24-Month Reliability Outlook 2011-2013 Stakeholder Information Session Monday, March 5, 2012
by user
Comments
Transcript
24-Month Reliability Outlook 2011-2013 Stakeholder Information Session Monday, March 5, 2012
24-Month Reliability Outlook 2011-2013 Stakeholder Information Session Monday, March 5, 2012 John Kehler, Steve Heidt and Sami Abdulsalam Agenda • Introductions • Reliability • System Performance • Criteria and Coordination Plan • Regional Update • Summary • Q&A 2 Role of Alberta Electric System Operator (AESO) • System Operations – Direct the reliable operation of Alberta’s power grid • Markets – Develop and operate Alberta’s real-time wholesale energy market to facilitate fair, efficient and open competition • Transmission System Development – Plan and develop Alberta’s transmission system to ensure continued reliability and facilitate the competitive market and investment in new supply • Transmission System Access – Provide system access for both generation and load customers 3 The Alberta Grid • 22,322 km transmission • Single balancing area of 660,000 km² • B.C. & Sask. Connections • over 167 generating units • 10,609 MW system peak • 164 market participants • 13,888 MW internal capacity net to grid 4 Reliability • “The System” – is controlled to stay within acceptable limits during normal conditions – performs acceptably after credible contingencies – limits the impact and scope of instability and cascading outages when they occur – facilities are protected from unacceptable damage by operating them within facility ratings – integrity can be restored promptly if it is lost, and – has the ability to supply the aggregate electric power and energy requirements of the electricity consumers at all times, taking into account scheduled and reasonably expected unscheduled outages of system components” 5 System Performance John Kehler Transmission System Performance • Transmission Lines – Reliability, Operational Efficiency and Market Efficiency Through Availability of the Transmission System – Transmission line outages (planned or unplanned) can lead to constraints and curtailment – Performance can be assessed by statistics and benchmarking • System Events – The analysis and investigations of events often leads to lessons learned and recommendations to improve the performance of the power system 7 Key System Performance Metrics Transmission system frequency and duration of unplanned outages Frequency and Duration to Generation Customers (Curtailed Generation) Frequency, Duration and Restoration to Load Customers (SAIFI and SAIDI) 8 Terminology Used in this Presentation • Outage - This is when a transmission line is forced out of service • Interruption - This is when an Outage effects a point of delivery or load customer • Event – This is when a transmission constraint caused by either; transmission outages or normal conditions where transmission overloads have occurred due to generation and load conditions • Delivery Point - This is the Point of Delivery from the transmission system to a DTS customer of the AESO • Frequency Per 100 km is the [number of outages] divided by the [kilometer years which in turn are divided by 100] • SARI System Average Restoration Index - A measure of the average duration of a Delivery Point interruption. It represents the average restoration time for each Delivery Point interruption • SAIFI System Average Interruption Frequency Index - A measure of the average number of momentary plus sustained interruptions that a Delivery Point experiences during a given year • SAIDI System Average Interruption Duration Index - A measure of the average total interruption that a Delivery Point experiences during a given year 9 Number (Frequency) of Unplanned Outages 12 Alberta Alberta CEA CEA 6 138/144 kV Alberta and CEA Frequency Per 100 km Frequency / Year Frequency /Year 69/72 kV Alberta and CEA Frequency Per 100 km 0 12 6 Alberta Alberta CEA 0 2005-2009 2006-2010 2005-2009 5 Year Rolling Window 6 Alberta CEA CEA Alberta 0 500 kV Alberta and CEA Frequency Per 100 km Frequency / Year 12 2006-2010 5 Year Rolling Window 240 kV Alberta and CEA Frequency Per 100 km Frequency / Year CEA 12 Alberta Alberta 6 CEA CEA 0 2005-2009 2006-2010 5 Year Rolling Window 2005-2009 2006-2010 5 Year Rolling Window 10 Average Outage Duration 138/144 kV Alberta and CEA Average Outage Duration 69/72 kV Alberta and CEA Average Outage Duration 80 80 CEA 40 Alberta CEA Hours Hours CEA Alberta 40 Alberta CEA Alberta 0 0 2005-2009 2005-2009 2006-2010 5 Year Rolling Window 5 Year Rolling Window 240 kV Alberta and CEA Average Outage Duration 500 kV Alberta and CEA Average Outage Duration 80 CEA 40 Alberta CEA Alberta Hours 80 Hours 2006-2010 40 Alberta CEA Alberta CEA 0 0 2005-2009 2006-2010 5 Year Rolling Window 2005-2009 2006-2010 5 Year Rolling Window 11 Impact to Delivery Points and Load for Unplanned Outages 69, 72, 138, 144, 240 and 500 kV Systems 5.0 2.5 CEA Alberta CEA Alberta Duration (Hours) Frequency 5.0 2.5 Alberta CEA Alberta CEA 0.0 0.0 2005-2009 2006-2010 5 Year Rolling Window 2005-2009 2006-2010 5 Year Rolling Window Alberta Delivery Point SARI Restoration Time (Hours) Alberta Delivery Point SAIDI Alberta SAIFI 5.0 Alberta Alberta 2.5 CEA CEA 0.0 2005-2009 2006-2010 5 Year Rolling Window 12 Grid and Market Operation Performance with Transmission System Planned and Unplanned Outages Annual Generation Curtailment (GWh) Due to Transmission Constraints Number of Transmission Constraint Events (Planned and Unplanned) Per Year 1000 100 8000 # of Hours GWhs 200 # of Events Annual Duration (Hours) 500 0 0 0 2008 2009 2010 2011 4000 2008 2009 2010 2011 2008 2009 2010 2011 • The numbers of transmission constraint events is down from 2011, hours where generation curtailment occurred are down and curtailed generation volumes (GWhs) are down • 2010 had major transmission lines out of service due to damage caused by storms 13 System Performance Constraint History- Fort McMurray Cutplane Fort McMurray Congestion Metrics Hrs Per Year / Events Per Year 1500 990 1000 500 769 438 3 670 438 2 8 41 7 0 2007 2008 2009 2010 2011 Area Limited due to Planned or Forced Outages Events where Facilities Constrained 14 System Performance Constraint History - KEG Area KEG Congestion Metrics Hrs Per Year / Events Per Year 1500 1121 1000 461 500 0 1 0 1 2007 2008 180 2 18 2 0 2009 2010 2011 Area Limited due to Planned or Forced Outages Events where Facilities Constrained 15 System Performance Constraint History – South of KEG (SOK) Hrs Per Year / Events Per Year SOK Congestion Metrics 6000 4871 4000 2000 1410 526 613 591 3 1 1 8 0 2007 2008 2009 2010 2011 0 Area Limited due to Planned or Forced Outages Events where Facilities Constrained 4871 hours of congestion primarily due to 928L outage 16 System Performance Constraint History - Southwest Area Hrs Per Year / Events Per Year Southwest Congestion Metrics 1487 1500 1223 968 1000 800 500 100 24 89 92 105 72 0 2007 2008 2009 2010 2011 Area Limited due to Planned or Forced Outages Events where Facilities Constrained 17 System Performance Constraint History - South East Area South East Congestion Metrics Hrs Per Year / Events Per Year 1500 1096 1000 500 0 0 0 0 0 0 1 58 6 2007 2008 2009 2010 2011 0 Area Limited due to Planned or Forced Outages Events where Facilities Constrained 18 Transmission-must-run Northwest Rainbow Lake Area TMR expected to reduce with completion of Northwest transmission upgrades in 2013 Northwest Grande Prairie Area Operating as a cutplane under new Rule 302.4 with associate ID # 2011-004(R) Calgary Area Minimum = 125 MW when SVC out of service or congestion on SOK path 19 TMR MWh Usage History for Different Areas of Alberta Rainbow Lake Area Calgary Area Grande Prairie Area NE Region 1000 GWhr 750 500 250 0 2006 2007 2008 2009 2010 2011 Year AESO 2011 Market Statistics 20 Performance During Major System Disturbances • No major disturbances for Alberta in 2011 • 2010 Major Disturbances – March 1 - Northwest Outage – June 1 – Under Frequency Event – June 30 – Loss of Load – April 8 – Snow storm – April 14 - Snow storm • Disturbance recommendations for the March 1 2010 AIES Disturbances are finalized in Alberta and are in the process of being closed off with WECC 21 Criteria and Coordination Plan Steve Heidt Preparing for Next Contingency Normal State (Prepared System) Contingency Meets Performance Criteria System in normal state must sustain next contingency and meet the performance criteria; not just operate within limits in normal state Prepare system for Next contingency System Ready for Next Contingency Contingency Meets Performance Criteria 23 Outage Coordination (within 7 days) • Objective is to maintain reliable operation • TFOs and GFOs are required to submit planned outages to the AESO which includes construction outages • AESO Approved transmission outages are published on our website • On a week ahead basis, AESO performs operational studies considering – Outage schedules for each day – Short term load forecast and known generation status • In consultation with TFOs, AESO develops procedures for the real time operators to manage constraints as required 24 Transmission Planning Regions Northeast Northwest 2011 Load 10% 2011 Capacity 7% 2011 Load 23% 2011 Capacity 22% Edmonton Central 2011 Load 15% 2011 Capacity 14% 2011 Load 20% 2011 Capacity 36% South 2011 Load 28% 2011 Capacity 22% Percentages of: 2011 year-to-date winter season peak – 10,609 MW Installed capacity as of end of 2011 – 13,659 MW 25 Regional Update South / Central Operations planning and Transmission Development Steve Heidt Interties Capacity • AB-BC PATH • AB-SASK PATH – One 500 kV and two 138 kV lines – Back to back AC/DC Converter – Transfer Capability – Intertie capability is restored to 150 MW in both directions – Export 800 MW – Import 780 MW • Implementation of Load Shed Service import (LSSi) program is in progress • MATL – 300 MW design capability – Total Transfer Capability (TTC) limits for various operating conditions are being studied 27 South Region • Thermal and voltage constraints in the west and east area • SATR and FATD will address most of the challenges • 786L overloads will be mitigated by the phase shift transformer Q1 2012 • NID for upgrading the North of Calgary system is in progress • Four 138 kV cables replaced to mitigate thermal constraint in the Calgary Downtown core • AESO is developing plans in the short and long term to address reliability concerns north and south Calgary and Airdrie areas 28 South Region - Southwest Area • Thermally limited area • Flow is out of the area; depends on wind generation • Russell phase shift transformer is being commissioned and will mitigate 786L overloads • Remaining constraints will be mitigated by SATR related developments as these come on line in stages • As expected, frequency and MWh of wind generation curtailment are down in 2011 compared to 2010 29 South Region - Southeast Area • The area is thermally, voltage limited, and angular stability limited • The two 240 kV three terminal lines were converted to 3-2 terminal lines with Milo Junction upgrade • Procedure in place to manage reliability of the south of Anderson (SOA) cutplane 30 South Region Calgary and Surrounding Areas • Calgary system is thermally constrained • Typically MW flow is into the area • Area operation managed through specific limits – Path 1 limits – SOK limits – Dynamic VAr requirements and monitoring • Under Voltage Load Shedding scheme • Four 138 kV cables replaced to mitigate thermal constraint in the Calgary Downtown core • AESO is developing plans in the short and long term to address area reliability concerns in south and north Calgary and Airdrie areas 31 Central Region • Voltage and thermal constraints in the central and east areas of the region • Yellowhead area NID competed that alleviated voltage and thermal constraints of the area • Central East upgrade NID approved in 2011 • Filed NID for the Red Deer area development plans July 2011 to address voltage and thermal constraints in the area 32 Central Region – Yellowhead Area • Thermal and voltage constraints • Commissioned 4 capacitor banks and 138 kV lines upgrades in 2011 to remove thermal and voltage constraints 33 Central Region Red Deer and Joffre Areas • Thermally limited for outflow and voltage for inflow • NID filed in July 2011 to mitigate thermal and voltage constraints 34 Central Region – Central East • Large geographic area that is has weak transmission support • Voltage and thermal limitations during single element outage • AUC Approved Central East NID in Q1 2011. Staged completion is expected from 2012 to 2017 • Includes new 240 kV connections to Hardisty area and south of Monitor in the Hanna area to provide area reinforcement • Cold Lake area reinforcements include new 240/144kV substation and 240kV lines connecting to Marguerite Lake and Bonnyville. Thermal protection RAS to be removed • Area operation is currently managed through the weekly coordination plans 35 Central Region - Hanna Area • Southeast system is constrained by voltage and dynamic stability • Hanna Region NID developments are expected to be complete by Q2 2013 that will remove most of the constraints and allow wind connections 36 Regional Update Northwest, Northeast and Edmonton Operations Planning and Transmission Development Sami Abdulsalam North Region • NW – Voltage stability, angular stability and thermally constrained area – Region is dependent on local generation (TMR) to supply load • NE – Ft Mac operates to a cutplane – Significant industrial load and base loaded co-generation – Expect over 500 MW growth in load over the two (2) years – 250-500MWs of Generation growth expected in the region by end of 2014 • Edmonton Area – Limits are based on thermal, angular and voltage stability – Bulk system is approaching capacity limit – Sundance 1 and 2 off-line since Jan 2011 38 Edmonton Region – Wabamun Area • Transmission system operating at its limit • Current limits are based on thermal, angular and voltage stability • One transmission facility outage requires significant generation curtailment • 4,035 MW of base loaded coal generation in KEG – Keephills Plant 1,230 MW (9.2%) – Genesee Plant 1,230 MW (9.2%) – Sundance plant 1,575 MW (11.7%) • Keephills 3 Energized 39 Edmonton Area Debottlenecking Project & KH3 Interconnection Update • Upgrades – Protection upgrades are complete – KH phase shifter energized – Livock PST to be energized in Dec-2012 – 500 kV and 240 kV upgrades and line configurations are in progress and will be complete in 2013 • Completion of the 240 kV line re-configurations and upgrades by 2012/2013 will result in – Mitigation of dynamic stability concerns in the area – Alleviation of congestion in the KEG loop and system between Sundance Plant and Edmonton area 40 North - South Bulk Transmission (Edmonton to Calgary) • Transfer limits (Operational Definition): – Summer = 2,050 MW – Winter = 2,150 MW – Limitation angular stability and thermal (138 kV overloads) • Maximum north to south flow range 1,601 to 2,202 MWs over the last three years 41 Northeast Region - Fort McMurray area • Constraints are a result of both generation and load • Current FMM cutplane limits are 575 MW out and 300 MW in • Transmission upgrades by 2012 – 260 MVAr capacitor banks • Will increase inflow and outflow limits • AESO studies will determine operating limits – 144kV System Reinforcement • ~ 630MWs out and ~ 440 MWs in after planned developments completion 42 Northeast Region - Cold Lake Area • Constraints are a result of both generation and load • Increase in the area generation and load relating to oil sands and pipeline facilities • Central East Transmission Development will help alleviate constraints in this area – New 240/144kV substation close to existing Mahihkan substation. – New 240kV lines (operated at 144kV) connecting the new 240kV sub to existing Marguerite Lake and Bonnyville Substations – Remove existing thermal RAS 43 Northeast Region - Fort Saskatchewan Area • Heartland Transmission Development – Support local demand – Accommodate growing demand in northeastern Alberta including Fort McMurray from oilsands development and pipelines – Support the backbone of the province’s transmission system – Facility application Approved by the commission 2011 44 Northwest Region Updates • Voltage stability, angular stability and thermally constrained area • Region is dependant on local generation (TMR) to supply load • NW Transmission Development project in progress – Completed developments in 2011-2012 • Three 144 kV lines in Rainbow Lake area • One SVC & one capacitor bank at a new substation – To be energized in 2013 • One synchronous condenser at Arcenciel • TMR Reduction in the Rainbow lake area in 2012 which will further reduce after energization of the Synch Condenser 45 Summary and Conclusions John Kehler Completed Transmission Upgrades and Development • South – Calgary area: 138 kV downtown cables – The two 240 kV three terminal lines were converted to 3-2 terminal lines with Milo Junction upgrade – New capacitor banks in the central east • North – Yellowhead: 4 capacitor banks, 138 kV line upgrades – Northwest: 144 kV line upgrades, 2-SVCs, Capacitor bank – Capacitor Bank in the Athabaska area – Keephills 3 – Keephills: Phase Shift Transformer • Intertie Restoration – LSSi 47 Transmission Upgrades and Development in Progress • NW: Synchronous Condenser • Ft McMurray: Capacitor bank, 144kV line upgrades • Russell Phase Shift Transformer • MATL • KEG Debottlenecking • System NIDs – Approved • Central East • Heartland • Hanna – Filed • • • • Red Deer South of Calgary Christina Lake System Development Northeast Fort MacMurray Transmission Development 48 Conclusions • System upgrades some are in and more are coming • Reduced curtailment in 2011 • System will continue to be reliable and well managed over the next 24 months 49 QUESTIONS Thank you