MONTE S. FORSTER Barrister & Solicitor SENT ELECTRONICALLY
by user
Comments
Transcript
MONTE S. FORSTER Barrister & Solicitor SENT ELECTRONICALLY
MONTE S. FORSTER* Barrister & Solicitor Monte S. Forster T 403 262.8848 F 1 866 224.5593 [email protected] SENT ELECTRONICALLY November 24, 2005 12th Floor, Fifth Avenue Place 425 – 1st Street SW Calgary, Alberta Canada T2P 3L8 * Denotes a Professional Corporation Alberta Energy and Utilities Board 640 – 5 Avenue SW Calgary, Alberta T2P 3G4 Attention: Mr. Jamie Cameron Dear Mr. Cameron: Re: Alberta Energy and Utilities Board (“Board”) Application No. 1363012; Board Decision 2005-096; Alberta Electric System Operator (“AESO”) 2005/2006 General Tariff Application (“2005/2006 GTA”); Milner Power Inc. November 24, 2005, Review and Variance Application I am enclosing a Review and Variance Application on behalf of Milner Power Inc. (“Milner”) dated November 24, 2005 (the “Application”), wherein Milner seeks, among other things, review and variance of the Board’s determinations in the context of the AESO’s 2005/2006 GTA to decline to consider Milner’s August 17, 2005 submissions, and to relieve the AESO of certain outstanding directives and undertakings. It is a matter of concern that the Board would summarily choose to ignore Milner’s August 17, 2005 submissions on the basis that it was then too late for the Board to consider new evidence in the GTA, and then choose, some two months later, to undertake a review of its decision, since issued, on the basis of new evidence filed by the AESO in September and October 2005. As the Board refused to even consider Milner’s submissions, the Board cannot say, and, of course, did not endeavour to say, that the information provided by Milner would not have altered the Board’s determinations in Decision 2005-096. The submissions were simply ignored as being out of time. Alberta Energy and Utilities Board Attention: Mr. Jamie Cameron November 24, 2005 Page 2 This disparity in treatment of Milner on the one hand, and of the AESO on the other, is, in itself, a matter of concern, and is an error warranting review. Nevertheless, Milner is not requesting, at this time, that the Board initiate a review of Decision 2005-096 (and the Board’s determination to refuse to consider Milner’s August 17, 2005 submissions) independently of Milner’s August 17, 2005 Complaint Application (the “Complaint”).1 Rather, Milner is advancing the present Application, in part, to ensure that the Board retains the ability to grant all necessary remedies requested in the Complaint. The Board was express that its decision to decline to consider Milner’s August 17, 2005 submissions was, “without prejudice to Milner’s right to pursue its complaint pursuant to Section 25 of the Electric Utilities Act.”2 Nonetheless, certain parties have argued that the Board’s decision to relieve the AESO of its earlier loss factor directives has prejudiced Milner in advancing its Complaint. In consequence of these submissions, and the want of any further direction from the Board, Milner has chosen to file the present Application as a precautionary measure. We request that the present Application be considered, as warranted, as a concomitant application to Milner’s Complaint. The fact Milner is requesting that the Board treat the present Application concomitantly with the Complaint should not be seen as an indication that Milner is not concerned that the matters raised in the Application (including the now evident significant variability in loss factors calculations resulting from the AESO’s proposed methodology or proposed method of implementing the methodology), be fully addressed, or that delay in considering the Application would be appropriate. Rather, it is an indication that each of the matters raised should be susceptible of full consideration in the context of the Complaint. In particular, Milner requests that the Board consider (concurrently with the parallel requests for relief in the Complaint) Milner’s present requests for extension of the AESO’s existing tariffbased loss factor methodology and that all necessary amendments to the AESO’s Rate Schedules be undertaken as soon as the Board’s schedule allows. 1 2 Application No. 1414213. Board cover correspondence to Decision 2005-096, dated August 28, 2005. Alberta Energy and Utilities Board Attention: Mr. Jamie Cameron November 24, 2005 Page 3 Please direct all correspondence concerning the present Application to the following: Ms. Pat Lucas Vice President Operations Milner Power Inc. Suite 1210, 715 – 5th Avenue S.W. Calgary, Alberta T2P 2X6 Telephone: 403.750.9308 Facsimile: 403.263.9125 Email: [email protected] Yours truly, <Filed electronically> MONTE S. FORSTER Mr. Monte S. Forster Barrister & Solicitor 12th Floor, 425, 1st Street S.W. Calgary, Alberta T2P 3L8 Telephone: 403.262.8848 Facsimile: 1.866.224.5593 Email: [email protected] ALBERTA ENERGY AND UTILITIES BOARD IN THE MATTER OF the Electric Utilities Act, SA 2003, c. E-5.1; the Alberta Energy and Utilities Board Act, RSA 2000, c. A-19.5; the Alberta Energy and Utilities Board Act, RSA 2000, c. A-19.5; the Transmission Regulation, AR 174/2004; and the Alberta Energy and Utilities Board Rules of Practice, AR 101/2001; AND IN THE MATTER OF the Alberta Electric System Operator’s 2005/2006 General Tariff Application and Alberta Energy and Utilities Board Decision 2005-096, wherein the Alberta Energy and Utilities Board granted approval of certain aspects of the Alberta Electric System Operator’s 2005/2006 General Tariff Application (Application No. 1363012) including requests by the Alberta Electric System Operator for approval of certain Rate Schedules and to be relieved of certain outstanding Loss Factor Directives; AND IN THE MATTER OF an Application by Milner Power Inc. for Review and Variance of Decision 2005-096 pursuant to section 126 of the Electric Utilities Act, SA 2003, c. E-5.1. MILNER POWER INC. REVIEW AND VARIANCE APPLICATION ELECTRIC UTILITIES ACT SECTION 126 NATURE OF THE APPLICATION TAKE NOTICE that Milner Power Inc.1 (the “Applicant”) brings the present Review and Variance Application (the “Application”) before the Alberta Energy and Utilities Board (“Board”) pursuant to section 126 of the Electric Utilities Act, SA 2003, c. E-5.1 (the “EUA”) and section 46 of the Alberta Energy and Utilities Board Rules of Practice, AR 101/2001, concerning the Board’s approval of the Alberta Electric System Operator’s (the “AESO’s”) 2005/2006 General Tariff Application (Application No. 1363012) (the “GTA”) and, in particular, concerning the Board’s determinations to decline to consider the Applicant’s August 17, 2005, submissions concerning, inter alia, the AESO’s request for relief from certain outstanding loss factor directives issued by the Board in Decisions 2000-1, 2000-27 and 2002-104; to grant relief to the AESO from the said directives and AESO undertakings to stakeholders in the AESO’s 2002 Negotiated Settlement, as approved by the Board in Decision 2002-064; and to approve certain Rate Schedules allowing the recovery of loss charges in accordance with the AESO’s newly proposed and finalized Loss Factor Methodology, which the AESO proposes to implement January 1, 2006, and pursuant to which final loss factors have been determined by the AESO as of November 18, 2005. 1 Milner Power Inc. is a wholly owned subsidiary of Maxim Power Corp. Milner Power Inc. owns and operates the H. R. Milner power station (the “Milner Plant”) a 144-MW coal-fired power station located near the town of Grande Cache, Alberta. RELIEF SOUGHT AND TAKE NOTICE that the Applicant seeks orders of the Board: (a) Directing that the Board’s determinations in Decision 2005-096 to ignore Milner’s August 17, 2005 submissions in the AESO’s GTA, be reviewed, and that the Board consider the said submissions; (b) Directing that the Board’s determinations in Decision 2005-096 to relieve the AESO of its undertakings to stakeholders in the AESO’s 2002 Negotiated Settlement and to relieve the AESO of those loss factor directives imposed by the Board in Board Decisions 2000-1, 2000-27 and 2002-104, be reviewed, and that the said determinations be varied in accordance with paragraph (c) hereof; (c) Directing that Decision 2005-096 be varied and that the AESO comply with the AESO’s undertakings to stakeholders and all outstanding Board directives concerning the study, selection and implementation of the AESO’s loss factor methodology in accordance with subsection 8(1)(d) of the Transmission Regulation, AR 174/2004 (the “Regulation”) and Board Decisions 2000-1, 200027, 2002-064 and 2002-104; (d) Directing that the AESO’s existing tariff-based loss factor methodology be extended beyond December 31, 2005 to June 30, 2006, or to such future date as the Board may direct, to permit the AESO to comply with the AESO’s undertakings to stakeholders and all outstanding Board directives as directed in paragraph (c) hereto; and (e) Directing that the AESO’s applied for Rate Schedules be amended, as necessary, to allow for the continuation of the recovery of losses in accordance with the AESO’s existing tariff-based loss factor methodology and with no changes to the AESO’s raw loss factors, until such time as that methodology is replaced by a new Board approved methodology. GROUNDS OF THE APPLICATION AND TAKE NOTICE that the grounds of the Application are that: (a) The Board improperly declined to consider the August 17, 2005 submissions of Milner in the GTA and consequently improperly relieved the AESO of its undertakings to stakeholders under the AESO’s 2002 Negotiated Settlement (as approved by the Board in Decision 2002-064), and improperly relieved the AESO of the AESO’s obligations to comply with certain loss factor directives issued by the Board in Decisions 2000-1, 2000-27 and 2002-104. The Board’s refusal to consider Milner’s August 17, 2005 submissions was itself an error of law and led to further errors of fact and law in Decision 2005-096; 2 (b) Since the date of Decision 2005-096 circumstances have changed in a substantial and unforeseen manner and render the continuation of the tariff unjust and unreasonable. The AESO has now issued its final loss factor calculations. These calculations vary substantially from the AESO’s calculations issued eight months earlier. The significant variation evidences either that the AESO does not have the means to properly calculate loss factors under its new proposed loss factor methodology or that the methodology allows such year to year variability in loss factors that the AESO’s proposed methodology and/or proposed implementation of the methodology, will fail entirely to send effective locational signals to generators and will thus fail to meet the objectives of the Alberta Government’s Transmission Development Policy (the “Policy”)2 and the Regulation; and (c) The principle of rate stability mandates that the existing tariff-based loss factor methodology and raw loss factors be continued until the Board approves an acceptable replacement methodology consistent with the Policy and the Regulation. STATEMENT OF FACTS 1. Milner incorporates by reference and adopts paragraphs 1 to 50 of Milner’s Complaint Application (Application No. 1414213) filed with the Board August 17, 2005 (the “Complaint”). 2. On August 17, 2005 Milner filed submissions with the Board in the GTA advising the Board that the Complaint had been filed as of that date pursuant to Sections 25 and 26 of the EUA. 3. Milner noted in its August 17, 2005 submissions that the AESO’s proposed loss factor methodology would fail to allocate costs to generators on the basis of the contribution (cost-causation) of each generating unit to system losses, and would thus fail to comply with the Regulation. Milner also noted that its Complaint included requests that the AESO’s proposed loss factor methodology be revoked or suspended until the AESO complied both with the Board’s outstanding loss factor directives3 2 November 2003 Transmission Development Policy Paper by the Alberta Department of Energy entitled “Transmission Development – The Right Path for Alberta – A Policy Paper” The Policy is available at the following link: http://www.energy.gov.ab.ca/docs/electricity/pdfs/transmissionPolicy.pdf 3 In Decision 2000-27 at pages 64 to 65, the Board directed EAL to study the following losses issues: • Whether it would be appropriate or necessary to develop a methodology for providing loss signals (that recognize the reduction or increase in system losses caused by adding a new generator at a specific location) for the siting of new generation. • Whether the Alberta system warrants the use of an “average MW in” approach for the purposes of calculating loss factors for economic dispatch. • Whether the “average MW in” approach provides optimal economic signals for both economic dispatch and siting of new generation. • Whether EAL should introduce optional five-year financial losses hedges in addition to or in substitution for the five-year locked in physical hedges. 3 and with the AESO’s outstanding loss factor undertakings in the AESO’s 2002 Negotiated Settlement.4 4. Milner requested in its August 17, 2005 submissions that the Board defer all rulings in the AESO’s GTA concerning the AESO’s request for waiver of the Board’s loss factor directives and further that the Board ensure that no ruling issued in the context of the 2006 GTA undermined the AESO’s Negotiated Settlement undertakings until the Board had an opportunity to fully consider the Complaint. 5. The Board released Decision 2005-096 on August 28, 2005. The Board issued the Decision with correspondence indicating that the Board was declining to consider Milner’s August 17, 2005 submissions in the context of the GTA. The Board expressly stated it was declining to consider Milner’s submissions because the time for filing evidence in the AESO’s GTA had passed. Although refusing to consider Milner’s submissions in the context of the GTA, the Board noted that its determination not to consider Milner’s submissions and its determination to relieve the AESO of its obligation to comply with the loss factor directives in the context of the GTA was, “without prejudice to Milner’s right to pursue its complaint pursuant to Section 25 of the Electric Utilities Act.”5 6. On October 7, 2005, in the course of submissions made in the Complaint, and ostensibly in response to a Board request of September 22, 2005, for submissions on certain limited points, TransAlta Utilities Corporation (“TransAlta”) and TransCanada Energy Ltd. (“TransCanada”) submitted that the Board should summarily dismiss all or a portion of the Complaint due to the Board’s determination in Decision 2005-096, for the purposes of the GTA, to waive compliance with the Board’s loss factor directives issued in Decisions 2000-1, 2000-27 and 2002-104. 7. On October 11, 2005, Milner responded to the Board’s correspondence of September 7, 2005 and replied, inter alia, to the submissions of TransAlta and TransCanada. Milner submitted that the Board’s refusal to consider Milner’s August 17, 2005 submissions and determination to relieve the AESO of its obligations to comply with the Board’s loss factor directives, did not undermine the importance of AESO compliance with directives of the substantive nature of the Board’s loss factor 4 The 2002 Negotiated Settlement specified in part (Decision 2002-064 at page 23): (j) Board Directives: The Settlement does not affect the TA’s obligations to comply with Board directives. The TA will, in a timely fashion and in any event not later than December 31, 2002, comply with all Board Directives. None of the Stakeholders, by signing this Settlement or otherwise, agree that the TA has complied with the Board Directives. The TA shall provide quarterly reports to the Stakeholders on the progress to date, and intended completion dates, for all outstanding Board Directives. For clarity, the COS Credit Rate Schedule shall be interim refundable as of January 1, 2002 pending a COT Credit application and approval by the Board. … (l) Audit and Adjustment of Loss Factor Methodology: The existing loss factor methodology will continue to apply in 2002. (m) Review of Loss Factor Methodology: The TA will conduct a fundamental review of the treatment of loss factor cost allocation and recovery methodologies. 5 Board August 28, 2005 cover correspondence to Decision 2005-096. 4 directives and was expressly without prejudice to Milner’s right to pursue the Complaint. Milner also noted that because the directives were issued in the context of and assumed compliance with the directives through a tariff-based methodology, the Board was arguably obliged to vary the directives to reflect the new rule-based methodology mandated by the Regulation. Milner further stated:6 The fact the Board has relieved the AESO from certain outstanding tariff-based directives in Decision 2005-096 does not foreclose the Board from issuing new directives to the same substantive effect in the [Complaint]. Additionally, whether the Board does or does not issue new directives to the same effect, the Board may still choose to revoke the AESO’s proposed methodology and direct that the AESO implement an “average MW in” approach and phase-in the new approach. The Milner [Complaint] Application is not premised on the existence of the Board’s directives. The Application is based, inter alia, on the need of the AESO’s loss factor methodology and the implementation of that methodology to comply with the EUA, the Transmission Development Policy, the Transmission Regulation, and the principles of justness and reasonableness. 8. On November 2, 2005, TransAlta replied to Milner’s October 11, 2005 submissions, again suggesting that the Complaint be dismissed in whole or in part. 9. On September 27, 2005, the AESO submitted its GTA refiling (Application No. 1420890). 10. On October 7, 2005 the AESO filed new evidence in the GTA and requested that the Board modify its approval of the AESO’s DTS rate design to “mitigate[] the impact of the $/month charge on small DTS services.”7 11. On October 31, 2005, in response to concerns raised by interveners, the AESO advised the Board that it was withdrawing its proposal for modification of its DTS rate design. Nonetheless, the AESO proposed that the Board rely on the evidence filed by the AESO on October 7, 2005, in determining whether Rather, the AESO proposed that the Board “rely on the information contained in it Supplementary Filing as part of the Board’s determination of an appropriate DTS rate design for 2006.”8 12. On November 7, 2005 the Board issued a “Notice of Board Review” and stated, in part:9 On November 7, 2005, the Board, pursuant to s. 46(1) of the AEUB Rules of Practice, made a determination that in light of the new evidence received from the AESO in the Refiling and Supplemental Filing, that it would review its findings in Decision 2005-096. In reaching its decision to review Decision 2005096, the Board determined that had the information contained in the Refiling and 6 Milner October 11, 2005 submissions, at page 9. AESO October 7, 2005 submissions, at page 1. 8 AESO October 31, 2005 submissions, at page 1. 9 Board November 7, 2005 Notice Letter, at page 2. 7 5 Supplementary Filing as it related to the impact of the customer POD charge on low load customers of 5 MW or less been before the Board in the original proceeding, the Board would have taken such information into consideration in its decision. For this reason, the Board considered that a review of its own decision was warranted to consider this information. 13. On November 18, 2005, the AESO issued its final loss factor calculations for 2006. For numerous AESO customers, the final loss factors to be applied for 2006 vary substantially from those calculated by the AESO in March 2005. 14. Forty-eight generators now have final loss factors higher than those predicted in March of 2005. On average these generators have seen their loss factors revised upward by 2.0% with one generator experiencing a 3.77% revision in its loss factor. Sixteen generators that were forecast to receive a credit in March were instead assessed a charge when the final loss factors were released.10 15. In thirty-three instances the final loss factors assigned to generators were lower than predicted in March. For these generators, the average change in the loss factors from that predicted in March was 2.5% with one generator experiencing a 6.37% revision in its loss factor. Ten generators that the AESO had assessed a charge in March were given a credit in the final loss factors.11 SUBMISSIONS IN SUPPORT OF THE APPLICATION 16. The Board’s refusal to consider Milner’s submissions in mid-August 2005 on the basis it was too late at that time to receive new evidence, and acceptance and consideration of new evidence filed by the AESO up to seven weeks later, is at best arbitrary, and amounts to an error of law. 17. As the Board refused to even consider Milner’s submissions, the Board cannot say that the information provided by Milner would not have altered the Board’s determinations in Decision 2005-096. 18. The AESO’s final loss factor calculations vary substantially from the AESO’s calculations issued eight months earlier. The significant variation evidences either that the AESO does not have the means to properly calculate loss factors under its new loss factor methodology or that the methodology or the AESO’s proposed implementation of the methodology allows for such year to year variability in loss factors that the AESO’s methodology will fail entirely to send effective locational signals to generators and will thus fail to meet the objectives of the Policy and the Regulation.12 10 The AESO’s final loss factors can be accessed that the following link: http://www.aeso.ca/files/2006_loss-factors_20051118_Final.pdf 11 See footnote 10 above. 12 The Policy states in part (page 6 of 19): 6 19. It is submitted that Milner’s August 17, 2005 submissions were improperly excluded from the Board’s consideration. Moreover, it is submitted that the significant variation now evident in the AESO’s loss factor calculations, and which appear to flow as a natural consequence of the AESO’s proposed methodology or proposed implementation of the methodology, warrant further study of the merits of the methodology, the implementation of the methodology and the “average MW in” methodology. 20. Milner accordingly requests that the Board review its determination not to consider Milner’s August 17, 2005 submissions and further that the Board review its determination to relieve the AESO of the Board’s directives in Decisions 2000-1, 2000-27 and 2002-104, and the AESO’s undertakings, approved in Decision 2002064. 21. Milner further requests that Decision 2005-096 be varied and that the AESO be directed to comply with all outstanding Board directives and its undertakings to stakeholders concerning the study, selection and implementation of the AESO’s loss factor methodology in accordance with subsection 8(1)(d) of the Regulation and Board Decisions 2000-1, 2000-27, 2002-064 and 2002-104. 22. Milner further requests, given the importance of the principle of rate stability, that the AESO’s existing tariff-based loss factor methodology be continued until the Board approves an acceptable replacement methodology consistent with the Policy and the Regulation. 23. Milner accordingly requests the Board direct that the AESO’s existing tariff-based loss factor methodology and raw loss factors be extended beyond December 31, 2005 to June 30, 2006, or to such other date as the Board may direct, to permit the AESO to comply with all outstanding Board directives and the AESO’s undertakings to stakeholders as requested herein. 24. Milner finally requests the Board revise Decision 2005-096 to permit the amendment of the AESO’s applied for Rate Schedules to allow for the continuation of the recovery of losses in accordance with the AESO’s existing tariff-based loss factor The primary purpose of allocating losses to generators is to act as an effective locational incentive. Therefore, the loss factor methodology should be a long term signal and relatively stable, to allow it to be factored into investment decisions. In order of priority, the loss methodology should: a. Provide a locational incentive for generators b. Allow the ISO to pursue transmission projects that will reduce overall transmission losses in the long term to the benefit of all consumers, as consumers ultimately pay for losses through their energy price. c. Where possible, provide a signal for generation dispatch, so as to minimize transmission losses on real time basis. Alberta Energy considers that the current loss methodology used by the ISO must be reviewed and made more consistent with average system losses as opposed to marginal locational losses. 7 methodology and with no changes to the existing raw loss factors until such time as that methodology is replaced by a new Board approved methodology. ALL OF WHICH IS RESPECTFULLY SUBMITTED THIS 24TH DAY OF NOVEMBER 2005. <Filed electronically> ____________________ MONTE S. FORSTER Counsel for Milner Power Inc. 8