Alberta Electric System Operator 2016 ISO Tariff Update Date:
by user
Comments
Transcript
Alberta Electric System Operator 2016 ISO Tariff Update Date:
Alberta Electric System Operator 2016 ISO Tariff Update Date: February 2, 2016 Prepared by: Alberta Electric System Operator Prepared for: Alberta Utilities Commission Contents 1 Introduction ........................................................................................................................................... 4 1.1 1.2 1.3 2 AESO 2016 Forecast Revenue Requirement ..................................................................................... 7 2.1 2.2 2.3 2.4 2.5 3 Background ................................................................................................................................................ 4 Organization ............................................................................................................................................... 5 Relief Requested........................................................................................................................................ 6 AESO Board Approval of Costs ................................................................................................................. 7 Wires Costs ................................................................................................................................................ 8 Ancillary Services Costs ........................................................................................................................... 13 Losses Costs............................................................................................................................................ 13 Administrative Costs ................................................................................................................................ 14 2016 Tariff Update .............................................................................................................................. 15 3.1 3.2 3.3 Specific Rate Changes ............................................................................................................................. 15 3.1.1 Rate PSC, Primary Service Credit ................................................................................................ 15 3.1.2 Regulated Generating Unit Connection Costs in Rate STS, Supply Transmission Service .......... 16 3.1.4 Rider J, Wind Forecasting Service Cost Recovery Rider .............................................................. 16 2016 Forecast Billing Determinants ......................................................................................................... 17 Bill Impacts ............................................................................................................................................... 19 4 2016 Maximum Investment Levels Update ...................................................................................... 22 5 Conclusion .......................................................................................................................................... 24 Appendices ........................................................................................................................ Filed Separately A B C D E F AESO Board Decision (Dated December 16, 2015) AESO 2016 Business Plan and Budget Proposal (Dated October 29, 2015) 2016 Rates Calculations Escalation Factor and Investment Levels Proposed 2016 ISO Tariff 2016 Rates, Rider J, and Section 8 of the ISO Tariff Proposed 2016 ISO Tariff 2016 Rates, Rider J, and Section 8 of the ISO Tariff (blackline) AESO 2016 ISO Tariff Update Application Page 2 of 24 Confidentiality: Public February 2, 2016 Tables Table 2-1 – 2016 Forecast, 2015 Updated Forecast, 2014 and 2013 Recorded Cost Components .... 7 Table 2-2 – AESO 2016 Forecast Revenue Requirement ($ 000 000) .................................................. 10 Table 3-1 – Calculation of 2016 Primary Service Credit ........................................................................ 16 Table 3-2 – 2016 Forecast and 2015 Recorded Billing Determinants .................................................. 18 Table 3-3 – 2016 Forecast, 2015, 2014 and 2013 Recorded Billing Determinants .............................. 19 Table 3-4 – Increase (Decrease) for 2016 Rate DTS Components ....................................................... 20 Table 3-5 – Increase (Decrease) for 2016 Rate STS Components ....................................................... 20 Table 4-1 – Escalation Factor for Composite Inflation Index ............................................................... 22 Table 4-2 – Calculation of 2016 Maximum Investment Levels.............................................................. 23 Appendix C: 2016 Rate Calculations ................................. Microsoft Excel Workbook Filed Separately C-1 C-2 C-3 C-4 C-5 C-6 C-7 C-8 C-9 C-10 C-11 C-12 C-13 C-14 C-15 C-16 AESO 2016 Forecast Revenue Requirement 2016 Forecast Transmission Facility Owner Wires Costs Revenue Requirement Allocation to Demand and Supply Transmission Service Tariff Revenue Offsets Demand Transmission Service Costs Classified to Demand, Usage, and Customers POD Cost Function and POD Cost Classification Demand Transmission Service Cost Recovery Demand Transmission Service Rate Calculation Supply Transmission Service Costs Classified to Demand and Usage Supply Transmission Service Rate Calculation Opportunity Service Rate Calculations 2016 Billing Determinants Rate Change Impact Compared to 2015 Approved Rates Fort Nelson Demand Transmission Service Rate Calculation 2016 Fort Nelson Billing Determinants Bill Impact Estimator AESO 2016 ISO Tariff Update Application Page 3 of 24 Confidentiality: Public February 2, 2016 1 Introduction 1 Pursuant to sections 30 and 119 of the Electric Utilities Act, S.A. 2003, c. E-5.1 (“Act”), the Alberta Electric System Operator (“AESO”) applies to the Alberta Utilities Commission (“Commission”) for approval of its 2016 update to the Independent System Operator (“ISO”) tariff. As outlined in further detail below, this annual tariff update application seeks approval of changes to the rates to be charged by the AESO for system access service and to the maximum investment levels provided under section 8 of the ISO tariff. 2 The updates proposed in this application change only the levels (that is, the dollar-based and percentage of pool price amounts) included in the rates and section 8 of the ISO tariff, based on costs and billing determinants forecast by the AESO for the 2016 calendar year. This application does not include any changes to the structure of the rates or to the provisions of the terms and conditions (other than maximum investment levels) currently approved in 2015 ISO tariff. 3 The AESO notes that since approving the AESO’s most recent major tariff application in Decision 34731 D01-2015, the Commission approved ISO tariff amendments (to rates, rider and definitions) associated 2 with the transmission constraint rebalancing charge in Decision 20623-D01-2015. The AESO has accordingly included these approved amendments in this tariff update application. 1.1 4 Background 3 On December 22, 2010, the Commission issued Decision 2010-606, in which the AESO’s proposed annual tariff update was summarized as follows: In conjunction with its proposal for major updates, the AESO proposed to make annual tariff update filings involving the following three principal components: an annual revenue requirement update using the approach to the wires cost forecast as described in section 2.2 of the Application, plus forecasts for ancillary services costs, losses costs and administration costs approved by the AESO Board for the forecast year; revised rate levels for each AESO rate calculated from the forecast revenue requirement and forecast billing determinants using rate calculations and rate design approved in the most recent comprehensive tariff application; and annual updates to investment amounts approved in the most recent comprehensive tariff reflecting an escalation factor based on the most recent Conference Board of Canada Alberta 4 consumer price index (CPI). 5 The Commission approved the AESO’s proposal in Decision 2010-606, and the AESO has subsequently applied for tariff updates between its major tariff applications in accordance with this approach. 6 The AESO’s most recent major tariff application was filed on July 17, 2013, by which the AESO sought 5 approval from the Commission for the 2014 ISO tariff. The AESO’s most recent tariff update application was filed on August 20, 2015, by which the AESO sought approval from the Commission for the 2015 ISO 6 tariff. The Commission approved the current form of the 2015 ISO tariff, effective January 1, 2016, first 7 by way of Decision 20753-D01-2015 on an interim basis and then by way of Decision 20753-D02-2015 1 Decision 3473-D01-2015, Alberta Electric System Operator 2014 ISO Tariff Compliance Filing Pursuant to Decision 2014-242, issued June 2, 2015, errata issued June 17, 2015 2 Decision 20623-D01-2015, Application for AESO 2015 Transmission Constraint Rebalancing Charge and Approval to Amend the ISO Tariff Pursuant to Decisions 2013-135 and 3528-D01-2015, issued November 5, 2015 3 Decision 2010-606, Alberta Electric System Operator 2010 ISO Tariff, issued December 22, 2010. 4 Decision 2010-606 at page 99, paragraph 537. 5 Exhibit 0002.00.AESO-2718. 6 Exhibit 20753-X0002. 7 Decision 20753-D02-2015, Alberta Electric System Operator 2015 ISO Tariff Update, issued December 21, 2015. AESO 2016 ISO Tariff Update Application Page 4 of 24 Confidentiality: Public February 2, 2016 on a final basis. The 2015 ISO tariff approved in that decision reflected costs and billing determinants for the 2015 calendar year. The AESO is now filing this annual tariff update application to reflect costs and billing determinants for the 2016 calendar year. 7 In accordance with the approach referred to above, this tariff update application consists of formulaic updates to: (i) the AESO’s annual revenue requirement, based on the AESO’s updated forecast costs for 2016; (ii) rate, rider, and maximum investment level amounts using the rate calculation methodology 8 already approved by the Commission in Decision 3473-D01-2015, and (iii) the investment amounts first 9 10 approved in Decision 3473-D01-2015 and then updated in Decision 20753-D02-2015, in accordance with the escalation factor described below. In the AESO’s view, the updates proposed in this application will limit potential misallocations that might occur if the AESO continued to rely on Rider C, Deferral Account Adjustment Rider, to allocate revenue and cost imbalances to market participants. 1.2 8 Organization Similar to previous ISO tariff update applications, this application is organized into the following sections: 1 Introduction — Provides background on the application and specifies the relief requested. 2 2016 Forecast Revenue Requirement — Summarizes the AESO’s forecast revenue requirement for 2016, including costs that have been approved either by the Commission (for transmission facility owner (“TFO”) tariffs) or by the AESO Board (for ancillary services, transmission line losses, and the AESO’s own administration). 3 2016 Tariff Update — Discusses the calculation of rate levels based on the 2016 forecast revenue requirement, 2016 wires costs functionalization and classification approved in Commission Decision 11 2013-421, and 2016 forecast billing determinants. 4 2016 Maximum Investment Levels Update — Discusses the calculation of 2016 maximum investment levels using the 2016 escalation factor. 5 Conclusion — Reiterates the relief requested. 9 This application also includes the following appendices: A AESO Board Decision — AESO Board decision issued on December 16, 2015, approving forecasted ancillary services costs, forecasted losses costs, and the AESO’s business plan and budget for 2016. B AESO 2016 Business Plan and Budget Proposal — Document prepared by AESO management in consultation with stakeholders, as submitted to the AESO Board on October 29, 2015, containing the AESO’s proposed 2016 business initiatives and proposed 2016 budgets and forecasts for ancillary services costs, transmission line losses costs, and administrative costs. C 2016 Rate Calculations — Microsoft Excel workbook which calculates the updated dollar and percentage of pool price amounts for the 2016 rates, based on the same methodology used for the AESO’s currently approved rates. D 2016 Escalation Factor and Investment Levels — Microsoft Excel workbook which calculates the composite inflation index and escalation factor used to update maximum investment levels. 8 See footnote 1. See footnote 1. See footnote 7. 11 Decision 2013-421, Alberta Electric System Operator 2014 ISO Tariff Application and 2013 ISO Tariff Update Negotiated Settlement – Cost Causation Study, issued November 27, 2013. 9 10 AESO 2016 ISO Tariff Update Application Page 5 of 24 Confidentiality: Public February 2, 2016 E 2016 Rates, Riders, and Section 8 of the ISO Tariff — The proposed 2016 rates, riders, and section 8 that incorporate the 2016 updated amounts included as Appendices C and D to this application. F 2016 Rates, Riders, and Section 8 of the ISO Tariff (blackline) — The blackline version of the proposed 2016 rates, riders, and section 8 that incorporate the 2016 updated amounts included as Appendix C to this application. 1.3 Relief Requested 10 For the reasons outlined below, the AESO submits that the tariff updates proposed in this application are just and reasonable, and respectfully requests that the Commission approve this annual tariff update application, including (i) the updated amounts included as Appendix C to this application, and (ii) the proposed 2016 ISO tariff Rate DTS, Rate FTS, Rate DOS, Rate XOS, Rate XOM, Rate PSC and Rate STS, Rider J and Section 8 included as Appendix E to this application, which incorporates the updated amounts. 11 The AESO respectfully requests that this application be approved effective April 1, 2016. If the timing of this application does not permit the granting of final approval prior to April 1, 2016, the AESO also requests that the Commission approve this application on an interim refundable basis effective as of that date. The AESO further requests that the Commission issue its approval (whether on an interim or final basis) on or before March 31, 2016 as this is the last approval date that will allow the AESO to implement the proposed tariff updates effective April 1, 2016 on a prospective basis. For additional clarity, the AESO requests that the updated rates, riders and investment levels proposed in this application apply on a go-forward basis only, commencing from the effective date approved by the Commission. Consistent 12 with the Commission’s statements in Decision 2014-242, the AESO submits that currently-approved deferral account rider and reconciliation mechanisms should continue to be used to address any variances between costs and revenues occurring prior to the approval of the applied-for rates. The AESO is not seeking any retroactivity with respect to the rates proposed for approval in this application. 12 The AESO requires a minimum of one month to program and test approved rates. As such, the AESO will begin programming and testing with the applied-for updated rates in March or April and will therefore be ready to perform calculations based on the applied-for updated rates when statements of account for April are issued in early May, consistent with an April 1, 2016 effective date. 12 Decision 2014-242, Alberta Electric System Operator 2014 ISO Tariff Application and 2013 ISO Tariff Update, issued August 21, 2014, paragraph 617. AESO 2016 ISO Tariff Update Application Page 6 of 24 Confidentiality: Public February 2, 2016 2 13 AESO 2016 Forecast Revenue Requirement The AESO’s revenue requirement consists of costs related to wires, ancillary services, transmission line losses, and the AESO’s own administration (which includes other industry costs and general and administrative costs). The AESO’s forecast costs for 2016 are detailed in column A of Table 2-1. For comparison, Table 2-1 includes costs approved in the AESO Board Decision for 2016 (included as 13 Appendix A to this application), updated forecast costs for 2015, and the recorded costs for 2014 and 2013, in columns B, C, D, and E, respectively. Table 2-1 – 2016 Forecast, 2015 Updated Forecast, 2014 and 2013 Recorded Cost Components 2016 Forecast Cost Component Wires Ancillary services Losses Administrative Revenue Requirement Updated ($ 000 000) Budget Proposal ($ 000 000) A 1,684.5 182.6 111.9 98.4 2,077.6 B 1,684.8 182.6 111.9 98.4 2,077.8 2015 2014 2013 Updated Forecast ($ 000 000) C 1,523.1 162.9 76.4 101.0 1,863.6 Recorded ($ 000 000) Recorded ($ 000 000) D 1,387.6 213.6 118.2 101.3 1,820.6 E 1,123.8 398.2 181.7 100.1 1,803.9 Note: Numbers may not add due to rounding 14 The 2016 updated forecast costs represent an increase of $214.0 million (or 11.5%) over the 2015 updated forecast costs. The increase primarily results from a forecast increase of $161.4 million (or 10.6%) in wires costs reflecting recent applications for TFO tariffs by transmission facility owners. Ancillary services costs are forecast to increase by $19.6 million (or 12.1%) and losses costs are forecast to increase by $35.5 million (or 46.5%), while administrative costs are forecast to decrease by $2.6 million (or 2.6%). 2.1 AESO Board Approval of Costs 15 The AESO is not seeking approval in this application of its 2016 forecast revenue requirement. The AESO’s forecast costs are approved through other processes provided for in relevant legislation. These costs, as provided in column B of Table 2-1, were addressed in the AESO 2016 Business Plan and Budget Proposal dated October 29, 2015, included as Appendix B to this application. 16 With respect to the AESO’s costs, including their approval processes: 17 (a) Wires-related costs reflect the amounts paid by the AESO to TFOs in the TFO tariffs approved by the Commission under section 37 of the Act. (The wires costs forecast included in the AESO 2016 Business Plan and Budget Proposal reflected TFO tariffs applied for or approved by the Commission at the time the AESO budget was prepared in late 2015, as discussed in more detail below.) 18 (b) Ancillary services costs reflect recovery of the prudent costs incurred by the AESO related to the provision of ancillary services acquired from market participants under subsection 30(4) of the Act. 13 2015 Updated Forecast includes actual recorded costs to November 30, 2015 and 1 month forecast costs for December 2015 AESO 2016 ISO Tariff Update Application Page 7 of 24 Confidentiality: Public February 2, 2016 19 (c) Losses costs reflect recovery of the prudent costs of transmission line losses under subsection 30(4) of the Act. 20 (d) Administrative costs reflect the transmission-related costs and expenses incurred by the AESO and described under subsection 1(1)(g) of the Transmission Regulation. 21 The ancillary services costs, losses costs, and administrative costs described above are approved by the AESO Board (consisting of the “ISO members” appointed under section 8 of the Act) in accordance with the Transmission Regulation. Section 3 of the Transmission Regulation addresses consultation and approval of those costs and requires that the AESO consult with market participants with respect to proposed costs to be approved by the AESO Board. Subsection 48(1) of the Transmission Regulation provides that a reference to “prudent” or “appropriate” in the Act in relation to the costs of ancillary services and losses means the amounts of those costs that have been approved by the AESO Board. In addition, subsection 46(1) of the Transmission Regulation provides that the AESO’s administrative costs, once approved by the AESO Board, must be considered as “prudent” by the Commission unless an interested person satisfies the Commission otherwise. 22 The practice established by the AESO to carry out consultation on ancillary services, losses, and administrative costs is the Budget Review Process. The Budget Review Process is a transparent stakeholder process which provides a prudence review with input from stakeholders. At the conclusion of the Budget Review Process, AESO management proposes a business plan and budget to the AESO Board, including a request for approval of ancillary services costs, losses costs, and administrative costs. 23 As part of the AESO Budget Review Process for its 2016 budget, AESO management consulted with stakeholders in a planning process that had been first established with stakeholders in 2009. In mid-2015, the AESO reviewed the business initiatives established for 2016 and prepared a forecast budget required to deliver those business initiatives. Following consultation with stakeholders and incorporating appropriate amendments arising from it, AESO management submitted the 2016 Business Plan and Budget Proposal to the AESO Board on October 29, 2015. This document (included as Appendix B to this application) includes details on the consultation process and on the proposal for the AESO’s business plan and budget as it relates to forecasted ancillary services costs, forecasted losses costs, and the AESO’s business priorities and budget for 2016. The 2016 Business Plan and Budget Proposal was also provided to stakeholders and posted on the AESO website. 24 The AESO’s 2016 forecast costs were approved by the AESO Board on December 16, 2015. A Board Decision Document was posted on the AESO website and is included as Appendix A to this application. 25 Additional information on the AESO’s business priorities and budget for 2016 is available on the AESO website at www.aeso.ca by following the path About AESO Our Business Business Plan and Budget 2016 Budget. 2.2 Wires Costs 26 The 2016 updated forecast costs for wires are $1,684.5 million and represent approximately 81.1% of the AESO’s transmission revenue requirement. Wires costs include primarily wires-related costs of TFOs as well as two small non-wires costs. 27 The 2016 Business Plan and Budget Proposal discussed in section 2.1 above included wires-related costs based on the TFO tariff approved by the Commission or applied for by TFOs at the time the AESO budget was prepared in late 2015. Those costs are included in column B, lines 1 through 10, of Table 2-2 below. For most of the TFOs, costs in column B reflect their tariff applications for 2016. For TFOs that have not filed a tariff application for 2016, costs in column B reflect their most recent tariff application or their most recent TFO tariff approval on a final basis. AESO 2016 ISO Tariff Update Application Page 8 of 24 Confidentiality: Public February 2, 2016 28 The AESO has determined the 2016 wires costs for TFOs using the following approach, which was 14 described in section 2.2.1 of the AESO’s 2014 ISO tariff application and 2013 ISO tariff update and 15 referred to in Decision 2014-242: (a) If a transmission facility owner has received final Commission approval for its applicable tariff, the AESO includes the approved cost for that transmission facility owner tariff. (b) If a transmission facility owner has applied for its tariff, the Commission has issued an initial decision on the application, and the transmission facility owner has submitted a refiling in compliance with the decision, the AESO includes the transmission facility owner tariff costs included in the refiling. (c) If a transmission facility owner has applied for its tariff but the Commission has not yet issued an initial decision on the application or an initial decision has been issued but the transmission facility owner has not yet submitted its compliance refiling, the AESO includes the tariff costs most recently approved by the Commission on a final basis for the transmission facility owner plus 72% of any increase or decrease included in the transmission facility owner’s tariff application above or below the prior approved costs. (d) If a transmission facility owner has not yet applied for its tariff, the AESO includes the transmission facility owner tariff costs most recently approved by the 16 Commission on either a final or interim basis. 17,18 29 As discussed in greater detail below, the Commission has issued decisions approving certain 2016 TFO tariffs, and applications have been filed for several 2016 TFO tariffs. Therefore, in accordance with the foregoing approach, the AESO has forecasted the 2016 wires costs in Table 2-1 to reflect these approval and applications. 30 As noted in the AESO’s 2014 ISO tariff application, “the inclusion of 72% of an applied-for increase or decrease in (c) above was determined from the percentages of applied-for changes which had received final approval in recent transmission facility owner tariff applications, and is not meant to indicate any predetermination of the result of a transmission facility owner tariff proceeding, nor be interpreted as 19 AESO support for any specific components of a transmission facility owner tariff application”. 31 The TFO tariff costs included in this application are included as Table C-2 of Appendix C to this application. These costs are also included in column A of Table 2-2 below. 14 Exhibit 0026.00.AESO-2718, Alberta Electric System Operator 2014 ISO Tariff Application and 2013 ISO Tariff Update, dated July 19, 2013, at pages 12-13, paragraphs 5357. 15 Decision 2014-242, Alberta Electric System Operator 2014 ISO Tariff Application and 2013 ISO Tariff Update, issued August 21, 2014, at page 9, paragraph 43. 16 Exhibit 0026.00.AESO-2718, at page 13, paragraphs 54-57. 17 Decision 20802-D01-2015, The City of Red Deer Compliance Filing to Decision 3599-D01-2015, issued October 23, 2015. 18 20818-D01-2015 FortisAlberta Inc. 2016 Annual Performance-Based Regulation Rate Adjustment Filing, issued December 17, 2015 19 Exhibit 0026.00.AESO-2718, at page 13, paragraph 58. AESO 2016 ISO Tariff Update Application Page 9 of 24 Confidentiality: Public February 2, 2016 Table 2-2 – AESO 2016 Forecast Revenue Requirement ($ 000 000) Line No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 2016 2016 2015 2014 2013 Updated Forecast Updated Recorded Recorded Forecast Budget Forecast A B C D E Description WIRES TFO Wires-Related Costs AltaLink ATCO Electric Isolated Generation Subtotal ATCO Costs ENMAX Power Corporation EPCOR Distribution & Transmission City of Lethbridge TransAlta Utilities Corporation City of Red Deer FortisAlberta (Farm Transmission) Subtotal TFO Wires-Related Costs Non-Wires Costs Invitation to Bid on Credits (IBOC) Location Based Credit Standing Offer (LBC SO) Subtotal IBOC/LBC SO Costs TOTAL WIRES COSTS 691.6 796.9 (2.9) 794.0 73.9 99.8 6.2 4.9 3.9 4.8 1,679.1 718.7 770.7 (2.9) 767.9 74.1 98.9 6.1 4.9 3.9 4.8 1,679.3 666.8 662.0 (2.9) 659.1 74.9 97.8 6.1 4.9 3.6 4.7 1,518.0 631.7 578.1 (3.7) 574.4 66.1 90.1 6.1 5.0 3.9 4.7 1,381.9 492.7 483.5 (5.8) 477.7 54.4 75.3 5.9 4.5 3.4 4.6 1,118.5 1.5 4.0 5.5 1,684.5 1.5 4.0 5.5 1,684.8 1.4 3.7 5.1 1,523.1 1.5 4.1 5.6 1,387.6 1.3 4.0 5.3 1,123.8 27.2 57.7 40.7 125.7 27.2 57.7 40.7 125.7 33.0 42.0 30.2 105.2 41.8 72.0 54.0 167.8 72.1 137.6 131.3 340.9 6.9 12.4 3.5 22.7 (1.3) 147.1 6.9 12.4 3.5 22.7 (1.3) 147.1 5.0 19.8 8.3 33.1 (1.0) 137.3 5.2 8.8 2.7 16.8 (3.7) 180.9 9.4 14.9 4.3 28.6 (7.3) 362.2 20 21 22 23 24 25 ANCILLARY SERVICES Operating Reserves Active Regulating Spinning Supplemental Subtotal Active Reserves Standby Regulating Spinning Supplemental Subtotal Standby Reserves Trading Fees and Other Related Charges Subtotal Operating Reserves 26 27 28 29 30 31 32 33 34 35 Other Ancillary Services Black Start Transmission Must Run (TMR) Under Frequency Mitigation Poplar Hill Interruptible Load Remedial Action Scheme (ILRAS) LSSi Reliability Services from BC Transmission Constraint Rebalancing (TCR) Subtotal Other Ancillary Services TOTAL ANCILLARY SERVICES 2.1 4.0 2.5 20.0 2.9 4.0 35.5 182.6 2.1 4.0 2.5 20.0 2.9 4.0 35.5 182.6 2.1 1.3 2.6 17.4 2.1 25.6 162.9 1.0 4.4 2.8 24.4 32.7 213.6 1.0 11.2 2.5 21.2 36.0 398.2 36 37 LOSSES Pool Payment TOTAL LOSSES COSTS 111.9 111.9 111.9 111.9 76.4 76.4 118.2 118.2 181.7 181.7 16 17 18 19 AESO 2016 ISO Tariff Update Application Page 10 of 24 Confidentiality: Public February 2, 2016 Table 2-2 – AESO 2016 Forecast Revenue Requirement ($ 000 000) (continued) Line 2016 No. 2016 2015 2014 2013 Forecast Updated Updated Recorded Recorded Budget Forecast A B C D E Description 38 39 40 41 OTHER INDUSTRY COSTS Regulatory Process Costs Western Electricity Coordination Council (WECC) Share of AUC Overhead TOTAL OTHER INDUSTRY COSTS 1.4 2.2 12.0 15.5 1.4 2.2 12.0 15.5 1.5 1.2 14.0 16.7 0.9 1.1 13.4 15.3 1.0 2.8 13.2 17.0 42 43 44 45 46 47 48 49 GENERAL AND ADMINISTRATIVE COSTS Administrative Costs Staff and Benefits Contract Services and Consultants Administration Facilities Computer and Telecom Services and Maintenance IT Wind Forecasting Interconnection Fees (offset) Subtotal Administrative Costs 47.2 4.2 3.5 5.7 6.6 0.2 67.4 47.2 4.2 3.5 5.7 6.6 0.2 67.4 44.6 7.6 3.6 5.8 5.8 0.2 67.5 45.0 10.3 3.7 4.6 6.1 0.3 70.0 43.7 11.5 3.7 4.9 6.1 0.3 70.2 50 51 52 53 54 General Costs Market System Replacement Interest Amortization and Depreciation Subtotal General Costs TOTAL G&A COSTS (0.2) 15.7 15.5 82.9 (0.2) 15.7 15.5 82.9 (0.2) 17.0 16.8 84.3 0.9 (0.7) 15.8 16.0 86.0 (0.5) 13.4 12.9 83.1 55 TOTAL G&A AND OTHER INDUSTRY COSTS 98.4 98.4 101.0 101.3 100.1 56 TOTAL REVENUE REQUIREMENT 2,077.6 2,077.8 1,863.6 1,820.6 1,803.9 Totals may not add due to rounding 32 The wires costs included in this application and set out in Table 2-2 above are based on the following Commission decisions and TFO tariff applications. Line 1 AltaLink Management Ltd. 33 AltaLink Management Ltd. (“AltaLink”) has applied for 2016 TFO tariff costs of $703.5 million (amended from an initial application for costs of $1,001.6 million). AltaLink’s 2014 tariff costs are $631.6 million, comprised of 2014 TFO tariff costs of $621.4 approved on a final basis in Commission Decision 201420 258 plus 72% of an applied-for 2014 amount of $14.3 million included in AltaLink’s 2012-2013 deferral 21 account reconciliation application. The AESO has included forecast 2016 wires costs of $691.6 million for AltaLink that have been calculated in two steps. First 2015 wires costs of $660.8 million have been forecasted as: (a) $631.6 million for 2014 tariff costs plus (b) 72% of AltaLink’s applied-for increase of $40.6 million (from $631.6 million for 2014 to $672.2 million for 2015). Then 2016 wires costs of $691.6 20 21 Decision 2014-258, AltaLink Management Ltd. Refiling Pursuant to Decision 2013-407 and Decision 2013-459, issued September 8, 2014. Exhibit 3585-X0655, AltaLink 2012 and 2013 Deferral Account Reconciliation Application, Proceeding 3585, dated July 31, 2015 AESO 2016 ISO Tariff Update Application Page 11 of 24 Confidentiality: Public February 2, 2016 million have been forecasted as: (a) $660.8 million for 2015 tariff costs plus (b) 72% of AltaLink’s appliedfor increase of $42.7 million (from $660.8 million for 2015 to $703.5 million for 2016). Lines 2-4 ATCO Electric Ltd. 34 ATCO Electric Ltd. (“ATCO Electric”) has applied for 2016 TFO tariff costs of $843.2 million (amended from an initial application for costs of $810.8 million). ATCO Electric’s 2014 tariff costs are $569.3 million, comprised of 2014 TFO tariff costs of $579.0 million as approved on a final basis in Commission Decision 22 2014-348 plus 72% of an applied-for 2014 amount of ($13.4) million included in ATCO Electric’s 201323 2014 deferral account reconciliation application. The AESO has included forecast 2016 wires costs of $796.9 million for ATCO Electric that have been calculated in two steps. First 2015 wires costs of $677.8 million have been forecasted as: (a) $569.3 million for 2014 tariff costs plus (b) 72% of ATCO Electric’s applied-for increase of $150.7 million (from $569.3 million for 2014 to $720.0 million for 2015). Then 2016 wires costs of $796.9 million have been forecasted as: (a) $677.8 million for 2015 tariff costs plus (b) 72% of ATCO Electric’s applied-for increase of $165.4 million (from $677.8 million for 2015 to $843.2 million for 2016). 35 ATCO Electric’s TFO tariff costs are offset by payments to the AESO in respect of pool price for electric energy provided to isolated communities in accordance with the Isolated Generating Units and Customer Choice Regulation. The isolated generation cost offset was estimated at $2.9 million based on 2014-2015 recorded volumes for isolated communities and the 2016 forecast pool price. 36 The 2016 net forecast cost for ATCO Electric is $794.0 million. Line 5 ENMAX Power Corporation 37 ENMAX Power Corporation (“ENMAX”) has received approval for 2015 TFO tariff costs of $73.9 million in 24 Commission Decision 20819-D01-2015. ENMAX has not yet applied for 2016 TFO tariff costs. The AESO has accordingly included $73.9 million as forecast ENMAX 2016 TFO tariff costs in this application. Line 6 EPCOR Distribution & Transmission Inc. 38 EPCOR Distribution & Transmission Inc. (“EPCOR”) has refilled for 2016 TFO tariff costs of $99.8 25 million. The AESO has accordingly included $99.8 million as forecast EPCOR 2016 TFO tariff costs in this application. Line 7 City of Lethbridge 39 26 The City of Lethbridge has applied for 2016 TFO tariff costs of $6.3 million. City of Lethbridge’s 2014 27 tariff costs are $6.1 million as approved on a final basis in Commission Decision 2013-364. The AESO has included forecast 2016 wires costs of $6.2 million for City of Lethbridge that have been calculated in two steps. First 2015 wires costs of $5.7 million have been forecasted as: (a) $6.1 million for 2014 tariff costs plus (b) 72% of City of Lethbridge’s applied-for decrease of $0.5 million (from $6.1 million for 2014 to $5.6 million for 2015). Then 2016 wires costs of $6.2 million have been forecasted as: (a) $5.7 million for 2015 tariff costs plus (b) 72% of City of Lethbridge’s applied-for increase of $0.6 million (from $5.7 million for 2015 to $6.3 million for 2016). 22 Decision 2014-348, ATCO Electric Ltd. 2013-2014 Transmission General Tariff Application Second Compliance Filing, issued December 15, 2014. Exhibit 21206-X0010, ATCO Electric Application for Disposal of 2013 and 2014 Transmission Deferral Account and Annual Filing for Adjustment Balances, Proceeding 21206, dated January 8, 2016 24 Decision 20819-D01-2015, ENMAX Power Corporation Decision on Request for Review and Variance of Decision 20124-D01-2015: 2014 Phase I Distribution Tariff and 2015-2015 Transmission General Tariff Compliance Filing, issued November 27, 2015 25 EPCOR Distribution & Transmission Inc. 2015-2017 Transmission Facility Owner Tariff and 2013 Generic Cost of Capital Compliance Refiling Application, Proceeding 21229, filed January 4, 2016. 26 City of Lethbridge 2015-17 TFO General Tariff Application, Proceeding 21213, filed December 24, 2015. 27 Decision 2013-364, City of Lethbridge 2012-1014 Transmission Facility Owner General Tariff Application, issued September 30, 2013. 23 AESO 2016 ISO Tariff Update Application Page 12 of 24 Confidentiality: Public February 2, 2016 Line 8 TransAlta Corporation 40 TransAlta Corporation (“TransAlta”) has not yet applied for its 2016 final TFO tariff costs. TransAlta’s 28 2014 TFO tariff costs are $4.9 million as approved in Commission Decision 20524-D01-2015. The AESO has accordingly included $4.9 million as forecast TransAlta 2016 TFO tariff costs in this application. For additional clarity, TransAlta’s 2014 TFO tariff was most recently approved by the 29 Commission; Decision 2014-369 which approved TransAlta’s 2015-2016 interim TFO tariff was issued before Decision 20524-D01-2015 and continued TransAlta’s 2012 TFO tariff amounts into 2016. Line 9 City of Red Deer 41 The City of Red Deer’s 2016 tariff costs are $3.9 million as approved on a final basis in Commission 30 Decision 20802-D01-2015. The AESO has accordingly included $3.9 million as forecast City of Red Deer 2016 TFO tariff costs in this application. Line 10 FortisAlberta Inc. (Farm Transmission) 42 Section 32 of the Act requires the AESO to pay owners of electric distribution systems for “farm transmission costs” as defined in the Act. FortisAlberta Inc. (“FortisAlberta”) has received approval for 31 2016 farm transmission costs of $4.8 million in Commission Decision 20818-D01-2015. The AESO has accordingly included $4.8 million as forecast FortisAlberta 2016 farm transmission costs in this application. Lines 12-14 Non-Wires Costs 43 The AESO includes as wires costs two cost components that are not related to TFOs: Invitation to Bid on Credit (“IBOC”) costs and Location Based Credit Standing Offer (“LBC SO”) costs. These two programs were initiated to provide non-wires solutions to transmission wires issues in Alberta and their costs are included as wires costs for rate-setting purposes. The $5.5 million cost for the two programs was forecast by the AESO in conjunction with ancillary services costs and, as evidenced by the AESO Board Decision included as Appendix A to this application, has been approved by the AESO Board. 2.3 Ancillary Services Costs 44 The forecast 2016 costs for ancillary services are $182.6 million and represent approximately 8.8% of the AESO’s transmission revenue requirement. Ancillary services, as defined in subsection 1(1)(b) of the Act, are services required to ensure that the interconnected electric system is operated in a manner that provides a satisfactory level of service with acceptable levels of voltage and frequency. The largest component of ancillary services costs is operating reserves, which represent the real power capability 32 above system demand required to provide for regulation, forced outages and unplanned outages. 45 Ancillary services costs are primarily a function of volume forecasts and market-based commodity pricing forecasts. The 2016 forecast costs for ancillary services were based on a forecast average pool price of $40.99/MWh. 2.4 46 Losses Costs The 2016 forecast costs for transmission line losses are $111.9 million and represent approximately 5.4% of the AESO’s transmission revenue requirement as provided in Table 2-1. Losses are the energy lost on the transmission system when power is transmitted from suppliers to loads. Losses are the residual of the metered generation plus scheduled imports less metered loads and less scheduled exports. 28 Decision 20524-D01-2015 TransAlta Corporation 2013-2014 General Tariff Application Refiling in Respect of Decision 3466-D01-2015, issued September 21, 2015 Decision 2014-369, TransAlta Corporation, as Manager of the TransAlta General Partnership 2015-2016 Interim Tariff Application, issued December 22, 2014 Decision 2013-214, City of Red Deer 2012-2014 Transmission Facility Owner General Tariff Application Compliance Filing, issued June 5, 2013. 31 Decision 20818-D01-2015, FortisAlberta Inc. 2016 Annual Performance-Based Regulation Rate Adjustment Filing, issued December 17, 2015. 32 AESO Consolidated Authoritative Document Glossary 29 30 AESO 2016 ISO Tariff Update Application Page 13 of 24 Confidentiality: Public February 2, 2016 47 Losses costs are a function of volume forecasts and market-based commodity pricing forecasts. The 2016 forecast costs for losses were based on a forecast average pool price of $40.99/MWh. 2.5 Administrative Costs 48 The 2016 forecast cost for administration is $98.4 million and represents approximately 4.7% of the AESO’s transmission revenue requirement. 49 Administrative costs are defined in paragraph 1(1)(g) of the Transmission Regulation as follows: 1(1)(g) “ISO’s own administrative costs” means 50 (i) the transmission-related costs and expenses of the ISO respecting the administration, operation and management of the ISO, (ii) the transmission-related costs and expenses of the ISO respecting reliability standards and reliability management systems, and (iii) the transmission-related costs and expenses required to be paid, or otherwise appropriately paid, by the ISO, except for the following: (A) costs for the provision of ancillary services; (B) costs of transmission line losses; (C) amounts payable under TFO transmission tariffs; The AESO Board approves the AESO’s administrative costs in their entirety. However, only the transmission-related portions of those costs (as defined in subsection 1(1)(g) of the Transmission Regulation) are recovered through the ISO tariff. Further, the AESO Board Decision provided as 33 Appendix A to this application allocates administrative costs among the three functions of the AESO; namely, transmission, energy market, and load settlement. The transmission-related portions of the AESO’s administrative costs are included in the AESO’s transmission revenue requirement detailed in Table 2-1 above. 33 Appendix A, AESO Board Decision, page 7 of 11. AESO 2016 ISO Tariff Update Application Page 14 of 24 Confidentiality: Public February 2, 2016 3 2016 Tariff Update 51 In accordance with the approach referred to in section 1.1 above, this application uses the rate calculation 34 methodology approved by the Commission in Decision 3473-D01-2015 in connection with the AESO’s 2014 ISO tariff application. Specifically, the AESO has used the 2014 rate calculations included as 35 Appendix B of the AESO 2014 ISO tariff compliance filing as the template for the 2016 rate calculations, updated to reflect the transmission constraint rebalancing charge approved in Decision 20623-D0136 2015 . The 2016 rate calculations are included as Appendix C to this application, in Tables C-1 through C-16. 52 The rate calculations use the following inputs: (a) the 2016 forecast revenue requirement discussed in section 2.1 of this application; (b) the functionalization of wires costs approved for 2016 in Decision 2013-421; (c) the 2016 forecast billing determinants prepared by the AESO. 3.1 Specific Rate Changes 37 and 53 Where applicable, rates in the ISO tariff have been updated to reflect the 2016 forecast revenue requirement, 2016 wires costs functionalization, and 2016 forecast billing determinants. Specifically, levels of dollar-based and percentage of pool price amounts have been updated in the following rates: Rate DTS, Demand Transmission Service; Rate FTS, Fort Nelson Demand Transmission Service; Rate DOS, Demand Opportunity Service; Rate XOS, Export Opportunity Service; and Rate XOM, Export Opportunity Merchant Service. 54 The levels for each of the above rates have been calculated in accordance with Appendix C to this application. The updated rate sheets themselves are provided in the proposed 2016 ISO tariff included as Appendix E to this application. 55 Additional incidental changes to Rate PSC, Primary Service Credit; Rate STS, Supply Transmission Service, and Rider J, Wind Forecasting Service Cost Recovery Rider, are discussed below. 3.1.1 Rate PSC, Primary Service Credit 56 Consistent with the calculation of the 2014 primary service credit, the 2016 primary service credit is calculated as: 79% of the substation fraction ($/month) tier of the Rate DTS point of delivery charge; 79% of the first three capacity (7.5 MW, 9.5 MW, and 23 MW) tiers of the Rate DTS point of delivery charge; and 100% of the fourth capacity (remaining capacity above 40 MW) tier of the Rate DTS point of delivery charge. 57 As the Rate DTS point of delivery charge has been updated in this application, the AESO has correspondingly updated the primary service credit as provided in Table 3-1 below. The primary service 34 See footnote 1. Proceeding 3473, Exhibit 0004.00.AESO-3473, Alberta Electric System Operator 2014 ISO Tariff Compliance Filing Pursuant to Decision 2014-242, revised as discussed in Exhibit 0044.01.AESO-3473, response to information request UCA-AESO-002. 36 See footnote 2. 37 Proceeding 2718, Exhibit 0265.02.AESO-2718, Alberta Transmission System Cost Causation Study Update dated January 17, 2014, at page 7, Figure 6. 35 AESO 2016 ISO Tariff Update Application Page 15 of 24 Confidentiality: Public February 2, 2016 credit amounts determined in Table 3-1 are reflected in Rate PSC of the proposed 2016 ISO tariff included in Appendix E to this application. Table 3-1 – Calculation of 2016 Primary Service Credit Rate DTS Charge PSC Factor Rate PSC Credit Substation fraction $8,604/month 79% $6,797.00/month First (7.5 × substation fraction) MW of billing capacity $3,484.00/MW 79% $2,752.00/MW Next (9.5 × substation fraction) MW of billing capacity $2,182.00/MW 79% $1,724.00/MW Next (23 × substation fraction) MW of billing capacity $1,522.00/MW 79% $1,202.00/MW All remaining MW of billing capacity $986.00/MW 100% $986.00/MW Rate Component 3.1.2 Regulated Generating Unit Connection Costs in Rate STS, Supply Transmission Service 58 The AESO most recently provided the derivation of the regulated generating unit connection costs (“RGUCC”) charge in an attachment to the AESO’s response to information request AUC-AESO-009 in its 38 2014 ISO tariff application proceeding. That attachment included a calculation of the RGUCC charge for each calendar year to 2020, based on the original determinations of the Alberta Energy and Utilities Board (referred to below) which established the RGUCC. In general, RGUCC charges decrease every year reflecting the on-going amortization of connection costs over the lives of the previously-regulated generating units. 59 The RGUCC charge calculation was reviewed in Decision 2007-106 in connection with the AESO’s 2007 general tariff application, where the Alberta Energy and Utilities Board stated that “The Board has 39 reviewed this calculation and considers the AESO RGUCC appears to be reasonable.” A value of $121.55/MW was included for the 2016 RGUCC in the attachment to the response to information request AUC-AESO-009 in the AESO’s 2014 ISO tariff application proceeding. 60 The regulated generating unit connection cost charge has accordingly been updated to $122.00/MW in Rate STS in the proposed 2016 ISO tariff included as Appendix E to this application, being the 2016 value rounded to the nearest dollar. 3.1.4 Rider J, Wind Forecasting Service Cost Recovery Rider 61 As the AESO explained in its 2014 ISO tariff application, Rider J charges recover both costs associated with the AESO’s contracted wind forecasting service as well as variances from forecasts of costs and 40 energy initially used to determine the values of the rider. Since first being implemented in 2011, Rider J is expected to recover in 2016 all costs of the contracted wind forecasting service incurred to date. 62 On a cumulative basis, the AESO overcollected $115,692 by the end of 2015, changing from a cumulative undercollection in all prior years to a cumulative overcollection for the first time by the end of 2015. The wind forecasting service annual cost forecast for 2016 is $304,560. Annual wind powered 38 39 40 Exhibit 0109.03.AESO-2718, Attachment AUC-AESO-009. Decision 2007-106, Alberta Electric System Operator 2007 General Tariff Application, issued December 21, 2007, at page 76. Exhibit 0026.00.AESO-2718, at page 13, paragraphs 124-126. AESO 2016 ISO Tariff Update Application Page 16 of 24 Confidentiality: Public February 2, 2016 generation metered energy forecast for 2016 is about 4.3 million MWh, up slightly from metered energy for 2015 of about 4.1 million MWh. The AESO proposes to set the Rider J charge at $0.05/MWh. The AESO will continue to monitor and report this amount in future tariff applications and updates. 63 The Rider J charge has accordingly been updated to $0.05/MWh in the proposed 2016 ISO tariff included in Appendix E to this application. 3.2 2016 Forecast Billing Determinants 64 The rate calculations for the 2016 rates update are based on the AESO’s forecast of billing determinants for 2016. The AESO prepares a long-term load forecast in accordance with the Act and the Transmission Regulation. The load forecast most recently prepared by the AESO is set out in the AESO 2014 Longterm Outlook, which contains a 2016 load forecast. This 2016 load forecast was adjusted to reflect expected changes in electricity consumption in 2016 due to a decline in economic growth rate compared to that included in the AESO 2014 Long-term Outlook. The forecast 2016 billing determinants are based on this adjusted 2016 load forecast. 65 The AESO expects to publish its next long-term outlook in the second quarter of 2016. The 2016 longterm outlook will more thoroughly incorporate the changes in economic growth as well as the impacts of the new climate change policy being implemented in Alberta. However, to facilitate a tariff update as early as possible in 2016, the AESO is proceeding with this 2016 tariff update application in advance of finalizing the 2016 long-term outlook. 66 To recognize the decline in expected economic growth rate, the AESO has reduced the forecast 2016 billing determinants, based on the AESO 2014 Long-term Outlook, by 1.5%. This reduction reflects the AESO’s current estimate as it continues to work on the next long-term outlook. The AESO considers that timely tariff updates reduce Rider C charges and the associated issue of inter-customer transfers in deferral account reconciliations, and is therefore applying for its 2016 tariff update as soon as possible. 67 The AESO 2014 Long-term Outlook includes a 20-year peak load and electricity consumption forecast for Alberta. The load forecast is generated from economic growth (gross domestic product or GDP) information, oilsands production forecasts, and population projections by select consumer sectors, with regional adjustments based on historical results and participant-driven growth expectations. The AESO 2014 Long-term Outlook, including its data file, is available on the AESO website at www.aeso.ca by following the path Transmission Forecasting. 68 To develop the AESO 2014 Long-term Outlook, the AESO produces hourly load forecasts by metering point, including adjustments for load supplied through on-site generation. Metering points are then correlated to system access service accounts to develop annual profiles for forecast hourly load at each point of delivery. Billing determinants are calculated directly from the per-point-of-delivery forecast hourly load profiles. In addition, the billing determinant for billing capacity also incorporates: current contract capacity and known contract capacity changes during the forecast year for each service account; and ratchets based on historical peak demand information in the AESO’s billing system as well as new forecast peak demands during the forecast year for each service account. 69 Substation fractions are applied to billing capacities to develop billing determinants for each of the point of delivery charge capacity tiers. Substation fractions are also applied to develop the billing determinant for “equivalent” market participants, used in the calculation of the fixed ($/month) tier of the Rate DTS point of delivery charge. 70 The AESO notes that the per-point-of-delivery annual profiles for forecast hourly load as well as the perpoint-of-delivery billing determinants are considered confidential information that should not be made AESO 2016 ISO Tariff Update Application Page 17 of 24 Confidentiality: Public February 2, 2016 publicly available. Forecast hourly load data for individual points of delivery and future contract capacity changes are clearly of a commercial and financial nature that is consistently treated as confidential by the AESO. The AESO further considers that the provision of such detailed information could result in harm to a market participant’s competitive position by disclosing patterns and trends that could be used to advantage by a competitor. 71 As has been the traditional practice in AESO rate calculations, the billing determinants used in the 2016 rate calculations are provided in aggregate, in Table C-12 of Appendix C to this application. 72 Additionally, Table 3-2 below provides a comparison of the forecast billing determinants in this tariff update to those recorded for 2015. Coincident metered demand and energy billing determinants have increased by 1.8% and 5.2% respectively compared to the 2015 recorded billing determinants, while number of DTS market participants has increased by approximately 1.5%. Billing capacity (which incorporates non-coincident metered demand, demand ratchets, and contract minimums) has not changed appreciably, with an increase of approximately 5.1% in the first demand tier, an increase of approximately 2.8% in the second demand tier, a decrease of approximately 0.5% in the third demand tier and a decrease of approximately 6.2% in the last demand tier. Table 3-2 – 2016 Forecast and 2015 Recorded Billing Determinants Rate DTS Billing Determinant Units 2015 Recorded 95,650.2 93,932.1 1,718.1 1.8% Coincident Metered Demand MW-months Billing Capacity Total Billing Capacity First (7.5×SF) MW Next (9.5×SF) MW Next (23×SF) MW All Remaining MW MW-months MW-months MW-months MW-months MW-months 150,245.3 150,192.2 37,549.4 35,719.7 33,643.9 32,722.6 40,708.1 40,893.2 38,343.9 40,856.7 53.0 1,829.6 921.3 (185.1) (2,512.8) 0.0% 5.1% 2.8% (0.5%) (6.2%) Highest Metered Demand MW-months 115,223.0 117,088.4 (1,865.5) (1.6%) Metered Energy (All Hours) DTS Market Participants Pool Price (Weighted by Volume) GWh 62,004.8 58,942.2 3,062.6 5.2% customer-months 5,317.8 5,237.1 80.6 1.5% $/MWh Average Increase (Decrease) (Weighted by Revenue) 73 Increase (Decrease) Amount % 2016 Forecast 40.99 33.34 7.65 22.9% 2.0% To further examine the reasonableness of the 2016 forecast billing determinants, Table 3-3 below provides a comparison of the forecast billing determinants in this rates update application to the 2013, 2014 and 2015 recorded billing determinants. The AESO considers that the increase in billing determinants forecast for 2016 is reasonable when compared to recorded billing determinants for the two prior years and expectations for 2016 as discussed at the beginning of this section. AESO 2016 ISO Tariff Update Application Page 18 of 24 Confidentiality: Public February 2, 2016 Table 3-3 – 2016 Forecast, 2015, 2014 and 2013 Recorded Billing Determinants Rate DTS Billing Determinants 74 2016 Forecast Units 2015 Recorded 2013 2014 Recorded Recorded Coincident Metered Demand MW-months 95,650.2 93,932.1 94,058.7 91,160.3 Billing Capacity (Total) MW-months 150,245.3 150,192.2 145,958.0 140,073.3 Highest Metered Demand MW-months 115,223.0 117,088.4 116,814.7 112,713.2 Metered Energy (All Hours) GWh 62,004.8 58,942.2 59,043.3 56,959.3 Market Participants (Total) customer-months 5,317.8 5,237.1 5,244.4 5,137.7 Overall, the AESO considers that the 2016 forecast provides an accurate estimate of billing determinants for the rate calculations in this application. 3.3 Bill Impacts 75 As noted in section 2 of this application, the AESO’s 2016 forecast revenue requirement represents an increase of 11.5% over the total recorded costs for 2015. 76 At the same time, billing determinants have also changed from the 2015 forecast on which currentlyapproved rates are based. As a result, the AESO’s 2016 updated rates represents an overall increase of 8.3% over the 2015 rates currently in place, including an increase of 8.7% to Rate DTS, Demand Transmission Service, and an increase of 1.7% to Rate STS, Supply Transmission Service. 77 Deferral accounts provide certainty that the AESO’s costs will be exactly recovered by revenue, either through base rates or through the deferral account rider and reconciliations. Increases in costs paid by the AESO will therefore flow to and impact market participants through deferral accounts if rates are not increased. The changes in rates summarized above improve the timeliness and accompanying accuracy of the recovery of costs from market participants. 78 The increases to the different components of Rate DTS are provided in Table 3-4 below. The Rate DTS increase of 8.7% represents a revenue-weighted average increase over all components of Rate DTS. 79 Individual increases experienced by market participants will vary, depending on the specific characteristics of a market participant’s service including peak demand coincidence, billing capacity, load factor, and hourly pool price and transmission constraint rebalancing charge at the time of usage. 80 To allow individual market participants to estimate the impact of the 2016 rates on their own Rate DTS bills, the AESO has included a bill impact estimator as Table C-16 in the rate calculations included as Appendix C to this application. The bill impact estimator calculates bills for a given set of billing inputs under both the current 2015 Rate DTS and the updated 2016 Rate DTS, to allow the impact of the rates update on an individual service to be estimated. AESO 2016 ISO Tariff Update Application Page 19 of 24 Confidentiality: Public February 2, 2016 Table 3-4 – Increase (Decrease) for 2016 Rate DTS Components Rate DTS Charge Bulk System Coincident Demand Energy Local System Billing Capacity Energy Point of Delivery Participant × SF First (7.5 × SF) MW BC Next (9.5 × SF) MW BC Next (23 × SF) MW BC Remaining MW BC Operating Reserve Transmission Constraint Rebalancing Charge Voltage Control Other System Support Net Change (revenue weighted) Unit Proposed (1 Apr 2016) Current (1 Jan 2016) Increase (Decrease) $/MW $/MWh $10,175.00 $1.17 $9,305.00 $1.09 9.3% 7.3% $/MW billing $/MWh $2,333.00 $0.81 $2,162.00 $0.76 7.9% 6.6% $/month $/MW $/MW $/MW $/MW $8,604.00 $3,484.00 $2,182.00 $1,522.00 $986.00 $7,865.00 $3,184.00 $1,994.00 $1,391.00 $901.00 9.4% 9.4% 9.4% 9.4% 9.4% % of Pool Price 6.66% 6.41% $/MWh $0.06 $0.00 $/MWh $/MW $0.06 $46.00 $0.05 $41.00 3.9% NA 20.0% 12.2% 8.7% 81 The changes to the different components of Rate STS are provided in Table 3-5 below. The Rate STS increase of 1.7% represents a revenue-weighted average increase over all components of the rate. 82 Individual decreases or increases experienced by market participants will vary, depending on the specific characteristics of a market participant’s system access service including whether it includes a previouslyregulated generating unit subject to the regulated generating unit (“RGU”) connection costs charge. Table 3-5 – Increase (Decrease) for 2016 Rate STS Components Rate STS Charge Losses RGU Connection Costs Net Change (revenue weighted) 83 Unit % of Pool Price $/MW Proposed (1 Apr 2016) 4.06% $122.00 Current (1 Jan 2016) 3.92% $149.00 Increase (Decrease) 3.6% (18.1%) 1.7% In particular, the AESO notes that the loss factors provided in Table 3-5 are representative average loss factors only. The actual losses charge applicable to an individual market participant will be based on a location-specific loss factor determined in accordance with section 501.10 of the ISO rules, Transmission Loss Factor Methodology and Requirements, as specified in Rate STS. The AESO notes that the losses AESO 2016 ISO Tariff Update Application Page 20 of 24 Confidentiality: Public February 2, 2016 41 charge remains as approved on an interim basis in Commission Decision 2014-242, and that locationspecific loss factors will be established using a methodology determined in Commission Proceeding 42 790. 41 42 Decision 2014-242, Alberta Electric System Operator 2014 ISO Tariff Application and 2013 ISO Tariff Update, issued August 21, 2014, paragraph 730. Proceeding 790, Milner Power Inc. Complaint Against the ISO Line Loss Rule, Registered August 25, 2015. AESO 2016 ISO Tariff Update Application Page 21 of 24 Confidentiality: Public February 2, 2016 4 2016 Maximum Investment Levels Update 84 The tariff update approach described in section 1.1 of this application includes updating investment amounts approved in the most recent comprehensive tariff application reflecting an escalation factor based on a composite of specified recent inflation indices. 85 The AESO has accordingly updated the composite inflation index used for developing the point of delivery cost function to 2016, using additional Statistics Canada cost index values and the most recent Conference Board of Canada forecast of the Alberta consumer price index. Table 4-1 below provides the composite inflation index values for 2014 and 2015, as included in the 2014 ISO tariff filing and the 2015 ISO tariff update, and for 2016 as updated in this application. Values prior to 2014 are excluded from Table 4-1 as they do not affect the escalation factor. Table 4-1 – Escalation Factor for Composite Inflation Index Year Basis Present Value Factor 2014 Tariff Application 2014 Forecast 1.5727 2015 Tariff Update 2015 Forecast 1.5834 2016 Tariff Update 2016 Forecast 1.6201 1.62012016 / 1.57272014 = 1.0302 2016 Escalation Factor (over 2014) 86 The resulting escalation factor for updating the 2016 maximum investment levels in section 8 of the ISO tariff is 1.0302, which represents a small increase to the 2016 maximum investment levels. The increase reflects increases in the latest underlying indices used for the composite index. The detailed calculation of the composite inflation index is included in Appendix D of this application. 87 The AESO has applied the resulting 1.0302 escalation factor to the 2014 Rate DTS maximum investment levels to determine the 2016 Rate DTS maximum investment levels, as summarized in Table 4-2 below. Table 4-2 also includes the calculation of the corresponding Rate PSC maximum investment levels for each year. AESO 2016 ISO Tariff Update Application Page 22 of 24 Confidentiality: Public February 2, 2016 Table 4-2 – Calculation of 2016 Maximum Investment Levels Rate DTS Investment PSC Factor Rate PSC Investment $76 050/year 21% $15 970/year First (7.5 × substation fraction) MW of contract capacity $30 800/MW/year 21% $6 470/MW/year Next (9.5 × substation fraction) MW of contract capacity $19 300/MW/year 21% $4 050/MW/year Next (23 × substation fraction) MW of contract capacity $13 450/MW/year 21% $2 820/MW/year All remaining MW of contract capacity $8 700/MW/year 0% $0/MW/year 2016 Escalation Factor (over 2014) 1.0302 Tier 2014 Maximum Investment Levels Substation fraction (for new points of delivery only) 2016 Maximum Investment Levels Substation fraction (for new points of delivery only) $78 350/year 21% $16 450/year First (7.5 × substation fraction) MW of contract capacity $31 750/MW/year 21% $6 670/MW/year Next (9.5 × substation fraction) MW of contract capacity $19 900/MW/year 21% $4 180/MW/year Next (23 × substation fraction) MW of contract capacity $13 850/MW/year 21% $2 910/MW/year All remaining MW of contract capacity $8 950/MW/year 0% $0/MW/year AESO 2016 ISO Tariff Update Application Page 23 of 24 Confidentiality: Public February 2, 2016 5 Conclusion 88 Based on all of the foregoing, the AESO submits that the tariff updates proposed in this application are just and reasonable, and comply with the update methodology approved by the Commission for the AESO’s tariff. The AESO respectfully requests that the Commission approve this tariff update application, including (i) the updated amounts included as Appendix C to this application, and (ii) the proposed 2016 ISO tariff Rate DTS, Rate FTS, Rate DOS, Rate XOS, Rate XOM, Rate PSC, Rate STS, Rider J and Section 8 included as Appendix E to this application, effective April 1, 2016. If the timing of this application does not permit the granting of final approval prior to April 1, 2016, the AESO also requests that the Commission approve this application on an interim refundable basis effective as of that date. The AESO further requests that the Commission issue its approval (whether on an interim or final basis) on or before March 31, 2016, as this is the last approval date that will allow the proposed tariff updates to be implemented by the AESO effective April 1, 2016 on a prospective basis. . 89 All of which is respectfully submitted this 2nd day of February, 2016. Alberta Electric System Operator Per: “Heidi Kirrmaier” Heidi Kirrmaier Vice-President, Regulatory AESO 2016 ISO Tariff Update Application Page 24 of 24 Confidentiality: Public February 2, 2016