February 18, 2016 Larry Friedman, Quality Assurance Manager Electroswitch Corporation
February 18, 2016
Larry Friedman, Quality Assurance Manager
Electroswitch Corporation
180 King Avenue
Weymouth, MA 02188
SUBJECT:
VENDOR INSPECTION OF ELECTROSWITCH CORPORATION
Dear Mr. Friedman:
This letter documents the U.S. Nuclear Regulatory Commission (NRC) staff’s plan to perform an
inspection of Electroswitch Corporation to review implementation of your quality assurance
program in accordance with Title 10 of the Code of Federal Regulations (10 CFR) Part 50,
Appendix B and 10 CFR Part 21. Specifically, the quality assurance program and Part 21
implementation, will be reviewed as they pertain to Electroswitch’s design, qualification,
commercial grade dedication, and manufacturing of safety related power switches and relays to
operating nuclear power plants. As discussed through conference call on February 17, 2016,
the inspectors plan to arrive at the Weymouth, MA facility, on Monday, April 25, 2016, and will
conduct the inspection through Friday, April 29, 2016. Subsequent to the inspection, a report
will be issued and transmitted to you via letter. The lead inspector for this effort is Eugene
Huang; you may contact him at 301-415-4140 or via electronic mail at [email protected].
This inspection activity has been assigned the following docket number: 99900833. Please
reference this number on any correspondence relating to this inspection activity sent to the
NRC.
Sincerely,
/RA/
Terry Jackson, Chief
Quality Vendor Inspection Branch-1
Division of Construction Inspection
and Operational Programs
Office of New Reactors
Docket No.: 99900833
Larry Friedman, Quality Assurance Manager
Electroswitch Corporation
180 King Avenue
Weymouth, MA 02188
SUBJECT:
VENDOR INSPECTION OF ELECTROSWITCH CORPORATION
Dear Mr. Friedman:
This letter documents the U.S. Nuclear Regulatory Commission (NRC) staff’s plan to perform an
inspection of Electroswitch Corporation to review implementation of your quality assurance
program in accordance with Title 10 of the Code of Federal Regulations (10 CFR) Part 50,
Appendix B and 10 CFR Part 21. Specifically, the quality assurance program and Part 21
implementation, will be reviewed as they pertain to Electroswitch’s design, qualification,
commercial grade dedication, and manufacturing of safety related power switches and relays to
operating nuclear power plants. As discussed through conference call on February 17, 2016,
the inspectors plan to arrive at the Weymouth, MA facility, on Monday, April 25, 2016, and will
conduct the inspection through Friday, April 29, 2016. Subsequent to the inspection, a report
will be issued and transmitted to you via letter. The lead inspector for this effort is Eugene
Huang; you may contact him at 301-415-4140 or via electronic mail at [email protected].
This inspection activity has been assigned the following docket number: 99900833. Please
reference this number on any correspondence relating to this inspection activity sent to the
NRC.
Sincerely,
/RA/
Terry Jackson, Chief
Quality Vendor Inspection Branch-1
Division of Construction Inspection
and Operational Programs
Office of New Reactors
Docket No.: 99900833
DISTRIBUTION:
ASakadales
ADAMS ACCESSION No.: ML16049A103
NRO-002
NRO/DCIP/QVIB-1
OFFICE NRO/DCIP/QVIB-1
EHuang
TJackson
NAME
02/18/16
02/18/16
DATE
OFFICIAL RECORD COPY