...

AESO 2005-2006 GTA Refiling Technical Meeting on Direction 6 Response Agenda

by user

on
Category: Documents
32

views

Report

Comments

Transcript

AESO 2005-2006 GTA Refiling Technical Meeting on Direction 6 Response Agenda
AESO 2005-2006 GTA Refiling Technical
Meeting on Direction 6 Response
(Corrected)
October 26, 2005
AESO 2005-2006 GTA Refiling
Technical Meeting on Direction 6 Response
John Martin, Regulatory
Stakeholder Presentation
October 26, 2005 — Calgary
Agenda
● Discussion limited to $/month POD charge
● Background to refiling and supplemental response
● Review of POD data
● Preliminary responses to EUB Information
Requests
● Process and options
● Questions
● Next steps
2
AESO Stakeholder Meeting
1
AESO 2005-2006 GTA Refiling Technical
Meeting on Direction 6 Response
(Corrected)
October 26, 2005
Original Direction 6
● Contained in Decision 2005-096 issued by EUB on
August 28, 2005
● Direction 6 stated (in part):
“Levy a customer-related POD charge, as
suggested in the TCCS [Transmission Cost
Causation Study]”
● AESO interpreted “POD charge” as it is defined
and used in its tariff
● AESO submitted refiling on September 27, 2005
noting concerns about $/month component of
POD charge
3
Interpretation of “POD Charge”
● POD is defined in tariff and is basis for DTS
contracts and DTS billing of customers
● POD equates to DTS contract
● POD equates to settlement point for billing
● Evidence provided during GTA proceeding was
consistent with POD as defined above
● Bill impact calculation included in EUB decision
applied full POD charge at dual-use site
● No parties (to AESO’s recollection) argued for
application of DTS-STS or equivalent ratio to POD
charge during 2006 GTA proceeding
4
AESO Stakeholder Meeting
2
AESO 2005-2006 GTA Refiling Technical
Meeting on Direction 6 Response
(Corrected)
October 26, 2005
EUB Clarification
● On October 20 the EUB clarified their intent that
the $/month component apply on a substation, not
POD, basis:
“…the new customer charge component of the
DTS rate ordered in Direction 6 would be
apportioned amongst the customers served by a
particular POD rather than applied in full to each
customer served by that POD”
5
Concerns Expressed to AESO
● Bill impact
● Small single DTS PODs (DISCO-served)
● Multiple DTS PODs
● Dual-use (DTS and STS) PODs
● Isolated generation sites (DISCO-served)
● Misalignment with costs
● Customer-owned substations
● PODs receiving Primary Service Credit
● “Changing of rules”
● Inability to respond to new rate structure
● Customers terminating service
AESO Stakeholder Meeting
6
3
AESO 2005-2006 GTA Refiling Technical
Meeting on Direction 6 Response
(Corrected)
October 26, 2005
AESO Response
● AESO identified concerns with $/month charge in
September 27 refiling
● Additional discussions with customers and further
review convinced the AESO the $/month charge
as refiled was problematic
● No immediate solution was apparent
● No time existed for stakeholder consultation
● AESO therefore decided to provide a
supplemental response, in a manner similar to the
alternative response provided to Direction 5A but
without public stakeholder consultation
7
$/Month Component Proposals
● In AESO’s September 27 refiling:
● $18,648.00/month at each Point of Delivery
● In AESO’s October 7 supplemental response:
● $4,252.00/MW for Billing Capacity less than 5 MW, or
● $21,260.00/month for Billing Capacity 5 MW or greater
● In response to EUB’s October 20 clarification:
● $22,144.00/month × Substation Fraction at each Point of
Delivery
DTS Capacity
Sub Fraction =
∑ All DTS and STS Capacities at Substation
8
AESO Stakeholder Meeting
4
AESO 2005-2006 GTA Refiling Technical
Meeting on Direction 6 Response
(Corrected)
October 26, 2005
No Clear Winner
● No proposal addresses all concerns
● New rate needs to be implemented on January 1
● Time needed for implementation in AESO’s billing
system
● AESO believes rate for 2006 should be approved
on a final basis, with further refinement occurring
as part of 2007 GTA development
● What should 2006 rate be?
● How does EUB determine what to approve?
● What further process is required?
9
Background Data
● AESO has 480 DTS Points of Delivery
● AESO has 450 substations serving DTS PODs
● After applying Substation Fractions, AESO has
406 “equivalent” substations serving DTS PODs
10
AESO Stakeholder Meeting
5
AESO 2005-2006 GTA Refiling Technical
Meeting on Direction 6 Response
(Corrected)
October 26, 2005
Data Category Definitions
● In response to EUB clarification and IRs
● AESO-served direct connected PODs: served at
transmission voltage and billed by AESO
● DISCO-served direct connected PODs: served at
transmission voltage and billed by DISCO
● DISCO-served distribution PODs: served at distribution
voltage and billed by DISCO
● Dual-use: at least one DTS POD and at least one STS
POS at same substation
● Multi-DTS: at least two DTS PODs and no STS POS at
same substation
● Single DTS: one DTS POD at substation
11
AESO-Served Direct Connected
PODs
Dual-Use
Less Than 5 MW
Number of PODs
17
Average Capacity
0.9 MW
Average Load Factor
11%
Average Monthly Bill
$2,098
5 MW to Less Than 20 MW
Number of PODs
6
Average Capacity
7.5 MW
Average Load Factor
9%
Average Monthly Bill
$15,222
Greater Than 20 MW
Number of PODs
8
Average Capacity
71.6 MW
Average Load Factor
4%
Average Monthly Bill
$126,827
Multi-DTS Single DTS
Total
–
–
–
–
–
–
–
–
17
0.9 MW
11%
$2,098
3
14.6 MW
58%
$62,451
6
15.1 MW
27%
$55,409
15
12.0 MW
26%
$40,743
1
54.4 MW
93%
$307,712
2
23.6 MW
41%
$92,627
11
61.3 MW
19%
$137,053
12
AESO Stakeholder Meeting
6
AESO 2005-2006 GTA Refiling Technical
Meeting on Direction 6 Response
(Corrected)
October 26, 2005
DISCO-Served Direct Connected
PODs
Dual-Use
Less Than 5 MW
Number of PODs
9
Average Capacity
1.5 MW
Average Load Factor
8%
Average Monthly Bill
$3,050
5 MW to Less Than 20 MW
Number of PODs
3
Average Capacity
15.0 MW
Average Load Factor
21%
Average Monthly Bill
$30,729
Greater Than 20 MW
Number of PODs
3
Average Capacity
33.3 MW
Average Load Factor
35%
Average Monthly Bill
$122,302
Multi-DTS Single DTS
Total
3
3.4 MW
77%
$23,760
27
2.4 MW
50%
$27,537
39
2.2 MW
42%
$21,596
8
12.0 MW
69%
$58,944
31
9.4 MW
64%
$57,467
42
10.3 MW
62%
$55,838
4
56.1 MW
86%
$301,831
20
48.0 MW
77%
$250,546
27
47.6 MW
74%
$243,895
13
DISCO-Served Distribution PODs
Dual-Use
Less Than 5 MW
Number of PODs
6
Average Capacity
1.9 MW
Average Load Factor
30%
Average Monthly Bill
$5,749
5 MW to Less Than 20 MW
Number of PODs
12
Average Capacity
9.6 MW
Average Load Factor
46%
Average Monthly Bill
$40,162
Greater Than 20 MW
Number of PODs
6
Average Capacity
45.2 MW
Average Load Factor
34%
Average Monthly Bill
$159,274
Multi-DTS Single DTS
Total
4
3.6 MW
69%
$21,765
33
2.1 MW
53%
$26,662
43
2.2 MW
51%
$23,288
10
9.8 MW
76%
$51,345
141
12.2 MW
67%
$70,382
163
11.8 MW
66%
$66,989
2
47.9 MW
75%
$222,302
117
42.6 MW
68%
$199,685
125
42.8 MW
67%
$198,107
14
AESO Stakeholder Meeting
7
AESO 2005-2006 GTA Refiling Technical
Meeting on Direction 6 Response
(Corrected)
October 26, 2005
1(a) Basis for Consideration
● Record in 2005-2006 GTA proceeding (AESO’s
application, IR responses, evidence, argument,
and reply) commented on:
● Impact on smaller customers
● Use of demand ($/MW) charge as alternative to customer
($/month) charge
● 5 MW as threshold below which special consideration
could be given to bill impact
● AESO’s alternate rate design could be considered
in the context of information already on the record
15
1(b) Impact on Larger Customers
● Customer ($/month) component would increase to
$22,144/month from $18,648/month for a
substation serving a single DTS POD
● From 5.6-10% increase for 5 MW single DTS POD
to 0.4-1.7% increase for 100 MW single DTS
POD, depending on load factor
● Compared to DTS rates in September 27 refiling
16
AESO Stakeholder Meeting
8
AESO 2005-2006 GTA Refiling Technical
Meeting on Direction 6 Response
(Corrected)
October 26, 2005
2(a) Small Site Breakdown
● 32 “small site” customers are DISCO-served direct
connected PODs
● Represents about 2% of AESO’s annual DTS
revenue requirement
17
2(b) DISCO Flowthrough Change
● DISCO flowthrough of AESO charges at
transmission connected sites remains appropriate
for harmonization between AESO and DISCOs
● Has been in place since 1998
● Allows costs to be directly assigned when able to
be identified
18
AESO Stakeholder Meeting
9
AESO 2005-2006 GTA Refiling Technical
Meeting on Direction 6 Response
(Corrected)
October 26, 2005
2(c) DISCO Averaging Alternative
● DISCO average would impose an average rate
representing an allocation of costs on customers
for whom AESO actual costs are known
● Assuming a DISCO average would be lower than
AESO actual costs, other DISCO customers would
be subsidizing the transmission connected DISCO
customers
● If DISCO average is higher than AESO actual
costs, DISCO customer would argue for
flowthrough of costs rather than average
19
3(a-c) Non-Affiliated Dual-Use Data
● IR seeks information on dual-use sites where
parties responsible for DTS and STS costs are
not affiliated
● AESO has no formal information on contractual
arrangements between parties responsible for
DTS and STS costs
● 17 “small site” customers are AESO-served direct
connected PODs at dual-use sites
● Represents about 0.1% of AESO’s annual DTS
revenue requirement
20
AESO Stakeholder Meeting
10
AESO 2005-2006 GTA Refiling Technical
Meeting on Direction 6 Response
(Corrected)
October 26, 2005
3(d-e) Non-Affiliated Dual-Use
Contracts
● AESO does not know details of relationship
between non-affiliated parties responsible for DTS
and STS costs
● AESO cannot provide any assurances that DTS
customer is not receiving the benefit of STS
reductions
21
4(a-c) Affiliated Dual-Use Data
● IR seeks information on dual-use sites where
parties responsible for DTS and STS costs are
affiliated
● AESO has no formal information on contractual
arrangements between parties responsible for
DTS and STS costs
22
AESO Stakeholder Meeting
11
AESO 2005-2006 GTA Refiling Technical
Meeting on Direction 6 Response
(Corrected)
October 26, 2005
4(d) Fixed Costs vs. Size
● AESO does not have cost information available
● Data submitted in response to Direction 13A
suggests some differences
● 0-15 MW: $1,300,000 + ($434,000/MW × Capacity)
● 15-60 MW: $2,300,000 + ($108,000/MW × Capacity)
● Large scatter in data for similar size projects
● Cost data does not account for distinctions
between radial line costs, transformation costs,
and costs for other items such as buswork,
switchgear, communications equipment, and site
itself
23
4(e) Postage Stamp Principle
● Electric Utilities Act, section 30(3):
“The rates set out in the [ISO] tariff…shall not be
different…as a result of the location…on the
transmission system”
● Rate differences based on size do not violate the
postage stamp principle
24
AESO Stakeholder Meeting
12
AESO 2005-2006 GTA Refiling Technical
Meeting on Direction 6 Response
(Corrected)
October 26, 2005
5(a-b) 12 CP Billing Implementation
● It would take about 10 to 12 weeks in total to
develop, program, test, and move to production
billing with a 12 CP approach.
● Direction in mid-November 2005 could be
implemented by February 1, 2006
● Direction in late November or early to midDecember 2005 could be implemented by
March 1, 2005
● 12 CP billing would cost $25,000 to $50,000 more
to implement than 1 CP billing
25
5(c) Interim Rate With True-Up
● The AESO recommends 1 CP billing approach for
Bulk System demand component
● Alternatively, the AESO recommends demand and
energy charges as proposed in its 2006 GTA
● The AESO does not support implementing a
revised rate structure through the deferral account
● Deferral account trues up differences in costs and
revenues, not in rate structure
● Seems more like retroactive rate making than deferral
account reconciliation
● Customers should know basis for charges in advance
26
AESO Stakeholder Meeting
13
AESO 2005-2006 GTA Refiling Technical
Meeting on Direction 6 Response
(Corrected)
October 26, 2005
6(a-b) Small Customer Rate Classes
● Rate classes should be based on distinct usage or
cost patterns
● Usage patterns have not been demonstrated to be
different for small customers
● Cost data is not available to assess differences for small
customers
● Establishing rate classes should be considered
after comprehensive investigation and through
consultation and regulatory process
● Stakeholders should have opportunity for input
27
7(a-b) Shared Substation Impacts
● Revised $/month charge would be:
● $22,144.00/month × Substation Fraction at each Point of
Delivery
28
AESO Stakeholder Meeting
14
AESO 2005-2006 GTA Refiling Technical
Meeting on Direction 6 Response
(Corrected)
October 26, 2005
Refiling Process to Date
● AESO refiled on September 27, 2005
● Parties provided comments
● EUB asked IRs on October 19 (with later
supplemental IRs)
● AESO to respond to IRs by October 28
● Parties to provide reply comments by November 4
● Tariff legislated to be effective January 1, 2006 by
Transmission Regulation
29
Discussion of Process
● Has EUB clarification addressed primary
concerns?
● Should AESO withdraw its supplemental response
to Direction 6?
● If so, what should EUB rely on to approve POD charge?
● Can other alternatives be offered to the EUB? In
what manner or process?
30
AESO Stakeholder Meeting
15
AESO 2005-2006 GTA Refiling Technical
Meeting on Direction 6 Response
(Corrected)
October 26, 2005
Discussion and Questions
● Is there more information that should be included
in IR responses?
● Will all relevant information be provided as part of
refiling process?
31
AESO Contacts
● Rob Senko
Director, Regulatory
(403) 539-2786
[email protected]
● John Martin
Manager, Regulatory
(403) 539-2468
[email protected]
● Information can be accessed on www.aeso.ca by
following path Quick Links ► Current Regulatory
Activities ► AESO 2005-2006 General Tariff
Application Refiling
32
AESO Stakeholder Meeting
16
Fly UP