Comments
Description
Transcript
Document 1757469
TABLE OF CONTENTS Page No. Introduction ...........................................................................................................................................1 Previous Studies....................................................................................................................................1 Willamette Queen Sternwheeler ......................................................................................................2 Union Street Railroad Bridge ............................................................................................................2 Hydraulics..............................................................................................................................................2 Pedestrian Bridge Design Criteria....................................................................................................4 Existing Site Conditions .......................................................................................................................4 Environmental Issues.............................................................................................................................4 Hazardous Materials Issues................................................................................................................5 Land Use................................................................................................................................................6 Right-of-Way .......................................................................................................................................6 Utilities....................................................................................................................................................7 Temporary Construction Access .........................................................................................................7 Bridge Alternatives..............................................................................................................................7 Estimate Project Schedule...................................................................................................................9 Estimated Project Costs .................................................................................................................... 10 Conclusions ......................................................................................................................................... 10 TABLE Table 1 – Estimated Project Costs FIGURES Figure No. Vicinity Map..........................................................................................................................................1 Bridge Alternative Plans and Elevations.....................................................................................2–9 RENDERINGS Bridge Alternative Elevations APPENDICES Appendix A – Hydraulic Data Appendix B – Historic Cost Data Appendix C – Estimated Design and Construction Schedule PRELIMINARY CONCEPT STUDY Minto Brown Island Pedestrian/ Bicycle Bridge City of Salem, Oregon Introduction The City of Salem is very interested in constructing a pedestrian bridge connection from downtown Salem and Riverfront Park to Minto Brown Island. Riverfront Park is a 23-acre park that offers many park amenities to downtown Salem. Minto Brown Island Park, with an area of 898.9 acres, has an extensive system of nature, pedestrian, and bicycle trails. These trails could connect directly to Riverfront Park and downtown Salem by way of a new pedestrian bridge that would complete a loop in the trail system and open up significant recreational opportunities that neither park can offer separately. Currently, the only access to Minto Brown Island is River Road, a 45-mile-per-hour minor arterial several miles to the south; it lacks complete sidewalks and bicycle lane. The proposed bridge would span Willamette Slough between Riverfront Park and Minto Brown Island just downstream from the confluence of Willamette Slough and Pringle Creek. The location of the proposed bridge, at River Mile 84.5, is also very near the confluence of the Willamette Slough and the Willamette River, as shown in Figure 1. The City of Salem (City) has retained OBEC Consulting Engineers to study preliminary bridge concepts for this project. The City has requested alternatives including long and short bridge spans as well as high- and low-level crossings. The alternatives are being considered due to navigation and hydraulic constraints as well as concerns about permitting the construction of permanent bridge foundations below the ordinary high water elevation of Willamette Slough. The various alternatives can be defined as follows: • • • • Alternative H-1: High-level pedestrian bridge clear-spanning Willamette Slough that provides navigation clearance for the Willamette Queen Sternwheeler Alternative H-2: High-level pedestrian bridge spanning Willamette Slough with in-water piers that provides navigational clearance for the Willamette Queen Sternwheeler Alternative L-1: Low-level pedestrian bridge clear-spanning Willamette Slough that provides clearance for smaller recreational boating and 100-year high water Alternative L-2: Low-level pedestrian bridge spanning Willamette Slough with in-water piers that provides clearance for smaller recreational boating and 100-year high water Previous Studies In 2006, the City studied four lower-level bridge crossing concepts to span the Willamette Slough at the site. In all cases the proposed concepts did not clear-span Willamette Slough or accommodate the Willamette Queen Sternwheeler, which uses the slough in the winter. The study indicated that obtaining a U.S. Coast Guard (USCG) permit for these low-level crossing concepts would be very challenging. One of the purposes of this study is to define in more detail the high Preliminary Concept Study Minto Brown Island Pedestrian/Bicycle Bridge City of Salem, Oregon OBEC Job No. 298-7 Page 1 level bridge alternatives; and the hydraulic, permitting, and scheduling issues not addressed in the previous report. Willamette Queen Sternwheeler Currently, the Willamette Queen uses Willamette Slough for excursions only during the winter when adequate water flow in the Willamette River allows backwater into the slough. The following information regarding the sternwheeler was provided by the City for use in this study: • • • Minimum Draft – 3.5 feet Minimum river flow to use Willamette Slough – 20,000 cubic feet/second (cfs) in main stem Willamette River Sternwheeler height above water with stacks raised – 38 feet; height above water with stacks lowered – 33 feet The bottom of the high-level crossing will be set to accommodate the sternwheeler at most average winter flows. This is discussed in more detail in the hydraulic section of this study. Union Street Railroad (RR) Pedestrian/Bicycle Bridge The former Union Pacific RR Bridge, located downstream from the proposed pedestrian bridge at River Mile 83.9, is currently being modified by the City into a pedestrian/bicycle bridge. The lift span of the existing bridge is not in operation, and the current project will permanently modify the bridge into a fixed span structure. The USCG permit for this project indicates that the bottom of the bridge in the main channel is at Elev. 150.9, which corresponds to the bridge modification design drawings corrected to USCG, U.S. Army Corps of Engineers (ACOE), and Federal Emergency Management Agency (FEMA) flood data datum (NAV 1929). Assuming 34 feet for clearance under the Union Street Pedestrian/Bicycle RR Bridge (low stack plus 1 foot clearance), the maximum water surface elevation for the sternwheeler to pass under the bridge is Elev. 116.9, corresponding approximately to a flow of 34,000 cfs in the river. For higher flows, the sternwheeler probably cannot pass under the bridge. Hydraulics River hydraulic conditions at the site are reasonably well defined. The proposed bridge site is located at River Mile 84.5. River gage 14191000 is located at River Mile 84.1, between the proposed bridge site and the Union Street Pedestrian/Bicycle RR bridge. The gage has been in continuous operation since 1923, and gage information provides the following hydraulics data at the gage, proposed bridge site, and Union Street Pedestrian/Bicycle RR bridge: Preliminary Concept Study Minto Brown Island Pedestrian/Bicycle Bridge City of Salem, Oregon OBEC Job No. 298-7 Page 2 Interval Approx. 1.2 years 10 years 50 years 100 years 20,000 30,000 40,000 50,000 60,000 70,000 80,000 90,000 Water Surface Elev. at M-B Island Site 116.0 116.9 119.3 121.6 123.6 124.9 125.3 127.9 100,000 129.1 128.6 128.2 163,000 232,000 269,000 136.9 141.7 143.7 136.4 141.2 142.9 136.0 140.8 142.0 River Flow (cfs) Water Surface Elev. at Gage WS Elev. at Union St. RR Bridge 115.5 116.4 118.8 121.1 123.1 124.4 125.8 127.4 115.1 116.0 118.4 120.7 122.7 124.0 125.4 127.0 In addition, USGS has created an average water daily statistics for this gage. Mean flows were recorded for each month over a 55-year period. This information assists in setting the bottom elevation of the high-level bridge crossing based on the months of operation for the sternwheeler. Month January February March April May June July August September October November December Mean River Flow (cfs) 51,000 41,000 32,000 25,000 21,000 15,000 8,000 7,000 9,000 12,900 31,400 48,000 At this time, the bottom of the proposed bridge for the higher-level crossing, Alternatives H-1 and H-2, has been set at Elev. 156.0. This elevation provides 34 feet of clearance (low stack plus 1 foot clearance) under the new pedestrian bridge. The maximum water surface elevation for the sternwheeler to pass under the bridge is assumed to be Elev. 122.0 for the purposes of this study, corresponding to approximately 50,000 cfs flow in the river. It is evident from the information provided in the above table that the sternwheeler excursions on the Willamette Slough could occur during the majority of wintertime. In the bridge construction cost estimates, an approximate change in cost is provided for each foot that the main span of the bridge is lowered or raised from the assumed navigational clearance requirements. Preliminary Concept Study Minto Brown Island Pedestrian/Bicycle Bridge City of Salem, Oregon OBEC Job No. 298-7 Page 3 The proposed bridge is located in the floodway of the Willamette River. The bottom of the main span for the lower-level crossings, Alternatives L-1 and L-2, has conservatively been placed at the 100-year base flood Elev. 143.7. The piers and approach slabs are below the 100-year flood, as are the banks of Riverfront Park and almost all of Minto Brown Island. The effects this project would have on flood conveyance and loss of floodwater storage would be determined in a detailed hydraulic and "no rise" analysis performed during the project final design. Results from the detailed analysis may indicate that the main span can be lowered; however, the current assumed bottom elevation of the main span is conservative. Again, in the bridge construction cost estimates an approximate change in cost is provided for each foot that the main span of the bridge is lowered or raised from the assumed hydraulic clearance requirements. Relevant hydraulic data is contained in Appendix A. Pedestrian Bridge Design Criteria The bicycle/pedestrian bridge design will conform to the current American Association of State Highway and Transportation Officials (AASHTO) Guide Specifications for the Design of Pedestrian Bridges and the LRFD Bridge Design Specifications. Geometric design criteria for the bridge will conform to AASHTO Guide for the Development of Bicycle Facilities and ODOT Oregon Bicycle and Pedestrian Plan. Bridge grades conform to the Americans with Disabilities Act (ADA), and maximum continuous grades of 5 percent are used on the approach spans to the bridge. Based on these references, a 14-foot rail-to-rail bridge deck width is desirable and a 12-footwide deck is the minimum acceptable standard. Since the funding for the project may be limited, bridge construction cost estimates are provided for both the 14- and 12-foot widths for comparison. Existing Site Conditions The proposed bridge crosses Willamette Slough at approximately right angles from Riverfront Park to an existing berm that will carry the approach trail from the west end of the bridge. The east end of the bridge is located in the developed Riverfront Park. For both the high and low bridge alternatives, the east bridge approach will pass over the path along the top of bank. In the case of the low-level crossing, minimal vertical clearance would be provided. The path may have to be depressed as it passes under the bridge approach spans, and any such lowering of the path will need to be minimized when considering the final bridge elevations. Lowering of the path more than 4 feet in Riverfront Park will create serious environmental issues due to buried hazardous materials that have been capped in this location; these issues will impact the project costs and schedule. Environmental Issues Environmental issues for the project include work in and on Willamette Slough and Minto Brown Island. The Willamette River and the Willamette Slough provide habitat for steelhead trout, and Chinook and Coho salmon. Chinook salmon and steelhead trout are listed as threatened under Preliminary Concept Study Minto Brown Island Pedestrian/Bicycle Bridge City of Salem, Oregon OBEC Job No. 298-7 Page 4 the federal Endangered Species Act (ESA). Anadromous fish species listed under the ESA are regulated by the National Marine Fisheries Service (NMFS), while listed resident freshwater fish species are regulated by the U.S. Fish and Wildlife Service (USFWS). The impacts to Willamette Slough include work bridge construction (all alternatives), tied arch erection shoring (Alternatives H-1 and L-1), and drilled shaft or similar bridge piers (Alternatives H-2 and L-2). A Biological Assessment (BA) for threatened or endangered species will be required for the final design phase of the project, in accordance with Section 7 of the ESA. The BA will be prepared to assess potential impacts to fish species under the ESA. The goal of the BA, which will include meetings with environmental regulators, is to obtain a status of "not to adversely affect" and "no taking" of ESA species by the project. Currently, it has been determined that the following permits will be required: Description of Local, State and Federal Permits Permits Likely Required Required By 1. Section 404 Joint Permit Application Army Corps of Engineers (ACOE)/ Oregon Dept. of State Lands (ODSL) Oregon Dept. of Fish & Wildlife (ODFW) U.S. Coast Guard (USCG) Oregon Dept. of Environmental Quality (ODEQ) Oregon Dept. of Environmental Quality (ODEQ) Oregon Dept. of Environmental Quality (ODEQ) Oregon Division of State Lands (ODSL) 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. Fish Passage Bridge Permit DEQ Stormwater Management Plan HAZMAT Compliance NPDES 1200-C Bridge Easement over Waters of the State Land Use – Floodplain Permit Principal River Conservation Area Review Building Permit (Requirement TBD) Development Application Erosion Control Permit Building Permit (Abutments) Grading Permit (Removal/Fill) City of Salem/Marion County (TBD) City of Salem City of Salem City of Salem City of Salem City of Salem City of Salem Hazardous Materials Issues The bridge site has a long history of pulp and paper manufacturing by Boise Cascade; the operation area included the Riverfront Park site and Minto Brown Island. Willamette Slough is also suspected to contain sediment from the pulp and paper-making operations. Boise Cascade shut down all operations in 1982. The Riverfront Park site was formerly used for an acid and pulp plant. A remnant of the operation includes the Eco Ball (formerly acid ball). The DEQ ID number for this site is 856. In 1995 and 1996 approximately 800 cubic yards of contaminated soil was removed from the site. Preliminary Concept Study Minto Brown Island Pedestrian/Bicycle Bridge City of Salem, Oregon OBEC Job No. 298-7 Page 5 The DEQ currently lists the status of the site as "No Further Action – Conditional" or CNFA, which means the site poses no unacceptable risk to human health; however, the site is not available for unrestricted use. Between 1960 and 1982 Minto Brown Island was used to store pulp mill liquors and other liquids in ponds. The DEQ ID number for this site is 355. The portion of the island used by Boise Cascade includes 50- and 100-million-gallon open holding ponds, and three capped waste areas consisting of an emergency holding pond, a buried solids area, and old landfill. The DEQ currently lists the status of the site as CNFA. All of the bridge alternatives will have ground-level and underground impacts to Riverfront Park, Willamette Slough, and Minto Brown Island that will include deep foundation systems. Due to the presence of capped waste areas and the potential of soils containing hazardous waste, conventional open excavation foundation systems are not recommended for this site. Recommended foundation systems include drilled shaft foundations and driven pile systems, which require minimal ground disturbance and soil removal during construction. The method selected to address the hazardous materials issues will be determined primarily by State DEQ requirements. Since this concept study cannot discuss these issues in depth, it is imperative environmental experts be on the design team to ensure that the final design meets DEQ requirements and that construction does not spread contaminants. While the City seeks to limit hazardous materials issues directly in Willamette Slough with Alternates H-1 and L-1, the bridge alternative discussions indicate that all bridge alternatives will affect the slough to some extent. Land Use Land use permits for the project may be required from the City. It is not anticipated that the land use process will adversely affect the scope and schedule of the project. Right-of-Way/Easements The City will be responsible for right-of-way. At this time, the City has a five-year lease with Boise Cascade for a bridgehead on Minto Brown Island. Oregon Parks and Recreation Department is currently trying to buy the land from Boise Cascade. Furthermore, the landings of the high bridge alternatives are sited in the South Waterfront Urban Renewal Area (URA); the URA will not have funding for any project until 2011 and the URA plan would likely need to be amended to add the bridge as a project. It is also likely the bridge would require a bridge easement over Waters of the State for a new crossing of Willamette Slough, as noted previously in the table "Description of Local, State and Federal Permits". At this time, the proposed contractor staging area for construction of the pedestrian/bicycle bridge is the vacant lot owned by Boise Cascade that is immediately east of the park. It is currently privately owned and subject to development. To be used as a staging area, a temporary easement for that purpose would be required. If the lot is no longer available, the Preliminary Concept Study Minto Brown Island Pedestrian/Bicycle Bridge City of Salem, Oregon OBEC Job No. 298-7 Page 6 staging area would need to be developed within the park property, which would likely be much more disruptive to park use and incur additional costs in repairing damage caused by heavy equipment and construction loads. Utilities The City will be responsible for utility coordination, with input from OBEC, on potential impacts that bridge construction may have on utilities. The only utility known at this time that may be affected is a storm sewer located near the east end of the bridge. Temporary Construction Access Construction of the bike/pedestrian bridge will require closing some pedestrian paths in Riverfront Park and directing construction traffic though the park. The proposed construction staging area for the contractor is the vacant lot owned by Boise Cascade that is immediately east of the park. Access to the construction area for the main and west approach spans will be provided by a pile-supported temporary work bridge across Willamette Slough. No construction access from Minto Brown Island should be assumed because the existing narrow berms on the island preclude passing of equipment, and very likely have limited structural capacity that would allow for heavy loads. The proposed construction access is shown on the bridge figures. However, if the lot is not available at the time of construction the staging area would need to be developed within the park property, and may create other problems as noted above. Construction of the bridge is anticipated to cover two construction seasons, and the staging area would be required for that time period. Bridge Alternatives Bridge alternatives considered include high- and low-level fixed span alternatives; reasons for the recommended type of fixed span are given in each narrative. Other alternatives considered are movable bridges such as horizontal and vertical swing spans, and lift span. However, these types of bridges are considerably more complex and, therefore, more expensive than fixed spans. Apparently, no movable bridge has been constructed in Oregon for 50 years. Besides construction cost, other disadvantages include safety considerations, such as climbing hazard; and operations and maintenance requiring full-time equivalent (FTE) bridge operators and maintenance personnel. For these reasons, only fixed span alternatives are recommended for this project. The alternatives considered are described as follows: Alternative H-1: High-level bridge, clear spans Willamette Slough, provides navigation clearance for Willamette Queen Sternwheeler This alternative consists of a main span that is a tied arch Preliminary Concept Study Minto Brown Island Pedestrian/Bicycle Bridge City of Salem, Oregon OBEC Job No. 298-7 Page 7 similar to that used on the Springwater Trail (McLoughlin Boulevard) Pedestrian Bridge constructed in 2006 in Portland. The possible cable-supported bridge types for the long main span include tied arch, cable-stayed, and suspension. Cablestayed is not recommended because of the additional costs involved in building the balance spans to either side of the main span; since the balance spans are over land, there are less expensive construction alternatives. The suspension bridge requires very large anchorages, which would have reduced efficiency because of their buoyancy, and may cause issues with hazardous materials associated with the large open excavations required. Additionally, the suspension bridge requires expensive side spans, and there are more cost-effective alternatives. The tied arch is contained entirely within the crossing of the slough and is a superior choice for this alternative. The McLoughlin Boulevard Bridge has a main span of 240 feet; a span of approximately 350 feet is required to span the Willamette Slough. The arch pipe diameter for the McLoughlin Boulevard Bridge is 18 inches; the approximate diameter for the pipe arch of the new bridge would be 24 to 30 inches. There are facilities in Portland to both bend and fabricate the arch pipes. The deck consists of prefabricated precast concrete deck panels suspended from suspender rods. The precast panels provide an extremely slender deck profile of 1'-2" thick. This is important because it greatly minimizes the length of the approach spans at they ramp up to the main span. While the tied arch main span provides the clear-spanning of Willamette Slough requested by the City, temporary falsework in the slough on driven piling is required. The arch segments will need to be supported on one or two falsework erection towers in the slough while welding the segments into a continuous structure. Additionally, a pile supported work bridge will be required for construction access for the main span and west approach spans on Minto Brown Island. Both east and west approach spans consist of conventional precast concrete slabs or box beams. The reasons for selecting this type of structure for the approach spans are provided in the discussion for Alternative H-2. All the foundations are assumed to be drilled shafts to minimize below-ground disturbance and associated hazardous materials issues. This alternate is shown in Figures 2 and 3 after this narrative. Alternative H-2: High-level, in-water piers, provides navigation clearance for the Willamette Queen Sternwheeler This alternative consists of a conventional precast concrete box beam main span, and east and west approach spans of conventional precast concrete slabs or box beams. Slabs and box beams are favored for use in pedestrian bridges for several reasons: they provide a top deck surface that does not require a cast-in-deck topping slab; their 4-foot standard Preliminary Concept Study Minto Brown Island Pedestrian/Bicycle Bridge City of Salem, Oregon OBEC Job No. 298-7 Page 8 width works well for providing a 12-foot-wide deck with side-mounted rails or 14-foot-wide deck with top mounted rails; and the span-to-length ratio of boxes is very efficient, minimizing the depth of the approach spans as they ramp up to the main spans. The impacts to Willamette Slough include a pile support work bridge that will be required for access construction of the main and west approach spans, and several drilled shafts within Willamette Slough. All the foundations are assumed to be drilled shafts to minimize belowground disturbance and associated hazardous materials issues. This alternate is shown in Figures 4 and 5. Alternative L-1: Low-level, clear spans Willamette Slough, provides clearance for 100-year high water and smaller recreational boating This alternative consists of a main span that is a tied arch, similar to that used on McLoughlin Boulevard Bridge. The tied arch is recommended for the same reasons noted for Alternative H-1. The tied arch main span has the same impacts to Willamette Slough (temporary pile support work bridge and arch erection falsework) as Alternative H-1. Both east and west approach spans consist of conventional precast concrete slabs or box beams. Reasons for selecting this type of structure for the approach spans are provided in the discussion for Alternative H-2. All the foundations are assumed to be drilled shafts to minimize below ground disturbance and associated hazardous material issues. This alternate is shown in Figures 6 and 7. Alternative L-2: Low-level, in-water piers, provides clearance for the 100-year high water and smaller recreational boating This alternative consists of a conventional precast concrete box beam main span for the same reasons as the multiple spans higher level crossing Alternative H-2. Both east and west approach spans consist of conventional precast concrete slabs or box beams. The main spans have the same impacts to Willamette Slough as Alternative H-2 (pile supported work bridge). This alternative is shown in Figures 8 and 9. Estimated Project Schedule OBEC has prepared a programming level schedule for the planning, design and construction of the bridge; the purpose of this schedule is to help the City with future project planning. Based on this schedule, once funding is secured and preliminary design starts, a conservative timeline for project development and construction would be approximately five years. Schedule assumptions include the following: • • • • Typical public agency design-bid-build methodology for project delivery model Time for Biological Assessment and Agency consultation included Coast Guard permitting including public review periods Right-of-way procurement included, condemnation timelines not considered Preliminary Concept Study Minto Brown Island Pedestrian/Bicycle Bridge City of Salem, Oregon OBEC Job No. 298-7 Page 9 • • Two-year construction season anticipated, project must be bid in early spring to capitalize on two full in-water work periods Phase I and II Hazardous Material studies included The planning level schedule is included in Appendix C. Estimated Project Costs The scope of the estimated construction and project costs is for bridge construction only including items such as staging, work access, and falsework. Engineer's cost estimates do not include acquisition of right-of-way/easements; approach paths and trails to the bridge; and improvement not specifically related to bridge construction. The construction and overall project costs are estimated in Table 1. Bridge costs are based on a price-per-square-foot (sf) basis at this time due to the high-level nature of this study. For planning cost purposes, 50 percent of the estimated construction cost is added to represent total project overhead costs including design, environmental study and permitting, construction administration, field engineering, and construction cost contingency. Project environmental costs include Biological Assessment and compliance, hazardous materials compliance, and permit preparation. The 50 percent project overhead costs are in line with the 40 percent typically used for scoping Federal-aid bridge projects and reflect the complications of hazardous materials issues. The estimated square foot bridge construction cost data is based on representative projects and is provided in Appendix B for conventional and long-span specialty (cable-supported) bridges. An estimated bridge cost of $300/sf is used for conventional precast box beam and slab bridges, depending on project size, and an estimated bridge cost of $550/sf is used for specialty bridges. Construction costs for both 12-foot and 14-foot-wide bridges, in accordance with the pedestrian bridge design criteria, have also been presented to give the City a full range of bridge crossing options. The actual hydraulic and navigational clearances will to be determined in final design, utilizing such processes as Coast Guard permitting and ACOE/FEMA "no rise" certification. The proposed bridge elevation of all alternatives has been assumed based on available data. For every foot a bridge alternative is lowered or raised in elevation to address final design analysis, the construction cost changes approximately $150,000 per foot because of the decrease or increase of approach span length to touch the bridge down to ground. This is another justification of the 50 percent project overhead and contingency at this time. A summary of project planning costs based on the above discussions is provided below. Details of these costs are provided in Table 1, which follows this narrative. Preliminary Concept Study Minto Brown Island Pedestrian/Bicycle Bridge City of Salem, Oregon OBEC Job No. 298-7 Page 10 Alternate –12' deck H-1 H-2 L-1 L-2 Alternate –14' deck H-1 H-2 L-1 L-2 Project Planning Costs (2009 Dollars) $6,813,000 $5,454,000 $4,815,000 $3,780,000 Project Planning Costs (2009 Dollars) $7,949,000 $6,363,000 $5,618,000 $4,410,000 It should also be noted for both Alternatives H-1 and L-1 that if a shorter tied arch main span is considered with a pier allowed in the water, the essence of a signature bridge can be captured at a lower cost than that shown. Conclusions A bridge from Riverfront Park to Minto Brown Island is feasible, although at a much higher cost than previously considered by the City. There are several major obstacles to constructing this bridge including: • • • right-of-way/easement acquisition construction access environmental permitting and hazardous materials mitigation Therefore, it is concluded that the cost history basis for the bridge estimate with higher project overhead costs is applicable and represents a realistic cost for the City's use. The estimated project duration including planning, design, and construction will be about five years, with construction lasting between two and three years. Preliminary Concept Study Minto Brown Island Pedestrian/Bicycle Bridge City of Salem, Oregon OBEC Job No. 298-7 Page 11 TABLE FIGURES Figure 1 RENDERINGS APPENDIX A OBEC Consulting Engineers Oregon/Washington Conventional Pedestrian Bridge Data April 2008 City of Eugene Cast-In-Place Concrete Federal Aid Padden Parkway (I-205) Pedestrian Bridge Clark County, WA Prestressed Girder Federal US Hwy. 101 (Honeyman State Park) Bridge Oregon State Parks Prestressed Slab Federal Aid Jackson County Prestressed Girder Jackson County 190' 200' 560' 70' 262' 175' 190' 100' 190' 70' 88' Net Deck Width Net Deck Area Bid/Completion 12' 2,100 SF 2004/2006 12' 2,280 SF 2004/2006 14' 2,800 SF 1996/1997 14' 7,840 SF 2001/2003 16' 1,120 SF 2004/2005 10' 2,620 SF 1998/1999 Bid (Structure + Mobilization) (Bridge Only) $607,000 $675,000 $515,000 $1,605,000 $205,000 $313,000 Bid SF Price $285 $396 $185 $205 $183 $120 2009 SF Price $325 $335 $360 $365 $215 $245 Springwater Trail (UPRR) Pedestrian Bridge City of Portland Prefabricated Truss Federal Aid Springwater Trail (Johnson Creek) Pedestrian Bridge City of Portland Steel Plate Girder Federal Aid Overall Length 175' Main Span Name Owner Type Funding 18th Avenue Pedestrian Bridge Bear Creek Trail Pedestrian Bridge Picture OBEC Consulting Engineers Oregon Long-Span Pedestrian Bridge Data April 2008 I-5 Beltline (Gateway) Pedestrian Bridge ODOT Cable-Stayed Federal Aid Springwater Trail (McLoughlin Blvd.) Pedestrian Bridge City of Portland Through-Arch Federal Aid Grants Pass (Rogue River) Pedestrian Bridge City of Grants Pass Stress-Ribbon Federal Aid Wildish Companies Suspension Private D/B DeFazio (Willamette River) Pedestrian Bridge City of Eugene Suspension Federal Aid Overall Length 503' 302' 658' 670' 606' Main Span 203' 241' 278' 430' 338' Net Deck Width Net Deck Area Bid/Completion 14' 7,042 SF 2006/2008 12' 3,624 SF 2004/2006 14' 9,212 SF 1999/2000 18.5' 12,395 SF 1999/2001 14' 8,484 SF 1997/2000 Bid (Structure + Mobilization) (Bridge Only) $2,035,000 $1,350,000 $1,438,000 $2,500,000 $2,645,000 Bid SF Price $289 $370 $156 $202 $312 2009 SF Price $375 $480 $240 $375 $550 Name Owner Type Funding McKenzie River (Wildish) Bridge Picture APPENDIX B APPENDIX C Task Name Days MINTO BROWN PEDESTRIAN BRIDGE CROSSING PRELIMINARY ENGINEERING Year 2 Year 3 Year 4 Year 5 M-1 M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21 M22 M23 M24 M25 M26 M27 M28 M29 M30 M31 M32 M33 M34 M35 M36 M37 M38 M39 M40 M41 M42 M43 M44 M45 M46 M47 M48 M49 M50 M51 1099 d? PRELIMINARY ENGINEERING 652 d? Task 1 - Project Management 652 d? Task 2 - Public Involvement 456 d? Task 3 - Location Surveying & Mapping 56 d? Task 4 - R/W Research, Mapping, Desc. 45 d? Task 5 - R/W Acquisition 261 d? Task 6 - Utility Relocation & Coord. 262 d? Task 7 - Environmental Doc's & Permits 455 d? Task 1 - Project Management Task 2 - Public Involvement Task 3 - Location Surveying & Mapping Task 4 - R/W Research, Mapping, Desc. Task 5 - R/W Acquisition Task 6 - Utility Relocation & Coord. Task 7 - Environmental Doc's & Permits Wetland Delineation Report for Review 46 d? Submit Delineation Report for Review 20 d Submit Delineation Report for Review Draft Archaeological Survey Report for Review 46 d? Draft Archaeological Survey Report for Review Submit Archaeological Survey Report for Review 20 d Hazardous Materials Phase 1 & Phase 2 Studies 267 d? Prepare Draft Biological Assessment (BA) 44 d Prepare Draft Biological Assessment (BA) Submit Draft BA for Review 33 d? Submit Draft BA for Review Prepare ACOE/DSL Permit 22 d? Submit & Track ACOE/DSL Permit with BA 261 d? Prepare Draft Land Use Permit Application 44 d? Submit Land Use Permit for Review 66 d? Prepare Coast Guard Permit Application 44 d? Submit Coast Guard Permit 261 d? Task 8 - Foundation Investigations Explorations & Foundation Report Task 9 - Hydraulic Analysis Hydraulic Investigations, Scour Analysis & Report Task 10 - Preliminary Structures & Roadway Analysis & Design 89 d? 89 d? 89 d? 89 d? 112 d? Wetland Delineation Report for Review Submit Archaeological Survey Report for Review Hazardous Materials Phase 1 & Phase 2 Studies Prepare ACOE/DSL Permit Submit & Track ACOE/DSL Permit with BA Prepare Draft Land Use Permit Application Submit Land Use Permit for Review Prepare Coast Guard Permit Application Submit Coast Guard Permit Task 8 - Foundation Investigations Explorations & Foundation Report Task 9 - Hydraulic Analysis Hydraulic Investigations, Scour Analysis & Report Task 10 - Preliminary Structures & Roadway Analysis & Design Preliminary Structures & Roadway Design 89 d? Preliminary Structures & Roadway Design Prepare & Submit Preliminary Design Report 23 d? Prepare & Submit Preliminary Design Report Submit Preliminary Report to City for Review 0d City Review 22 d? FINAL ENGINEERING DESIGN Task 11 - Advance Structure & Roadway Plans Submit Preliminary Report to City for Review City Review FINAL ENGINEERING DESIGN 493 d? 233 d? Task 11 - Advance Structure & Roadway Plans Prepare Advance Structure Plans & Details 198 d? Prepare Advance Structure Plans & Details Prepare Advance Roadway/Path Plans & Details 198 d? Prepare Advance Roadway/Path Plans & Details Prepare Cost Estimate 65 d? Prepare Cost Estimate Prepare Proposed Construction Schedule 65 d? Prepare Proposed Construction Schedule City Review 34 d Advance Plans Project Team Meeting 0d Task 12 - Final Structure & Roadway Plans City Review Advance Plans Project Team Meeting Task 12 - Final Structure & Roadway Plans 174 d? Prepare Final Structure Plans & Details 174 d? Prepare Final Structure Plans & Details Prepare Final Roadway/Path Plans & Details 174 d? Prepare Final Roadway/Path Plans & Details Prepare Final Cost Estimate 45 d? Prepare Final Cost Estimate Task 15 - Specifications & Special Provisions Advance PS&E Documents to County for Review 43 d? City Review 34 d? Final PS&E Documents for Bidding 45 d? Task 16 - Bidding Assistance Task 15 - Specifications & Special Provisions 264 d? 60 d? Advance PS&E Documents to County for Review City Review Final PS&E Documents for Bidding Task 16 - Bidding Assistance Respond to Contractor Questions 15 d? Respond to Contractor Questions Three Week Advertisement 15 d? Three Week Advertisement PROPOSED BID OPENING DATE 0d Reviews Bids & Issue Notice to Proceed 45 d Reviews Bids & Issue Notice to Proceed Contractor Receives Notice to Proceed 0d Contractor Receives Notice to Proceed CONSTRUCTION 438 d? Construction Activities 438 d? In-Water Work 88 d? In-Water Work 86 d? PROPOSED BID OPENING DATE CONSTRUCTION Construction Activities In-Water Work In-Water Work