Alberta Electric System Operator (AESO) 2005/2006 General Tariff Application August 28, 2005
by user
Comments
Transcript
Alberta Electric System Operator (AESO) 2005/2006 General Tariff Application August 28, 2005
Decision 2005-096 Alberta Electric System Operator (AESO) 2005/2006 General Tariff Application August 28, 2005 ALBERTA ENERGY AND UTILITIES BOARD Decision 2005-096: Alberta Electric System Operator (AESO) 2005/2006 General Tariff Application Application No. 1363012 August 28, 2005 Published by Alberta Energy and Utilities Board 640 – 5 Avenue SW Calgary, Alberta T2P 3G4 Telephone: (403) 297-8311 Fax: (403) 297-7040 Web site: www.eub.gov.ab.ca Contents 1 INTRODUCTION................................................................................................................. 1 2 2005 OWN COST OUTSTANDING MATTERS .............................................................. 2 2.1 Incentive Compensation Program Parameters ............................................................... 2 2.2 Disallowance of Costs .................................................................................................... 3 3 2005 PHASE I REVENUE REQUIREMENT ................................................................... 4 3.1 2005 Revenue Requirement and Deferral Account Treatment ...................................... 4 4 2006 PHASE I REVENUE REQUIREMENT ................................................................... 5 4.1 2006 Own Costs Process ................................................................................................ 5 4.2 Forecast Methodology.................................................................................................... 6 4.2.1 Key Forecast Inputs .......................................................................................... 6 4.3 TFO Wires Related Costs............................................................................................... 8 4.4 Non-Wires Costs ............................................................................................................ 9 4.5 Ancillary Services Forecast.......................................................................................... 12 4.6 Transmission Losses .................................................................................................... 13 5 RATE DESIGN ................................................................................................................... 13 5.1 Legislative Requirements ............................................................................................. 13 5.2 Rate Design Principles ................................................................................................. 15 5.3 Transmission Wires Cost Causation Study (TCCS) .................................................... 17 5.3.1 Functionalization of Costs .............................................................................. 19 5.3.2 Classification of Costs .................................................................................... 21 5.4 Ancillary Services Cost of Service Study .................................................................... 24 5.4.1 Classification of Ancillary Services................................................................ 25 5.5 Demand Transmission Service Rate Design ................................................................ 25 5.5.1 Unbundling ..................................................................................................... 25 5.5.2 Classification of Costs .................................................................................... 26 5.5.3 Ratchet ............................................................................................................ 29 5.5.4 Standby Tariffs................................................................................................ 30 5.6 Supply Transmission Service Rate (STS) .................................................................... 30 5.7 Fort Nelson BC Rate .................................................................................................... 30 5.8 Export Rates ................................................................................................................. 33 5.8.1 Firm Export/Import Rates ............................................................................... 33 5.8.2 Generator Remedial Action Scheme (GRAS) ................................................ 36 5.8.3 Opportunity Import and Export Rates............................................................. 37 5.9 Primary Service Credit and Finalization of COS Credits ............................................ 38 5.10 Opportunity Service Rates ........................................................................................... 40 5.11 Rate Riders ................................................................................................................... 41 5.11.1 Rider B .......................................................................................................... 41 5.11.2 Rider C .......................................................................................................... 41 5.11.3 Rider E .......................................................................................................... 41 6 TERMS AND CONDITIONS – CONTRIBUTION POLICY........................................ 42 6.1 Customer Contribution Policy ..................................................................................... 42 6.1.1 High Level Policy Principles .......................................................................... 42 6.1.2 Designation of System-Related Costs ............................................................. 47 EUB Decision 2005-096 (August 28, 2005) • i 6.1.3 “Standard” and “Optional” Interconnection Facilities .................................... 49 6.1.3.1 AESO Standard Service Definition ................................................................ 49 6.1.4 Maximum Investment Formula....................................................................... 55 6.1.5 Contribution Waivers for Expansion at Multiple Customer PODs ................ 58 6.1.6 Other Contribution Policy Issues .................................................................... 60 6.1.6.1 Application of Contribution Policy to Dual-Use Sites ................................... 60 6.1.6.2 Staged Load .................................................................................................... 62 6.1.6.3 Distribution vs Transmission Interconnections .............................................. 62 6.1.6.4 Discount Rates ................................................................................................ 63 6.1.6.5 Common Facilities .......................................................................................... 63 6.1.6.6 Conditions for Customer Contribution Adjustments ...................................... 66 6.1.6.7 Pre-Paid Operations and Maintenance Charge ............................................... 66 6.2 Generator System Contribution ................................................................................... 69 6.3 Contribution Policy Next Steps.................................................................................... 73 6.3.1 Contribution Policy Implementation Timing .................................................. 73 6.3.2 Disco/AESO Contribution Policy Harmonization .......................................... 73 6.4 TransCanada Standard Interconnection Facilities Complaint ...................................... 73 7 TERMS AND CONDITIONS – OTHER ......................................................................... 74 7.1 System Access Applications ........................................................................................ 74 7.2 Right of “Set-Off” ........................................................................................................ 75 7.3 TFO Investment in Optional Facilities Constructed for Distribution Facility Owners (Discos) ................................................................................................................................. 76 7.4 Merchant Transmission Interconnections .................................................................... 78 7.5 Contract Term, Reductions, and Termination .............................................................. 80 7.6 Letters of Credit Security in Respect of Construction Projects ................................... 83 7.7 Consistency, Business Practice Documents and Other T&C Issues ............................ 84 8 OTHER MATTERS ........................................................................................................... 88 8.1 Disposition of Outstanding Board Directions .............................................................. 88 9 REFILING OF APPLICATION ....................................................................................... 91 10 ORDER ................................................................................................................................ 91 APPENDIX A – RATE DESIGN SPREADSHEET ................................................................ 92 APPENDIX 1 – HEARING PARTICIPANTS ......................................................................... 93 APPENDIX 2 – SUMMARY OF BOARD DIRECTIONS ..................................................... 95 APPENDIX 4 – ABBREVIATIONS ....................................................................................... 101 ii • EUB Decision 2005-096 (August 28, 2005) 2005/2006 General Tariff Application Alberta Electric System Operator To conclude, with regard to the rate design principles discussed above, the Board considers that cost causation must be afforded the most weight in attempting to balance these sometimes competing principles when evaluating a proposed rate design. That is, in reviewing a proposed rate design, the Board finds that it is critical that the rate design proposed ensures that a customer that causes a cost must be prepared to pay that cost. The principle of rate shock, which can conflict with this cost causation principle, must take a secondary consideration to cost causation in arriving at an appropriate rate design. The balance of the criteria can usually be seen as complimentary to cost causation. On balance, if rates reflect causation, barring unusual regulatory events such as regulatory lag or a dramatic change in cost structure, there should be little need to be concerned about the principles of rate shock and gradualism. The Board has considered all of these factors in arriving at its preferred classification of costs and rate design, as contained in sections 5.3, 5.4 and 5.5 of this Decision. 5.3 Transmission Wires Cost Causation Study (TCCS) The AESO filed a cost of service study in response to Direction 21 contained in Decision 200132. The TCCS covered the wires portion of transmission costs only and a summary of the study results was produced at pages 4-6 of Section 4 of the Application. The TCCS investigated transmission wires costs and included an analysis of net book value data by transmission facility from the four major transmission facility owners in Alberta, namely, AltaLink, ATCO Electric, Enmax, and EPCOR. The study assessed, or “sub-functionalized”, transmission wires costs to bulk system, local system, and POD (including radial lines exclusively used by a single POD) functions based on three approaches: voltage level, economics, and volume-distance. The study’s final recommendation was functionalization based on the average of the three methods, these being voltage level, economics and MW-kM. The three methods are described in detail in the Application.27 The TCCS also classified costs as demand-related, usage-related, or customer-related, based on zero intercept and minimum system approaches to determine the principal drivers of costs within each function. The TCCS results were summarized in Tables 4.2.1 and 4.2.228 of the Application and are reproduced below: Table 4.2.1 Function Bulk System Local System POD Total Note: Functionalized and Classified Transmission Wires Costs, $ 000 000 Classification Total Demand Usage Customer $144.6 $117.9 $ 26.7 $ 60.2 49.7 10.5 147.8 63.7 1.0 83.1 $352.6 $231.2 $ 38.3 $ 83.1 Totals may not add due to rounding For rate design purposes, the functionalized and classified wires costs are generally converted to percentages of total costs, as provided in Table 4.2.2. 27 28 Appendix B, pages 13-32 of the Wires Cost of Service Study or TCCS Section 4, P. 5 of the Application EUB Decision 2005-096 (August 28, 2005) • 17 2005/2006 General Tariff Application Table 4.2.2 Function Bulk System Local System POD Total Note: Alberta Electric System Operator Functionalized and Classified Transmission Wires Costs (“Pure”), % of Total Classification Total Demand Usage Customer 41.0% 33.4% 7.6% 17.1% 14.1% 3.0% 41.9% 18.1% 0.3% 23.6% 100.0% 65.6% 10.9% 23.6% Totals may not add due to rounding For comparison, the AESO noted the current AESO DTS rate was based on transmission wires costs classified 60% as demand-related, 40% as usage-related, and 0% as customer-related. Dr. Rosenberg, in evidence filed on behalf of the ADC, was generally supportive of the TCCS but expressed reservations regarding the minimum system analysis that PSTI used to support its recommended classification of transmission wires costs into demand and energy components. Specifically, Dr. Rosenberg stated the minimum system approach led to an overstatement of the energy portion of the wires costs. Apart from this concern, Dr. Rosenberg indicated that other aspects of the PSTI study reasonably adhered to the tenets of cost causation. Therefore, while not endorsing the minimum system component of PSTI’s analysis, Dr. Rosenberg considered it was reasonable to accept the results of the study for the purpose of designing DTS rates in this case. IPCAA submitted evidence prepared by Drazen Consulting. IPCAA noted that the TCCS had not attempted to allocate the costs among various classes of service and stated that the purpose of defining rate classes was to recognize differences in costs that should be appropriately recognized between groups of customers. Absent this consideration, IPCAA considered the usefulness of the TCCS to be limited. IPCAA suggested some insight into differences in behaviour that give rise to cost incurrence may have been useful to examine the possible need to distinguish cost responsibility among sub-groups of AESO customers. IPCAA also noted that the study claimed that maximum stress upon the system did not coincide with system peak. IPCAA disagreed with this finding on the basis that this claim was based upon an examination of very few of the bulk lines in the Province. Both IPCAA and EnCana claimed that POD costs may have been overstated in the functionalization step due to the use of Net Book Value (NBV) in the analysis. They maintained that, as POD costs were of a more recent vintage and as no major new bulk lines had been constructed for several years, the use of NBV would tend to distort the results of the study, causing POD costs to be more heavily weighted. FIRM concurred with this latter claim and suggested that replacement costs new (RCN) be used rather than NBV. EnCana also claimed that functionalization of wires costs on the basis of voltage was flawed as it was inconsistent with the AESO’s approach to planning and that some of the lower voltage lines still in use may have originally been built to serve the bulk function. EnCana suggested the findings of the study should be rejected and that the Board should instead rely on the functionalization proposed by the AESO in the Application. In addition to its comments respecting the use of RCN, FIRM also suggested that high side switches and bus work be functionalized as local costs rather than POD related costs, noting the 18 • EUB Decision 2005-096 (August 28, 2005) 2005/2006 General Tariff Application Alberta Electric System Operator testimony of Mr. Reimer to that effect.29 The Board notes, however, Mr. Reimer stated that the cost information received from the utilities did not contain sufficient detail to allow for the detailed breakdown suggested by FIRM. TCE expressed concern over the amount AESO proposed to use as the Regulated Generation Unit Connection Costs (RGUCC). The Board acknowledges the above suggestions and concerns of the parties and will address them in more detail below. The Board notes, however, that the TCCS was the only cost of service study filed in this process. Furthermore, the Board notes that no party, with the exception of EnCana, has questioned that the study is directionally incorrect or suggested that it be ignored by the Board. Indeed, both IPCAA and ADC have used the study as evidence to bolster their arguments for a higher demand related component in the final rate design. The Board considers the TCCS to be an excellent first step and commends the AESO and Mr. Reimer for their initiative and effort in this regard. The Board will rely upon the results of the study in the development of its approved rate design. 5.3.1 Functionalization of Costs As noted above, the study assessed, or “sub-functionalized”, transmission wires costs to bulk system, local system, and POD (including radial lines exclusively used by a single POD) functions based on three approaches: voltage level, economics, and volume-distance. The study’s final recommendation was functionalization based on the average of the three methods. The parties raised some concerns with the functionalization of costs but, in the Board’s view, appeared to accept the study as reasonable. In the evidence of Dr. Rosenberg,30 the ADC stated the following: PSTI considered three different approaches to determine the transmission wires functional categories: 1) voltage level, 2) economics and 3) MW-km. The three methods provide results that are somewhat similar, particularly for the voltage level and MW-km approaches. The POD function is the same in all three approaches. The variation occurs between bulk and local system. According to PSTI, all three methods have strengths and weakness. Since this type of study is relatively new, PSTI recommended that functionalization be based on the average results of the three methods. The resulting functionalization is 45.7% bulk system, 15.7% local system and 38.6% point of delivery. I support the proposed functionalization of the transmission system as reasonable. IPCAA noted that the TCCS used depreciated historical book costs and stated the relative weighting of the cost of various functions will differ whether they are based on current costs or depreciated original cost. IPCAA stated that no major transmission has been built in Alberta in many years. This, combined with the addition of PODs as load has continued to grow, means that POD costs were likely more heavily weighted in the present analysis than would be the case if all assets were of similar vintage. Both EnCana and FIRM supported IPCAA’s claim. In its reply, the AESO stated: 29 30 T241, L. 2 Rosenberg Evidence, page 21 EUB Decision 2005-096 (August 28, 2005) • 19 2005/2006 General Tariff Application Alberta Electric System Operator Examining the depreciation evidence filed in AltaLink’s 2004-2007 GTA as referenced by EnCana, one finds the following information for AltaLink’s two largest asset accounts: Substation Facilities: Transformers and Regulators Average Service Life (Survivor Curve) 38 years Composite Remaining Life 24.2 years Transmission Plant (Lines): Transmission Facilities Average Service Life (Survivor Curve) 42 years Composite Remaining Life 23.0 years The AESO submits that these two accounts demonstrate that both substation and line facilities have similar lives and are of comparable vintage, and any resulting variance of the approximately 50% of TFO costs represented by depreciation and operating and maintenance expense would not be substantive enough to lead to rejection of the Transmission Cost Causation Study as recommended by EnCana.31 The Board notes that, while the amount of dollars related to the bulk system may increase in the future, and therefore the percentage of costs allocated to bulk system costs will increase, this will not, however, decrease the absolute dollars allocated to POD costs. Moreover, it is NBV which drives the return, tax and depreciation calculations of the TFO revenue requirements. As these items comprise the bulk of the revenue requirement of the TFOs, the Board considers NBV to be an appropriate basis upon which to base the functionalization of costs. For all of the above reasons, the Board does not share the concern of IPCAA and EnCana. FIRM and EnCana submitted that the use of voltage level to differentiate between bulk and local wires may not be accurate since older, low voltage lines may have originally been constructed to serve as bulk lines but would now be classified as local lines. This, they argued, could distort the amounts allocated to each function, lowering bulk costs and raising local related wires costs. EnCana stated that this approach was not consistent with the AESO’s planning, noting that 138kv and 240kv lines were often substitute technical options for the same transmission need. The Board notes that three different approaches were used to functionalize costs and Mr. Reimer described the three approaches in detail at pages 20 to 33 of the TCCS. In the Board’s view, Mr. Reimer was very direct and candid in describing the strengths and weaknesses of the approaches. In particular, Mr. Reimer stated the following: The three options provide different views of how transmission property can be functionalized in an objective way. Subjective functionalization was rejected because the results were not repeatable, and there was no assurance that a reasonable group of experts could come to an agreement with respect to functionalization of transmission property. The three methods provide results that are somewhat similar. The POD definition does not change and the functionalization of POD property remains stable. The variation occurs as to the distinction between Bulk System and Local System. All three methods have strengths and weaknesses. We consider that the MW-kM method is the strongest because it most closely aligns the purpose of transmission facilities to 31 AESO Reply Argument page 12. 20 • EUB Decision 2005-096 (August 28, 2005) 2005/2006 General Tariff Application Alberta Electric System Operator their functional category. Since this type of study is relatively new, we recommend that the functionalization be based on the average results of the three methods.32 The Board considers that the averaging of the three different approaches provides sufficient balance to the findings of the TCCS. Finally, the Board notes that TCE expressed concern with the amount the AESO proposed to allocate to RGUCC claiming it was too high and was just a placeholder as per Decision U97065. In reply, the AESO acknowledged that although the RGUCC costs were established as a placeholder in Decision U97065, additional evidence was submitted during EAL’s (ESBI Alberta Ltd.)1999-2000 GTA proceeding, resulting in the following conclusion in Decision 2000-1 (p. 119): Although Mr. Crowe noted the shortcomings and possible inaccuracies of his study, the Board accepts his results as confirming the reasonableness of the $43.9 million deemed by the Board to be generation connection costs for existing generators. The AESO submitted that the EUB’s acceptance removed the “placeholder” nature of the RGUCC and provided a basis for continuing it as determined in Decision 2000-1. The Board agrees. The Board, having addressed the concerns of the parties with respect to the functionalization proposed in the TCCS, accepts the findings of the TCCS as reasonable and will rely upon them in its final approved rate design. 5.3.2 Classification of Costs The TCCS used a minimum system approach to classify bulk and local wires costs and a zero intercept approach to classify POD related costs. The TCCS also noted that a complicating factor in classifying the costs of the bulk system was the fact that the time of maximum stress on the bulk system did not coincide with peak load conditions. The TCCS proposal for the classification of costs is detailed at pages 34-45 of the TCCS. ADC was critical of the use of the minimum system approach for bulk and local wires costs. ADC claimed that such an approach was unorthodox and was generally used to classify distribution costs between demand and customer-related components. ADC noted that system investment was lumpy and the lead time for transmission projects was frequently much longer than for generation projects. ADC maintained that the fact that the transmission grid may be configured to exceed the system’s minimum requirements does not imply that the excess transmission investment was constructed to minimize energy costs. IPCAA was also critical of the TCCS use of a minimum system analysis. IPCAA claimed that there was no evidence that past practice was to increase conductor size to reduce line losses, that conductor optimization or size could not be generalized and that it was difficult to generalize about loss savings given that losses varied with the load on a line. 32 TCCS, page 33 EUB Decision 2005-096 (August 28, 2005) • 21 2005/2006 General Tariff Application Alberta Electric System Operator IPCAA was also critical of the TCCS for attempting to define demand in terms of coincident load at maximum system stress (CLMS), noting that the TCCS only reviewed two bulk lines and that CLMS included significant opportunity transactions.33 IPCAA noted that Mr. Reimer himself stated: A. MR. REIMER: No. I think generally I would expect peak stress on the Bulk System to be more coincident to the system peak load than what was found, in this case, on the north-south corridor:34 IPCAA appeared to agree with the TCCS that a portion of POD costs could be classified as customer-related and in their rate design proposal have advocated the implementation of a customer charge. EnCana supported IPCAA’s criticism of the TCCS, stating that there was no evidence that the minimum system approach had been used in any other jurisdiction. Specifically EnCana submitted that PSTI's use of the minimum system approach was inappropriate because it did not attempt to identify the causes behind transmission expansion. Instead, it only reflected the capacity-optimization decisions once a primary ‘need’ exists. In EnCana’s view, the driver of the primary ‘need’ is the central question that must be addressed in any sound cost causation study. The Board agrees that the use of a minimum system analysis may be somewhat unorthodox, as described by ADC. However, the Board notes the following passages from the TCCS:35 The nature of cost causation for transmission service is an evolving science. The cost of transmission service within the context of the vertically integrated structure was small in comparison to total cost and therefore transmission costs were not normally the focus of attention. … Performing a Cost of Service Study on transmission alone is not a common practice and therefore, there is no one common or standardized method for conducting such a study. The Board notes that the contentious point of the minimum system analysis is that it maintains embedded costs are incurred to optimize losses. In its reply argument the AESO stated the following:36 ADC stated (ADC Argument, p. 19) that “the only contentious part of the study was the use of the minimum size method to determine that 11 percent of the costs were energy related.” IPCAA argued (IPCAA Argument, p. 8-9) that the Transmission Cost Causation Study did not provide any evidence that embedded costs were incurred to optimize losses. In fact, the Study contained the following information: Since electric transmission system costs are capital intensive, decisions made at the planning stage drive costs over the life of the transmission facilities. Therefore, understanding the transmission planning process is crucial to understanding cost causation for a transmission system. (p. 8) 33 34 35 36 IPCAA argument, page 13 Transcript Volume 1, page 223 lines 10 to 14. TCCS. page 3 AESO reply, page 15 22 • EUB Decision 2005-096 (August 28, 2005) 2005/2006 General Tariff Application Alberta Electric System Operator The nature of a transmission facility is such that the facility is sized to meet the forecast demand, and a conductor optimization study is typically performed to determine the optimum conductor size to optimize losses. (p. 36) The cost of a substation was assessed with a normal efficiency transformer, and a high efficiency transformer that may be suitable for a high load factor customer. (p. 43) These excerpts indicate that planners do study the efficient expansion of the transmission system, and that there are capital costs associated with energy efficiency in both conductors and transformers. However, Mr. Reimer described (T0834) the difficulty in recreating history to determine precisely what embedded costs would have been associated with energy efficiency. Given these challenges, a simplified approach was taken in the Transmission Cost Causation Study to assess costs associated with energy efficiency. The AESO submits that costs are incurred to optimize losses on the transmission system… Parties also questioned the use of CLMS to moderate the demand charge otherwise called for. With respect to this matter, the Board notes that the TCCS appears to have studied only two of many bulk lines in its analysis. IPCAA has argued that one of the two lines studied, the Edmonton-Calgary line, had significant loading caused by opportunity service at the time of CLMS. Indeed, the Board observes that Mr. Reimer, as referenced above, has acknowledged that CLMS may be expected to be more coincident with system peak. As such, the discount that Mr. Reimer proposes in demand related charges may not be fully justified. The Board expects that, in future studies, the AESO will conduct a more thorough review of all those lines comprising the bulk system. This should give a more accurate indication as to the exact portion of costs that are energy related. However, the Board also considers that a reasonable portion of TFO costs are related to O&M and that a material percentage of these may be energy related. Unfortunately, the impact of this factor does not appear to have been researched in this current study and therefore the Board cannot draw a firm conclusion respecting its impacts on the demand charge. Nonetheless, based upon the percentage that O&M expenses comprise of a TFO’s revenue requirement,37 the Board considers that such an analysis would support a reasonable classification of costs as energy related. The Board expects the AESO to address these issues in future cost of service studies. The Board also notes the following from the TCCS:38 While transmission planning models consider one point in time, transmission planning criteria are based on experience and judgment to ensure reliable operations year round, and planners will optimize conductor size in order to minimize the total cost of wires and losses. The transmission planning process is often used as justification for classification of all wires costs by demand, because transmission planners consider demand under various scenarios. In the event that transmission planning criteria are violated, the transmission system is upgraded to accommodate the forecast demand. However, transmission planning criteria are based on experience and judgment, and therefore, it is too simplistic to classify transmission costs as completely demand related. 37 38 AltaLink 2004-2007 GTA Application TCCS, page 34 EUB Decision 2005-096 (August 28, 2005) • 23 2005/2006 General Tariff Application Alberta Electric System Operator Given the above, the Board is prepared to accept that some portion of embedded wires costs are energy related. The Board also notes that preparing a cost of service study for transmission on a stand alone basis is a relatively new and unique process. The Board acknowledges the difficulties faced by Mr. Reimer in preparing his analysis and in the circumstances the Board considers the TCCS to be a good first step and is willing to accept its recommendations in the Board’s approved rate design. 5.4 Ancillary Services Cost of Service Study In response to Directions 10 and 11 of Decision 2001-32, the AESO filed an Ancillary Services Cost of Service Study. The study was prepared by Mr. Randy Stubbings of Envision Consulting and was summarized at pages 11-15, Section 4 of the Application. The AESO’s proposed classification was summarized in Table 4.3.1 of the Application and is reproduced below. The AESO explained the results of the study and their proposal as follows:39 Ancillary services costs to the AESO can also be viewed as a function of payments to ancillary service providers, and can be classified for rate design purposes as demandrelated or usage-related. The costs could then be recovered through tariffs as fixed or variable charges, in accordance with the classification of the ancillary service payments. Basing rate design for ancillary services solely on alignment with payments to ancillary services providers may not always accord with the cost classification set out in the AS Cost Study, as cost causation is only one of several rate design criteria. In particular, the AESO is proposing ancillary services rates that also consider rate stability, simplicity of understanding, and economy of billing. In Decision 2001-32, the EUB also noted “that the first step to self-provision [of ancillary services] is to unbundle the various system support services in the TA’s tariff” (p. 41) and provided Direction 11 to “include rate proposals for unbundling SSS and proposals for customer self-supply of SSS” (p. 59). Based on the AS Cost Study and rate design considerations, the AESO proposes to unbundle certain ancillary services. The AESO recognizes that each of the many individual ancillary services (as detailed in the AS Cost Study) could be identified separately in the rate schedule, but considers such detailed unbundling would be premature and would unnecessarily complicate billing during the time that the market for such services is developing. For example, the AS Cost Study concludes that the cost of regulating reserves should be classified in accordance with customers’ ranges of demand over a given period. Rates designed on this basis would degrade rate stability on an individual customer basis, and would also increase billing costs as extensive information system changes to the billing and metering systems would be required to support the resulting tariffs. Accordingly, the AESO has unbundled ancillary services into three separate and distinct tariff charges categorized by separate cost recovery approaches: a) operating reserves charge, structured as a usage charge which varies as a percentage of pool price, averaged over all hours; b) voltage control charge, structured as a flat (non-varying) usage charge; and c) other system support services charge, structured as a demand charge. 39 Application, Section 4, pages 11-12 24 • EUB Decision 2005-096 (August 28, 2005) 2005/2006 General Tariff Application Alberta Electric System Operator Table 4.3.1 Proposed Ancillary Services Charges and Classification Ancillary Service Current Classification Proposed Classification Component MW MWh % of PP MW MWh % of PP Operating Reserves Charge Operating Reserves Generator RAS Black Start - - 100% 100% 100% - - 100% 100% 100% Voltage Control Charge Transmission Must Run - - 100% - 100% - 40% 100% - 53.4% - Other System Support Services Charge Under Frequency Mitigation Poplar Hill 100% ILRAS (see note) 60% Notes: 5.4.1 100% 100% 46.6% MW indicates classification as demand MWh indicates classification as flat (non-varying) usage % of PP indicates classification as usage varying as percentage of pool price Changes in classification are indicated in bold in the table Classification of ILRAS changes to reflect the change in classification of wires costs The MWh component of ILRAS is recovered in the DTS rate schedule as part of the DTS Interconnection Charge, to avoid a small $/MWh component in the OSS Services Charge ILRAS Interruptible Load Remedial Action Scheme Classification of Ancillary Services The only party to submit any comments with respect to the AESO’s proposal was FIRM. FIRM maintained that TMR costs should be allocated on a basis more reflective of cost causation and recommended that the AESO rate design for the TMR component of voltage control reflect the 1:2 ratio of TMR costs for DTS-MWH on-peak and off-peak charges. FIRM acknowledged such a muted price signal would not significantly affect customer consumption behavior but claimed it would better reflect cost causation. In reply the AESO submitted that if a price signal is so muted that it will not affect customer behaviour, then there is little point in providing such a signal. If such a unique bill charge will vary by so little compared to an all-hours average charge and will seem illogical to many customers (as explained by Mr. Martin at T0657-58), then the AESO submitted there was no justification to warrant its implementation. The Board agrees with the AESO and approves the recovery of TMR costs on a flat usage basis. Consistent with the Board’s determinations with respect to classification of wires costs, the costs for ILRAS should be classified as 80% demand and 20% energy. The demand portion should be allocated on the same basis as the bulk wires. 5.5 Demand Transmission Service Rate Design 5.5.1 Unbundling The AESO has stated that it considers the level of unbundling proposed in the Application to be adequate and any further steps in this regard should be deferred until the 2007 tariff. The AESO stated that it did not consider a bill containing seven to nine distinct charges to be simple. EUB Decision 2005-096 (August 28, 2005) • 25 2005/2006 General Tariff Application Alberta Electric System Operator Both IPCAA and ADC supported unbundling. IPCAA maintained that unbundling would result in a tariff where charges are better aligned with the various cost components and cost drivers. Both IPCAA and ADC pointed out that unbundling would allow for different billing determinants. The Board does not agree with the AESO. The Board considers that unbundling, as recommended in the TCCS report, would allow for rates that are more reflective of cost causation, more visible and capable of sending more appropriate price signals to customers. With respect to the concern raised by the AESO that such a bill would be too complex for its customers, the Board considers the customers of the AESO to be few in number, sophisticated in nature, and well able to understand and respond to such a bill. The Board therefore directs the AESO, in its refiling, to unbundle the wires portion of the DTS rate into bulk, local and POD segments. The Board notes this is necessary to facilitate the cost allocation decided upon below. 5.5.2 Classification of Costs The AESO’s proposal for classification of wires costs was originally presented in the Application.40 The AESO submission proposed three adjustments to the cost results of the TCCS. First, the AESO reduced the demand weighting to reflect billing demand non-coincidence with the point of system maximum stress. Second, the AESO eliminated the customer charge amount and added it back to demand. Third, and most significantly, the AESO deducted the current STS wires revenue from demand and re-classified it as energy related. The AESO acknowledged that its proposal did not meet the goal of cost causation but stated that it planned further consultation in 2007 and other rate design considerations may affect the rate design ultimately developed in 2007.41 The AESO also maintained that phasing in the STS wires revenues into the DTS rate on an energy basis would maintain customer neutrality and would avoid undue rate shock to low load, low load factor customers. The AESO was largely supported in its proposed rate design by FIRM and EnCana. EnCana supported the unbundling proposed in the TCCS but also supported the classification of the STS wires costs as energy related. The resultant demand/energy split is approximately the same. Proponents of the AESO proposal appear to support it for three main reasons: 1. Gradualism or rate shock – The parties state that low load, low load factor customers will see huge rate increases and maintain that these should be tempered. All agree this can be accomplished by classifying the STS wires amount as energy related. This would also achieve customer neutrality to the phase out of the STS charge. 2. Transmission Regulation – Parties assert that the regulation requires classification of STS charges as energy related, as a means to ensure revenue neutrality. 3. Decision 2000-1 – Parties submit that the Board’s determination in Decision 2000-1 to classify all STS wires charges as energy was based upon cost causation. 40 41 Application, Section 4, pages 7-9 Application, Section 4, page 9 26 • EUB Decision 2005-096 (August 28, 2005) 2005/2006 General Tariff Application Alberta Electric System Operator The Board has noted in the previous section on rate design principles that it considers cost causation to be the most important principle and the Board is in agreement with ADC and IPCAA that rates should reflect this principle to the greatest extent possible. With respect to gradualism or rate shock concerns, the Board notes that the AESO has stated that DTS rates will rise by 66% in total, largely due to the legislative requirement that load pay for all wires costs. Regardless of the rate design chosen, DTS customers will see significant increases in their AESO billings. The Board points out, however, that this relates to AESO billings only. In the past when the Board has considered rate shock, the Board has considered the effect an increase will have on a customer’s total bill. The Board continues to believe that this is the most appropriate manner in which to assess rate design proposals. Only this approach allows the Board to keep bill impact in true perspective. The Board notes that, in information response ADC-AESO-012(c), the AESO provided the impact upon a customer’s total bill as a result of their proposed rate design. In response to an undertaking requested by the Board42, the AESO provided the effect upon a customer’s bill when demand factors of 60, 70 and 80% were used. Exhibit 030-126 revealed that a demand factor of 80% resulted in an 8% increase in costs, when commodity charges were included. The Board does not consider this to be unreasonable. The Board did not request the AESO to factor in the effect of allocating some of the demand charge to a customer charge. The Board has prepared such a spreadsheet and it is attached as Appendix A.43 As can be seen in Appendix A, when considering the effect upon a low load factor customer of the increase in DTS rates only, the addition of a customer charge, including commodity charges, results in an increase of approximately 47%. This could be considered significant. As noted above, the Board considers that it must evaluate the effect that a change in rate design will have upon a customer’s total bill. The Board notes that, in response to an undertaking requested by the Cities, Exhibit 030-022, the AESO acknowledged that all 17 of the low load factor customers identified in response to IR IPCAA-AESO-23(a) are generators. The Board considers it appropriate to account for the drop in the STS portion of their AESO billings that these customers will receive as a result of the shift in costs to load. The Board has prepared such an analysis and it is also attached as part of Appendix A.44 The result clearly indicates that, when the drop in STS billings is factored in, these low load factor customers actually experience a decrease in total billings. In the end, therefore, when considering the total effect upon low load factor customers of an increase in DTS rates and decreases in STS rates, it is clear to the Board from the evidence that the rate shock referenced is simply not significant. It does not justify a failure to move to more cost based rates. Indeed, when the reduction of STS charges is considered, customers may actually see decreases in their total AESO billings. With respect to the requirements of the Transmission Regulation, the Board has examined Section 30 of the regulation and concludes that there is no requirement for the Board to pass through STS costs on an energy basis. Section 30 simply requires that costs be just and reasonable. Associated with this issue is the notion of revenue neutrality. The Board notes the 42 43 44 Exhibit 030-126 Appendix A, sheet titled “DTS only increase” Appendix A, sheets titled “Rate Shock Analysis” and “Rate Shock no STS losses” EUB Decision 2005-096 (August 28, 2005) • 27 2005/2006 General Tariff Application Alberta Electric System Operator evidence Mr. Sullivan presented on behalf of the ADC. This evidence clearly indicates that the energy market may not be as efficient as postulated by the AESO. In the Board’s view there is no evidence to conclude that STS charges in total will be recouped by load, let alone that they can be recouped evenly across all hours. Finally, the Board will address the suggestion that Decision 2000-1 classified STS charges as energy related because it believed that this was in accordance with cost causation. The evidence in that proceeding indicated that EAL (ESBI Alberta Ltd.) originally proposed to recover a significant portion of the STS wires costs on a demand basis. The evidence of the Coalition in that proceeding was that the imposition of a demand charge on generators could lead to an inefficient energy market and have a detrimental effect upon the PPA (Power Purchase Arrangements) auction, which was imminent at that time. Based upon the evidence before it in that proceeding, the Board classified the STS portion of wires costs as energy. This determination was not made on the basis of cost causation but rather as an exception to the principle45. Reallocating all wires costs to load now allows the Board the opportunity to classify such costs in a manner more in keeping with cost causation. The Board concurs with ADC and IPCAA that rates should be more in keeping with cost causation. The Board above has dismissed the parties’ concerns about rate shock or gradualism and the potential complexity resulting from unbundling. The Board in the prior section on rate design principles has determined that most other rate design principles are complimentary to cost causation. The Board considers that wires costs should be classified as 20% energy to be collected evenly over all hours. There should be a full POD customer charge as determined in the TCCS. This should amount to approximately 24% of total costs as per table 24 at page 47 of the TCCS. The balance of wires costs should be collected through two demand charges – one related to the bulk system and the second relating to local system and POD related costs. The Board, as stated above, agrees with the AESO’s proposal and Mr. Reimer’s suggestion that a reduction be made to the demand related portion of the bulk wires to account for the lack of coincidence of system peak with point of maximum stress. The demand charge for local and POD costs should be collected on the basis of non-coincident peak (NCP), including the use of a ratchet, as proposed by the AESO. With respect to the demand charge for bulk wires, the Board notes that ADC and IPCAA have both proposed different alternatives. Both, however, would use some form of coincident peak to allocate this demand charge. The parties advocate this approach on the basis that the bulk system is largely constructed and sized, and costs incurred, to meet the peak load of the system. The Board agrees. ADC has proposed a 12 CP approach that would use a 12 month average of the system peaks and base a customer’s individual charge on their monthly coincidence with the 12 month average.46 IPCAA proposes to use an average of several peak hours to allocate the demand charge.47 While the Board sees a certain degree of academic merit to the IPCAA approach it considers that it may be more complex to administer. The Board considers that both approaches would provide an appropriate price signal to customers. 45 46 47 Decision 2000-1, pages 121-123 Rosenberg Evidence, page 31 IPCAA Argument, page 20 28 • EUB Decision 2005-096 (August 28, 2005) 2005/2006 General Tariff Application Alberta Electric System Operator Therefore, the Board directs the AESO to use the 12 CP approach proposed by Dr. Rosenberg. The average of 12 CP should address the seasonality concerns of IPCAA. As noted by IPCAA, however, a reasonable degree of diversity exists on the bulk system and for this reason no ratchet will apply to this demand charge. As a summary of the above findings the AESO, in its refiling, is directed to amend its DTS rate design as follows: 5.5.3 20% of all wires costs will be collected on an all hours energy basis Levy a customer-related POD charge, as suggested in the TCCS Levy a demand charge on bulk wires utilizing a 12 CP allocator Levy a demand charge on local and POD related costs utilizing an NCP allocator. Ratchet The AESO introduced its proposal for a revised ratchet in the Application.48 The AESO proposed to reduce the current 5 year declining ratchet to a 2 year, 90% ratchet. The AESO stated that it was proposing the change in response to concerns expressed by customers. The AESO explained that its proposal for a 90% ratchet could be achieved with only a 1% drop in interconnection revenue and would therefore preserve revenue stability. The AESO maintained that, in the absence of contract-based billing, ratchets are appropriate to recover revenue from customers who may be leaving the system. The revenue is required to balance the financial impacts for the remaining customers who would otherwise bear the full cost of facilities which become under-utilized due to other customer’s actions. The ratchet provided a balance between flexibility for customers and the need to recover any stranded system costs from remaining customers. Interveners made a number of comments with respect to the AESO proposal. TCE argued the ratchet level should be reduced to 66% from the proposed 90% as this would be more in line with Disco levels and it would be fairer. EnCana argued that the 5 year notice period for reduction in service should be reduced to 2 years as well, to be consistent and fair. FIRM argued the opposite view, maintaining that the ratchet should be maintained at the current 5 year level, to be consistent with the 5 year notice period and protect customers from stranded costs. In response to intervener comments, the AESO noted that TCE’s proposed ratchet level of 66% would entail a 10% drop in interconnection revenue. In response to EnCana and FIRM, the AESO noted EnCana stated that with respect to the ratchet provisions in Article 14.2 of the proposed terms and conditions of service “…that two Customers who are similar in all respects will be assessed different penalties based on whether or not notice of termination or reduction has been provided.” The AESO explained if one customer has provided a notice of termination while the other has not, those customers were not “similar in all respects.” As explained at T0161-62, the specific provisions in Article 14.2 were designed to ensure the AESO gets as clear an indication as possible of the customer’s intention with respect to demand on the transmission system. The AESO submitted the ratchet provisions in Article 14.2 should be approved as filed. 48 Application, Section 4, pages 16-18 EUB Decision 2005-096 (August 28, 2005) • 29