Comments
Description
Transcript
• E’n teigjr ~
• E’n ~ Entergy teigjr Entergy Entergy Nuclear Nuclear Operations, Operations, Inc. Inc. Palisades Nuclear Plant 27780 Blue Star Memorial Highway Highway Covert, Covert, MI Ml 49043-9530 49043-9530 Tel 269 7642000 764 2000 Tel 269 Anthony Anthony J. Vitale Vitale Site Vice President Site Vice President PNP 2014-011 PNP February 28, 2014 February Nuclear Regulatory U.S. Nuclear Regulatory Commission u.s. ATTN: Document Control Desk 11555 Rockville Pike Rockville, MD 20852 SUBJECT: Palisades Nuclear Plant Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Palisades Nuclear Plant Docket No. 50-255 License No. DPR-20 REFERENCES: 1. NRC Order Number EA-12-049, EA-1 2-049, Order Modifying Licenses with Regard 1. to Requirements for Mitigation Strategies for 8eyond-Design-8asis Beyond-Design-Basis External Events, dated March 12, 2012 (ADAMS Accession No. 1 2054A736) 12054A736) 2. NRC Interim Staff Guidance JLD-ISG-2012-01, Compliance with Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis 8eyond-Design-8asis External Events, Revision 0, dated August 29, 2012 (ADAMS Accession No. ML12229A174) ML 12229A174) 3. NEI NEI 12-06, 12-06, Diverse and Flexible Coping Strategies (FLEX) implementation Implementation Guide, Revision 0, dated August 2012 (ADAMS Accession 2242A378) Accession No. No. ML1 ML 12242A378) 4. Entergy Nuclear Operations, Inc. Inc. (ENO) letter letter to NRC, NRC, PNP 2012-091, 2012-091, Initial Status Report in Response to March 12, 2012 Commission Order 12,2012 Modifying Licenses with Regard to Requirements for Mitigation Strategies Strategies for Beyond-Design-Basis 8eyond-Design-8asis External Events (Order Number EA-12-049), dated 2012 (ADAMS 25,2012 (ADAMS Accession No. No. dated October October 25, ML1 2300A065 ML 12300A065 5. 5. Entergy Entergy Nuclear Nuclear Operations, Operations, Inc. Inc. (ENO) (ENO) letter letter to to NRC, NRC, PNP PNP 2013-01 2013-010, 0, Overall Overall Integrated Integrated Plan in in Response Response to March March 12, 12,2012 Commission 2012 Commission Order Order Modifying Modifying Licenses Licenses with Regard Regard to to Requirements Requirements for Mitigation Strategies Strategies for Beyond-Design-Basis 8eyond-Design-8asis External External Events Events (Order (Order Number Number EA-12-049), 2013 28,2013 EA-12-049), dated dated February February 28, PNP 2014-011 2014-011 PNP Page 22 of of 22 Page 6. Entergy Entergy Nuclear Nuclear Operation, Operation, Inc. Inc. (ENO) (ENO) letter 6. letter to to NRC, NRC, PNP PNP 2013-064, 201 3-064, Pailsades Nuclear Nuclear Plant Plant First First Six-Month Six-Month Status Status Report Palisades Report in in Response Response to to March 12,2012 Commission Order 12, 2012 Commission Order Modifying Modifying Licenses March Licenses with with Regard Regard to to Requirements for Mitigation Strategies for for Beyond-Design-Basis Beyond-Design-Basis Requirements for Mitigation Strategies External Events Events (Order (Order Number Number EA-12-049), EA- 12-049), dated External dated August 28,2013 28, 2013 Madam: or Madam: Dear Sir or On March 12, 12, 2012, the Nuclear Regulatory Commission Commission (NRC) issued an order (Reference On Nuclear Operations, Inc. Entergy Nuclear Inc. (ENO). Reference 11 was immediately immediately effective and 1) to Entergy directs ENO to develop, implement, and maintain guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities in the event of a beyond-design-basis external event. Reference 11 required submission of an initial status report 60 days following issuance of the the final interim staff guidance (Reference 2) and an overall integrated plan pursuant to Section IV, Condition C. Reference 2 endorses industry guidance document NEI12-06, NEI 12-06, Revision 11 (Reference 3) with clarifications and exceptions identified in Reference 2. Reference 4 provided the Palisades Nuclear Plant (PNP) initial status report regarding mitigation strategies. Reference 5 provided the PNP overall integrated plan. 1 requires submission of a status report at six-month intervals following submittal Reference 1 of the overall integrated plan. Reference 3 provides direction regarding the content of the status reports. Reference 6 provided the first six-month status report. The purpose of this letter is to provide the second six-month status report pursuant to Section IV, Condition C.2, of Reference 1, that delineates progress made in implementing the requirements of Reference 1. The attachment provides an update of milestone accomplishments, including any changes to the compliance method, schedule, or need for relief and the basis, if any. any. This letter contains no new commitments and no revised commitments. II declare under penalty of perjury that the foregoing is true and correct; executed on February 28, 28, 2013. Sincerely, Sincerely, ajv/jse ajv/jse Attachment: Attachment: cc: cc: Palisades Nuclear Nuclear Plant Second Second Six-Month Six-Month Status Report in Response to March March 12, 12, 2012, 2012, Commission Commission Order Modifying Modifying Licenses Licenses with with Regard Regard to Requirements for for Mitigation Mitigation Strategies Strategies for for Beyond-Design-Basis Beyond-Design-Basis External External Events Events (Order (Order Number Number EA-12-049) EA-12-049) Office Office Director, Director, NRR, NRR, USNRC USNRC Administrator, Administrator, Region Region Ill, III, USNRC USNRC Project Project Manager, Manager, Palisades, Palisades, USNRC USNRC Inspector, Resident Palisades, Resident Inspector, Palisades, USNRC USNRC ATTACHMENT ATTACHMENT Palisades Nuclear Nuclear Plant Plant Second Second Six-Month Six-Month Status Report in Status Report Palisades Response to in Response to March 12,2012 12, 2012 Commission Commission Order Order Modifying Modifying Licenses Licenses with March Regard to with Regard to Requirements for Mitigation Mitigation Strategies Strategies for Beyond-Design-Basis Beyond-Design-Basis External Requirements External (Order Number Events (Order Number EA-12-049) EA-1 2-049) Events 11 Introduction (END) developed for Palisades Nuclear Entergy Nuclear Operations, Inc. (ENO) Nuclear Plant Plant (PNP) an overall integrated plan plan (Reference 1), 1), which documented the diverse and flexible strategies in response response to Reference Reference 2. This attachment provides an update of milestone (FLEX), in milestone accomplishments since submittal of the last status report (Reference 3), including any the compliance method, schedule, or need for relief/relaxation and the basis, if changes to the any. Accomplishments 2 Milestone Accomplishments The following milestone(s) have been completed since July 31, 2013, and are current as of 31, 2014. January 31,2014. • First Six-Month Status Report - • Second Six-Month Status Report February 2014 • FLEX Strategy Evaluation - January 2014 — August 2013 — Complete with submission of this document in — 3 Milestone Schedule Status The following provides an update to Attachment 2 of the overall integrated plan. It provides the activity status of each item, and whether the expected completion date has changed. The dates are planning dates subject to change as design and implementation details are developed. • Perlorm Perform Staffing Staffing Analysis The Perform Perform Staffing Analysis milestone milestone completion completion date has been changed to April 2014. This This new new milestone target completion completion date date does does not impact the the Order Order implementation date. date. • Modifications Evaluation Evaluation The The Modifications Evaluation milestone milestone target completion date date has has been been changed changed to to April April 2014. 2014. This This new new milestone target completion date date does does not not impact impact the Order implementation implementation date. date. Page Page 11 of of 10 10 Target Target Completion Completion Date* Date* Activity Activity Status Status 2013 Feb 2013 Feb Complete Complete Update 11 Update Aug 2013 Aug Complete Update 2 Feb 2014 Complete Update 3 Aug 2014 Not Started Started Update 4 Update Feb 2015 Feb Not Started Not Update 5 Aug 2015 Not Started Not FLEX Strategy Evaluation Jan 2014 Complete Perform Staffing Analysis Dec 2013 Started Apr 2014 Jan 2014 Started Apr 2014 N-i Walkdown N-1 Feb 2014 Started Design Engineering May 2014 Started IImplementation mplementation Outage Oct 2015 Not Started Jun 2014 Started Jan 2015 Started Oct 2015 Not Started Milestone Milestone Submit Overall Overall Integrated Integrated Submit Implementation Plan Plan Implementation Revised Target Revised Target Completion Completion Date Date Updates Six-Month Status Updates Modifications Modifications Evaluation Engineering and Implementation On-site FLEX Equipment Purchase and Procure Off-site FLEX Equipment Develop Strategies with RRC Install Off-Site Delivery Station (If Necessary) Procedures Pressurized Water Reactor Owners Group (PWROG) issues Nuclear Nuclear Steam Supply Supply System (NSSS) (NSSS)Specific_Guidelines Specific Guidelines Create PNP FLEX FSG Jun Jun 2013 2013 Complete Complete Mar Mar 2015 Not Started Not Create Create Maintenance Maintenance Procedures Procedures Mar Mar 2015 2015 Not Not Started Develop Develop Training Training Plan Plan Training Training Complete Complete Jun 2015 2015 Jun Sept Sept 2015 2015 Not Started Started Not Not Not Started Started Validation Validation I Demonstration Demonstration Oct Oct 2015 2015 Not Started Started Not Submit Submit Completion Completion Report Report Oct Oct 2015 2015 Not Not Started Started Training Training *Target "Target Completion Completion Date Date is is the the last last submitted submitted date date from from either either the the overall overall integrated integrated plan plan or or previous previous six-month six-month status status reports reports Page Page 22 of of 10 10 Changes to Compliance Compliance Method Method 4 Changes The following changes changes are are being being incorporated incorporated to FLEX strategy The to the FLEX strategy for for PNP. PNP. 1. Overall Overall Integrated Integrated Plan Plan (OIP) (OIP) page page 9, 9, item item 33 (and (and other 1. other locations locations of DIP) states of OIP) states the the battery life four will be hours. The four hour be four hours. hour battery battery capacity battery life will capacity was determined determined to to provide insufficient insufficient margin margin for transition to Phase Phase 2. 2. Based provide Based on on analysis and and planning planning load shed, the installed installed battery battery capacity will be for a deeper load be extended to eight hours hours Open Item Item 016). 016). Therefore, the time time at at which a portable FLEX (see Open FLEX generator is required to be deployed and operational has has been extended from hour 4 to hour 8 required based on battery capacity. 10, item item 9 (and other locations of DIP) stated that LC-19 will be 2. OIP page 10, be repowered FLEX generator. This remains the primary from the portable FLEX primary strategy to provide power to battery chargers. However, Load Center 20 will also be modified similar to Load Center 19 to provide diverse connection locations to the battery chargers. QIP page 11, item 10 (and other locations of OIP) stated that a FLEX portable 3. OIP transfer pump will be used to refill the CST. The Phase 2 core cooling strategy has changed such that the CST refill will not be used. Instead inventory for feeding the steam generators will be provided by the FLEX portable transfer pump directly to the main feed water (MFW) system piping or the auxiliary feed water (AFW) system piping via hose connections, thereby bypassing the CST. DIP page 11, item 10 (and other locations of OIP) DIP) requires commencement of 4. OIP deployment of a portable FLEX pump two hours after the event such that it can be operational four hours after the event. This was based on the limited protected inventory of the condensate storage tank (CST) and the primary system makeup storage tank (T-81). Additional inventory in the CST and T-81 will now be protected (see Open Item 013) which increases the volume available for Phase 1 1 of the beyond-design-basis external event (BDBEE). Therefore, the time at which the FLEX pump is required to be deployed and operational has been delayed from hour 4 to hour 8 based on CST and T-81 protected inventory. Additionally, the strategy of refilling the CST has changed such that the CST refill will not be used. used. Instead inventory for feeding the steam generators will be provided directly to the main feed water (MFW) (MFW) system piping or the auxiliary feed water (AFW) system piping via hose connections, thereby bypassing the CST CST (see Open Item 017). 5. DIP locations of OIP page page 11, 11, item 14 14 (and other other locations of DIP) OIP) credits the battery room exhaust exhaust fans for removal removal of hydrogen hydrogen from the battery rooms. ItIt has has been been determined that the the battery battery room exhaust exhaust fans fans are are not not robust robust and and cannot be be credited. credited. Therefore Therefore aa new strategy developed developed for control of hydrogen hydrogen will will employ employ the use use of portable portable fans for ventilation in in battery rooms. Also see Open Open Item Item 018. 018. 6. 6. OIP OIP page page 11, 11, item item 15 15 (and (and other other locations locations of of DIP) DIP) credits the the volume volume control control tank tank (VCT) and injection safety refueling water tank (VCT) and safety injection refueling water tank (SIRWT) (SIRWT) as as borated borated sources sources of of water water for for primary primary coolant coolant system system (PCS) (PCS) inventory inventory and and reactivity reactivity control. control. However, However, itit has has been been determined determined that that the the VCT VCT and and SIRWT SIRWT are are not not robust robust for for all all applicable applicable external external hazards. hazards. Therefore Therefore the the VCT VCT and and SIRWT SIRWT are are no no longer longer the the credited credited sources sources of of borated borated water. water. Concentrated Concentrated boric boric acid acid storage storage tanks tanks (T-53A (T-53A and and T-53B) T-53B) will will now now be be credited in Phase Phase 2. 2. Later Later in in credited as as the the borated borated water water sources sources for for these these functions functions early early in Page 10 Page 33 of of 10 Phase 22 (> the boric (>24 hours), the boric acid acid batching batching tank tank (T-77) (T-77) will Phase 24 hours), will be be used batch used to to batch required borated inventory. Also borated water water inventory. Also see see Open Open Item Item 0116. required 0116. 7. 01 page 12, 12, item item 16 DIP states that 16 states fuel pool that spent spent fuel pool (SFP) (SFP) equipment equipment (hoses 7. P page (hoses and and monitor monitor nozzles) will will be deployed at be deployed at hour hour 18 prevent SFP 18 to to prevent from dropping SEP level level from nozzles) dropping below below the the of 15 15 feet feet above level of the fuel fuel at above the 20.93. Under at hour hour 20.93. Under worst case level conditions it is case conditions it is estimated that that boiling could occur boiling could beginning at occur beginning at approximately approximately 5.6 estimated 5.6 hours. hours. Therefore Therefore operators would would be required to be required SFP area to enter enter the the SFP area under under potentially operators potentially onerous onerous order to protect in order protect personnel personnel from the need conditions. ItIt was determined that in need to enter enter boiling that actions should be the SFP area after itit is already boiling be taken taken for deployment deployment of cooling equipment SEP cooling equipment (hoses and and monitor nozzles) nozzles) prior prior to the start of boiling. The SFP approximately five hours after event initiation and prior to action will now be taken at approximately SEP boiling in order to mitigate potential habitability concerns after SFP after boiling. mobile water purification 8. OIP page 12, item 21 (and other locations of OIP) credit a mobile unit (and/or other large regional response center (RRC) equipment) 24 hours after the event. This timing was determined to be unlikely and unsupported by by the RRC for large equipment such as purification units, units, 4160 V diesel generators, and boration large units. Therefore the purification units will not be credited until 72 hours after the event. 9. OIP page 18, in the section for PWR Installed Equipment Phase 1, it is stated that the turbine driven auxiliary feedwater (TDAFW) pump is not credited for seismic events because the turbine driver is not seismically qualified. The TDAFW TDAEW system (including the turbine driver) has now been qualified as seismically robust and is credited for all external events. See Open Item 015 in this report for additional information. DIP page 19, under Steam Generators Available for Cooling (Modes 1-4), states that 10. OIP a modification will be required to provide for remote manual operation of the ADVs to begin cooling down the plant at hour 2. The modification selected, and which will allow for the remote manual operation of the ADVs, is the installation of backup 1 and connection point for an air compressor to nitrogen bottles to last through Phase 1 be connected for Phase 2. 11. OIP page 19, under Key Reactor parameters (and other locations of DIP) 11. OIP) the level indications for tank T-81 and SIRWT are credited. Because the CST and T-81 are cross-tied, it has been been determined that the level indication for the CST is sufficient to indicate the available inventory in in both both tanks. Therefore level indication for T-81 is redundant and and is not required. SIRWT level indication is not not required because the tank is no longer credited. 12. 12. DIP OIP page 62 (and other locations of DIP) OIP) states use of multiple ELEX FLEX generators. PNP PNP has has determined that that itit is is preferable preferable to to use use only one one FLEX generator generator in in the PNP PNP strategy. strategy. This This FLEX FLEX generator generator will will be sufficiently sufficiently sized sized to carry all all the the loads loads that are are planned planned for use in the FLEX strategy. 13. 13. During During analysis analysis of site site seismic capabilities capabilities itit was was determined determined that that PNP is is susceptible susceptible to to soil soil liquefaction. liquefaction. Therefore Therefore new new storage storage locations locations are are being being developed developed and and Attachment will be 3 of DIP updated for storage, Attachment 3 of OIP will be updated for storage, staging staging and and routing. routing. Also Also see see Open Open Item Item OIl. 011. Page Page 44 of of 10 10 5 Need for Relief/Relaxation and Basis for the Relief/Relaxation implementation date and no ENO expects to comply with the order implementation no relief/relaxation is required required at this time. 6 Open Items from Overall Integrated Plan and Interim Staff Evaluation The following tables provide a summary and status of any open items documented in the integrated plan and any open items or confirmatory items documented in Interim overall integrated Interim Staff Evaluation (ISE). A fourth table includes a listing of audit questions and the status of each item. Overall Integrated Plan Open Item Dli. Perform analysis on Palisades' Palisades’ 011. susceptibility to soil liquefaction and potential consequences on the FLEX implementation plan. Status Started Preliminary borings were performed on site soil liquefaction susceptibility was and soi/liquefaction identified. Based on this information a set of FLEX equipment will be stored inside the protected area (PA) for the seismic event. The other set of FLEX equipment will be stored outside of the PA and be protected against the tornado event. Both locations will be protected from all other BDBEEs. Additional planning is under way to address other impacts to equipment storage and deployment. See also Change to Compliance Method Item 13. 012. Develop Phase 3 deployment strategy with correspondence with the RRC. Started 013. Evaluate the need to missile protect primary system makeup storage tank (T-81) and other external tanks. Started 014. Select the location of FLEX equipment storage facility. The CST volume alone is insufficient to provide the required inventory, when considering available on site resources for SG makeup during Phase 1. Additional inventory is required and can be provided by tank T-81. T-81 will be verified/credited as robust for all applicable external events. As required, modifications will be implemented to protect both the CST and primary system makeup tank for all applicable external events. See also Change to Compliance Method Item 4. Started Refer to Cli. 011. One set of equipment will be stored in Sea-Land containers inside the PA for the Seismic event. An additional set(s) of equipment will be stored outside the PA in a structure(s) providing an an appropriate level level of protection for the tornado tornado event. event. Both Both sets will be be protected against the other applicable (screened-in) BDBEE external hazards. Page 5 of 10 10 Overall Integrated Integrated Plan Plan Open Item Open Item Overall 015. Perform Perform seismic seismic evaluation evaluation of of turbineturbine015. driven auxiliary auxiliary feedwater feedwater pump pump (TDAFWP) (TDAFWP) driven driver K-8. K-8. driver 016. Evaluate strategies to extend battery coping time. 017. Evaluate sources of non-borated water in addition to condensate storage tank (T-2) T81. and T-81. 018. Palisades Probabilistic Risk Assessment (PRA) to provide justification why battery room ventilation is not required until 24 hours. 019. 019. Evaluate Evaluate the effects effects of FLEX on on security security procedures. 0110. 0110. Evaluate Evaluate requirements requirements of of mobile mobile purification purification unit unit from from RRC. RRC. Status Status Started Started Seismic evaluation Seismic evaluation documents documents the the seismic seismic qualification of qualification the pump and associated of the pump and associated components. The components. The TDAFW TDAFW pump pump is is qualified qualified the exception exception of an with the an outlier outlier related related to aa check for bolt bolt tightness. Bolt Bolt tightness on the pump is being performed performed under WO# W0# 372138 and documented 46465. documented under under EC EC See also Change to Compliance Method Method Item 9. Item Started The battery load shedding strategy is currently being revised to extend the battery coping time through shedding loads in addition to those identified in the station blackout procedure. Preliminary results indicate a coping time of at least 8 hours for the installed batteries accompanying the expected deep load shed list. See also Change to Compliance Method Item 1. Complete/Closed After depletion of T-2 and T-81 T-81,, makeup to the SGs will be from a portable pump with the credited suction source being Lake Michigan. Modifications to credit sources of non-borated water for sources other than T-2 and T-81 were determined to not be required. Complete/Closed Palisades PRA provided multiple evaluations for battery room hydrogen generation. It was determined that supplemental ventilation is required approximately 1.5 1.5 hours after charging begins for removal of hydrogen. Ventilation is not required for Phase 22 temperature control. This supplemental ventilation has been included in the included in Palisades Palisades strategy. See See also also Change to Compliance Method Item Item 5. Started The The security plan/program will be be updated updated to correspond correspond to to FLEX FLEX procedures. procedures. Complete/Closed Complete/Closed ItIt was was determined determined that that the the 250 250 gpm gpm RRC RRC demineralized demineralized water water treatment treatment unit unit is is preferred preferred over over the the 100 100 gpm gpm RRC RRC reverse reverse osmosis in order order to to support support SG SG makeup makeup osmosis unit unit in and and provide provide makeup makeup to to the the RRC RRC mobile mobile Page Page 66 of of 10 10 Overall Integrated Plan Plan Open Item Status Status boration unit. 011 1. Evaluate requirements of mobile mobile 0111. boration unit from RRC. Complete/Closed The required flow rate of borated water for PNP is aa maximum of 58.3 gpm. methods of of venting the fuel 0112. Evaluate methods handling building. 0113. Evaluate the use of high-efficiency LED lighting. 0114. Perform evaluation to determine if additional parameters will need to be activities, monitored during FLEX activities. 0115. Perform analysis to ensure survivability of containment. 0116. Evaluate borated water sources in addition to safety injection refueling water tank (SIRWT). Complete/Closed The strategy for venting the fuel handling building will be to open an existing double leaf door/hatch on the roof of the building. Complete/Closed The use of high-efficiency LED lighting has been evaluated for its impact to battery coping time and control room heat loads. LED lighting would have minimal impact and is not required or recommended. Complete/Closed In addition to NE112-06, NEI 12-06, PWROG FLEX guidance was reviewed for key parameter monitoring. The NE112-06 NEI 12-06 and PWROG guidance regarding recommended instrumentation has been incorporated into . the FLEX strategy and the power supply for these instruments evaluated. All the credited instruments are powered by battery/DC buses and available throughout the event. Started Containment analysis has been completed using the Modular Accident Analysis Program (MAAP) and is being reviewed for owner’s acceptance. Preliminary results of owner's this analysis show containment design parameters will not be exceeded for the at-power scenario (Le., (i.e., event initiating in Mode 1). For the most conservative (i.e., Mode 5 reduced shutdown scenario (Le., inventory), preliminary results of the analysis show that actions will be required to prevent exceeding the design limits of containment. Complete/Closed All additional sources of borated water were evaluated for use following a BDBEE. The concentrated boric acid storage tanks (T-53A and T-53B) T -53 B) are the credited source of borated water. These tanks are analyzed to provide sufficient borated water for greater than 24 hours. After 24 24 hours, borated water will be batched as necessary for inventory inventory control using using the boric acid batching tank T-77. See also Change to Compliance Compliance Page 7 of 10 10 Plan Open Item Item Overall Integrated Plan 0117. Entergy, for the Palisades site, will negotiate and execute a contract with Strategic Alliance for FLEX Emergency Response (SAFER) that will meet the requirements of NEI 12-06, Section 12. 0118. Evaluate a location to install a tee in the service water system to allow the ultimate heat sink (UHS) FLEX pump to provide cooling, cooling. 0119. Evaluate the use of lake water to cool the steam generators during an extended loss of ac power (ELAP). 0120. Evaluate time until primary coolant system (PCS) makeup is necessary in Modes 5 & 6. 5&6. 0121. Evaluate connection to ensure cooling water can be provided for containment air fans. 0122. Evaluate the robustness of the charging pumps. Status Method Item 6. Complete Complete/Closed Several locations in the service water system were evaluated. A pipe elbow downstream of service water system (SWS) pump P-7C was identified as the best location for connecting a pipe tee to allow flow from the RRC UHS pump. Started An analysis has been completed and is being reviewed for owner's owner’s acceptance that determines the impacts on the steam generators when using lake water as the makeup source. Complete/Closed An evaluation was performed that documented the time until PCS makeup is required in shutdown modes. The time when makeup is required varies greatly depending on the status of the PCS when the event (i.e., PCS level, pressure, and occurs (Le., temperature). The most limiting scenario was found to be such that PCS makeup could be required as early as one hour after the event if the PCS is vented and at reduced inventory. High risk evolutions such as vented PCS and reduced inventory will be managed by outage risk planning and contingency actions such as pre-staging equipment as discussed in the NRC endorsed white paper on Shutdown / Refueling Modes. Complete/Closed Cooling water flow to the containment air tans fans is through the service water system addressed in the status update to Cl 01 18. 18. Connection of the RRC supplied FLEX UHS pump to the SWS will provide the necessary means/connection for cooling water flow to the containment air coolers. Complete/Closed The charging pumps have have been evaluated as robust for seismic events. The The pumps pumps are Page 88 of 10 10 Overall Integrated Plan Open Item Status located inside the auxiliary building and protected against all other external hazards. hazards. Interim Staff Evaluation Open Items The U.S. Nuclear Regulatory Commission (NRC) has not issued an Interim Staff Evaluation for Palisades; therefore, there are no open items for the Interim Staff Evaluation identified at this time Interim Staff Evaluation Confirmatory Items The NRC has not issued an Interim Staff Evaluation for Palisades; therefore, there are no confirmatory items from the Interim Staff Evaluation identified at this time Audit Question Open Items PAL-002 PAL-003 PAL-004 PAL-007 PAL-008 PAL-Oil PAL-011 PAL-012 PAL-013 PAL-0l4 PAL-014 PAL-015 PAL-O16 PAL-016 PAL-0l7 PAL-017 PAL-0i8 PAL-018 PAL-019 PAL-020 PAL-021 PAL-022 PAL-O23 PAL-023 PAL-024 PAL-025 PAL-026 PAL-027 PAL-028 PAL-030 PAL-033 PAL-035 PAL-O36 PAL-036 PAL-037 PAL-039 PAL-039 PAL-04O PAL-040 PAL-041 PAL-043 Status Closed Closed Closed In progress In progress In progress In progress In progress In progress Closed In progress In progress In progress In progress Closed In progress Complete In progress Closed In progress progress In In progress In In progress In progress In progress In progress In In progress In In progress In progress In Closed Closed In In progress Closed In In progress Page 99 of of 10 10 Status N/A Status NIIA N//A Completion or Target Date Aug Aug Aug Aug Aug Aug 2014 2014 2014 2014 2014 2014 Aug 2014 Oct 2015 Oct2015 Aug 2014 Aug 2014 Aug 2014 e-Portal updated Aug 2014 Aug 2014 2014 Aug 2014 Aug 2014 Aug 2014 Aug 2014 Aug 2014 Aug 2014 Oct 2015 2014 Aug 2014 Oct Oct 2015 Aug 2014 . Audit Question Open Items Question Open Items Audit PAL-044 PAL-044 PAL-045 PAL-04S PAL-046 PAL-046 PAL-047 PAL-04? PAL-048 PAL-048 PAL-049 PAL-049 PAL-050 PAL-OSO PAL-051 PAL-OS 1 PAL-053 PAL-OS3 PAL-054 PAL-OS4 PAL-055 PAL-OSS PAL-057 PAL-OS? PAL-057 PAL-OS? 7 Status Status progress In progress In progress In progress In progress In progress In progress In progress In progress In progress In progress In progress In progress In progress In progress In progress In In progress In progress In progress In Closed In progress In In progress Completion or Completion or Target Target Date Date Aug Aug 2014 2014 Aug Aug 2014 2014 Aug Aug 2014 2014 Aug 2014 2014 Aug Aug 2014 2014 Aug Aug 2014 2014 Aug Aug 2014 2014 Aug 2014 Aug 2014 Aug 2014 Aug 2014 Aug 2014 Potential Interim Staff Evaluation Impacts The NRC has not yet issued an interim staff evaluation for PNP; therefore, there are no potential impacts to the interim staff evaluation identified at this time. S8 References The following references support the updates to the Overall Integrated Plan described in this attachment. 1. Entergy Nuclear Operations, Inc. (ENO) letter to NRC, PNP 2013-010, 2013-01 0, Overall 12, 2012 Commission Order Modifying Licenses Integrated Plan in Response to March 12,2012 with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), dated February 28,2013 28, 2013 2. NRC Order Number EA-12-049, EA-1 2-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, dated ML12054A736). March 12, 2012 (ADAMS Accession No. ML 120S4A?36). 3. Entergy Nuclear Operation, Inc. (ENO) letter to NRC, PNP 2013-064, Palisades Nuclear Plant First Six-Month Status Report in Response to March 12, 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), dated August 28, 2013. Page Page 10 10 of of 10 10