Street Acceptance Flowchart VDOT — Fairfax County Initial Submittal
Street Acceptance Flowchart
VDOT — Fairfax County
Plan Approval
Begin Construction
Legend
Developer
Initial Submittal
(Developer/Engineer to Fairfax County/VDOT)
Fairfax County
VDOT
In-Place Utilities
&
Post Construction Package
(Developer to Fairfax County/VDOT
upon Roadway Construction Completion)
Joint Inspection (s)
(Fairfax County/VDOT/Developer)
Project Record
Required Fees Schedule
BOS Package
(VDOT to Fairfax County & Developer)
Board Resolution
Required Fees Payment
Fees Payment, County Certification &
Board Resolution
(Final Package)
(Developer/Fairfax County to VDOT)
Project Assembly to Richmond
Final Acceptance Report
(Notification to Fairfax County & Developer)
May 2015