small clearances between the stationary and pumping rings of the seal, the LHSI and ORS pumps outboard seals would continue to function as required for the duration of the mission time. The HHSI pump shafts are sealed with single stage mechanical seals at each end of the pump. The seals are cooled by pumped fluid. Following a LOCA, the HHSI pumps initially take suction from the Refueling Water Storage Tank (RWST) containing cooled, demineralized borated water such that the seal water is initially clean at the start of the mission time. The potential for debris-laden recirculation fluid to reach the seal cavity was evaluated to determine if seal cooling could be degraded, seal faces could be worn excessively, or the seal internal mechanism could be fouled preventing proper operation. The evaluation concluded that the HHSI pump seals would be adequately cooled and seal faces would not wear significantly from particulate debris during the mission time. In addition, the amount of debris entering the seal chamber would be insignificant such that the function of the seal internal mechanism would not be affected. The seal analysis determined that no additional leakage is anticipated as a result of debris-laden pumped fluid. Therefore, the HHSI pump seals meet performance criteria and would continue to function as required for the duration of the mission time. * Mechanical Dynamic Performance The increased flow clearances resulting from the abrasive and erosive wear of pump components were evaluated to determine if ECCS and RSS pumps would operate satisfactorily, without excessive vibrations, to provide the required flow to cool the core and depressurize the containment for the required mission time post-LOCA. Serial No. 09-003 Docket Nos. 50-338 and 50-339 Attachment 1 Page 17 of 42 The LHSI, HHSI, IRS, and ORS pumps were found to satisfy the WCAP-1 6406P, Rev. 1, dynamic performance requirements criteria for the required 30 day mission time. However, the increased flow clearances due to wear calculated for the HHSI pumps resulted in the potential for overpressurization of the pump outboard mechanical seal. A detailed plant-specific analysis was performed by the pump manufacturer to assess the wear of these pumps due to debris-laden pumped fluid. The pump vendor evaluation of HHSI pump internal wear was based on the WCAP-16406-P, Rev. 1, methodology along with a detailed analysis of North Anna-specific debris constituents. Specifically, since the testing referenced in WCAP-16406-P, Rev. 1, that resulted in packing-type abrasive wear was performed with coatings particulate debris, detailed debris characterization for the North Anna debris-laden recirculation fluid were determined. The North Anna debris mix consists of 70 ppm particulate, of which less than 10 ppm is coatings debris. The pump vendor evaluation concluded that, since the WCAP-16406-P, Rev. 1, tests resulted in packing formation observed at 920 ppm but not at 92 ppm coatings debris concentration, there is no concern for formation of packing in the North Anna HHSI pump running clearances based on the low concentration of particulate. Therefore, there would be no packing-type abrasive wear over the HHSI pumps mission time. Free-flow abrasive wear and erosive wear were determined to cause wear at close clearance HHSI pump internals locations. The most critical diametral clearance enlargement determined from the vendor analysis for a 30-day mission time is 0.83 mils at the balance drum and is bounding for the other close clearances within the pump. This calculated wear is within design tolerances for the pump and will not affect pump mechanical dynamic performance or the outboard mechanical seal pressure. Heat Exchangers Tube leakage or failure could occur due to excessive wall thinning as a result of wear in heat exchangers. The heat exchangers in the recirculation flowpath have been evaluated for wear effects dueto debris-laden fluid flow. The evaluation concluded that the actual wall thickness of the heat exchangers tubes minus the tube wall thickness lost due to erosion during a 30-day period is greater than~the minimum wall thickness required to withstand both the internal tube design pressure and the external shell design pressure. Therefore, the heat exchanger tubes have sufficient wall thickness to withstand the erosive effect of the debrisladen water for a period of 30 days post-LOCA. Serial No. 09-003 Docket Nos. 50-338 and 50-339 Attachment 1 Page 18 of 42 In addition, tube blockage will not occur since the internal tube diameter is greater than the maximum debris size and the flow velocity is greater than the settling velocity. Other Components Manually throttled valves, motor operated valves, flow venturis, orifices, and RS nozzles in the recirculation flow path were evaluated for the effects of wear due ,to the debris-laden fluid flow. These components were evaluated individually and, with the exception of the plate orifices in the Safety Injection System flowpath, were found to meet the criteria set forth in WCAP-16406-P, Rev. 1. A system evaluation was also performed to determine the cumulative effect of wear on system flowrates and the hydraulic performance requirements were determined to be met. The wear of the plate orifices in the Safety Injection System flowpath was included in the evaluation of system flow effects and found to have an insignificant effect. Relief valves in the recirculation flowpath have been evaluated for the ability to reseat in the event of opening considering the debris-laden fluid. None of these relief valves have the potential to lift during the recirculation phase; therefore, the potential for debris blockage in the open position does not exist. Piston check valves were evaluated for the potential to malfunction due to debris, and it was determined that failure of the piston check valves to close would have no effect on system functions required for the recirculation phase. Instrumentation Instrumentation, except for the Reactor Vessel Level Instrumentation System (RVLIS), in the recirculation flow path that is required to function after a LOCA is mounted either horizontally or vertically on top of the recirculation flowpath piping, or the associated instrument sensing lines are oriented horizontally or vertically (from above) at the pipe taps. The orientation of the instrument in the pipe will allow the debris to continue flowing beyond the instrumentation. The RVLIS measures reactor vessel water level with a differential pressure transmitter connected through instrument tubing to the top and bottom of the reactor vessel. There is no flow through the RVLIS tubing so debris would not be drawn into the RVLIS connections. Additionally, no debris is expected to accumulate in the reactor vessel upper head near the RVLIS connection. The flows in the reactor vessel lower plenum during recirculation would be minimal, so debris is expected to collect around the instrument nozzle penetrations, one of which is used for the RVLIS connection. However, since the instrument nozzle extends above the inside surface of the reactor vessel lower head, and there is no flow through the RVLIS sensing tubing, debris would not collect near the Serial No. 09-003 Docket Nos. 50-338 and 50-339 Attachment 1 Page 19 of 42 tubing open end in sufficient quantity to prevent the RVLIS from sensing lower head pressure produced by vessel water level changes. The debris collecting in the lower plenum would not affect RVLIS water level measurements. Therefore, instrumentation will not be adversely affected by debris in the recirculation flowpath. 3.n Downstream Effects - Fuel and Vessel This information supplements the Downstream Effects - Fuel and Vessel informationincluded in the supplemental response to GL 2004-02 dated. February29, 2008. Dominion completed a LOCA Deposition Analysis Model (LOCADM) to quantify the maximum expected deposition of chemical precipitates on the North Anna Unit 1 and 2 fuel and the resultant maximum clad temperature. The results show that the maximum clad temperature is approximately 375 0 F at the start of recirculation. The maximum temperature is well below the acceptance criterion limit of 800 0 F. The scale buildup starts at recirculation and reaches a maximum of 967 microns (38 mils) at the end of 30 days. This value takes into account the potential for strainer bypass and includes a factor of 2 times the expected aluminum release and is well below the acceptance criterion of 1270 microns (50 mils). The results are essentially the same as shown in Figure 5-3 of WCAP16793-NP, Rev. 0. Thus, the conclusions of the WCAP for the fuel and vessel analysis are applicable to North Anna Units 1 and 2 and demonstrate acceptable long-term core cooling in the presence of core deposits. Although this analysis to date has incorporated conditions and limitations imposed on use of WCAP-16793-NP, Rev. 0, the initial NRC comments provided for this technical report have been withdrawn and the WCAP is currently in revision. The source of the revision is understood to be related to the fuel blockage analysis, not the fuel deposit methodology. Upon issuance of revised guidance, and the anticipated Regulatory Issue Summary to inform the industry of the NRC staff's expectations and plans regarding resolution of this remaining aspect of GSI-191, Dominion assumes that the existing analysis for North Anna Units 1 and 2 will remain bounding of plant conditions and limitations on LOCADM use in a final SER for WCAP-16793-NP. This assumption will be confirmed through review of the revised WCAP-16793-NP and associated final NRC SER. The results of this review will be reported within 90 days following issuance of the final documents. 3.o Chemical Effects This information supplements the Chemical Effects information included in the supplementalresponse to GL 2004-02 dated Febroary29, 2008. Serial No. 09-003 Docket Nos. 50-338 and 50-339 Attachment 1 Page 20 of 42 Overview Dominion contracted AECL to perform chemical effects head loss testing and, evaluation for North Anna Units 1 and 2. The methodology for chemical effects testing and evaluation used observations of the Integrated Chemical Effects Tests (ICET), the Westinghouse Owners Group document WCAP-16530-NP, Rev. 0, "Evaluation of Post-Accident Chemical Effects in Containment Sump Fluids to Support GSI-191," and various NRC-sponsored research presented at public meetings or posted on the NRC website. Chemical effects bench-top tests were performed and conservatively assessed the solubilities and behaviors of precipitates, and the applicability of industry data on the dissolution and precipitation tests to station-specific conditions and materials. Reduced-scale testing was performed to establish the influence of chemical products on head loss across the strainer surfaces by simulating the plant-specific chemical environment present in the water of the containment sump after a LOCA. Reduced-scale testing was conducted for greater than 30 days after the formation of a debris bed and initial chemical addition at a specified temperature and flow rate to assess the possibility of precipitate formation and any. subsequent change in strainer head loss. These tests verified that adequate NPSH is available to support the operation of the LHSI and RS pumps during the post-LOCA recirculation mode. Potential for Sufficient "Clean" Strainer Surface Area North Anna Units 1 and 2 chemical effects head loss testing was conducted at the AECL Chalk River Laboratories. It is expected that, due to debris settling and very low pool velocities, much of the debris generated following a large break LOCA will not reach the strainer. For a small break LOCA, even less debris would be expected to reach the strainer. In addition, the strainer construction at North Anna Units 1 and 2 spans a significant arc of the containment basement annulus and debris from any particular break will likely be drawn to a localized portion of the strainer rather than tend to cover the entire strainer surface. Despite these factors that encourage the existence of open strainer surface area, no credit is taken for open strainer surface area in the evaluation of head loss due to chemical effects. Debris-bed Formation The worst-case strainer head loss is obtained for North Anna Units 1 and 2 with a thin-bed of fibrous and particulate debris. Extensive testing without chemical precipitants has determined that the thin-bed fiber thickness is nominally 1/4 inch. Since the fibrous and particulate debris constituent mixtures for North Anna Units 1 and 2 are esse)ntially the same for any of the limiting break locations, the break that produces the maximum particulate load produces the worst-case head Serial No. 09-003 Docket Nos. 50-338 and 50-339 Attachment 1 Page 21 of 42 loss when an approximately 1/4 inch thick fibrous bed is deliberately formed following the addition of particulate. The same break that produces the worstcase head loss in the absence of chemical effects is expected to produce the worst-case head loss with chemical precipitants added to the debris-bed. Debrisbed formation for the chemical effects testing followed the same procedure that was used for previous head loss testing to ensure the worst-case debris-bed was formed (i.e., head loss was highest). All of the particulate was added to the test loop, which contained borated water with sodium hydroxide (NaOH) at pH 7 to simulate the post-LOCA sump water. Once the particulate was well distributed throughout the test loop water, fibrous debris was added. Fibrous debris was prepared consistent with previous head loss tests to ensure individual fiber separation and maximum head loss. Fibrous debris was added in four increments, each of which had enough fiber to form a 1/16 inch thick fiber bed, spaced to allow sufficient time for the debris to pack onto the strainer and begin collecting particulate debris. No sodium aluminate additions to the debris bed were made until after the head loss had stabilized. Plant Specific Materials and Buffers The sump pH buffer used at North Anna Units 1 and 2 is sodium hydroxide solution that is sprayed in along with RWST water during quench spray pump operation. As described later under the AECL Method section, potential reactive materials in containment have been evaluated and aluminum was determined to be the chemical effects contributor of concern for the North Anna Units 1 and 2 sump strainer evaluation. The total quantity of aluminum in containment has been determined and categorized as either submerged, unsubmerged-sprayed, unsubmerged-unsprayed, or encapsulated based on its exposure to sump or spray water. Except for encapsulated aluminum, which does not contribute to the aluminum in post-LOCA sump water, each category of aluminum was evaluated for its contribution to aluminum in solution. Aluminum quantities for North Anna Unit 2, which is the bounding unit, are as follows: Exposure Category Surface Area (ft2) Mass (Ibm), Submerged 185.5 1084.7 Unsubmerged - Sprayed 352.3 851.4 Unsubmerged - Unsprayed 392.7 1980.8 Containment sump water and spray temperature and pH have been evaluated at various time periods following the LOCA. The worst case or bounding values of pH and temperature were used in the analysis of aluminum corrosion (high pH, 4. Serial No. 09-003 Docket Nos. 50-338 and 50-339 Attachment 1 Page 22 of 42 high temperature) and precipitation (low pH). Containment sprays are assumed to continue for the entire 30 days following a LOCA. Approach to Determine Chemical Source Term Chemical effects testing and evaluation were performed for North Anna Units 1 and 2 by AECL and consisted of a chemical effects assessment, bench-top testing and reduced-scale tests. Separate Effects A plant-specific chemical effects assessment was performed using the AECL method, which includes single-effects bench-top testing. AECL Method The AECL method for'assessment of chemical effects on strainer head loss was audited by the NRC (Reference North Anna Power Station Audit Report dated February 10, 2009, ADAMS ML090410626). The NRC staff visited Dominion's Innsbrook facility from November 12-14, 2008, to perform a chemical effects audit for North Anna Power Station Units 1 and 2. Prior to the on-site portion of the audit, the staff reviewed relevant documents related to chemical effects bench-top testing and integrated head loss test results for North Anna. The NRC staff also visited AECL's Chalk River Facility on May 5-9, 2008, to observe integrated chemical effects head loss testing for the Dominion plants. The NRC staff reviewed the overall chemical effects approach, including the AECL test facilities, North Anna safety systems drawing from the sump, observed systematic non-chemical head loss differences, chemical effects head loss test results, and analytical conservatisms. The audit report includes detailed descriptions and evaluations of the head loss testing facilities. The report also documents a detailed review of head loss testing results and a review of the significant conservatisms incorporated into the sump strainer performance analysis and an assessment of the post-LOCA NPSH margins. The NRC staff concluded that the chemical effects audit of North Anna is complete with no open items or requests for additional information. The AECL methodology for the determination of chemical effects on sump strainer performance consisted of three elements: 1. An assessment of potential precipitates, including determination of reactive material amounts present in the containment sump pool, pH and temperature profiles in containment, and a review of existing test and scientific literature data. Serial No. 09-003 Docket Nos. 50-338 and 50-339 Attachment 1 Page 23 of 42 2. Bench-top testing to demonstrate that the solubility behavior of potential precipitates determined from literature is reproducible under plant conditions and to confirm that precipitates can be produced, if required, for reducedscale testing. 3. Reduced-scale testing to determine the influence of chemical products present in the containment sump pool on the head loss across the ECCS strainer. Assessment of Potential Precipitates AECL reviewed the published results of the Integrated Chemical Effects Tests (ICET), the Westinghouse Owners Group document WCAP-16530-NP, and various NRC sponsored research presented at public meetings or posted on the NRC website. In addition, AECL representatives attended most of the NRC public meetings on chemical effects in 2006 and 2007 and reviewed all of the relevant presentations from these meetings. The following conclusions were drawn from the data reviewed: 1. The ICET tests clearly show that, at the pH values studied, aluminum corrosion can give rise to the formation of an aluminum-bearing precipitate. However, the tests also show that: a) Aluminum corrosion may be inhibited by species present in the sump environment (e.g., phosphates, silicates). b) The precipitate formed included boron. The presence of boron can affect the mass or flocculation properties of the aluminum-bearing precipitate formed. '2. For the surface areas of materials used in these tests, only low concentrations of iron, nickel, magnesium and zinc dissolved into the simulated sump water, and these species did not lead to the formation of significant amounts of precipitates. 3. Significant concentrations of silicon and calcium from dissolution of fiberglass'and Cal-Sil can be present in the sump solutions. If trisodium phosphate (TSP) is present, precipitates containing calcium and phosphate, or calcium, phosphate and carbonate, can form. In the absence of TSP, the calcium and silicon do not lead to the formation of significant chemical precipitates. 4. Concrete does not appear to be a significant source of calcium in solution. 5. Thermodynamic modeling alone cannot properly predict the identity or quantities of precipitates formed under PWR sump conditions; kinetic factors are very important. 6. There is no evidence of direct chemical effects from paint debris. 7. While WCAP-16530-NP suggests that sodium aluminum silicate is a possible precipitate, a review of the literature on the thermodynamics and (- Serial No. 09-003 Docket Nos. 50-338 and 50-339 Attachment 1 Page 24 of 42 kinetics of aluminosilicate formation suggests that this is unlikely under PWR post-LOCA sump water conditions. Based on these conclusions, it was further concluded that in PWR post-LOCA containment sump water, only two precipitates would be of concern: aluminum hydroxide or oxyhydroxide, and calcium phosphate (likely hydroxyapatite). Since North Anna Units 1 and 2 do not use TSP as a pH buffer for the sump water, only the formation of aluminum hydroxide was further evaluated. This evaluation was based on the available experimental data including ICET tests, WCAP-16530-NP, and data from the reviewed literature. The AECL study used the basic methodology outlined in WCAP-1 6530-NP to calculate the mass of aluminum released. However, rather than use the WCAP-16530-NP release equation, the data from WCAP-16530-NP and other sources were used by AECL to develop a semi-empirical release equation. To model the aluminum release rate, the pH and temperature dependencies of the corrosion rates were evaluated separately. This allowed better comparison with existing literature data on aluminum corrosion. AECL determined aluminum corrosion rate expressions based on pH and on temperature from review of literature data. The time dependence of the corrosion rate was also evaluated but no term for the time dependence was included in the final release model. Neglecting time dependence was considered to be a conservatism. Containment aluminum inventories can be divided into exposure categories of submerged, unsubmerged-sprayed, unsubmerged-unsprayed, or encapsulated based on its exposure to sump or spray water. Except for encapsulated aluminum, which does not contribute to the aluminum in postLOCA sump water, each category of aluminum was evaluated for its contribution to aluminum in solution. Each category has a temperature evolution profile and a worst-case scenario pH. In addition, unsprayed aluminum has a limited time period during which transport of aluminum corrosion products to the sump can occur, which limits its contribution to the sump aluminum concentration. The aluminum released to the containment sump was calculated based on the aluminum surface areas and sump and spray water pH based on the correlation: ALUMINUM RELEASE OVER INTERVAL = CORROSION RATExINTERVAL LENGTHxALUMINUM SURFACE AREA Serial No. 09-003 Docket Nos. 50-338 and 50-339 Attachment 1 Page 25 of 42 where CORROSION RATE (i.e., aluminum release rate) is dependent upon pH and temperature and is determined from the following equation developed by AECL: Release Rate (mg/m 2 ,s) = 55.2 • exp (1.3947 • pH - 6301.1 • T-1), where T is in degrees Kelvin. The results of the application of the AECL release rate model was compared to the WCAP-16530-NP model results using North Anna aluminum inventories and were found to predict a greater 30-day release of aluminum. For unsubmerged-unsprayed aluminum, a detailed heat transfer and condensation evaluation was performed to determine the time required to equalize the temperature between the aluminum surface and the containment environment. When the temperature is equalized, no further condensation will take place resulting in no further contribution of aluminum to the sump water. The following conservatisms were included in the calculation of aluminum release in support of chemical effects testing: 1. The maximum expected temperatures of the sump and spray water were used during the corrosion calculations for each time interval. 2. The maximum expected pH values were used during the corrosion calculations for each time interval. 3. No credit was taken for the possible inhibitory effect of silicate or other species on aluminum corrosion. 4. No credit was taken for the presence of any oxide films formed on the aluminum surfaces prior to the LOCA. 5. All the aluminum released by corrosion enters the solution, i.e., no aluminum oxides remain on the aluminum surfaces. 6. No credit was taken for the effect of the presence of oxygen in the sump water. Literature data suggest the corrosion rate of aluminum in aerated pH 10 alkaline water is a factor of two lower than that measured in nitrogen-deaerated water. 7. No credit was taken for the decrease in corrosion rate as a factor of exposure time that results from the development of a passive film. Based on these conservatisms, it is believed that the aluminum release into the sump water is significantly overestimated. The total aluminum mass released to the sump water was calculated using the aluminum release rate equation above along with the North Anna-specific aluminum inventory based on exposure category, sump and spray water pH, and sump and spray water temperatures for specific time intervals following a Serial No. 09-003 Docket Nos. 50-338 and 50-339 Attachment 1 Page 26 of 42 LOCA. Data from the North Anna LOCA analysis was evaluated to determine the maximum containment sump and spray water pH as input to the chemical effects evaluation. The sump and spray water pH values for corresponding time intervals following a LOCA are provided in Table 3.o-1. Table 3.o-1: Summary of Post-LOCA Sump and Spray Water pH Time Interval after LOCA (sec.) Maximum Sump pH Maximum Spray pH 0 - 4 hours 8.2 10.5 4 hours - 30 days 8.1 8.1 The calculation of sump aluminum mass assumed a long-term sump and spray pH of 8.5 for conservatism and a spray pH of 10.5 for the first 4 hours following a LOCA, along with the containment sump and water vapor (spray) temperatures tabulated in Table 3.0-2. The precipitation behavior of aluminum hydroxide under representative North Anna Units 1 and 2 post-LOCA sump water conditions was further evaluated in bench-top testing. Serial No. 09-003 Docket Nos. 50-338 and 50-339 Attachment 1 Page 27 of 42 Table 3.o-2: Containment Sump and Water Vapor Temperature Time Interval after Maximum Vapor Maximum Sump LOCA (sec.) Temperature (OF) Temperature (*F) 0-20 270 240 20-150 270 270 150-600 255 265 600-1,200 250 260 1,200-1,800 240 250 1,800-2,400 240 235 2,400-3,000 235 228 3,000-3,800 225 225 3,800-4,200 205 218 4,400-7,200 185 215 7,200-14,400 135 180 14,400-28,800 135 160 28,800-57,600 135 140 57,600-86,400 135 135 86,400-172,800 135 130 172,800-259,200 135 125 259,200-30 days 110 120 Serial No. 09-003 Docket Nos. 50-338 and 50-339 Attachment 1 Page 28 of 42 Bench-Top Testing Bench-top testing was conducted to gain an understanding of the chemistry to be expected in reduced-scale testing. The bench-top testing consisted of the following tasks: * Precipitation Testing of Aluminum Hydroxide * Dependence of Walnut Shell Properties on Chemistry Precipitation Testing of Aluminum Hydroxide AECL conducted bench-top tests to determine aluminum solubility under the worst-case conditions expected in the post-LOCA sump water. Two series of tests were conducted: station-specific precipitation tests and aluminum solution stability tests. In the station-specific precipitation tests, the sump water chemistry conditions that are expected to exist after 30 days were used for determination of aluminum precipitation. These chemistry conditions are considered the most conservative since after 30 days, the temperature of the sump water has decreased to a stable, low value, and the dissolved aluminum concentration has reached its maximum value. For additional conservatism, a pH of 7.0 was maintained since this is the lowest expected sump pH based on accident analysis.. The concentration of aluminum used for the bench-top testing was 44 mg/L, which was based on preliminary determinations of the aluminum inventory in containment and the post-LOCA containment sump water pH and temperature. The use of this high aluminum concentration provided conservative bench-top test results. In the aluminum solution stability tests, it was sought to determine pH values at which 2.5 to 100 mg/L aluminum solutions remained kinetically stable for 30 days. The station-specific bench-top tests for aluminum precipitation were conducted in three flasks identified as Warm, RT (room temperature), and BL (blank). The flasks were maintained at 1400F and two (Warm and RT) included insulation debris. All three of the flasks contained borated water to which sodium aluminate was added. The solutions were stirred slowly with a magnetic stirrer and once the pH was adjusted to the target value, the solutions were allowed to stand for 30 days. The pH was nearly constant throughout the 30 days. Turbidity measurements were taken for the Warm and RT flasks daily (at test temperature for the Warm flask samples and at room temperature for the RT flask samples). The mass of any precipitate formed after 30 days was determined by filtering the BL solution through a 0.1-pm pore size filter, drying the filter, and then weighing the dried filter; however, very little precipitate formed in any of the tests. Samples of the BL filtrate were taken for elemental analysis using Inductively Coupled Plasma Atomic Emission Spectrometry (ICP-AES). Serial No. 09-003 Docket Nos. 50-338 and 50-339 Attachment 1 Page 29 of 42 A measurable mass of precipitate was recovered from the North Anna benchtop test solution, indicating that precipitation is predicted at the 44 mg/L concentration of aluminum used in the bench-top tests. Based on elemental analysis, the precipitate was determined to consist of mainly Al and 0 indicating the formation of aluminum hydroxide or oxyhydroxide species. The aluminum solution stability tests consisted of two parts: the first, a titration of aluminum solutions starting at high pH against nitric acid, was used to establish lower limits at which precipitation would occur; the second brought aluminum solutions down to 1 pH unit above the established lower limit and monitored the turbidity over 30 days. Tests were conducted at room temperature, 104'F, and 140'F. The results provided a stability map of Al concentration vs. pH in which the North Anna station-specific conditions were predicted to be unstable with respect to aluminum precipitation. Dependence of Walnut Shell Properties on Chemistry Walnut shell powder is used in the debris head loss tests to simulate epoxy coating which is conservatively anticipated to be broken into very small particulate sizes (nominally 10pm) post-LOCA. Tests were carried out as part of the bench-top testing to determine if exposure to chemicals would dissolve or alter the walnut shell particulate. Particle size and dissolution tests carried out to characterize the effects of exposure of walnut shells to borated water containing sodium aluminate showed no obvious change on particle size distribution or particle morphology. Measurements of the total organic carbon in the test solution gave inconsistent results with respect to the amount of walnut shell dissolution, while measurements of the weight change suggested a maximum weight loss of 12%. No significant effect on the results of reduced-scale testing is expected from walnut shell dissolution or weight change. Reduced-Scale Testing Reduced-scale testing was conducted for North Anna Units 1 and 2 to determine the debris bed head loss. Two different test rigs were used to perform the testing. Test Rid 33 was used to determine total strainer size requirements, as described in Section 3.f of the previous supplemental response (Dominion letter dated February 29, 2008), but was not used for the reduced-scale chemical effects testing. To expedite reduced-scale chemical effects testing, a multi-loop test rig, Test Rig 89, was designed and constructed to facilitate the performance of concurrent testing of multiple Serial No. 09-003 Docket Nos. 50-338 and 50-339 Attachment 1 Page 30 of 42 strainer configurations and post-accident containment sump conditions for several of Dominion's nuclear units (i.e., Surry, North Anna and Millstone). The differences in debris-only head loss testing results for the two different test rigs were evaluated during the North Anna Chemical Effects Audit performed by NRC staff in 2008 (Reference North Anna Power Station Audit Report dated February 10, 2009, ADAMS ML090410626). The NRC staff ultimately concluded that, although the reasons for differences in head loss for the two test rigs could not be definitively identified, the significant conservatisms incorporated into the sump strainer performance analysis bound the uncertainties associated with the formation of debris beds in the multi-loop Test Rig 89. Test Description Reduced-scale chemical effects testing was performed to establish the influence of chemical products on the head loss across the containment sump strainer surfaces after a LOCA. Tests were carried out for North Anna Units 1 and 2 RS and LHSI strainers using the multi-loop Test Rig 89. Fibrous and particulate debris and chemicals were added into the test rig to simulate the plant-specific chemical environment present in the water of the containment sump. Each test was operated for more than 30 days, after the formation of a debris bed and initial chemical addition, at a specified temperature and flow rate to assess the possibility of precipitate formation and subsequent head loss change. The following includes descriptions of the test facility, debris load, chemical environment, and the chemical addition procedure. Test Facility The test facility consists of six single test loops. Each test loop has the same configuration except that the strainer box orientation and fin pitch distance may be different. Each single test loop. includes a 16 in. x 16 in. x 36 in. strainer box (volume approximately 40 gal) and a 12 in. diameter x 18 in. long cylindrical debris addition tank (volume approximately 9 gal). Two fins were installed inside each strainer box with a pre-determined pitch distance. The fins have perforated material on the sides facing each other, while the sides facing away from the other fin have cover plates to cover the fin holes. For North Anna testing, the fins and strainer boxes were horizontally oriented to simulate the installed RS and LHSI strainer module orientation. The topside and underside of the strainer box have clear windows to enable observation of any precipitates and the debris bed on the strainer screens inside the box. Stainless steel tubes and fittings are utilized to connect the strainer box to other components of the loop. The loop is capable of producing flow rates from 1 to 20 gpm. The flow rates can be adjusted via a variable frequency drive. A magnetic flow meter is installed to provide feedback for constant flow Serial No. 09-003 Docket Nos. 50-338 and 50-339 Attachment 1 Page 31 of 42 rate control. Each loop is equipped with a 6kW in-line stainless steel heater to provide heating to a maximum temperature of 140°F (600C). Cooling is provided by an in-line stainless steel cooler using service water. Figure 3.o-1 provides a representation of a single loop of the Test Rig 89 multi-loop test facility. Physical debris including fiber and particulate, and chemicals including liquid solutions, can be added through the debris addition tank. The debris addition tank is equipped with a paddle-type stirrer to keep the debris suspended, and mixed debris can be slowly metered out of the tank. Each test loop is connected to a header tank located at an elevation of 15 feet above floor level. The header tank can be used to accommodate extra fluid from debris addition or thermal expansion and to control the loop pressure. Chemical solutions can also be added in small quantities via the chemical injection points. Each loop is instrumented with a thermocouple to measure the water temperature and a flow meter to measure the flow rate through the test loop. The strainer box is instrumented with a differential pressure transmitter for measuring the debris bed head loss. Two manual pressure gauges are also connected upstream and downstream of the test screen to allow for verification of the pressure and to provide back-up measurements in case the differential pressure transmitter should fail. The pump speed, heater and cooler are controlled by a programmable logic controller (PLC). The water temperature and flow rate and the debris bed head loss are monitored and recorded by the PLC. Monitoring of pH, turbidity, and concentrations of elements in solution is via grab samples. Serial No. 09-003 Docket Nos. 50-338 and 50-339 Attachment 1 Page 32 of 42 Figure 3.o-1: Test Rig 89 Single Test Loop (One of Six) Debris Load Debris composition for the reduced-scaled chemical effects testing for the North Anna Units 1 and 2 sump strainer was the same as was used for the strainer head-loss testing as described in the previous supplemental response (Dominion letter dated February 29, 2008) for "Break BK2" (the limiting debris source). Test debris quantities were directly scaled from the total debris by the ratio of the total modeled strainer area to the test section area, termed the "debris-scaling factor." The Rig 89 RS strainer test module area is 5.74 ft 2 while the total modeled area was 4210 ft2 . Therefore, the RS strainer debris-scaling factor is 733.4. The LHSI strainer debris-scaling factor is 284.0 since the LHSI strainer test module area is 5.74 ft2 and the modeled surface area is 1630 ft2 . Serial No. 09-003 Docket Nos. 50-338 and 50-339 Attachment 1 Page 33 of 42 The full particulate debris load for each test was added at the start of the test, and then additions of fibrous debris were made in 1/16 in. theoretical bed thickness increments. The theoretical bed thickness is defined as the uncompressed fiber volume divided by the test module surface area. The first fiber addition (1/16 in.) was made 30 minutes after the addition of the particulate debris. The second fiber addition (an additional 1/16 in.) was made 30 minutes after the first addition. Subsequent fiber additions were only made once the pressure increase resulting from previous additions had stabilized (changed by less than 5% or 0.01 psi, whichever was greater, and exhibited no general steadily increasing trend in pressure, within 25 minutes (approximately five tank turnovers)). Fiber additions were continued until the debris bed thickness had reached the thin bed thickness as determined by previous thin bed tests (1/4 inch). Chemical Environment North Anna-specific post-LOCA sump Water chemical conditions at the end of the 30-day mission time for ECCS were simulated in the reduced-scale tests. The water was maintained at the conservatively low minimum pH limit of 7.0 to enhance precipitate formation. Sodium aluminate (NaAIO 2 ) was added to the test solution, after the particulate addition and debris bed formation, to produce the desired concentration of aluminum in solution. The test fluid also included boric acid and sodium hydroxide concentrations that were equivalent to the expected post-LOCA sump water conditions. Chemical Addition Procedure After the debris bed was formed and the pressure drop had stabilized, sodium aluminate solutions were added into the loop through the chemical injection points. Over the course of the test, 19 sodium aluminate additions were made to the LHSI strainer test loop, for a total 52.77,g NaAIO 2 , and 24 sodium aluminate additions weremade to the RS strainer test loop, for a total 69.37 g NaAIO 2 . Precipitate Generation Chemical additions for the chemical effects testing were accomplished by addition of sodium aluminate solutions into the test loop through chemical injection points in the test rig. Aluminum precipitates were generated in-situ, mainly on the fibers and particles, by a heterogeneous precipitation mechanism. Serial No. 09-003 Docket Nos. 50-338 and 50-339 Attachment 1 Page 34 of 42 Chemical Injection into the Loop Three methods of sodium aluminate addition were employed through the course of the testing. Each method was successively developed in an attempt to approximate more closely the aluminum release rate into solution in the postLOCA containment sump. Method A. The first method used an injector to inject 3.6 L (or less) of 200 mg/L Al solutions over 20-30 minutes, repeated every hour as necessary. The sodium aluminate was added every 3 days to approximate the predicted aluminum release rate into solution. Solutions of sodium aluminate were made with borated loop water (water obtained from the test rig) adjusted to pH 12 to facilitate dissolution of sodium aluminate. The advantages of this addition method were that the test rig water volume was kept constant, and there were no dilution effects on other chemicals. The disadvantage was that, since sodium hydroxide was added to the loop water, it was necessary to add nitric acid to adjust the loop pH back to 7.0. It was found that the follow-up nitric acid addition caused precipitate to form in localized low pH environments around the addition point. Method B. The second method also used an injector, as described above. In this method, deionized water was used to dissolve the sodium aluminate. To compensate for the dilution of the test loop solution caused by the addition of the deionized water, boric acid dissolved in loop water was added to the loop in a separate step. The combined effect of (basic) sodium aluminate additions and (acidic) boric acid additions was that the loop pH remained stable, and nitric acid additions were no longer required. After a number of injections, the aluminum concentration did not reflect the expected concentration, and a third injection method was instituted. Method C. This method used a metering pump for the sodium aluminate additions, which permitted a more favorable mixing environment for the sodium aluminate and avoided the addition of slugs of solution with a high aluminum concentration. For each addition, 3.5 L of 200 mg/L Al solution was metered into the test loop at a flow rate of 545 mL/hr. As in Method B above, deionized water was used as a solvent for the sodium aluminate and boric acid dissolved in loop water was injected in a separate step. The amount of injected aluminum at the end of the test was 60.4 mg/L of which 2.6 mg/L remained in solution for the LHSI strainer test, and 79.4 mg/L of which 2.3 mg/L remained in solution for the RS strainer test. Serial No. 09-003 Docket Nos. 50-338 and 50-339 Attachment 1 Page 35 of 42 Technical Approach to Debris Transport North Anna plant-specific analysis determined the amount and type of debris that could be generated and transported to the sump strainer post-LOCA. Essentially all debris (or applicable surrogate) that is analyzed to reach the containment sump strainer was included in the reduced-scale testing. RMI debris was not included in the chemical effects test, as RMI does not affect debris bed formation or the resultant head loss when present in the. relatively small quantities existing in North Anna Units 1 and 2. Head-Loss Testing Without Near-Field Settlement No specific credit was taken for near-field debris settlement in the strainer head loss analysis for chemical effects. Debris was added during the tests by mixing in the debris addition tank and then slowly metering into the strainer test box. A mixer was used in the debris addition tank to prevent debris settling on the floor of the tank. A magnetic brush was used intermittently to sweep the strainer box floor in an attempt to keep fibrous debris from settling. At the end of the tests, the amount of debris attached to the strainer module fins was measured, with the following results: RS Strainer Test: LHSI Strainer Test: 97% 95% Test Termination Criteria The termination criteria used for the tests are described below. 1. Little or no precipitate forms in 30 days; aluminum concentrations in solution remain at the specified value (10.3 mg/L). 2. Precipitate forms and the head loss exceeds the allowable debris bed head loss or the available test rig NPSH margin. 3. Precipitate forms but criterion 2 is not met. Aluminum will be added to the test loop to maintain the specified concentration until the maximum mass of aluminum, scaled to the aluminum release mass based on containment aluminum inventory, is added. Serial No. 09-003 Docket Nos. 50-338 and 50-339 Attachment 1 Page 36 of 42 Data Analysis Test ProcedureSummary Each test loop of the reduced-scale multi-loop test rig had a volume of 200 L, and each head tank had a volume of about 30 L. Each test strainer module had a surface area of 5.74 ft2 . To begin each test, the chemical environment was established by filling each loop with a pH 7 boric acid solution (2800 mg/L B). Test solution temperature was maintained at 104 0 F for the tests, and, for comparison, allowable debris bed head losses were corrected for temperature using the dynamic viscosity ratio. Particulate debris was added followed by fibrous debris that established a debris thin bed. Once the head loss had stabilized, chemical additions began. Throughout the tests, daily water samples were taken for ICP-AES analysis to determine the concentrations of Al, B, Ca, Fe, K, Na, P, and Si. Sample analysis results consistently showed much lower concentration of aluminum in the test solution than was calculated based on sodium aluminate additions, indicating that the aluminum had either precipitated or deposited (plated out) on surfaces such as the debris bed. Aluminum additions were made to the test loops in an attempt to reach a test strainer aluminum load equivalent to the containment strainer aluminum load resulting from a 10.3 mg/L Al concentration in the containment sump. The strainer aluminum load was determined by calculating the total expected aluminum mass in the proportioned sump volume for the individual strainer (either LHSI or RS strainer) and dividing by the individual strainer surface area. The proportioned sump volume is the total sump volume proportioned by the individual strainer flowrate relative to the total strainer flowrate. After chemical additions were completed, the test temperature was reduced to 70°F to evaluate the effect of temperature on head loss. A flow sweep was performed by reducing flow to 90%, then 80%, then back to 100% to evaluate the response of head loss to flow velocity changes. Test Results In the North Anna LHSI test (identified as test NA-LHSI-C1), there were 19 additions of aluminum over the duration of the test (in the form of sodium aluminate solutions), resulting in reaching a 2.31 g/ft2 strainer aluminum load. The allowable debris bed head loss limit of 3.2 psi1 was exceeded during the 1 The head loss limits determined previously for debris bed head loss testing (see the original supplemental response in Dominion letter dated February 29, 2008) were established as the test criteria for the LHSI and RS strainer chemical effects testing. Subsequently, final head loss criteria were developed and are compared to debris bed test results in Section 3.f, Table 3.f-2 of this attachment. Serial No. 09-003 Docket Nos. 50-338 and 50-339 Attachment 1 Page 37 of 42 test. Data analysis determined that the 1 1 th Al addition, which resulted in 1.18 g/ft2 strainer aluminum load, produced an acceptable 2.9 psi head loss. In the North Anna RS test (identified as test NA-RS-C2), there were'24 additions of aluminum in total resulting in reaching a 3.09 g/ft 2 strainer aluminum load. The allowable debris bed head loss limit of 2.7 psi1 was exceeded during the test.2 Data analysis determined that the 1 4 th Al addition, which resulted in 1.58 g/ft strainer aluminum load, produced an acceptable 2.6 psi head loss. A summary of the test head loss results are presented in Table 3.0-3. The pressure drop curves (head loss across the strainer section vs. time) for the LHSI and RS strainer tests are provided in Figures 3.0-2 and 3.0-3, respectively. The curves indicate debris addition, aluminum addition, temperature changes, and flowrate changes during the test and the corresponding effect on strainer head loss. Evaluation of Results In both the North Anna LHSI and RS strainer tests, the allowable debris bed head loss was exceeded prior to adding the maximum aluminum to the test solution. The maximum sump aluminum load that could be tolerated by the LHSI strainer was determined to be 1.18 g/ft2, which is equivalent to 5020 g total sump aluminum load. The maximum sump aluminum load that could be tolerated by the RS strainer was determined to be 1.58 g/ft2 , which is equivalent to 8790 g total sump aluminum load. Therefore, the sump aluminum load was determined to be limited to 5020 g by the LHSI strainer. Sump Chemical Load Calculation The aluminum inventory in containment that is subject to corrosion post-LOCA was evaluated for aluminum release to the sump water using a reduced pH of 8.5, which remains conservative with respect to the expected pH post-LOCA (see Table 3.o-1). The calculated sump aluminum load of approximately 4943 g is expected to be released within 30 days of event initiation based on the current North Anna Unit 2 aluminum inventory, which is limiting for both units. The expected aluminum release post-LOCA is less than the limiting sump aluminum load of 5020 g. Therefore, conservatively assuming all aluminum released to the containment sump water results in increased head loss across the strainer debris bed, the resulting head loss would be kcceptable. Programmatic controls have been established as part of the design control process and containment close-out verification following maintenance or Serial No. 09-003 Docket Nos. 50-338 and 50-339 Attachment 1 Page 38 of 42 refueling operations to limit the amount of aluminum bearing materials inside containment during operation such that the calculated aluminum release limit will not be exceeded. Table 3.o-3: Summary of Test Rig 89 Chemical Effects Test Results Rig 89 Test Loop Test Loop Temperature (*F) Test Loop Flowrate (gpm) Strainer Aluminum Load (g1ft 2) Head Loss Test/Limit (psi) 104 14.26 0 0.74/3.2 104 14.26 1.18 2.9/3.2 104 14.26 2.31 3.7a 104 12.43 2.31 2.9 / NA 104 11.19 2.31 2.4 /NA 104 9.94 2.31 1.9 /NA ~LH,$sl'Stainer Test NA-LHSI-C1 (prior to Al addition) NA-LHSI-Cl (Al addition at head loss limit) NA-LHSI-Cl (end of Al addition) NA-LHSI-C1 (flowrate reduction to 12.43 gpm) NA-LHSI-Cl (flow sweep 90%) NA-LHSI-Cl (flow sweep - 3'.2 80%) NA-LHSI-C1 (flow sweep 104 12.43 2.31 2.9/NA 100%) NA-LHSI-C1 (temperature 70 12.43 2.31 2.4 / NA reduction) NA-LHSI-Cl (flow sweep 70 11.19 2.31 1.9 / NA 90%) NA-LHSI-Cl (flow sweep .70 9.94 2.31 1.7 / NA 80%) NA-LHSI-Cl (flow sweep 70 12.43 2.31 2.4/ NA 100%) a. Head loss peaked at 5.41 psi after the 19"' Al addition, then abruptly dropped to 2.1 psi possibly due to debris bed break caused by high differential pressure - and subsequently recovered to 3.7 psi. b. Head loss initially increased to 3.1 psi during temperature reduction, then decreased to 2.4 psi. Serial No. 09-003 Docket Nos. 50-338 and 50-339 Attachment 1 Page 39 of 42 Table 3.o-1: Summary of Test Rig 89 Chemical Effects Test Results (cont.) Rig 89 Test Loop R. Te st NA-RS-C2 (prior toAI Strainer Head Loss Test Loop Flowrate (gpm) .. Aluminum Load (gift2 ) .... Test/Limit (psi 104 17.2 0 0.3/2.7 104 17.2 1.58, 2.6/2.7 104 17.2 3.09 3.88c / 2.7 104 10.23 3.09 1.6/ NA .104 9.21 3.09 1.34 /NA 104 8.18 3.09 1.09 /NA 104 10.23 3.09 1.64 / NA 70 10.23 3.09 1.81 /NA 70 9.21 3.09 1.5 /NA 70 8.18 3.09 1.22 / NA 70 10.23 3.09 1.81 / NA Test Loop Temperature (OF) .._ _ _ _ _ _ _ _. . ..... .. addition) NA-RS-C2 (Al addition at head loss limit) NA-RS-C2 nd of Al (end of Al addition) NA-RS-C2 (flowrate reduction to 10.23 gpm) NA-RS-C2 (flow sweep 90%) NA-RS-C2 (flow sweep 80%) NA-RS-C2 (flow sweep 100%) NA-RS-C2 (temperature reduction) NA-RS-C2 (flow sweep 90%) NA-RS-C2 (flow sweep - -' 80%) NA-RS-C2 (flow sweep - 100%) c. Head loss peaked at 4.38 psi after the 20(n Al addition, then abruptly dropped to 2.7 psi possibly due to debris bed break caused by high differential pressure. Serial No. 09-003 Docket Nos. 50-338 and 50-339 Attachment 1 Page 40 of 42 Figure 3.0-2: Test NA-LHSI-CI Chemical Effects Test - Head Loss vs. Time NA-LHSI Chemical Effects Test 45 6 40.5 5.4 36 4.8 c• 31.5 4.2 3.6 CL S27 0 0) 0 22.5 ~-18 2.4 13.5 1.8 E 9 1.2 I- J-4.5 0.6 0 0 02/05/08 17/05/08 01/06/08 16/06/08 01/07/08 16/07/08 31/07/08 0:00 0:00 0:00 0:00 0:00 0:00 0:00 Time (standard) 15/08/08 0:00 -J M ' Serial No. 09-003 Docket Nos. 50-338 and 50-339 Attachment 1 Page 41 of 42 Figure 3.0-3: Test NA-RS-C2 Chemical Effects Test - Head Loss vs. Time NA-RS-C2 Chemical Effects Test 45 - 5 ----------------- --------------------------- --------Temperature (0C) 24th Foat(UGM---------------17th --------- 40.5 36 ---- 31.5 Head loss(PSI) - 0 - -- 16th------- 3.5 2--h 3 2.5 I15th Z- ........ 18 -- |3 1 - -At -5- 3rd A E--------------------6th ! 5t 4) A[ --- 4 -------------- 27 UE 22.5 -- 4.5 Al Al--------------Al 3rdlfibe 18th 21th---- 19th 0. 00t 13/05/08 24/05/08 05/06/08 16/06/08 28/06/08 09/07/08 21/07/08 01/08/08 13/08/08 0:00 12:00 0:00 12:00 0:00 12:00 0:00 12:00 0:00 Time (standard) (Aa 0 Serial No. 09-003 Docket Nos. 50-338 and 50-339 Attachment 1 Page 42 of 42 3.p Licensing Basis Dominion's February 29, 2008 supplemental response discussed the licensing bases changes that had been implemented for North Anna Units 1 and 2 associated with the resolution of the sump issues considered in GSI-191 and GL 2004-02 in the form of Updated Final Safety Analysis Report (UFSAR) Revisions, analysis methodology changes, and license amendment requests. A UFSAR change and Technical Specifications Bases change were made to establish the limit for the long-term containment sump pH to 8.5 from 9.5 to be consistent with the calculation of sump aluminum load discussed in Section 3.o. Serial No. 09-003 Docket Nos. 50-338 and 50-339 ATTACHMENT 2 RESPONSE TO GENERIC LETTER 2004-02 AUDIT OPEN ITEMS NORTH ANNA POWER STATION UNITS 1 AND 2 VIRGINIA ELECTRIC AND POWER COMPANY (DOMINION) Serial No. 09-003 Docket Nos. 50-338 and 50-339 Attachment 2 Page 1 of 6 Responses are provided to GL 2004-02 Audit Open Items not resolved in the previous North Anna supplemental response (Dominion letter dated February 29, 2008). NRC GL 2004-02 AUDIT OPEN ITEMS NORTH ANNA UNITS I AND 2 Open Item No. and Subject Open Item 5.3-1 Downstream Effects-Core Blockage Item Although downstream evaluations were in progress during the audit, the licensee has not made any final conclusions as to whether the cores at North Anna Power Station could be Resolution See Section 3.n "Downstream Effects - Fuel and Vessel" for Dominion's response to this open item. blocked by debris following a LOCA, and this area is incomplete. The licensee should summarize the method and results of its evaluation of this issue in its GL 2004-02. supplemental response. Open Item 5.3-2 Downstream Effects Evaluations Preliminary See Section 3.m "Downstream Effects The licensee's evaluations of the downstream effects of debris on systems and components are Components and Systems" for Dominion's response to this open item. preliminary, based in part on the generic methodology of WCAP-16406-P which is under review by the NRC staff. NAPS will reassess the evaluation based on the conclusions and findings associated with the staff's review of WCAP16406-P Revision 1. The licensee should provide the staff a summary of the method and results of this evaluation. Serial No. 09-003 Docket.Nos. 50-338 and 50-339 Attachment 2 Page 2 of 6 NRC GL 2004-02 AUDIT OPEN ITEMS NORTH, ANNA UNITS 1 AND 2 Open Item No. Item Resolution and Subject Open Item 5.3-3 I tLocations The evaluation documented that the ECCS instrument locations are adequate because of an assumption of "good engineering practice." This See Section 3.m "Downstream Effects Components and Systems" for Dominion's response to this open item. assumption needs to be verified, such as by means of isometrical drawings or an ECCS survey. The licensee should provide the staff a summary of the method and results of this verification. Open Item 5.3-4 Debris Bypass Testing The licensee had not made a final determination on how the bypass testing data is going to be implemented in the downstream effects evaluation for ECCS and internal vessel components. The licensee should provide the of the testing."onsremEfecs method and results of its staff a summary bypas bypass testing. :Components See Section 3.n in previous North Anna supplemental response (Dominion letter dated February 29, 2008) for a detailed discussion on bypass flow testing with respect to the vessel and core. See Section 3.m "Downstream Effects and Systems" for Dominion's response to this open item with respect to components and systems. Serial No. 09-003 Docket Nos. 50-338 and 50-339 Attachment 2 Page 3 of 6 NRC GL 2004-02 AUDIT OPEN ITEMS NORTH ANNA UNITS 1 AND 2 Open Item No. and Subject Open Item 5.3-5 Fixed Throttle Valve Setting Item The downstream component evaluation did not reference operating procedures or testing history in order to demonstrate high confidence that throttle valves will remain in their fixed position during ECCS operation. Throttle valve fixed position is the basis for assuming the system's hydraulic resistance to be fixed. The licensee should address the-full potential range of throttle valve positions in their revised downstream evaluation. The licensee did not quantify seal leakage andassociated with downstream effects into the Quantification adAuxiliary Building, nor evaluate the effects on Assessment of Downstream equipment qualification, sumps and drains EfectkTatg aseSa operation, or on room habitability. The licensee summarize the method and results of its Leakageshould evaluation of these subjects in its GL 2004-02 supplemental response. Open Item 5.3-6 Resolution See Section 3.mn "Downstream Effects Components and Systems" for Dominion's response to this open item. Throttle valves are locked in their fixed position and are not affected by debris in the recirculation fluid. See Section 3.mn "Downstream Effects Components and Systems" for Dominion's response to this open item. Mcaia elpromnei o desl affected by debris in the recirculation fluid. Serial No. 09-003 Docket Nos. 50-338 and 50-339 Attachment 2 Page 4 of 6 NRC GL 2004-02 AUDIT OPEN ITEMS NORTH ANNA UNITS I AND 2 Open Item No. and Subject Item Resolution Open Item 5.3-7 Range of System Flows The licensee did not fully-define the range of fluid velocities within piping systems. Fluid velocities used were based on nominal system operating characteristics and did not take into account the range of possible system flows. NAPS staff should re-assess ECCS flow balances based on the results of system and component wear evaluations and should provide a summary of the method and results to the NRC staff. See Section 3.m "Downstream Effects Components and Systems" for Dominion's response to this open item. Component wear is not significant and has a negligible effect on system flow. Open Item 5.3-8 The preliminary downstream component evaluation did not consider the use of minimum and maximum system operating points; instead, best-efficiency performance values were used. See Section 3.m "Downstream Effects Components and Systems" for Dominion's response to this open item. Component wear is not significant and has a ECCS Minimum and Maximum Operating Points The ECCS operating point values were not referenced back to system bases calculations. The licensee should evaluate this issue and provide a summary to the staff. negligible effect on system flow. Serial No. 09-003 Docket Nos. 50-338 and 50-339 Attachment 2 Page 5 of 6 NRC GL 2004-02 AUDIT OPEN ITEMS NORTH ANNA UNITS 1 AND 2 Open Item No. and Subject Open Item 5.3-9 Use of Manufacturer's Pump Performance Curves Item The pump performance inputs considered in the preliminary downstream components evaluation were obtained from manufacturer's pump performance curves. The evaluation should consider the use of degraded pump curves or in- See Section 3.m "Downstream Effects Components and Systems" for Dominion's response to this open item. represent actual system operating conditions. The licensee should evaluate this issue and provide a summary to the staff. pump performance curves. The licensee had yet to perform an overall system evaluation that integrates the results of the downstream components evaluation. The evaluation should address compliance with 10 CFR 50.46, "Long Term Core Cooling." The licensee should evaluate this issue and provide a summary to the staff. See Section 3.m "Downstream Effects Components and Systems" for Dominion's response to this open item. beter crve better asthee estng urvs servce service testing curves as these curves Open Item 5.3-10 Overall Downstream ECCS Evaluation Resolution terconse wit manuater's determi with manufacturer's determined pm efracto be consistent uvs Serial No. 09-003 Docket Nos. 50-338 and 50-339 Attachment 2 Page 6 of 6 NRC GL 2004-02 AUDIT OPEN ITEMS NORTH ANNA UNITS 1 AND 2 Open Item No. and Subject Open Item 5.4-1 Evaluate Chemical Effects Item The licensee's chemical effects analysis was incomplete at the time of the audit. Also, the licensee has not evaluated the contribution of coatings to chemical effects by: (1) leaching constituents that could form precipitates or affect other debris; and (2) changing form due to the pool environment. Since the licensee's integrated chemical effects testing plans have not been completed, the staff could not review the application of the debris bed head loss acceptance criteria to verify that the long-term and short-term acceptance criteria are bounding with respect to intermediate conditions. The licensee should provide the staff a summary of the method and results of its chemical effects evaluation and testing. Resolution See Section 3.o "Chemical Effects" for Dominion's response to this open item.