LWR Activities in Korea
IAEA TWG-LWR
Vienna, June 18-20, 2013
Presented by Jong-Tae Seo
1. Overall Status
2. Operating Plants
3. New Plants under Construction
4. National Plan
5. Proposal for Future IAEA
Activities
2/18
1. Overall Status
Units (MWe)
HANUL
Kori

Ulchin
8 (7,937)

In Operation


2 (2,800)

Under Construction
Under Planning
Shin Ulchin #3,4 2 (2,800)
Under Planning
Shin Kori #5,6
2 (2,800)
Wolsong
HANBIT
Younggwang 6 (5,900)


6 (5,900)
6 (4,779)
In Operation
# 1,2,3,4 (HWR) 4 (2,779)
SWS# 1(PWR)
1 (1,000)
In Operation
# 1,2,3,4,5,6
6 (5,900)
Shin Ulchin #1,2 2 (2,800)
Under Construction
Shin Kori #3,4
In Operation
# 1,2,3,4,5,6
#1 ~ 4, SKN #1,2 6 (5,137)

8 (8,700)

Under Construction
ShinWolsong #2 1 (1,000)
3/18
1. Overall Status
Units (MWe)
In Operation
Under Construction
Total
23
20,716
5
6,600
28
27,316
Capacity Factor
Korea
100
World Average
84.3%
90
80
70
60
`00
`01
`02
`03
`04
`05
`06
`07
`08
`09
`10
`11
`12
4/18
1. Overall Status
Generation Mix
Power Generation
Installed Capacity
9%
8% 3%
1% 2%
25%
(20,716 MW)
22%
25%
as of January 1, 2013
(150,327 GWh)
39%
30%
Total: 81,806 MW
30%
6%
Nuclear
Coal
Gas
Oil
Hydro
Others
Total: 504,869 GWh
Generation in 2012
5
5/18
2. Operating Plants
Kori unit 1
•
Reactor vessel head
replacement will be completed
July 2013
Hanul (Ulchin) units 3 & 4
•
•
Unit 4 SG replacement will be
completed by August 2013
Unit 3 SG replacement planned
in February 2014
6/18 6
2. Operating Plants
Wolsung unit 1
•
•
30 year license expired in 2012.11
Under licensing review for continued
operation
Additional Stress Test is on-going
•
Hanbit (Yonggwang ) unit 3
•
•
Shutdown for CEDM nozzle
repair
Completion date : June 2013
7/18 7
2. Operating Plants
Shin-Kori units 1&2
•
•
Shutdown for cable replacement
Both units will be on-line in October
Shin-Wolsong unit 1
•
•
Shutdown for cable replacement
Both units will be on-line in October
8/18 8
3. New Plants under Construction
Shin-Wolsong 2 (OPR1000)
•
•
•
Unit #2 HFT : 2012.4.30
Unit #1 Fuel Loading : 2011.12.3
Commercial Operation :
Unit #1 : 2012. 7.31
Unit #2 : 2013. 12
•
•
•
•
Unit #3 CHT : 2012.5.1
Unit #3 HFT : 2012.11
Unit #3 Fuel Loading : 2013.10
Commercial Operation :
Unit #3 : 2013.12
Unit #4 : 2014.12
99.6 %
In Progress
Shin-Kori 3&4 (APR1400)
96.5 %
In Progress
9/18 9
3. New Plants under Construction
Shin-Hanul 1&2 (APR1400)
•
•
•
39.0%
Construction Permit : 2011.12.3
Unit #1 First Concrete : 2012.7
Commercial Operation :
Unit #1 : 2017.4
Unit #2 : 2018.4
In Progress
Barakah NPP in UAE
•
•
•
•
•
19.4 %
In Progress
PSAR Submit : 2010.12.31
Construction Permit : 2012.7
Unit #2 First Concrete : 2013.5
Unit #1 RV Setting : 2014.7
Commercial Operation : 2017.5
~ 2020.5
10/18
10
3. New Plants under Construction
Shin-Kori 5&6 (APR1400)
•
•
PSAR Submitted for
Construction License : May 2012
Commercial Operation : Unit #5 : 2019
Unit #6 : 2020
Shin-Hanul 3&4 (APR1400)
•
•
Contract Negotiation
Commercial Operation : Unit #5 : 2020
Unit #6 : 2021
11/18
11
3. New Plants under Construction
NPP Construction Schedule
1995
2000
2005
95 / 96
YGN 3&4
98 /99
Ulchin 3&4
01/02
Yonggwang 5&6
Ulchin 5&6
2010
2015
2020
2013. 6
OPR 1000
(Operation)
04/05
2010 / 2011
Shin-Kori 1& 2
2011 / 2012
Shin-Wolsong 1& 2
OPR 1000
(Construction)
2013 / 2014
Shin-Kori 3&4
2017 / 2018
Shin-Ulchin 1&2
2017~ 2020
Braka (UAE) 1,2,3,4
2019 / 2020
Shin-Kori 5&6
2020 / 2021
Shin-Ulchin 3&4
APR 1400
(Construction)
APR 1400
(Planning)
12/18
4. National Plan
National Energy Master Plan (2008~2013)
39 units
In Operation
Installed
Capacity
2030
41%
Generation
Share
59%
New 5&6
APR+
TBD
New 3&4
APR+
TBD
New 1&2
APR+
TBD
SKN 7&8
APR+
2022/2023
SUN 3&4
APR1400
2020/2021
SKN 5&6
APR1400
2018/2019
Future Units
20 units
In Operation
26%
Installed
Capacity
2007
Generation
Share
35%
SUN 1&2
APR1400
2016/2017
SKN 3&4
APR1400
2013/2014
SWN 1&2
OPR1000
2011/2012
SKN 1&2
OPR1000
2010/2011
Units Under Construction
13/18
4. National Plan
National Energy Master Plan Revision (2013~2018)
 The 2nd National Energy Master Plan Development
 Expert Committee review started
 Will be completed in the Second half of 2013
 Challenges
 Post-Fukushima Impact
 Low Gas Price
 Recent CFSI (Counterfeit, Fraudulent, and Suspected Items)
issues with anti-nuclear movement
14/18
4. National Plan
Nuclear Policy of New Government
Key Words from President : Safety First
with Public Trust
Responsible management System
to build up public trust
Top priority to ensure safe operation
of nuclear power plants
Safe nuclear energy as
an important resource
Safety
First
Safe
Energy
Infra.
Public
Trust
15/18
4. National Plan
New National Agenda
 Licensee’s Quality Management System
 Shorten Quality Inspection Interval : 2 years to 1 year
 Increase Inspectors : 5 to 15
 Life Extension of Old Reactors
 Kori unit #1 and Wolsong unit #1
 “Stress Test” based on comprehensive Safety Assessment
 Technical Competency of Regulator
 Periodic evaluation on technical competency
 Develop education and training program
 Government Reorganization
 NSSC under the control of Prime Minister
 9 commissioners (National Assembly designate 4)
16/18
4. National Plan
Changes in Regulatory System
President
President
NSSC
Prime
Minister
NSSC
Prime
Minister
Other
Ministries
MKE
Nuclear
Industry
National
Assembly
MEST
Nuclear
R&D
KINS/KINAC
MKE : Ministry of Knowledge and Economy
MEST : Ministry of Education, Science and
Technology
Other
Ministries
MOTIE
Nuclear
Industry
MSIP
Nuclear
R&D
KINS/KINAC
MOTIE : Ministry of Trade, Industry and Energy
MSIP : Ministry of Science, ICT and
Future Planning
17/18
5. Proposal for Future IAEA Activities
 Global Nuclear Supply Chain Management and Control
 Nuclear Supply Chain becomes Global
 Quality of Nuclear Equipment Starts from Vendors/Subvendors and Material Suppliers
 Quality Control and Inspection Program on each Entities in the
Supply Chain need to be Improved
 Globally Acceptable Guidance on the CFSI Treatment needs to
be developed