Alberta Electric System Operator AESO 2006 General Tariff Application January 31, 2005
by user
Comments
Transcript
Alberta Electric System Operator AESO 2006 General Tariff Application January 31, 2005
Alberta Electric System Operator AESO 2006 General Tariff Application January 31, 2005 Section 6 — Terms and Conditions of Service Page 1 of 42 6 5 10 15 20 25 2006 TERMS AND CONDITIONS OF SERVICE The AESO proposes the following changes to its terms and conditions of service for 2006: (a) Extensive revision of the customer contribution policy, including a maximum local investment level of $27,000 per MW of DTS contract capacity per year of contract term, as well as waivers for contributions from distributors at multiple-user PODs; (b) Introduction of a $10,000-$50,000/MW system contribution for generators refundable over ten years with satisfactory performance, in accordance with Part 4 of the Transmission Regulation; (c) Revisions to streamline the system access application process concurrent with a simplification and reduction of application fees; (d) Definition of Maximum TMR Compensation as a cost determination methodology to limit the amount that can be paid for transmission must-run service, in accordance with Section 23 of the Transmission Regulation; and (e) Updating and simplification throughout the terms and conditions. Of those changes listed above, the following were originally filed as part of the AESO’s 2005 tariff application on October 3, 2004: • revision of customer contribution policy, • revisions to align with revised system application process, and • updating and simplification throughout. These items have been updated, revised if necessary, and refiled as part of this 2006 tariff application, and are intended to replace in their entirety the similar material originally filed for 2005. The introduction of a system contribution for generators and the definition of Maximum TMR Compensation are added to this application as required by the Transmission Regulation. The specific changes are described in more detail in the following sections. 30 6.1 35 40 Customer Contribution Policy The AESO’s current customer contribution policy was approved in Decision 2001-6 on the ESBI Alberta Ltd. (EAL) 2001 General Rate Application Customer Contribution Policy, and was built on four major principles: (a) Harmonization with the contribution policies of distribution facility owners (DFOs) inasmuch as the AESO’s contribution policy would be revenue-based and 80% of transmission projects would not require a contribution, such that neither distribution nor transmission contribution policy would provide an incentive for a customer to prefer connection to one system over the other; (b) Imposition of an economic siting discipline on customers; (c) Consistency with the “postage stamp” principle set out in Section 30(3) of the Electric Utilities Act (“The rates set out in the tariff shall not be different for owners of electric distribution systems, customers who are industrial systems or a person who has Alberta Electric System Operator AESO 2006 General Tariff Application January 31, 2005 Section 6 — Terms and Conditions of Service Page 2 of 42 (d) 5 made an arrangement under section 101(2) as a result of the location of those systems or persons on the transmission system….”); and Consistent application to all load customers. Decision 2001-6 also included approval for the classification of project costs as system costs or customer-related costs, with allowance for discretionary application in unique circumstances. Generally, system costs are not subject to a customer contribution and were described as those associated with a looped extension. Customer-related costs may be subject to a contribution and were described as those associated with a radial extension. 10 The EUB also provided the following direction in Decision 2001-6: 2. 15 20 25 In view of the growing experience with the new policy and its interaction with the DISCO’s contribution policy, the Board directs EAL to address any needed changes to the contribution policy at the next GTA. Since implementation of the current contribution policy as approved in that Decision, the AESO considers that the policy can be refined to better meet the objectives noted above and to reduce the need for discretionary classification of project costs. The AESO is proposing changes to four specific areas of its customer contribution policy: • classification of system and local costs; • form and level of the local investment, • waivers for multiple-user Points-of-Delivery (PODs); and • applicability to dual-use (demand and supply service at the same point of connection) customers. The proposed change to the classification of system and local costs applies to both load customers and generators, in the determination of customer-related costs. The remaining changes to the AESO’s customer contribution policy apply to load customers only. 30 Generators will continue to pay all customer-related costs of their interconnection as in the current contribution policy. In accordance with Part 4 of the Transmission Regulation, a generator will also pay a system contribution. The system contribution is discussed in Section 6.2 of this Application. 35 40 Classification of System and Customer-Related Costs — The initial step in determining a customer contribution is classifying the project costs as system or customer-related, with the resulting contribution based on the customer-related costs and the contribution policy. Despite the defined classification of system and customer-related costs currently in use, some discretion on the part of the AESO in assigning certain project costs has occasionally been required. In particular, system enhancement costs, such as protection upgrades, may be defined as system or customer-related depending upon who benefits from the enhancement. This approach introduces a level of unpredictably for customers. Alberta Electric System Operator AESO 2006 General Tariff Application January 31, 2005 Section 6 — Terms and Conditions of Service Page 3 of 42 5 10 15 There are essentially three approaches to classifying system and customer-related costs, as illustrated in Figure 6.1.1. In these alternatives, “bulk system” refers to facilities that are used to serve a large number of transmission customers, including looped facilities. “System enhancements” refers to upgrades of existing facilities, including breakers, protection, and communication systems, as well as shared portions of radial lines. “Local connection” refers to all new facilities serving just the new customer, including all contiguous construction from the customer substation along newly-constructed radial line, including a new breaker at an existing substation if required. In each alternative, local connection costs are classified as customer-related and bulk system costs are classified as system. However, the classification of system enhancement costs varies between the three alternatives. Figure 6.1.1 Alternative Classifications of Project Costs Customer-Related 20 1 Local Connection System Costs System Enhancement Customer-Related Costs 25 2 Local Connection System Enhancement Bulk System System Costs Bulk System 30 Customer-Related Costs 35 40 3 Local Connection System Enhancement System Costs Bulk System In Alternative 1, the customer-related cost is limited to local connection costs, and system enhancement costs and bulk system costs are both classified as system costs. This alternative provides a good level of predictability for customers and may be consistently applied to both load and generation projects. Alberta Electric System Operator AESO 2006 General Tariff Application January 31, 2005 Section 6 — Terms and Conditions of Service Page 4 of 42 5 In Alternative 2, the customer-related costs include all local connection costs as well as system enhancement costs determined to benefit the interconnecting customer. The balance of system enhancement costs and the bulk system costs are classified as system costs. This alternative most closely resembles the current approach and was assumed not to change the current level of unpredictability of customer-related costs. 10 In Alternative 3, the customer-related costs include all local connection and system enhancement costs, and only bulk system costs are classified as system costs. This alternative provides a good level of predictability for customers but results in inconsistency between load and generation projects. 15 To reduce the need for discretionary cost classification in Alternative 2, to provide a high level of predictability, and to provide consistency in the treatment of load and generator projects, the AESO proposes to define all system enhancement costs as system costs, as illustrated in Alternative 1. 20 25 Specifically, the AESO proposes that system costs be defined as those costs relating to facilities constructed for the use and benefit of several individual points of connection, including upgrading of such facilities arising from load or supply increases of one or more customers. Costs will typically be classified as system when the facilities are non-contiguous to the local connection or when construction consists of upgrades to the existing looped network. System costs will include the cost of upgrading existing breakers and protection to accommodate the customer and any upgrades to communications systems at existing substations. In all cases, for costs to be considered system the interconnection configuration must accord with AESO standards. Where the interconnection configuration requested by the customer does not conform to AESO standards, the AESO will deem all excess costs (that is, costs above those which would arise from facilities which do conform to AESO standards) to be customer-related costs and payable by the customer in accordance with Article 9.3(c).. 30 35 In addition to such non-standard configuration costs as set out above, customer-related costs are defined as those costs relating to local connection facilities typically comprising the customer substation and all contiguous construction from the customer substation back along any newly constructed line, including a new breaker if required at an existing substation. Where the local connection includes only facilities that tap into an existing transmission line, the customer-related costs will not include any upgrades to existing substations. The cost of communications both at the customer’s substation and back to the existing system will be considered customer-related costs, but any other enhancements to the existing system will be excluded from customer-related costs. 40 The proposed clarification of customer-related and system costs as just discussed was assumed to have no material effect on the contribution levels discussed in the next section, although the AESO recognized that the change could impact the customer contributions determined for individual projects. The proposed definitions would be implemented on the Alberta Electric System Operator AESO 2006 General Tariff Application January 31, 2005 Section 6 — Terms and Conditions of Service Page 5 of 42 effective date of the approved tariff, and contributions for projects already committed to prior to that date would not be re-assessed to reflect the new definitions. 5 Calculation of Customer Contribution — The AESO proposes to change the calculation of the Customer Contribution, as set out in paragraph 9.3 of the proposed terms and conditions of service and reproduced below: The Customer’s contribution to the Customer-related costs will be calculated as follows: 10 Customer Contribution = Customer-related costs less the Local Investment 15 20 25 Where: (a) for a Customer taking service under Rate DTS: (i) the maximum Local Investment = $27,000/MW of DTS Contract Capacity/Year of DTS contract term; (ii) the Local Investment will not exceed the Customer-related costs; and (iii) the DTS System Access Service Agreement term = 5 to 20 years, as determined by the Customer; and (b) for a Customer taking service under any other rate, the maximum Local Investment = $0. The proposed calculation is essentially a unit $/MW/year maximum, and is significantly simpler than the current calculation as described in paragraph 9.4 of the current Terms and Conditions of Service: The Customer’s contribution to the demand-related costs shall be calculated as follows: 30 (a) 35 40 Customer contribution = demand-related costs – roll-in ceiling, where: (i) roll-in ceiling = commitment term amount + revenue-related amount; (ii) commitment term amount = $400,000 for every one-year commitment term after the first five-year commitment term. A commitment term is a period within which the Customer commits to maintain its Contract Capacity at or above its initial Contract Capacity. The maximum commitment term amount is $6 million. (iii) revenue-related amount = three times the levelized annual revenue from the new or expanded service, where the levelized revenue is determined based on the projected Contract Capacities that are contracted at the time of the calculation of the Customer contribution. The discount rate to be used in the calculation of the levelized annual revenue shall be that established under Article 9.12. Alberta Electric System Operator AESO 2006 General Tariff Application January 31, 2005 Section 6 — Terms and Conditions of Service Page 6 of 42 (b) If the calculation in (a) results in a negative Customer contribution, no Customer contribution is payable. The AESO will make no payment to the Customer with respect to any excess of the roll-in ceiling over the demandrelated costs. 5 (Note that the AESO is now using the more common term “maximum investment” rather than “roll-in ceiling”, in response to stakeholder feedback on unfamiliarity with the “roll-in ceiling” term. Both terms represent the same concept, recognizing that it is the transmission facility owner (TFO) who would make the “investment” in facilities, not the AESO.) 10 15 20 25 30 35 40 The proposed form of the maximum local investment provides better harmonization with the similarly-structured load-based investment policies of most distribution facility owners (DFOs). By using an average unit investment that varies with contract term, the maximum local investment also allows customers to lessen the effect of eliminating the current commitment term amount by contracting for a longer DTS contract term. The EUB previously stated (Decision 2001-6 on the ESBI Alberta Ltd. (EAL) 2001 General Rate Application Customer Contribution Policy, page 60) that by including a revenue-related amount in the roll-in ceiling EAL had followed “the Board’s direction to develop a contribution policy based on the concept of excess of project cost over supporting revenue for the connection of customer costs for customers….” However, the AESO notes that the commitment term amount of the roll-in is generally substantially greater than the revenuerelated amount of the roll-in, and considers that moving to a maximum local investment based on a unit $/MW/year amount more closely aligns with revenue based on $/MW and $/MWh rate components. The inclusion of a direct revenue-related amount in the current contribution calculation also raises some concerns for the AESO with respect to the significant increases to DTS rate levels resulting from the implementation of the Transmission Regulation’s requirement that all costs of the transmission system (except for losses) be allocated to load customers and exporters, as discussed in Sections 4.1 and 4.2 of this Application. In Decision 2001-38 on ATCO Electric’s 2001-2002 Distribution Tariff Phase II, the EUB stated (page 120): The Board also notes with concern the impact on investment levels of potential changes in rate levels and structures…. The Board does not consider that rate rebalancing or changes in revenue to cost ratios should automatically result in a change in the investment levels for the affected rate classes. Moving to a maximum local investment based on a unit $/MW/year amount eliminates changes to investment levels resulting directly from a change to rate levels. Alberta Electric System Operator AESO 2006 General Tariff Application January 31, 2005 Section 6 — Terms and Conditions of Service Page 7 of 42 Finally, the AESO recognizes that the current commitment term amount provides customers with the opportunity to select contract terms in yearly increments, and has therefore retained that provision in the proposed contribution calculation. 5 10 15 Level of Proposed Unit Investment Amount — In the proceedings culminating in Decision 2001-6 on the EAL 2001 General Rate Application Customer Contribution Policy, EAL provided background on the development of the current roll-in ceiling. In particular, EAL noted its intention to minimize intergenerational inequities by setting a roll-in level so that 80% of transmission projects subject to a contribution calculation would not result in a customer contribution. In Decision 2001-6 the EUB noted (page 70): The level of the Roll-in Ceiling appears to have been chosen…so that 80% of system expansion projects would not require a contribution. The Board considers this to be a fair manner to set the roll-in level as it preserves a balance between the need of new customers for service without a need for subsidy from existing customers. In practice, the current roll-in ceiling has not met that 80/20 target, as more than 90% of such projects have not required a customer contribution. 20 25 30 Through analysis, the AESO has determined that a maximum local investment of $27,000/MW/year can be expected to more closely reach the intended result where 80% of transmission projects would not require a customer contribution. As the AESO has a limited number of transmission projects subject to a customer contribution calculation in any year, the analysis included a sample comprised of ten recent projects and fifty scenario projects. The scenario project costs were estimated using various high level substation configurations with differing line components and SCADA requirements. Table 6.1.1 provides the results of the analysis for the proposed contribution policy. Data from the table is also illustrated in Figure 6.1.2. Based on the analysis and as illustrated in Table 6.1.1 and Figure 6.1.2, a maximum local investment of $27,000/MW/year would more closely align the AESO’s contribution policy with a goal where 80% of transmission projects do not require a contribution. 35 40 The AESO also examined ten recent projects to assess whether the proposed change to the classification of system and customer-related costs (as discussed previously) would shift costs from customer-related to system. Based on that analysis, customer-related costs are not materially reduced as a direct result of the proposed classification and the level of the proposed unit investment amount does not need to be adjusted to accommodate the proposed classification of system and customer-related costs. Alberta Electric System Operator AESO 2006 General Tariff Application January 31, 2005 Section 6 — Terms and Conditions of Service Page 8 of 42 Table 6.1.1 5 10 15 20 25 30 35 40 DTS Capacity MW 3.0 3.0 3.0 3.0 4.0 4.0 4.0 4.0 5.0 5.0 5.6 5.6 6.0 6.0 6.0 6.0 6.0 6.1 6.1 6.4 7.0 7.0 7.9 7.9 8.0 9.0 10.0 10.0 10.0 10.0 10.0 10.5 10.5 11.0 11.0 12.0 13.0 20.0 Comparison of Customer Contributions Under Current and Proposed Contribution Policies for Analyzed Projects Project Cost $ 000 000 $ 1.8 1.8 2.1 2.1 1.9 2.0 2.1 2.2 1.8 2.4 3.4 3.4 2.0 2.0 3.1 3.2 5.1 2.5 2.5 5.1 1.8 1.8 3.2 3.5 3.7 1.8 5.2 5.2 10.8 10.9 10.9 3.9 4.0 2.2 2.2 2.8 4.8 2.2 Current Contribution Policy Proposed Contribution Policy Maximum Actual Maximum Actual Roll-In Contribution Investment Contribution $ 000 000 $ 000 000 $ 000 000 $ 000 000 $ 6.3 $ $ 1.6 $ 0.1 6.3 1.6 0.2 6.3 1.6 0.5 6.3 1.6 0.5 6.5 2.2 6.5 2.2 6.5 2.2 6.5 2.2 6.6 2.7 6.6 2.7 6.6 3.0 0.4 6.6 3.0 0.4 6.7 3.2 6.7 3.2 6.7 3.2 6.7 3.2 6.7 3.2 1.8 6.7 3.3 6.7 3.3 6.7 3.5 1.6 6.8 3.8 6.8 3.8 6.9 4.3 6.9 4.3 6.9 4.3 7.0 4.9 7.1 5.4 7.1 5.4 7.1 3.7 5.4 5.4 7.1 3.7 5.4 5.5 7.1 5.4 7.2 5.7 7.2 5.7 7.2 5.9 7.2 5.9 7.4 6.5 7.5 7.0 8.3 10.8 - Alberta Electric System Operator AESO 2006 General Tariff Application January 31, 2005 Section 6 — Terms and Conditions of Service Page 9 of 42 Table 6.1.1 5 10 15 20 25 30 Comparison of Customer Contributions Under Current and Proposed Contribution Policies for Analyzed Projects (continued) Current Contribution Policy Proposed Contribution Policy DTS Project Maximum Actual Maximum Actual Capacity Cost Roll-In Contribution Investment Contribution MW $ 000 000 $ 000 000 $ 000 000 $ 000 000 $ 000 000 20.0 2.3 8.3 10.8 23.0 4.5 8.6 12.4 25.0 2.0 8.8 13.5 25.0 2.1 8.8 13.5 30.0 4.5 9.4 16.2 30.0 4.6 9.4 16.2 35.0 4.5 9.9 18.9 35.0 4.5 9.9 18.9 35.0 5.9 9.9 18.9 35.0 6.0 9.9 18.9 39.1 8.7 10.4 21.1 40.0 3.2 10.5 21.6 40.0 3.2 10.5 21.6 40.0 5.9 10.5 21.6 40.0 5.9 10.5 21.6 40.0 6.7 10.5 21.6 40.0 6.8 10.5 21.6 40.0 9.0 10.5 21.6 55.0 14.3 12.2 2.2 29.7 55.0 14.4 12.2 2.2 29.7 60.0 5.8 12.8 32.4 60.0 5.8 12.8 32.4 Totals $263.4 $486.7 $ 11.7 $607.3 $ 16.4 Projects 60 5 12 Percentage Not Requiring Contribution 92% 80% Alberta Electric System Operator AESO 2006 General Tariff Application January 31, 2005 Section 6 — Terms and Conditions of Service Page 10 of 42 Figure 6.1.2 Alternative Classification of Project Costs Cost and TFO Investment Project 5 Current Maximum Roll-In Proposed Maximum Investment 10 15 20 Project Cost, Roll-In, and Investment, $ 000 000 $16 $14 $12 $10 $8 $6 $4 $2 $0 25 10 20 30 40 50 60 DTS Capacity (MW) Local Investment at Dual-Use Sites — The AESO currently uses the following ratio to determine dual-use customer costs that would be eligible for local investment: 30 35 40 [DTS ÷ (DTS + STS)] × customer-related costs The dual-use ratio was intended to provide a reasonable sharing of customer-related costs between load and supply given that load costs are, for the most part, rolled into rates while generator costs are paid fully by the generator as a customer contribution. In particular, the dual-use ratio was introduced to limit the AESO’s commitment term amount, which was not revenue based, to help minimize the potential for investment without a corresponding revenue stream. As the proposed maximum local investment will be based on DTS contract capacity, a revenue stream is assured through the DTS rate and application of the dual-use ratio is no longer required to address potential mismatches between investment and revenue. The AESO therefore recommends that its proposed customer contribution policy be applied at dual-use sites on a “load first” principle, based on providing least-cost standard service to meet the DTS load requirement. Alberta Electric System Operator AESO 2006 General Tariff Application January 31, 2005 Section 6 — Terms and Conditions of Service Page 11 of 42 For example, if a concurrent load and supply interconnection is requested, the AESO would estimate the customer-related cost in respect of the DTS load based on the least-cost standard of providing service. The local investment would then be calculated as: 5 local investment for load = $27,000/MW × DTS contract capacity × contract term, up to the estimate of least-cost standard service customer contribution 10 15 = total customer-related costs for load and generator less local investment for load If the project accommodates an increase in generation capacity at an existing dual-use site or the addition of a generator at an existing load site, the generator will simply be required to pay the resulting customer-related costs as a customer contribution. As there is no increase in DTS capacity, there is no additional local investment available. Conversely, if the project accommodates an increase in load capacity at an existing dualuse site or the addition of a load at an existing generation site, local investment will be available based on the incremental DTS capacity being added at the site. 20 local investment for load = $27,000/MW × incremental DTS contract capacity × contract term, up to the estimate of least-cost standard service to serve the load 25 The recommended “load first” approach is consistent with the AESO’s proposed customer contribution policy whereby the costs rolled into rates are proportional to the expected revenue from the service. Eliminating the dual-use ratio ensures that all load is treated equitably, regardless of location on the system and whether or not a generator shares the same point of connection. 30 35 Staged Load — The AESO proposes to apply the customer contribution policy to accommodate material increases or decreases in a customer’s load, provided the customer signs a corresponding System Access Service Agreement with a contract term that extends a minimum of five years after the start date of the last staged contract capacity. The local investment will be made available to the customer at the start of the project but will be adjusted to accommodate the staged load by taking the present value of the investment in the incremental load for the remaining contract term. Alberta Electric System Operator AESO 2006 General Tariff Application January 31, 2005 Section 6 — Terms and Conditions of Service Page 12 of 42 The following example provides an illustration of the investment in staged load: 5 Stage Stage 1 Stage 2 Year 1 5 Incremental Load 10 MW 5 MW Incremental Cost $5,000,000 $ - Remaining Term 20 years 16 years As indicated, the total project cost occurs in Year 1. A discount rate of 10% is used in this example. 10 15 Stage 1 maximum local investment = $27,000 × 10 MW × 20 years = $5,400,000 million Stage 2 maximum local investment = PV ($27,000 × 5 MW × 16 years) = PV (2,160,000) = $1,475,000 Total maximum local investment = $6,875,000 available in Year 1 Discount Rate — In Decision 2001-25 on the ESBI Alberta Ltd. (EAL) 2001 General Rate Application Refiling Customer Contribution Policy, the EUB provided the following direction (pages 4-5): 20 Accordingly, the Board directs EAL to delete subsections (a) and (b) and substitute the following wording for Article 9.12: 9.12 25 30 35 40 The discount rate applicable to payments due under this Article shall be determined as follows: (a) For unassigned transmission facilities, for transmission facilities supplied to the TA by an investor owned Transmission Facility Owner or for facilities supplied to the TA by an income tax paying municipally owned Transmission facility Owner: . .65(GCB + 1%) + .35(GCB + 3.5%)/(1 - T) where GCB is equal to the yield on 30-year Government of Canada bonds and T is equal to combined federal and provincial income tax rate for investor owned TFOs. (b) For transmission facilities supplied to the TA by a non income tax paying municipally owned Transmission Facility Owners: the yield on 30-year Government of Canada bonds plus 1.9 percent. The Board expects that EAL will monitor any changes in the typical Board approved capital structure or cost of equity and will bring forward proposed changes, as necessary, to Article 9.12 in a future GTA. Alberta Electric System Operator AESO 2006 General Tariff Application January 31, 2005 Section 6 — Terms and Conditions of Service Page 13 of 42 5 10 The Board directs EAL, at the next GTA, to provide examples of the use of the investor owned TFO discount rate and the municipally owned TFO discount rate for each of the following calculations: • The cost of advancement under Article 9.2 • The calculation of levelized annual revenue under Article 9.4(a)(iii) • Credit arrangements under Article 9.5 • Recalculations of Customer contributions under Article 9.7 The AESO notes that the discount rate provisions directed by the EUB appear essentially unchanged as Article 9.9 in the proposed terms and conditions of service. As directed, the AESO has updated capital structure to 33% equity and 67% debt (the values for ATCO Electric Transmission, a fully-taxable TFO) as determined in EUB Decision 2004-052 on Generic Cost of Capital, and cost of equity to 9.50% as determined in EUB Order U2004423 on 2005 Return on Equity. 15 The AESO further provides the following examples of the use of the discount rate in respect of the proposed customer contribution policy. 20 25 30 Discount rate assumptions • Canadian Government 30 year bond rate: • Combined federal and provincial tax rates: • Return on equity • Taxable TFO equity ratio • Taxable TFO discount rate • Non-taxable TFO equity structure • Non-taxable TFO Discount Rate: 5.68% 33.87% 9.50% 33.0% 9.27% 35.0% 7.70% Cost of Advancement Cost of advancement assumptions: • Planned transmission expansion • CPI (inflation to determine future cost) Cost of advancement calculation: 4 years 2% 35 40 (a) Current value of advanced system cost (b) Future value of system-related costs (current cost plus inflation: $2.0 × 1.024) (c) Present value of inflated system-related costs ($2.2 ÷ discount rate4) (d) Cost of advancement (a – c) Taxable TFO $ 000 000 $2.0 $2.2 Non-Taxable TFO $ 000 000 $2.0 $2.2 $1.5 $1.6 $0.5 $0.4 Alberta Electric System Operator AESO 2006 General Tariff Application January 31, 2005 Section 6 — Terms and Conditions of Service Page 14 of 42 The proposed contribution policy no longer relies on a levelized revenue calculation. The AESO therefore requests relief from the EUB in respect of its direction to provide “The calculation of levelized annual revenue under Article 9.4(a)(iii)” and “Recalculations of Customer contributions under Article 9.7”. 5 10 15 20 With respect to credit arrangements, the proposed interconnection process anticipates the customer and the TFO working more closely together, with the customer paying the required customer contribution directly to the TFO. As such, the AESO does not expect to arrange credit with customers. As well, the AESO notes that although credit arrangements have been possible under the terms of Article 9.5 of the current terms and conditions, no such credit arrangements have been made to-date. The AESO therefore does not offer credit arrangements in the proposed terms and conditions, and requests relief from the EUB in respect of its direction to provide examples related to such credit arrangements. Waivers for Multiple-User Points of Delivery (PODs) — The AESO proposes to waive customer contributions in respect of transmission projects at PODs where multiple users are served by a distribution utility, as set out in Article 9.5 of the proposed terms and conditions of service: (a) Effective January 1, 2006, the AESO will waive all or part of a Customer Contribution in respect of a transmission expansion project at a multiple-user POD where a Distributor is the Customer and where the Distributor: (i) provides sufficient documentation to satisfy the AESO that, subject to Articles 9.5(b) and (c), the Customer Contribution results from a transmission expansion project required by multiple end-use sites served by the Distributor; and (ii) executes a twenty year System Access Service Agreement in respect of the multiple–user POD. (b) The AESO will not consent to such waiver for any portion of a transmission expansion project that is attributable to the requirements of one or more single end-use sites each with a load of 2 MW or greater, or an identifiable group of end-use sites with a single owner (including Affiliates) with an aggregate load of 2 MW or greater, where such site(s) are served by the Distributor. In such cases, where a portion of the project can be attributed to multiple end-use sites served by the Distributor, the AESO will prorate the Customer Contribution in proportion to the loads of the single, group, and multiple end-use sites accordingly. (c) The AESO will not consent to such waiver for any portion of a transmission expansion project that exceeds the AESO Standard Facilities required to provide service to the Customer. 25 30 35 40 Alberta Electric System Operator AESO 2006 General Tariff Application January 31, 2005 Section 6 — Terms and Conditions of Service Page 15 of 42 The AESO is proposing this waiver to address distinctions relating to the principles underlying its customer contribution policy, as presented in the opening of Section 6.1. (a) As regulated utilities with a right and obligation to serve, owners of distribution facilities coordinate with the AESO in planning transmission and distribution facilities to arrive at the most effective solution to end-user electricity needs at the lowest overall cost, regardless of any local investment limitations imposed by the AESO customer contribution policy. (b) No effective economic signal or siting discipline can be imposed on a distribution utility in respect of transmission projects where that project is caused by increasing load from multiple end-use customers. The distribution utility has little if any influence over the amount, timing, or location of end-user load growth. In general, any growthrelated transmission project contributions required from a distribution utility would be rolled into the utility’s distribution tariff in accordance with utility-specific practices, and spread across all the utility’s customers with no effect on siting or load growth. (The AESO appreciates that distribution end-use customers are subject to local distribution connection costs, where the price signal is effective.) 5 10 15 20 25 30 35 40 The main impact of transmission project contributions, if recovered through a distribution utility’s distribution tariffs, is the potential for disparities in the price paid for transmission access by different distribution utilities’ end-use customers. For example, service area obligations may require a distribution utility to provide transmission access to multiple enduse customers at remote sites or sites which incur high project costs for other reasons. As a result, that distribution utility’s customers will pay a higher rate for transmission access than customers of other distribution utilities in the province. Such a result may be inconsistent with the principle stated in Section 30(3)(a) of the Electric Utilities Act that the AESO’s tariff “shall not be different for owners of electric distribution systems, customers who are industrial systems or a person who has made an arrangement under section 101(2) as a result of the location of those systems or persons on the transmission system.” (emphasis added). In general, the AESO does not look beyond the service provided at its point of delivery to treat all load customers consistently, for the purpose of achieving a fair and reasonable application of its contribution policy. However, the AESO’s tariff does impact all electricity consumers in Alberta. Waiver of customer contributions at multiple-user PODs, as proposed, would result in fair and equitable transmission access rates to all load customers. In Decision 2001-6 on the EAL 2001 General Rate Application Customer Contribution Policy, the EUB provided the following directions: 6. In order to have empirical data, the Board directs EAL to provide at the next GTA, for each of the years 1998, 1999, and 2000, the following information for those multiple customer PODs that would Alberta Electric System Operator AESO 2006 General Tariff Application January 31, 2005 Section 6 — Terms and Conditions of Service Page 16 of 42 have required a transmission contribution using the proposed contribution policy: • the number of customers downstream of the POD, • the initial (or reinforcement) cost of the radial line • the transmission contribution The above information should be supplied for each of the following: • Each new multiple customer POD installed. • Each existing multiple customer POD where increased capacity was installed. • the impact that the above annual transmission contributions associated with multiple customer PODs would have had on that DISCO’s total annual transmission access payments. 5 10 7. 15 20 25 The Board directs EAL to provide the above same information, at the next GTA, on an actual basis for each month in 2001 during which the new TA contribution policy was in place. The AESO’s records of transmission projects associated with multiple-user PODs for 1998 through 2000 do not provide sufficient detail to respond fully to Direction 6. The AESO instead offers the requested information for 2001 through 2003, plus one project from early 2004, as provided in Table 6.1.2. The data in Table 6.1.2 shows one payment of a customer contribution by a distribution utility under the AESO’s current contribution policy, at ATCO Kinosis. The Table also shows the AESO’s proposed contribution policy applied to the same projects would result in the payment of two customer contributions, at ATCO Brintnell and at ATCO Kinosis. At ATCO Brintnell, the contribution would be flowed through to specific customers. At ATCO Kinosis, 72% of the contribution would be flowed through to specific customers and 28% would be waived for multiple users, based on the proportion of load at the site. 30 35 The end result is that there would be no effect on annual transmission access payments by distribution utilities under the AESO’s proposed customer contribution policy compared to the current policy, except at ATCO Kinosis. At ATCO Kinosis, transmission access payments would actually be reduced by the elimination of a $256,000 contribution required under the current contribution policy. Alberta Electric System Operator AESO 2006 General Tariff Application January 31, 2005 Section 6 — Terms and Conditions of Service Page 17 of 42 Table 6.1.2 Contribution Data for Multiple-User PODs CustomerNumber of Actual Proposed 2005 Policy Related End-Use Customer Calculated After Cost Customers Contribution Contribution Waiver Note $7,180,262 $ 269 $ - $ 700,262 $ 700,262 (1) 262 2,051 523,000 7,410 98,000 134 255,000 911 785,000 11,517 245,000 72,000 2 61,200 - (2) 280,000 143 810,000 592 270,000 1,500,000 29,005 508,000 353 508,000 496,000 522 496,000 280,700 2,727 280,700 287,100 15,109 287,100 384,000 1,332 384,000 1,995,000 9,119 4,799,395 2,247 1,630,000 622 427,000 21,076 465,000 3,449 725,000 17,809 412,000 4,647 325,000 1,929 374,000 3,920 6,749 2,929,422 1 3,796,210 1 7,178,000 181 256,000 3,128,000 2,252,160 (3) Project Description Year ATCO Brintnell New Substation 2001 ATCO Cranberry Lake to Kidney Lake New Substation/Line 2001 ENMAX #24 New Substation 2001 FortisAlberta High River 65S Breaker Addition 2002 FortisAlberta Leismer 72S Meter Addition 2002 FortisAlberta Lac La Nonne 994S Station Regulator 2002 FortisAlberta Nisku 139S Breaker Addition 2002 FortisAlberta CP Rail 945S 2002 ATCO Sulphur Point Breaker Addition 2002 ATCO Veteran Substation Upgrade 2002 ENMAX #11 Substation Upgrade 2002 FortisAlberta Hayter 277S Breaker Addition 2002 FortisAlberta Hughenden 213S Breaker Addition 2002 FortisAlberta Benbow 297S Breaker Addition 2002 FortisAlberta North Calder 37S Breaker Addition 2002 FortisAlberta Warner 344S Breaker Addition 2002 FortisAlberta St. Albert 99S Transformer/Breaker Addition 2003 FortisAlberta Pinedale New Substation 2003 FortisAlberta Suffield (Phase 1-2) Transformer/Regulator Addition 2003 FortisAlberta Sherwood Park Breaker Addition 2003 FortisAlberta Acheson Breaker Addition 2003 FortisAlberta Stony Plain Breaker Addition 2003 FortisAlberta Blackfalds Breaker Addition 2003 FortisAlberta Plamondon Breaker Addition 2003 FortisAlberta Whitecourt Breaker Addition 2003 ENMAX #22 Substation Upgrade 2003 ATCO Corridor Crow Lake New Substation 2003 ATCO Corridor Gregoire New Substation 2003 ATCO Kinosis New Substation 2004 (1) ATCO Brintnell contribution would be flowed through to specific customer (2) Aquila CP Rail contribution would be waived for a single site smaller than 2 MW (3) ATCO Kinosis contribution would be prorated on share of 7.5 MW load: 2.1 MW waived for multiple-users, 5.4 MW flowed through to two specific customers Alberta Electric System Operator AESO 2006 General Tariff Application January 31, 2005 Section 6 — Terms and Conditions of Service Page 18 of 42 The effect of the proposed contribution policy on AESO rates is summarized in Table 6.1.3. Table 6.1.3 5 10 15 20 25 30 35 40 Effect of Contribution Policy on Revenue Requirement Current Policy Customer Cost Year Rolled into Tariff 2001 $ 7,180,262 2002 6,278,800 2003 19,508,027 2004 (1 project) 6,922,000 Total $39,889,089 Proposed Policy Customer Cost Rolled into Tariff $ 6,480,000 6,278,800 19,508,027 4,925,840 $37,192,667 Proposed Policy Revenue Requirement Reduction $ 700,262 0 0 1,996,160 $ 2,696,422 The proposed multiple-user waivers will result in “systemizing” transmission project costs that would otherwise be paid through customer contributions. However, such costs are customer-related, not system, costs. The AESO therefore plans to calculate a contribution for customer-related costs at multiple-user PODs, and if such contributions are waived they will be recorded and tracked. Where contributions have been waived at PODs shared between large individual users and multiple users, refunds of contributions to the individual users will continue to be available if additional multiple-user transmission projects are completed at the POD. In the absence of any other factors, the waivers could influence the DISCO’s preference for transmission projects or distribution projects to meet load growth since the cost of a transmission solution would be recovered from all consumers through the AESO tariff while the cost of a distribution solution would increase the DISCO’s rate base and be recovered from just the DISCO’s consumers. Although the waiver adds another difference between transmission and distribution solutions, such a concern is not new. Current processes, especially joint planning between the AESO and the DISCOs and the subsequent needs applications to the EUB, impose the necessary cost discipline on the DISCOs and ensures that engineering solutions consider the economics of Alberta consumers as a whole. Alberta consumers are further protected by the specific exclusion from the waiver, in Article 9.5(c), of aspects of projects that exceed the AESO standard facilities required to service the distributor. As defined in the proposed terms and conditions, AESO standard facilities “generally consist of a single radial transmission circuit and a single transformer to supply an individual Point of Connection.” However, DISCOs frequently have multiple Points of Delivery in relatively close proximity, such that service may be provided from alternate or multiple PODs. Through the joint planning between the AESO and the DISCOs, the AESO expects the optimal solution to be determined based on consideration of the technical and economic feasibility of transmission service through existing capacity at existing PODs, transmission service through new capacity at an existing or new POD, or a distribution solution, and having regard for the applicable reliability, protection, and operating criteria and standards. Again, this concern is not new, and Article 9.5(c) simply makes explicit, with respect to contribution waivers, the ineligibility of above-standard facilities addressed in Alberta Electric System Operator AESO 2006 General Tariff Application January 31, 2005 Section 6 — Terms and Conditions of Service Page 19 of 42 Article 9.13(c) and previously addressed in Article 22 of the current terms and conditions. Also, Article 9.1 expressly excludes shifts of demand from an existing POD from being eligible for local investment. 5 Changes Requiring Adjustments to Customer Contributions — In Decision 2001-6 on the EAL 2001 General Rate Application Customer Contribution Policy, the EUB provided the following direction: 28. 10 15 20 25 The Board considers that the handling of contributions prior to the time the facilities are put into service is worthy of further examination at the next GTA and therefore, the Board directs EAL, at the next GTA, to submit revised practices for these circumstances. Where a material change occurs related to any component of a customer contribution, including a reallocation between system and customer-related costs, the AESO proposes to recalculate and adjust the customer contribution as appropriate. For example, if a material change occurs before the customer contribution is paid, the AESO will collect the adjusted amount and not the original amount from the customer. The AESO proposes in Article 9.7 of its terms and conditions of service that recalculation of the customer contribution can occur at any time prior to the end of the twenty-year refund period. The AESO also identifies, as a specific circumstance that may give rise to a contribution adjustment, that the AESO subsequently deems all or part of a customer’s facilities to be system related. That specific inclusion should address the concern expressed by the EUB in its view that timing of the AESO’s annual planning update could result in some customers paying a contribution for facilities that would be treated as a system expansion within five years of energization. Common Facilities — Section 16(4) of the Transmission Regulation states: 30 35 40 16(4) If another person makes use of the facilities for which a local interconnection cost has been paid, (a) the cost of the use of those facilities by that other person or persons must be allocated to all users in accordance with the ISO tariff, and (b) the original local interconnection cost, or a portion of it, must be refunded to the person who paid it in accordance with the ISO tariff. Article 9.8 of the proposed terms and conditions of service has been revised to state that if facilities are installed to serve a customer and later used to serve other customers, those facilities will be deemed to be system-related and any customer contribution paid by the original customer for those facilities will be refunded. These provisions address the requirements of the quoted clause of the Transmission Regulation. Alberta Electric System Operator AESO 2006 General Tariff Application January 31, 2005 Section 6 — Terms and Conditions of Service Page 20 of 42 Administrative Cost of Contribution Refunds — Decision 2001-6 on the EAL 2001 GRA Customer Contribution Policy included the following direction: 11. 5 10 15 20 25 30 35 40 Further, the Board directs EAL, in the next GTA, to address any change in the recommended project cost threshold for refunds beyond the 10 year period or any administrative cost levy to compensate for the extra administrative cost involved. The Board accepts TCE’s argument that customers would be willing to pay for any incremental administrative costs. Accordingly, at the time this issue is addressed, the Board will consider whether the effective date for the requirement for customers to pay the additional administrative costs should be the effective date of the new contribution policy. The AESO has determined that the administrative cost to refund load customer contributions are relatively small, particularly in light of the need for a similar process described in the next section of this Application in respect of generator system contributions as required by the Transmission Regulation. Consequently, the AESO is prepared to track and refund load customer contributions over a twenty year period, at no direct cost to customers. The associated terms and conditions of service remain unchanged. However, given that the above noted administrative cost is relatively small, the AESO proposes to eliminate the $50,000 refund threshold in the AESO’s current terms and conditions, reproduced below: 9.8(c) Commencing in year 11, any project whose remaining adjustment is less than $50,000 shall be deemed to have an adjustment balance of zero, and no further refunds shall be due. Prepaid Operations and Maintenance — Article 9.13 of the proposed terms and conditions of service provides for the payment of an additional prepaid operations and maintenance charge of 12% on customer related costs for STS customers and on facilities in excess of AESO standard facilities for all customers. Section 16(1)(a) of the Transmission Regulation requires owners of generating units to pay all local interconnection costs for connecting to the transmission system. However, interconnections incur on-going operations and maintenance costs beyond their initial capital costs. The AESO therefore proposes to include a prepaid operations and maintenance charge to ensure load customers do not pay these costs related to generator interconnections. Facilities in excess of AESO standard facilities will also have a prepaid operations and maintenance charge applied. By definition, service can be provided through AESO standard facilities, and all customers share in the on-going operations and maintenance costs associated with such standard facilities the averaging of costs in the AESO’s rates. However, it is inappropriate for all customer to share in on-going costs when an individual customer elects facilities in excess of the standard. Alberta Electric System Operator AESO 2006 General Tariff Application January 31, 2005 Section 6 — Terms and Conditions of Service Page 21 of 42 5 10 For this application, the AESO has proposed to charge prepaid operations and maintenance at 12% of capital cost. This charge is not based on a detailed analysis by the AESO, but is based on the minimum such charge used by other utilities in Alberta. A preliminary review by the AESO indicates this is the minimum reasonable level, and additional analysis for each TFO may result in higher prepaid operations and maintenance charges in future rate applications. Non-Standard Configurations — Article 9.14(c) of the proposed terms and conditions of service replaces previous Article 22.4 and continues to recognize the long-standing practice wherein facilities requested by the customer that exceed the AESO standard facilities required to provide service to the Customer are at the customer’s cost. Costs arising from customer-requested facilities that exceed the AESO standard facilities required to provide service are also not eligible for the waivers for multiple-user PODs discussed earlier. 15 6.2 20 25 30 35 40 System Contributions for Generators Part 4 of the Transmission Regulation requires the AESO to include in its tariff provisions relating to the local interconnection costs of generating units and the generating unit owner’s contribution: Local interconnection costs 16(1) The ISO must include in the ISO tariff (a) local interconnection costs, as defined by the ISO, payable by an owner of a generating unit for connecting to the transmission system; (b) the terms and conditions of service and provisions for the recovery of local interconnection costs from owners of generating units. (2) The ISO must make reasonable efforts to ensure that the interconnection of a generating unit to the transmission system is undertaken in a timely manner. (3) The owner of a generating unit that interconnects with the transmission system, and who has paid local interconnection costs, may not prohibit interconnection or access to the interconnection facilities by other market participants. (4) If another person makes use of the facilities for which a local interconnection cost has been paid, (a) the cost of the use of those facilities by that other person or persons must be allocated to all users in accordance with the ISO tariff, and (b) the original local interconnection cost, or a portion of it, must be refunded to the person who paid it in accordance with the ISO tariff. Alberta Electric System Operator AESO 2006 General Tariff Application January 31, 2005 Section 6 — Terms and Conditions of Service Page 22 of 42 5 10 15 20 25 30 35 40 Generating unit owner’s contribution 17(1) The ISO must include in the ISO tariff (a) the amount, determined under subsections (2) and (3), payable by an owner of a generating unit to the ISO; (b) terms and conditions related to clause (a). (2) The amount payable by owners of generating units is the sum of the following: (a) for upgrades to existing transmission facilities, a charge of $10 000/MW; (b) a charge of not more than $40 000/MW, as provided in the ISO tariff, payable by owners of generating units that locate in an area of the transmission system where generation exceeds load, and the amount of the charge is to be determined based on the location of the generating unit relative to load. (3) A charge under subsection (2)(b) may be revised from time to time, but must (a) be stable and predictable; (b) be calculated in a simple and transparent manner; (c) be based on generation size; (d) vary based on the generation location relative to load in Alberta; (e) be determined and payable in accordance with the ISO rules and ISO tariff, be paid before commencement of construction of the local interconnection facility and be paid once only for that specific location and generating unit; (f) not affect charges determined and paid by owners of generating units or owners of prospective generating units before such revisions. (4) The ISO tariff must include terms and conditions (a) providing for the refund of money paid under this section, to the owner who paid it, over a period of not more than 10 years from the date it was paid, subject to satisfactory operation of the generating unit determined under rules made under subsection (5), where satisfactory operation may vary by generation type; (b) providing for forfeiture to the ISO of money paid under this section, or suspension of the refunds, if the generating unit is not operated satisfactorily; (c) providing for the means and times at which the refunds are to be made; (d) providing for the prudent administration, management and investment of money held by the ISO under this section and for the accounting for those funds; Alberta Electric System Operator AESO 2006 General Tariff Application January 31, 2005 Section 6 — Terms and Conditions of Service Page 23 of 42 (e) (5) providing for the disbursement of money earned on investments. The ISO must make rules to be used to assess the satisfactory performance of a generating unit by generating unit type. 5 Application of sections 16 and 17 limited 18 Sections 16 and 17 do not apply to a generating unit connected to the transmission system before this Regulation comes into force. 10 15 The requirements under Section 16 of the Transmission Regulation are already addressed in the provisions relating to customer contributions in the proposed terms and conditions, specifically: (a) Local interconnection costs payable by a generator are defined in Articles 9.3 and 9.4. (b) The timeliness of generator interconnections is addressed in Article 13.2. (c) Prohibition of other customer’s interconnections is not permitted by the Regulation, and does not need to be further addressed in the AESO tariff. (d) Refunds when another customer connects to facilities for which a customer contribution was paid are addressed in Article 9.8. 20 25 30 35 40 Section 17 of the Transmission Regulation requires the AESO to include terms and conditions relating to the amount of and subsequent refund of a “generating unit owner’s contribution”, in addition to the payment of local interconnection costs as required by Articles 9.3 and 9.4 of the terms and conditions. The AESO developed a generator contribution policy to address the requirements of Section 17, published a Generator Contribution Policy Discussion Paper on November 25, 2004, and presented at a stakeholder workshop on December 3. Comments from that workshop and additional consultation resulted in revisions to the proposed policy, which were presented at a stakeholder workshop on January 19, 2005. Additional comments received have resulted in the final Generator Contribution Policy Recommendations included as Appendix D of this Application. The AESO notes that a material revision to the proposal for rules regarding satisfactory performance is included in the final policy, compared to the rules proposals presented in earlier stakeholder sessions. Based on the Generator Contribution Policy Recommendations, the determination of the “system contribution” required by the Transmission Regulation is described in Article 9.9 of the terms and conditions of service and the refund based on satisfactory performance is described in Article 9.10. Although the Generator Contribution Policy Recommendations provide more background and detail on the system contribution provisions included in the terms and conditions, in the event of a conflict in interpretation the terms and conditions prevail. Section 17(2) of the Transmission Regulation establishes that the system contribution shall be the sum of $10,000/MW for upgrades to existing transmission facilities and $0/MW to $40,000/MW payable in areas where generation exceeds load. Article 9.9(b) of the terms Alberta Electric System Operator AESO 2006 General Tariff Application January 31, 2005 Section 6 — Terms and Conditions of Service Page 24 of 42 5 and conditions states that STS Contract Capacity will be used to calculate the total system contribution, and that areas of the transmission system where generation exceeds load and the associated system contribution factors will be provided by the AESO in advance of their effective dates. To meet the “stable and predictable” requirements of Section 17(3)(a) of the Transmission Regulation, the AESO proposes to establish system contribution factors for two-year periods. The first system contribution factors will apply for 2006 and 2007, and are provided in Table 6.2.1. The detailed calculation of the factors and amounts are provided in the Generator Contribution Policy Recommendations provided as Appendix D 10 Table 6.2.1 15 20 25 30 35 40 Area Northwest Northeast Edmonton Central East Calgary Southwest System Contribution Amounts for 2006-2007 System Contribution Factor 0.0000 1.0000 0.5333 0.0000 0.2558 0.0000 0.2517 Area Contribution $/MW $ 0 40,000 21,300 0 10,200 0 10,100 Base Contribution $/MW $10,000 10,000 10,000 10,000 10,000 10,000 10,000 Total System Contribution $/MW $10,000 50,000 31,300 10,000 20,200 10,000 20,100 The area contribution — the first component of the system contribution — is simply $40,000/MW multiplied by the system contribution factor, which is greater than zero only in areas where generation exceeds load and which varies based on the location of generation with respect to load, in accordance with Section 17(2)(b) of the Transmission Regulation. The base contribution — the second component of the system contribution — is the $10,000/MW amount specified by section 17(2)(a) of the Regulation. The Generator Contribution Policy describes the calculation of the system contribution factor, which is based on peak generation capacity and peak load in each area and can be a simple and transparent calculation in accordance with section 17(3)(b) of the Transmission Regulation. Determining the system contribution as a $/MW amount ensures the charge varies with generator size in accordance with section 17(3)(c) of the Regulation, while the variation of system contribution factors reflects the generation location relative to load in accordance with section 17(3)(d). Section 17(3)(e) of the Regulation requires that the system contribution be paid before construction begins, and is addressed in Article 9.2 of the terms and conditions. Section 17(3)(e) also requires that a contribution be paid only once for a specific generator, which is addressed in Article 9.9(a) of the terms and conditions. Section 17(2)(f) of the Regulation Alberta Electric System Operator AESO 2006 General Tariff Application January 31, 2005 Section 6 — Terms and Conditions of Service Page 25 of 42 requires that changes to the system contribution do not affect charges already paid, and no retroactive application is provided for in the terms and conditions. 5 10 Section 17(4) of the Transmission Regulation provides for the refund of the system contribution over a period of not more than 10 years from the date it was paid, subject to satisfactory performance of the generator. The AESO proposes in Article 9.10 that the contribution be refunded in nine equal annual amounts, with the possibility of skipping one year due to unsatisfactory performance and receiving the final payment in the tenth year. The possibility of skipping a year takes into account the possibility of a major disruption in performance unforeseen by the generator. allows for “Force Majeure” events, high rainfall years for irrigation system hydro generators, low wind years for wind generators, and similar events out of the generator’s control, without penalizing the refund of the system contribution. 15 20 25 30 The system contribution must be paid before construction and must be refunded within ten years of payment subject to satisfactory performance. Since satisfactory performance can only begin after construction is complete, and since construction of both the generating unit and interconnection facilities takes time, Article 9.10(b) provides for the refund of the system contribution in fewer than nine equal annual amounts, based on the number of years after the commercial operation date of the generator and the ninth year after payment. However, to ensure that the interconnection does proceed, if the commercial operation date is later than five years after payment of the system contribution, one-fifth of the contribution is forfeited for each additional year the commercial operation date is delayed beyond five years. If the commercial operation date does not occur within ten years after the system contribution is paid, the whole contribution is forfeited. These provisions are summarized in Articles 9.10(b) and (c) of the terms and conditions. For simplicity, the AESO proposes to administer the refund of system contributions on a calendar year basis. Recognizing that few commercial operation dates occur on January 1, Article 9.10(d) of the terms and conditions provide for the prorating of both the refund and the satisfactory performance requirements in the first year of operation. Some possible refunds of system contributions are illustrated in Table 6.2.2 35 Table 6.2.2 40 Illustrative Examples of System Contributions and Refunds Generator A Year Status Amount 0 Paid Jul 1 $100,000 Refunds 1 COD Jul 1 (5,882) 2 On (11,765) 3 Off 0 Generator B Status Amount Paid Jul 1 $100,000 0 COD Jul 1 (6,667) On (13,333) Generator C Status Amount Paid Jul 1 $100,000 0 0 0 Alberta Electric System Operator AESO 2006 General Tariff Application January 31, 2005 Section 6 — Terms and Conditions of Service Page 26 of 42 5 10 15 20 25 4 5 6 7 8 9 10 Forfeit On On On On On On On (11,765) (11,765) (11,765) (11,765) (11,765) (11,765) (11,765) $ 0 Off On Off On On On On 0 (13,333) 0 (13,333) (13,333) (13,333) (13,333) $13,333 0 0 0 COD Jul 1 (10,000) On (20,000) On (20,000) On (20,000) $30,000 Notes: “COD” refers to commercial operation date Based on a mid-year COD, the first year’s refund is half the annual amount “On” indicates a year in which generator performance was satisfactory “Off” indicates a year in which generator performance was not satisfactory The examples in Table 6.2.2 reflect the following events: (a) Generator A receives a prorated refund in the partial first year of operation (Year 1), does not meet the performance standard for Year 3 and skips that refund, but otherwise operates satisfactorily and is refunded the total system contribution over ten years. (b) Generator B receives a prorated refund in the partial first year of operation (Year 2), does not meet the performance standard for Year 4 and for Year 6, and therefore forfeits one annual amount. (c) Generator C does not begin operating until mid-way through Year 7, and therefore forfeits 1½ annual amounts reflecting that operation was delayed 1½ years beyond Year 5. The provisions of Articles 9.10(b), (c), and (d) of the terms and conditions, as described above, therefore meet the requirements of Sections 17(4)(a) regarding refunds and 14(4)(b) regarding forfeiture or suspension of the refunds. 30 Article 9.10(e) and (f) describes the process by which a generator reports annual performance by January 31 and that refunds will be issued by February 28, thereby satisfying the requirements of Section 17(4)(c) of the Regulation. 35 40 Section 17(4)(d) of the Transmission Regulation requires the AESO to prudently administer, manage, and account for system contributions held. The AESO proposes to treat the system contributions as no-cost capital, similar to the traditional treatment of customer contributions by utilities in Alberta. The system contributions held would be reported in the general tariff applications of the AESO. Such treatment would reduce the need for the AESO to borrow to finance cash flows during the year, resulting in lower interest expense included in the AESO’s general costs to the benefit of AESO load and export customers who pay all costs of the transmission system (except for losses), and thereby satisfying the requirement in Section 17(4)(e) for the disbursement of money earned through the system contributions. Alberta Electric System Operator AESO 2006 General Tariff Application January 31, 2005 Section 6 — Terms and Conditions of Service Page 27 of 42 5 Section 17(5) of the Transmission Regulation requires the AESO to make rules to be used to assess satisfactory performance of a generating unit. The AESO notes that the draft performance criteria initially proposed received several comments during the consultation process on the generator contribution policy. The AESO now intends to propose a draft rule establishing an annual capacity factor for generating units based on resource type, based on the ten-year history of electric energy capacity and generation by resource type provided in the EUB’s Alberta Electric Industry Annual Statistics for 2002. The proposed annual capacity factors are: 10 Table 6.2.3 Proposed Performance Standard for System Contribution Refunds Resource Type Coal Natural Gas — Base Load Natural Gas — Peaking Hydro Wind Biomass & Waste 15 Annual Capacity Factor 75% 50% 10% 20% 20% 75% 20 The proposed performance criteria also include a requirement for commercial operation and an undercontracting penalty; those provisions continue unchanged from the draft criteria originally presented to stakeholders. 25 30 Although the proposed performance standard is presented in this Application for completeness, the AESO notes the standard is to be established as an ISO Rule, not through EUB regulation. The AESO intends to continue consultation on the performance standard with the expectation that the rule-making process will begin in May 2005, will include further consultation on the rules themselves, and will result in performance standard rules being published in August 2005. 35 Finally, Section 18 of the Transmission Regulation states that Section 16 and 17 provisions do not apply to a generating unit that was interconnected before the Regulation came into force on August 12, 2004. Consistent with other aspects of its tariff, the AESO proposes that the system contribution become effective with the rest of the tariff on January 1, 2006. Article 9.9(c) of the terms and conditions expressly states that system contributions are not required from generators who sign System Access Service Agreement before January 1, 2006. 40 6.3 System Access Applications The AESO proposes to amend Article 5 (previously 7) of the terms and conditions of service to accord with the AESO’s revised interconnection process. The new process has been established through stakeholder collaboration that included representatives from the AESO, Alberta Electric System Operator AESO 2006 General Tariff Application January 31, 2005 Section 6 — Terms and Conditions of Service Page 28 of 42 the EUB, ENMAX, EPCOR, FortisAlberta, ATCO, AltaLink, VisionQuest, Canadian Natural Resources Limited, and EnCana. Implementation of the transmission interconnection process is continuing to be developed among those parties. 5 10 15 Essentially, the new single-stage process allows for a more active presence by the transmission facilities owner (TFO) and a more direct working relationship between service providers and customers, which is intended to streamline system access applications. Although the AESO will retain oversight of all transmission interconnections, it will no longer perform each of the day-to-day tasks related to such projects. For example, payment of customer contributions will normally be made directly by the customer to the TFO, although determination and administration of customer contributions will remain with the AESO. As part of the new interconnection process, Article 5 includes the following three revisions to the level and applicability of system application fees. The existing fee structure was established through the AESO’s 2002 Negotiated Settlement and was intended to create a manageable interconnection queue by introducing fees large enough to discourage customers that did not seriously intend to proceed with interconnection. The AESO proposes to revise three aspects of system application fee. 20 (a) System application fees are proposed to be simplified and reduced. The current twostage application fee has been revised to a single charge in accordance with the new single-stage interconnection process. Table 6.3.1 provides a comparison of proposed and current fees. 25 Table 6.3.1 Proposed and Current Application Fees Proposed Application Fees Project Size Fee < 15 MW $10,000 > 15 MW and ≤ 25 MW $20,000 > 25 MW $50,000 30 Current Application Fees Project Size Stage 1 Fee Stage 2 Fee < 10 MW $5,000 $5,000 > 10 MW and ≤ 15 MW $8,000 $8,000 > 15 MW and ≤ 25 MW $15,000 $15,000 > 25 MW $40,000 $50,000 35 40 (b) System application fees will be refundable upon energization of the customer’s facilities. Implementing a refundable fee continues to discourage non-serious applications, but will allow the cost of transmission system planning to be more appropriately recognized in the AESO’s standard tariff. Alberta Electric System Operator AESO 2006 General Tariff Application January 31, 2005 Section 6 — Terms and Conditions of Service Page 29 of 42 (c) System application fees will be eliminated for transmission projects arising from distribution load growth caused by multiple users. The elimination of such fees recognizes that: • distribution load growth can be better managed through the planning, rather than the transmission interconnection, process; and • application fees are unnecessary to discourage non-serious customers when the expansion is due to load growth on a distribution network. 6.4 Maximum Transmission Must-Run Compensation 5 10 Section 23 of the Transmission Regulation includes the following provisions related to the maximum amount to be paid for transmission must-run (TMR) service: 15 20 25 30 Recovery of must-run costs 23(1) For the purpose of section 30(2)(a)(ii) of the Act, the compensation must be no greater than an amount that would result in the recovery of fixed, operating and maintenance costs, including a reasonable rate of return, using a methodology described in the ISO tariff. (2) The ISO must include in the ISO tariff a cost determination methodology and related terms and conditions of service for the purposes of subsection (1). TMR service is real (in MW) or reactive (in VAR) support provided by a Customer in response to a direction by the AESO made to ensure voltage stability and reliable electrical service in a region of Alberta. The AESO has developed operating procedures for specific regions which specify TMR requirements under various operating conditions. In most cases the AESO acquires TMR services through commercial contracts. Such contracts may have been the result of a competitive procurement process or the result of a bi-lateral negotiation with a supplier. In cases where commercial contracts are not in place, TMR services are acquired under Article 11 (previously Article 24) of the AESO’s terms and conditions. Acquisition of TMR services under Article 11 is commonly referred to as “conscription”. 35 40 Acquisition of TMR services under Article 11 is also the subject of a separate proceeding before the EUB. Article 11 as it appears in the proposed terms and conditions reflects the AESO’s Article 24 Amendment Application, dated August 16, 2004. The Section 23 requirement of the Transmission Regulation to define the maximum amount to be paid for TMR service is separate and in addition to the applied-for amendment. In response to Section 23, this section describes the methodology to determine the maximum amount to be paid for TMR services, and may limit the compensation specified in a contract or in Article 11. If the compensation specified in a contract or in Article 11 Alberta Electric System Operator AESO 2006 General Tariff Application January 31, 2005 Section 6 — Terms and Conditions of Service Page 30 of 42 exceeds the maximum, the compensation would be reduced to the maximum as determined in this methodology. Existing TMR contracts are structured such that the maximum is very unlikely to be exceeded, and the maximum also would not be exceeded by Article 11 as proposed in the Amendment Application. 5 The AESO has defined the approach to calculate maximum TMR compensation in Article 1.1 of the terms and conditions: 10 15 20 25 30 35 40 “Maximum TMR Compensation” means the maximum amount to be paid by the AESO for Transmission Must-Run (TMR) service that would result in the recovery of fixed, operating, and maintenance costs, including a reasonable rate of return for the TMR service provider, based on the following components determined monthly: (a) Undepreciated Capital Investment (UCI) reflecting the Customer’s property, plant, and equipment for the specific generating asset providing the TMR service less accumulated depreciation for the specific generating asset; (b) amortization and depreciation amounts associated with the Customer’s investment in the generating asset providing TMR service over the economic life of the asset and consistent with amounts reported in the Customer’s audited financial statements; (c) capital structure reflecting debt, equity, or other financing of the Customer’s investment in the generating asset at a deemed capital structure of 70% debt and 30% common equity; (d) a 12% rate of return on equity and an interest rate on debt equal to a 10-year Government of Canada Bond interest rate plus 0.5%; (e) income tax costs reflecting the marginal income tax rates for both federal and provincial portions of income tax; (f) total return costs reflecting one-twelfth of the sum of: • annual amortization and depreciation amounts, • the product of UCI time the debt percentage of capital structure times the interest rate, • the product of UCI times the equity percentage of capital structure times the rate of return on equity, and • the product of the tax rates times the equity return amount determined above, unless the generating asset is at or near the end of its life and the UCI amount is at zero, in which case total return costs will reflect a reasonable minimum return amount; (g) total operation and maintenance costs reflecting direct as well as a prorated share of indirect or fixed operation and maintenance costs associated with the generating asset, where the prorated share is based on the number of hours of TMR service compared to the total of hours of TMR service and a reasonable portion of hours in-merit in the energy market; (h) total fuel costs reflecting direct as well as a prorated share of indirect or fixed fuel costs associated with the generating asset, where the prorated share is Alberta Electric System Operator AESO 2006 General Tariff Application January 31, 2005 Section 6 — Terms and Conditions of Service Page 31 of 42 (i) 5 (j) based on the number of hours of TMR service compared to the total of hours of TMR service and a reasonable portion of hours in-merit in the energy market; credits for common costs, if applicable, reflecting revenues or benefits attributable to a service in addition to the TMR service and associated with the generating asset; and adjustment for partial use of the generating asset where the asset is only partially directed for TMR service and the remainder of the unit’s capacity is available to provide other electric services. 10 The remainder of this section provides additional background on the components included in the Maximum TMR Compensation definition. 15 20 25 30 35 Undepreciated Capital Investment (UCI) — The appropriate amount of the Customer’s investment in the generating unit providing TMR service must be determined first. The AESO refers to the term undepreciated capital investment or UCI to mean the Customer’s property, plant, and equipment for the specific generating asset providing the TMR service less accumulated depreciation for the specific generating asset. The UCI amount forms the basis in determining a return of and on the investment in subsequent steps. In a relatively simple case, the UCI would be the entire remaining undepreciated cost of the generating unit providing TMR service if the generating unit was a stand-alone facility and the TMR direction was for the full capacity of the generating unit. In more complicated cases, the facility may produce other products such as steam or hot water, or make other electricity sales in addition to the TMR service. Also, the level of the TMR service will likely be for only a portion of the generating unit’s capacity. Another complexity arises where the Customer may have investments in administration or head office facilities and the Customer may consider that the TMR compensation mechanism should provide for a return of and on these types of facilities. A final complexity concerns whether contributions made in respect of the capital costs of the facilities providing the TMR service made by the AESO or its predecessor in prior periods should be treated as a deduction to the UCI calculation. The following principles will be applied in determining the relevant UCI. • 40 Firstly, UCI for TMR compensation should only be based on the generating unit providing the TMR service and should not include any costs for administration or head office facilities. In the case where facilities are only used to generate electric power, such as simple cycle gas turbines, the UCI for the generating unit should be used in determining the return of and on investment. Alberta Electric System Operator AESO 2006 General Tariff Application January 31, 2005 Section 6 — Terms and Conditions of Service Page 32 of 42 • Secondly, the UCI amount should be based on the Customer’s property, plant, and equipment costs for the specific generating unit providing the TMR service. These costs must be consistent with the amounts reported in the Customer’s audited financial statements. In cases where specific generating unit costs are not individually reported in such financial statements, the Customer should be required to provide upon request the necessary documentation to the AESO so that these amounts may be independently verified and affirmed for their accuracy. • Thirdly, the UCI amount should be net of all accumulated depreciation. The accumulated depreciation amount would also be consistent with the calculation methods and amounts reported in the Customer’s audited financial statements. Upon request, the Customer should be required to provide the necessary documentation to the AESO so that accumulated depreciation amounts may be independently verified and affirmed for their accuracy. • Fourth, if the AESO or its predecessor has provided the Customer with prior capital contributions towards the facilities used to provide the TMR service in prior periods, these amounts should be deducted from the UCI calculation. Without such a reduction, a Customer would receive excessive compensation. 5 10 15 20 Given the long-term economic life of generating units and in order to simplify the applicable calculations, the AESO proposes to use the UCI at the start of a calendar year and to determine the value for each month in which TMR services are provided. 25 30 35 40 In cases where TMR service is provided by a generating unit at or near the end of its life and the UCI amount is at zero, return will reflect a reasonable minimum return amount. Amortization and depreciation — This step determines the appropriate amortization or depreciation amount associated with the Customer’s investment in the generating unit providing TMR service. The appropriate amortization period and the applicable depreciation rates for calculating the depreciation amount included in TMR compensation need to be determined. The AESO considered whether the amortization period and depreciation calculation should be adjusted to take into account the period when TMR service was provided. The AESO concluded that TMR service does not reduce the economic life of the asset. As a result, the asset’s total amortization period should be equal to the economic life of the asset. The applicable amortization period, depreciation rates, and resulting depreciation amount for the asset should be consistent with how these amounts have been reported in the Customer’s audited financial statements. Upon request by the AESO, documentation necessary to independently verify and affirm that the asset specific amortization period, depreciation rates, and resulting depreciation amount should be provided by the Customer Alberta Electric System Operator AESO 2006 General Tariff Application January 31, 2005 Section 6 — Terms and Conditions of Service Page 33 of 42 to ensure these amounts are consistent with the methods and amounts reported in the Customer’s audited financial statements. 5 10 15 Capital structure — This step determines an appropriate capital structure or the means of financing the Customer’s investment in the generating unit providing TMR service. Such financing typically includes debt financing, common equity financing, and possibly other methods. For simplicity the AESO proposes that a deemed capital structure is used with 70% debt and 30% common equity. This debt-equity ratio is consistent with the evidence of the Ancillary Services Group dated February 21, 2002, filed in the Board’s proceeding into Decision 2002-103. Rate of return on equity and interest rate on debt — This step determines the appropriate equity rate of return and debt rate for return on investment. Generating units providing TMR services are typically independent power producers. The AESO is not aware of any generic reference to a market-based rate of return for an entity in the IPP business. Some stakeholders have indicated that the short-term services, such as TMR, should receive a rate of return greater than a typical IPP. 20 The equity rate of return on the equity portion of financing should reflect a general marketbased cost of supplying equity capital for investment in an IPP. The AESO proposes to use a 12% rate of return as was proposed in the evidence of the Ancillary Services Group dated February 21, 2002. 25 The debt rate on the portion financed by debt should reflect a general market-based cost of supplying debt to an IPP. The AESO proposes to use the debt rate formula proposed in the evidence of the Ancillary Services Group dated February 21, 2002. The debt rate would be equal to a 10-year Government of Canada Bond interest rate plus 0.5%. 30 35 40 The rate of return has not been adjusted for the specific service or the specific duration of the service provided. The provision of TMR service for a period of time does not affect the capability of the unit in future periods, or expose the service provider to incremental risk. TMR compensation provides financial upside compared to the energy market and therefore no adjustment is required. In selecting the rate of return level, the AESO considered other potential references it was aware of. A rate of return formula has been approved for regulated utilities in Alberta in Generic Cost of Capital Decision 2004-052. Applying the formula yields a value of 9.5% for 2005. The method used in the Power Purchase Arrangements (“PPAs”) as approved under Decision U99113 yields a value of about 9.5%, and is based on the average of daily close of trading yields (%) for Canadian government bonds of 10 years or more maturity plus an equity risk premium assumed constant over time at 4.5%.In the evidence of the Ancillary Services Group dated February 21, 2002, a 12% rate of return was proposed. Alberta Electric System Operator AESO 2006 General Tariff Application January 31, 2005 Section 6 — Terms and Conditions of Service Page 34 of 42 5 In selecting the debt rate, the AESO considered other potential references. In the evidence of the Ancillary Services Group dated February 21, 2002, a debt rate equal to a 10-year Canada Bond interest rate plus 0.5% was proposed. An average debt rate for each Customer could be calculated from the Customer’s audited financial statements. Income tax costs — Equity returns create an income tax cost. The income tax rates will be assumed to be at marginal tax rates for both federal and provincial portions of tax. 10 15 20 25 Total return costs — The total monthly return costs would be calculated as the sum of: • the amortization and depreciation monthly amount, determined as 1/12th of the annual amount; • monthly debt costs, determined as 1/12th of the product of the UCI times the debt percentage of the capital structure times the annual debt rate; • monthly equity return costs, determined as 1/12th of the product of the UCI times the equity percentage of the capital structure times the annual equity rate of return; and • monthly income tax costs, determined as the product of the tax rates and the monthly equity return amounts. In cases where TMR service is provided by a generating unit at or near the end of its life and the UCI amount is at zero, return will reflect a reasonable minimum return amount. On a monthly basis, the TMR share of total monthly return costs will be a pro-rated share based on the number of hours of TMR service compared to the sum of the number of hours of TMR service plus the number of non-TMR service hours in which the unit was in merit in the energy market. The number of non-TMR, in-merit service hours will be reasonably reduced if the characteristics of the Customer’s unit were such that the unit would not be capable of capturing the benefits of all of the in-merit hours. The TMR share of total monthly return costs may also be reduced if the unit was only partially used for TMR service. 30 Operation and maintenance costs — Direct operation and maintenance costs or those incurred only and entirely for the provision of the TMR service should be included. If indirect or fixed O&M costs are also associated with the provision of TMR service, a reasonable estimate of the indirect or fixed O&M costs will also be included. 35 40 On a monthly basis, the TMR share of indirect or fixed O&M costs will be a pro-rated share based on the number of hours of TMR service compared to the sum of the number of hours of TMR service plus the number of non-TMR service hours in which the unit was in merit in the energy market. The number of non-TMR, in-merit service hours will be reasonably reduced if the characteristics of the Customer’s unit were such that the unit would not be capable of capturing the benefits of all of the in-merit hours. The TMR share of indirect or fixed O&M costs should also be pro-rated if the unit was only partially used for TMR service as described in step 10. Alberta Electric System Operator AESO 2006 General Tariff Application January 31, 2005 Section 6 — Terms and Conditions of Service Page 35 of 42 Fuel costs — Direct fuel costs or those incurred only and entirely for the provision of the TMR service should be included. If indirect or fixed fuel costs are also associated with the provision of TMR service, a reasonable estimate of the indirect or fixed fuel costs will also be included. 5 10 15 On a monthly basis the TMR share of indirect or fixed fuel costs will be the pro-rated share based on the number of hours of TMR service compared to the sum of the number of hours of TMR service plus the number of non-TMR service hours in which the unit was in merit in the energy market. The number of non-TMR, in-merit service hours will be reasonably reduced if the characteristics of the Customer’s unit were such that the unit would not be capable of capturing the benefits of all of the in-merit hours. The TMR share of indirect or fixed fuel costs may also be reduced if the unit was only partially used for TMR service. Credits for common costs — Some generation facilities may provide additional services to industrial or other processes. For example, a cogeneration plant may provide steam or hot water from the generation facilities to an industrial plant. Common costs are fuel, operating, and maintenance expenses or costs associated with property, plant, and equipment where such costs or facilities are used for a service in addition to the TMR service. Administration and head office costs will not be considered as common costs. 20 The UCI of all common facilities up to the point where other services are sold or provided would be included in the UCI under step one above. The depreciation provisions, return on equity, etc. would be based on the UCI including all of the common facilities. Similarly, all fuel, operating, and maintenance costs would be included as costs. 25 30 35 40 The credit for common costs is the revenue and other benefits received from the provision of other services. For example, if steam is sold from a cogeneration facility, the revenue from the sale of the steam would be a credit. If instead of sale of the steam, a benefit was derived for provision of the steam, the effect of the benefit would be considered as a credit. For example, natural gas may be provided to a cogeneration complex in exchange for the steam. In such a case, the reduction in the requirement to purchase fuel would be reflected as a credit. The monthly revenue and other benefits received from the provision of other services would be deducted from the TMR cost amounts in order to determine the net cost. On a monthly basis, the TMR share of the credit will be the pro-rated share based on the number of hours of TMR service compared to the sum of the number of hours of TMR service plus the number of non-TMR service hours in which the unit was in merit in the energy market. The number of non-TMR, in-merit service hours will be reasonably reduced if the characteristics of the Customer’s unit were such that the unit would not be capable of capturing the benefits of all of the in-merit hours. The TMR share of the credit may also be reduced if the unit was only partially used for TMR service. Alberta Electric System Operator AESO 2006 General Tariff Application January 31, 2005 Section 6 — Terms and Conditions of Service Page 36 of 42 5 Adjustment for partial use of the unit for TMR service — In cases where the unit is only partially directed for TMR service and the remainder of the unit’s capacity is available to provide other electric services, an adjustment will be made to recognize the partial TMR use. The portion of the UCI of the unit and other fixed or indirect costs of the unit to be considered for TMR compensation would be based on the average MW directed for TMR service as a percentage of the average maximum MW capacity of the unit. Maximum amount of TMR compensation — The maximum amount would be the sum of the TMR portions of total return costs, the O&M costs, and fuel costs. 10 15 20 Other matters — The AESO may wish to verify that the information provided by the Customer was accurate. The AESO would normally expect the full cooperation of the Customer in its review of the information provided to ensure accordance with the principles above. However, in certain circumstances, information and calculations provided in respect of the TMR compensation by the Customer may require review and verification through an independent audit. In order to determine if compensation for TMR service has exceeded the maximum, AESO will monitor compensation of TMR service providers. If AESO judges that compensation paid to a customer for TMR services associated with a generating unit may be approaching or exceed the maximum defined in the terms and conditions, the AESO will determine the maximum for the Customer’s unit based on costs of the unit in accordance with the above methodology. The AESO will the adjust compensation, as needed, to comply with the terms and conditions. 25 30 Finally, to ensure that the maximum TMR compensation limit applies to both contracted and conscripted TMR services, the AESO has added one sentence to the Article as included in the Amendment Application. The AESO acknowledges that its December 3, 2004, letter to the EUB in the Amendment Application process stated, “As a result, the AESO has no intention of applying for any further amendment to Article 24 [proposed Article 11].” On further review, the AESO believes explicit recognition of the maximum TMR compensation limit required by the Transmission Regulation should be included in Article 11. The AESO therefore proposes the following addition to the end of Article 11.1: 35 Notwithstanding the foregoing, the compensation shall not exceed the Maximum TMR Compensation. 40 The AESO apologizes if this creates any concerns for parties involved in the Amendment Application proceeding, but believes it simply recognizes the existence of legislation which would have precedence in any case. Alberta Electric System Operator AESO 2006 General Tariff Application January 31, 2005 Section 6 — Terms and Conditions of Service Page 37 of 42 6.5 5 10 15 20 25 Other Changes to Terms and Conditions of Service In addition to the specific changes already discussed and those discussed below, the AESO has generally amended its terms and conditions of service by simplifying language, reorganizing articles, and removing the bulk of the appendices which will instead be available from the AESO on request. As a general guideline, process related articles and appendices were removed so that the AESO can make non-material changes without triggering a formal regulatory submission. A full blackline comparison of the current and proposed terms and conditions is included as Appendix E to this Application. Definitions and Interpretation (Article 1, Previously 1) — Definitions have been updated and revised to reflect current legislation and revisions to other articles of the terms and conditions of service. Several new definitions have been added, including the maximum compensation to be paid for transmission must-run generation as required by Section 23(1) of the Transmission Regulation. Application of Tariff (Article 2, Previously 2) — Other than restructuring for clarity, the intent and content of this article remains unchanged. Provision of System Access Service (Article 3, Previously 3) — The list of specific Articles under which the AESO reserves the right to withhold, limit, or discontinue service has been amended to provide such right where the Customer does not abide by the Tariff in its entirety. This change has been made to accord with the AESO’s provision of service in Article 3.1, which relies on a similar level of compliance. Customer Interconnection Requirements (Article 4, Previously 5) — Amendments include the condition that the AESO compliance waiver is subject to system reliability concerns. 30 System Access Application (Article 5, Previously 7) — Material revisions are discussed in Section 6.3. 35 Security and Customer Agreements (Article 6, Previously 8) — Article 6 has been amended to recognize the revised interconnection process discussed in Section 6.2. 40 In Decision 2001-6 on the EAL 2001 General Rate Application Customer Contribution Policy, the EUB summarized intervenors’ concerns with respect to EAL’s ability, through terms and conditions, to mitigate the risk associated with serving new demand customers. In response to these concerns, the EUB provided the following directions: 20. Accordingly, the Board directs EAL, in its refiling, to amend the contribution policy to clarify that EAL has the discretion to limit the Alberta Electric System Operator AESO 2006 General Tariff Application January 31, 2005 Section 6 — Terms and Conditions of Service Page 38 of 42 contractual term in order to mitigate the risk associated with serving new demand customers. 21. 5 10 15 20 The discretion over commitment term required by Direction 20 is no longer needed with the elimination of the commitment term amount in the AESO’s proposed calculation of maximum local investment (as discussed in Section 6.1) and the contract termination provisions of Article 14. The discretion over forms of security required by Direction 21 is provided by proposed Article 6 (previously 8) on Security and Customer Agreements and proposed Article 15 (previously 10) on Financial Security, Billing, and Payment Terms. These articles provide the AESO with the tools to mitigate the risk of stranded costs. Changes from the previous articles are consistent with the security requirements set out in the current ISO Rules for the Energy Market and permit the AESO to stipulate the form, timing, and realization of security, summarized as follows: • • 25 • 30 35 Accordingly, the Board directs EAL, at the next GTA, to address the proposal to amend Article 10 to provide the TA with discretion over what forms of security it will accept to mitigate the risk that a customer might abandon service and create the potential for stranded costs. Form of security — guarantee, cash deposit, or irrevocable letter of credit (Clauses 6.2(a) and 15.1(b)); Timing of security – when the customer commits to construction (Article 6.1) or before granting service to the customer (Article 15.1(b)), with additional or replacement security (as determined by the AESO) able to be requested at any time after the customer commits to construction (Clauses 6.2(b) and 15.1(c)); and Realization of security — the AESO may recover costs by realization of security or by offsetting such costs against other amounts owed by the AESO to the customer or its affiliates (Article 15.8). Metering (Article 7, Previously 12) — Detailed requirements regarding meter data submission have been removed, and reliance placed instead on the Electricity and Gas Inspection Act, the AESO Measurement System Standard, and the Settlement System Code where such requirements are established. Provision of Information by Customers (Article 8, Previously 11) — The detailed rationale for information required from customers has been replaced with a blanket term that customers must provide any information required by the AESO in the discharge of its duties. 40 Customer and System Contribution Policy (Article 9, Previously 9) — Material revisions are discussed in Sections 6.1 and 6.2. Alberta Electric System Operator AESO 2006 General Tariff Application January 31, 2005 Section 6 — Terms and Conditions of Service Page 39 of 42 5 Demand Opportunity Service (Article 10, Previously 6) — Process details have been replaced with the condition that customers interested in taking Demand Opportunity Service must meet the requirements and submit the applications as detailed in the AESO’s Demand Opportunity Business Practices. This amendment permits non-material procedure changes without the time and expense of a regulatory application. Ancillary Services (Article 11, Previously 24) — Article 11 has been revised to accord with the AESO’s Article 24 Amendment Application, dated August 16, 2004, as discussed in Section 6.4. 10 Under-Frequency Load Shedding (Article 12, Previously 4) — No material changes are proposed for this article. 15 20 25 30 Contract Capacity Allocation (Article 13, Previously (In Part) 15) — Article 13.1 and 13.2 are new in the proposed terms and conditions, and set out the AESO’s terms for and definition of contract capacity allocation for new or expanding points of connection. Article 13.1 states that the AESO will allocate contract capacity at the time the customer commits to construction. Article 13.2 allows the AESO to re-allocate contract capacity if the customer fails to act in a timely manner to meet the agreed-upon in-service date. These clauses address circumstances where the delay of one customer could block system access for another. Reductions or Termination of Contract Capacity (Article 14, Previously (In Part) 15) — Article 14 has been expanded to include the provision that in reducing contract capacity the customer will be required to sign a revised System Access Service Agreement and may be required to pay a customer contribution. The potential for additional contribution recognizes that the proposed local investment is based on contract capacity over a contract term. The maximum local investment would therefore be reduced in proportion to a reduction in contract capacity, to a level potentially below the customer-related costs and therefore requiring a customer contribution. Article 14.3 has been added to provide customers that request early contract termination the option of making a lump sum payment to the AESO, as an alternative to ongoing monthly billing. 35 40 Financial Security, Billing, and Payment Terms (Article 15, Previously 10 and (In Part) 15) — Security requirements have been amended to accord with Article 6 on security and customer agreements, as discussed above. The process for issuing statements of account has been revised to reflect the three steps consisting of initial, interim, and final statements to accord with the energy settlement schedule. Article 15.3(c) provides that, in the case of interim and final statements of account for charges or refunds of less than $1,000, the AESO has discretion to not issue such statements. Alberta Electric System Operator AESO 2006 General Tariff Application January 31, 2005 Section 6 — Terms and Conditions of Service Page 40 of 42 Peak Metered Demand Waiver (Article 16, Previously 21) — Article 16.1(b) has been expanded and made distinct to distribution facility owners, to clearly set out the information required by the AESO in respect of pre-scheduled distribution maintenance and the related peak demand waiver. 5 10 Service Interruptions and Force Majeure (Article 17, Previously 13) — To add clarity, the wording in Article 17.1 on service interruptions has been changed to “The AESO specifically does not guarantee uninterrupted…” service in respect of listed activities, from “The AESO will not be responsible for interruptions…” as a result of listed activities. Article 17.2 has been added to explicitly permit the AESO, on six months’ notice, to temporarily suspend System Access Service to accommodate the construction, commissioning, or testing of new facilities. The AESO recognizes the disincentive for an existing customer to agree to such suspension where the new facilities are required for a competitor, and intends to rely on this provision only in circumstances where such agreement is not obtained. 15 20 25 Limitation of Liability (Article 18, Previously 14) — As a response to certain liability protection issues that arose during the AESO’s 2003 General Tariff Application, the EUB directed the AESO by letter dated June 25, 2003 to initiate a process through which the EUB could make a determination in respect of the issues raised. As part of that process, the AESO proposed an interim amendment to the liability provisions of its tariff enabling the AESO to expressly indemnify ancillary service providers. The EUB approved the amendment in Decision 2003-059 on the AESO’s 2003 General Tariff Application Liability Protection, on an interim basis until the matter could be heard in full. In its final determinations in Decision 2003-109 on the AESO’s 2003 GTA Liability Protection, the EUB provided the following directions: 1. The Board directs the AESO forthwith to initiate discussions with appropriate members of the Government of Alberta in furtherance of the Board’s recommendation. The Board also directs the AESO to advise the Board and all parties to this proceeding that discussions have commenced. 2. Furthermore, the Board directs the AESO to advise the Board of the progress of these discussions no later than April 1, 2004 and to provide the AESO’s views on the likelihood of the Board’s recommendation being implemented, in whole or in part. 3. The Board also encourages the AESO, in the context of these discussions, to explore with the Government the reasons for the exclusion of directors from individual protection under the EUA with a view to determining whether they should be protected either under section 90 or in relation to those entities for whom the Board has recommended protection in this Decision, or both. 30 35 40 Alberta Electric System Operator AESO 2006 General Tariff Application January 31, 2005 Section 6 — Terms and Conditions of Service Page 41 of 42 4. In that regard, if matters cannot be concluded with the Government of Alberta as recommended in this Decision by July 1, 2004, then the Board directs the AESO to advise the Board to that effect no later than July 1, 2004. At the same time, if those matters cannot be concluded, the Board directs the AESO to recommend a process that will lead to Board approval of a tariff based solution, no later than December 1, 2004, by proposing the necessary amendments to the T&Cs of the AESO, TFOs and DISCOs in order for them to be effective January 1, 2005. 5. The Board directs the AESO to further amend Article 14 by providing that the amendments to Article 14 approved on an interim basis in Decision 2003-059 and confirmed in this Decision will terminate effective December 31, 2004. 5 10 15 The AESO responded to Directions 1 and 2 by way of letters to the EUB dated January 23, 2004 and April 1, 2004, respectively. 20 25 In respect of the remaining directions, the AESO notes that the Liability Protection Regulation (A.R. 66/2004) was enacted on March 31, 2004. The Regulation specifically extended the liability protection of the AESO, as provided in Section 90 of the Electric Utilities Act, to include, without limitation: (a) (b) (c) (d) (e) 30 (f) (g) an ancillary services provider, a power purchase arrangement owner, an owner of a transmission facility, an owner of an electric distribution system, a person who is a member of a joint venture with or is a partner of a person referred to in clauses (a) to (d), including a general partner of a limited partnership, an affiliate of a person referred to in clauses (a) to (e), and each director, officer and employee of a person referred to in clauses (a) to (f). 35 Additionally, the Liability Protection Regulation specifically requires that the ISO must indemnify black start service providers in the same manner and in the same circumstances as other Independent System Operator persons under Section 90(5) of the Electric Utilities Act. 40 In accordance with the above, the AESO proposes to amend the limitation of liability article by deleting the indemnity provisions for ancillary service providers and instead broadening the liability protection for an AESO Person as defined in the Electric Utilities Act and the Liability Protection Regulation. Alberta Electric System Operator AESO 2006 General Tariff Application January 31, 2005 Section 6 — Terms and Conditions of Service Page 42 of 42 Dispute Resolution (Article 19, Previously 16) — Article 19.1 has been added to ensure all disputes are documented appropriately. 5 Confidentiality (Article 20, Previously 25) — No material changes are proposed for this article. Miscellaneous (Article 21, Previously 19, 20, and 23) — Other than restructuring for clarity, the intent and content of this article remains unchanged. 10 Metering Equipment Information (Appendix A, Previously D) — No changes are proposed for this appendix. 15 Regulated Generating Units (Appendix B, Previously E) — No changes are proposed for this appendix. Deleted Articles (Previously 22) — The AESO proposes to delete the previous Article 22 on transmission system expansion as terms of transmission expansion procurement and direct assignment are no longer required under the Transmission Regulation. 20 Deleted Appendices (Previously A, B, and C) — The AESO proposes to delete: • Appendix A — Intentionally left Blank; • Appendix B — System Access Service Agreement Proformas; and • Appendix C — Construction Commitment Agreement Proforma. 25 The deletion of the agreement proformas will enable on-going, non-material changes to these agreements without the time and expense of gaining regulatory approval. The AESO will make such agreement proformas available to customers upon request. 30