...

VC Summer Unit 2/3 Update | NUCLEAR  Alan Torres

by user

on
Category: Documents
26

views

Report

Comments

Transcript

VC Summer Unit 2/3 Update | NUCLEAR  Alan Torres
NUCLEAR | South Carolina’s Clean Energy Solution
VC Summer Unit 2/3 Update
Alan Torres
New Nuclear Deployment
SCANA/South Carolina Electric & Gas
NND Site Aerial View
Cooling Towers
Contractor Support Personnel
HLD
MAB
Unit 3
Unit 2
CV Assembly
Storage
Turbine Building
First Quarter 2014 | Earnings Conference Call
2
Unit 2 Module CA‐20
• Module CA‐20 is the Auxiliary Building and Fuel Handling area
• On hook date is May 2014
3
| Unit 2 Nuclear Island Concrete Placement
Unit 2 Nuclear Island
Inside Unit 2 Containment Vessel
Aux Building
77
Unit 3 Nuclear Island
CR‐10 module
8
| New Nuclear ProjectNew Nuclear Project
U3 Containment Vessel Bottom Head
U2 CWS Pump House Excavation
U2/U3 Containment Vessel Rings Offsite Water Treatment
9
Turbine Building Layout
Condenser A Condenser B CH‐81A
Condenser C
CH‐81C
CH‐81B
CH‐80
CH‐82
WaterBoxes
10
U2 Turbine Building
CH81A
CH81B CH80
CH82
Condenser A
Condenser B
Condenser C
11
Components Arriving on Site
Unit 2 Aux Transformers
Unit 2 Integrated Head Package
Unit 2 Diesel Generators
12
12
Upcoming 2014 Construction Milestones
Unit 2
Nuclear Island
• Set Structural Module CA20—Auxiliary Building & Fuel Handling area
• Place Concrete in CA20
• Fabricate and Set CA05—CVS / Access Tunnel / PXS‐B Walls
• Fabricate and Set CA01—Steam Generator and Refueling Canal • Fabricate and Set CA02 —IRWST / Pressurizer Wall • Fabricate and Set CA03 —IRWST Southwest Walls • Set First‐Floor Mechanical Modules
• Start Shield Building
Turbine Building
• Complete Condenser component installation
• Complete foundation at Elevation 100’0”
• Start First‐Bay foundation
13
Upcoming 2014 Construction Milestones
CA20
CVBH
CA04
CA05
CA Modules in Nuclear Island
14
Upcoming 2014 Construction Milestones
CA Modules Inside Containment
15
Upcoming 2014 Construction Milestones
First Quarter 2014 | Earnings Conference Call
Unit 2 Auxiliary Building First Floor Mechanical Modules
16
Upcoming 2014 Construction Milestones
Unit 3
Nuclear Island
• Set Containment Vessel Bottom Head (CVBH)
• Grout CVBH
• Place first level of concrete in CVBH
• Fabricate and Set CA04—Reactor Vessel Cavity
• Place Auxiliary Building walls – A2 Elevation (66’6”‐82’6”)
Turbine Building
• Complete Backfill
• Install 82’6” basement foundation and walls
• Fabricate and install Condenser components
• Install CH Structural Steel modules
First Quarter 2014 | Earnings Conference Call
17
Doosan Manufacturing Update
Unit 2 RV‐Ready to Ship
Hydro test Complete for Unit 2A SG
Upper internal welding of Final Vessel for Unit 2B SG
18
Mangiarotti Manufacturing Update
CMT – Unit 3 Upper Pedals
CMT – Unit 2 Tanks 1 & 2
ACC – Unit 2 – Tanks 1 & 2
ACC – Unit 3 ‐ Tank 2 – Shell to Lower Crown
19
Toshiba, Keihin ‐ Japan
Generator Rotor
Low Pressure “A” Turbine
Low Pressure “B” Turbine –
Prep for Blade Assembly
20
Questions
Fly UP