Discussion Paper Market Participant Choice to Construct, Own, Operate and Maintain Transmission
by user
Comments
Transcript
Discussion Paper Market Participant Choice to Construct, Own, Operate and Maintain Transmission
Discussion Paper Market Participant Choice to Construct, Own, Operate and Maintain Transmission Lines Connecting its Facilities to the Interconnected Electric System Date: Prepared by: Prepared for: Version: September 29, 2011 Doyle Sullivan, Director, Regulator Market Participants and Interested Stakeholders 1.0 Table of Contents 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. Executive Summary ............................................................................................................................. 3 Purpose ................................................................................................................................................. 3 Introduction ........................................................................................................................................... 3 Eligible Market Participants................................................................................................................. 4 Eligible Connection Projects ............................................................................................................... 5 Model ..................................................................................................................................................... 5 Integration into the Existing AESO Connection Process ................................................................. 6 Request For Proposal Approach ........................................................................................................ 7 Connection Queue Administration ..................................................................................................... 7 TFO Requirements and Obligations ................................................................................................... 8 10.1 10.2 Legislative Domain ..................................................................................................................................... 8 AESO Documents ...................................................................................................................................... 9 11. ISO Rule Changes ................................................................................................................................ 9 12. Next Steps ............................................................................................................................................. 9 Appendix 1 – Legislative References...................................................................................................... 10 Appendix 2 – ISO Rules 9.3, Transmission Facility Projects ............................................................... 13 1. Executive Summary The AESO is initiating discussion and consultation on providing market participants the opportunity to construct, own, operate and maintain the transmission facilities required to connect their facilities to the interconnection electric system; referred to as “market participant choice” for purposes of this discussion paper. The AESO is commencing discussion and consultation on market participant choice as it believes it is permitted within the existing legislated framework and can be implemented providing there are no adverse impacts on the Alberta interconnected system and market participants, This discussion is also in response to market participants who have expressed the desire for an alternative to the incumbent transmission facility owners (“TFOs”) constructing, owning, operating and maintaining those connections. The AESO understands this desire results generally from both the perceived high cost and extensive schedule associated with incumbent TFOs constructing the connection projects. In summary, at this point in time the AESO considers that all market participants who require a connection to the transmission system and all types of connection projects may be eligible to participate in market participant choice. Should a market participant choose to provide its own connection project, the market participant would assume all accountabilities of TFO, including construction, ownership, operations and maintenance, and all other obligations stipulated in legislation and AESO authoritative documents. The market participant would also be required to meet all normal obligations applicable to the type of system access service it is seeking connection to the system for. The AESO currently believes that minimal changes may be required to its authoritative documents to accommodate market participant choice, and that the existing connection process can effectively and efficiently support market participant choice with a few key procedural changes. 2. Purpose The purpose of this discussion paper is to set out concepts related to market participant choice and seek feedback seek feedback on those concepts. Stakeholders are encouraged to comment on this discussion paper using the attached stakeholder comment matrix. Please provide written comments to [email protected] by Friday, October 28, 2011. Should you have any questions on this discussion paper, please contact Nicole Weigel at 403 – 539 - 2874. 3. Introduction Market participant choice refers to providing the opportunity for a market participant to construct, own, operate and maintain (“own”) the transmission facilities required to connect a market participant’s facilities to the interconnected electric system. For clarity, market participant choice does not include bulk transmission system projects. Section 35(1) of the EUA provides authority for the AESO either to direct a TFO to prepare a facility application or to request a proposal from a market participant. Therefore, the legislative framework fundamentally supports market participant choice. For convenience, section 35(1) of the EUA can be found in Appendix 1. Market participant ownership of transmission facilities is not entirely a new concept in Alberta; while it is not be a well established practice, it has occurred in a few cases under a variety of historical circumstances. While market participant are permitted to own transmission facilities, there are at the same time some important reliability, operational and planning concerns that must properly be addressed. Specific Page 3 concerns relate to access to the transmission facilities for subsequent users for possible integration to the interconnected electric system as system facilities, and the challenges related to a “patchwork” of transmission facility operators in Alberta. With respect to access to the transmission facilities, section 39(3)(e) of the Electric Utilities Act (EUA) is clear that a TFO (whether incumbent or not) must provide the AESO with the use of the transmission facilities for the purpose of carrying out the AESO’s duties and responsibilities, as such, in the AESO’s view, gaining access to the transmission facilities is not a barrier. For convenience, section 39(3)(e) of the EUA can be found in Appendix 1. In addition, section 28(3) of the Transmission Regulation states that an owner of a generating unit interconnected to the transmission system may not prohibit interconnection or access to the interconnection facilities by other market participants. With respect to a patchwork of transmission facility operators, any market participant, including incumbent TFOs, owning transmission facilities are required to comply with legislation and regulation requirements, Alberta Utilities Commission rules, ISO rules, ISO tariff and Alberta Reliability Standards. This comprehensive set of requirements ensures that all transmission facilities are built to a minimum set of requirements and operated in a safe, reliable, consistent and coordinated manner. In addition, consistent with current practices, market participants and TFOs are required to execute joint operating agreements 1 prior to energizing transmission facilities and those joint operating agreements set out matters such as ownership and operating procedures. While market participant choice may result in additional transmission facility owners and operators, the end state should not result in any kind of patchwork operation of the interconnected electric system given that all TFOs operate to the same requirements and to the joint operating agreements in place. In the AESO’s view, no barriers exist to advancing market participant choice and as such the AESO wishes to discuss and seek feedback from stakeholders on matters relating to market participant choice. Using the stakeholder comment matrix provided please provide comments on the Introduction and indicate if you see any barriers to advancing market participant choice. 4. Eligible Market Participants The AESO is considering choice for all types of market participants that require connections to the transmission system, as listed below. Different considerations may have to be taken into account for the different types of market participants, such as waivers by distribution facility owners (“DFOs”) for direct connect loads under section 101 of the EUA. For convenience, section 101 of the EUA can be found in Appendix 1. 1. Direct connect generators 2. Direct connect loads 3. Dual use (generation and load) 4. Market participants who own industrial systems 5. Owners of an electric distribution facility (DFOs) 1 References to a joint operating agreement exist in ISO Rules OPP 604, Commissioning Transmission Facilities and Loads, ISO Rules OPP 605, Commissioning Generators and Associated Transmission Facilities, and the AESO’s energization checklist used in the AESO connection process. Page 4 As a note, the definition of an “electric distribution system” in the Electric Utilities Act (“EUA”) states that an electric distribution system does not include a transmission facility. While an electric distribution system cannot include a transmission facility, the AESO suggests DFOs should not be precluded from consideration of market participant choice as contemplated in this discussion paper, provided the DFOs undertake the necessary steps to support ownership of transmission facilities. Using the stakeholder comment matrix provided please indicate if you agree with the proposed eligible market participants. If you do not agree please provide rationale supporting your position. 5. Eligible Connection Projects In the AESO’s view, all transmission connection projects at all voltage levels can be eligible for market participant choice. Some connection projects will be simple and straightforward, such as a T-Tap. Other connection projects may be more complicated, such as in-out connections which may include more complex bus configurations such as ring buses. Many factors can introduce complexity into the design of a connection project, and this discussion paper is not intended to list all the factors or propose solutions to address those complexities. Market participants choosing to own transmission facilities would be required to work with incumbent TFOs to coordinate the construction and connection to the interconnected electric system, coordinate the operation of the transmission facilities, and execute a joint operating agreement with the incumbent TFO such that the system can be operated in a coordinated, safe and reliable manner. Using the stakeholder comment matrix provided please indicate if you agree or disagree that all transmission connection projects should be eligible for market participant choice. If you believe that the types of projects eligible should be limited please indicate those limitations and the supporting rationale. 6. Model Section 35(1) of the EUA allows the AESO to request a proposal from a market participant. In the AESO’s view this proposal must include responsibility for all facets of the life cycle of those facilities which includes construction, ownership, operation, maintenance, replacement and/or retirement of those facilities; referred to as the “own model”. In the AESO’s view the own model will deliver the most efficient approach for advancing market participant choice. For convenience, section 35(1) of the EUA can be found in Appendix 1. If upon energization and commissioning of the transmission facilities, the market participant – who is then, by definition, a TFO, chooses to transfer those transmission facilities to the incumbent TFO or another party, it may pursue such a transfer subject to receiving the necessary regulatory approvals. The transfer logistics are outside the scope of this discussion paper as the AESO does not have any authority to approve or refuse transfers. Using the stakeholder comment matrix provided please provide comments on using the own model as the approach for advancing market participant choice. If proposing an alternate model please provide the logistics of that model and rationale supporting that model. Page 5 7. Integration into the Existing AESO Connection Process Maximum efficiencies will be realized by utilizing the existing connection process. In the AESO’s view, the existing connection process can effectively support market participant choice and a separate and distinct process is not required. In essence, this means the market participant would be “wearing two hats” throughout the process: that of a TFO, and that of the end-use market participant. The diagram below provides a high level overview of the connection process and indicates the key procedural changes required at various stages to accommodate market participant choice. The diagram below, or this discussion paper, do not provide a list of the detailed activities performed by a TFO throughout the AESO’s connection process. For additional information on TFO activities please refer to the connection process documentation on the AESO website at www.aeso.ca. Stage 0: Identify Project Stage 1: Connection Study Scope Market participant confirms that it chooses to own transmission facilities, or declines. Stage 2: Connection Proposal Stage 3: NID and Facility Application Stage 4: Application Filings and AUC Approval Stage 5: Construction and Prepare to Energize Stage 6: Energize, Commission and Close AESO prepares and issues the functional specifications and requests a proposal to provide service (PPS) from the market participant. AESO reviews the PPS and approves the PPS provided it meets the need. AESO directs the market participant, functioning as a TFO to submit a facility application to the Commission. Market participant submits a facility application to the Commission. The first key procedural change would occur at Stage 0. At this stage a market participant would be required to confirm, in writing, that it intends to own the transmission facilities to its facilities, or not, and, if it does seek to own the transmission facilities then confirm that it will assume all requirements, obligations and responsibilities imposed on a TFO throughout the connection process 2, and, expects the AESO to treat it accordingly. Following this written acknowledgement the AESO would carry out activities in accordance with the existing connection process. The second key procedural change would occur at Stage 3. At this stage, the AESO would prepare and issue the functional specifications to the market participant, and in accordance with 35(1) of the EUA, the AESO would request a PPS from a market participant rather than directing an incumbent TFO to provide the PPS, provided the market participant met the suggested Stage 0 requirements. The AESO would review the PPS received from the market participant and provided it met the project need the AESO would direct the market participant to file a facility application as it would any incumbent TFO. Section 14(1) and (2) of the Hydro and Electric Energy Act, makes reference to a “person” which suggests that the Commission can issue a permit to a party other than an incumbent TFO. Therefore, in the AESO’s view, it can direct a party other than an incumbent TFO to submit a facility application to the Commission. In addition, section 15.4 of the Hydro and Electric Energy Act further suggests that a “person” may make an application and the Commission may combine this application with a needs identification document 2 TFOs carry out many activities throughout the connection process including but not limited to: studies, cost estimates, proposals, consultation, facility application, design, procurement, construction, construction management, energization and commissioning. Stakeholders are encouraged to review the AESO’s connection process documentation to gain a better understanding of TFO responsibilities. Page 6 submitted by the AESO under section 34(1) of the EUA. Again this reinforces that submission of a facility application is not restricted to an incumbent TFO. For convenience, sections 34(1) and 35(1) of the EUA, and sections 14 and 15.4 of the Hydro and Electric Energy Act can be found in Appendix 1. The AESO anticipates that some changes may be required to existing documentation used in the AESO’s connection process but in the AESO’s view the suggested procedural changes will enable the AESO to efficiently and effectively integrate market participant choice into the existing connection process. Using the stakeholder comment matrix provided please indicate if you agree or disagree that the proposed procedural changes can effectively integrate market participant choice into the existing connection process. If you disagree please proposed alternate procedures and the rationale supporting those alternate procedures. 8. Request For Proposal Approach Section 35(1) of the EUA allows the AESO to request a proposal, during Stage3 of the Connection Process, from a market participant(s); note the use of the plural term. For purposes of scoping and advancing market participant choice the AESO proposes that it request that proposal, referred to in section 35(1) of the EUA, only from the market participant requesting system access service. For clarity, the AESO is not suggesting that it request proposals from several market participants with respect meeting the need for an individual system access service request. For convenience, section 35(1) of the EUA can be found in Appendix 1. Using the stakeholder comment matrix provided please indicate if you agree or disagree that the request for a proposal be made only to the market participant requesting system access service. If you disagree with the proposed approach, please provide the supporting rationale for your position. 9. Connection Queue Administration As suggested in Section 7 above, a market participant seeking to own the transmission facilities connecting its facilities to the interconnected electric system must provide written confirmation to that respect at Stage 0 of the connection process, or decline the opportunity to own transmission facilities. If a market participant chooses to own the transmission facilities at Stage 0 and later in the connection process determines that it does not want to own the transmission facilities, the AESO proposes that it cancel the project resulting in the loss of the market participant’s connection queue position. Should the market participant wish to proceed with the project, it would be required to submit a new system access service request and obtain a new connection queue position. And, conversely, if a market participant declines ownership of the transmission facilities at Stage 0 and later in the connection process determines that it chooses to own the transmission facilities, the AESO proposes that it cancel the project resulting in the loss of the market participant’s connection queue position. Should the market participant wish to proceed with the project, it would be required to submit a new system access service request and obtain a new connection queue position. In the AESO’s view, a market participant should accept responsibility for understanding all requirements and obligations of a TFO prior to making a decision, and if it changes that decision then the project would be cancelled and the queue position revoked. Using the stakeholder comment matrix provided please indicate if you agree or disagree that the project should be cancelled and the queue position revoked if a market participant changes it position regarding owning transmission facilities. If you disagree please indicate why the proposed approach is inappropriate and suggest another approach with supporting rationale. Page 7 10. TFO Requirements and Obligations 10.1 Legislative Domain The incumbent TFO and any new TFOs emerging from market participant choice are required to comply with all Acts, Regulations and Alberta Utilities Commission Rules applicable to TFOs. In the AESO’s view, new TFOs have the responsibility to review and understand the legislative domain as it applies to owning transmission facilities and should not be treated any differently than incumbent TFOs. Market participants interested in participating in market participant choice are encouraged to review legislation including but not limited to the Electric Utilities Act, the Hydro Electric and Energy Act, the Public Utilities Act, the Surface Rights Act, the Transmission Regulation and the Alberta Utilities Commission Rules to understand TFO requirements and obligations. While the purpose of this discussion paper is not to list out all the requirements and obligations of a TFO, there are three notable legislative requirements: 1. AESO directions to a TFO. The EUA and the Transmission Regulation provide the AESO with authority to direct a TFO to perform activities and the TFO is required to comply with those directions unless there is real or substantial risk of damage to the transmission facilities, safety to employees or the public, or undue injury to the environment. Sections 35 and 39 of the EUA, and section 14 of the Transmission Regulation set out requirements and obligations regarding AESO directions. For convenience the above noted sections of the EUA and the Transmission regulation can be found in Appendix 1. 2. TFO Cost Recovery. The cost recovery mechanism for costs incurred as a result of an AESO direction is set out in sections 40(1) and 41(1) of the Transmission Regulation. For convenience the above noted sections of the Transmission regulation can be found in Appendix 1. 3. TFO tariff. Section 37(1) of the EUA requires a TFO to submit a tariff to the Commission for approval setting out the rates to be paid by the Independent System Operator for use of the owner’s transmission facility. For convenience, section 37(1) of the EUA can be found in Appendix 1. Therefore, unless the Commission exempts a TFO from this requirement the TFO must submit a tariff. Following the concept that the market participant is acting as both a TFO and end-use customer, there would be two streams of payments in all cases: the payment of the TFO tariff by the AESO to the TFO, and the payment of the AESO tariff (including applicable rates and contributions as specified in the terms and conditions) by the end use customer. Depending on whether the market participant is a load or generator, or both, different tariff provisions are applicable, and these would provide the foundation for the streams of payments. Also, the connection project cost would have to be transparent as it impacts both the TFO tariff and the contributions under the current AESO tariff. Using the stakeholder comment matrix provided please indicate if you agree that new TFOs, emerging from market participant choice, should be treated the same as an incumbent TFO with respect to the legislative requirements and obligations. Please also address the tariff requirements specifically. If you disagree please provide rationale for that position. Page 8 10.2 AESO Documents Market participants who decide to own transmission facilities are required to comply with all AESO documents 3 applicable to TFO owners and operators of those transmission facilities. In the AESO’s view, market participants who subsequently become new TFOs, as a result of market participant choice, have the same responsibilities as incumbent TFOs. Using the stakeholder comment matrix provided please indicate if you agree that new TFOs, emerging from market participant choice, should be treated the same as an incumbent TFO with respect to requirements and obligations set out in AESO documents. If you disagree please provide rationale for that position. 11. ISO Rule Changes Presently, ISO rules 9.1 (“ISO rules 9.1”), Transmission Facility Projects sets out the existing service areas, the incumbent TFOs and ISO directions to those TFOs, TFO requirements regarding cost estimates, proposals and project reporting, ISO project reporting, project procurement, confidentiality and interpretation. For convenience, ISO rules 9.1 can be found in Appendix 2. The AESO is of the view that ISO rules 9.1 may eventually need to be amended to apply to all TFOs removing references to incumbent TFOs and the respective service areas. Using the stakeholder comment matrix provided please indicate if you agree that ISO rules 9.1 should be changed to apply to new TFOs? If you do not agree with this approach please provide an alternative approach and rationale for that approach. Using the stakeholder comment matrix provided please indicate if you think any other ISO rules should be developed or changed to support market participant choice. 12. Next Steps Stakeholders are encouraged to comment on this discussion paper using the attached stakeholder comment matrix. Please provide written comments to [email protected] by Friday, October 28, 2011. Should you have any questions on this discussion paper, please contact Nicole Weigel at 403 – 539 - 2874. After receiving and considering written comments, the AESO will consider and respond to comments and issue a recommendation paper setting out a recommended approach for advancing market participant choice. 3 Key relevant AESO documents include ISO rules, ISO tariff, Alberta Reliability Standards, and AESO standards and the AESO Connection Process. Page 9 Appendix 1 – Legislative References For convenience specific references to legislation or regulations, made in this discussion paper, have been replicated below. Electric Utilities Act Alleviation of constraints or other conditions on transmission system 34(1) When the Independent System Operator determines that an expansion or enhancement of the capability of the transmission system is or may be required to meet the needs of Alberta and is in the public interest, the Independent System Operator must prepare and submit to the Commission for approval a needs identification document that (a) describes the constraint or condition affecting the operation or performance of the transmission system and indicates the means by which or the manner in which the constraint or condition could be alleviated, (b) describes a need for improved efficiency of the transmission system, including means to reduce losses on the interconnected electric system, or (c) describes a need to respond to requests for system access service. Transmission facilities directions and proposals 35(1) The Independent System Operator may, at the time of preparing a needs identification document, after submitting a needs identification document to the Commission or after receiving Commission approval of a needs identification document, (a) direct the owner of a transmission facility to submit, for Commission approval under the Hydro and Electric Energy Act, a transmission facility proposal to meet the need identified, or (b) request market participants to submit, for approval by the Independent System Operator, a proposal to meet the need identified. (2) The owner of a transmission facility must comply with a direction from the Independent System Operator under subsection (1) unless the owner gives written notice to the Independent System Operator, giving reasons, that (a) a real and substantial risk of damage to its transmission facility could result if the direction were complied with, (b) a real and substantial risk to the safety of its employees or the public could result if the direction were complied with, or (c) a real and substantial risk of undue injury to the environment could result if the direction were complied with. (3) Subject to subsection (2), on receiving a direction the owner of a transmission facility must prepare an application to meet the requirements or objectives of the direction and apply to the Commission for approval under the Hydro and Electric Energy Act. Transmission facility owner’s tariff 37(1) Each owner of a transmission facility must submit to the Commission for approval a tariff setting out the rates to be paid by the Independent System Operator to the owner for the use of the owner’s transmission facility. Duties of transmission facility owners 39(1) Each owner of a transmission facility must operate and maintain the transmission facility in a manner that is consistent with the safe, reliable and economic operation of the interconnected electric system. (2) Each owner of a transmission facility must, in a timely manner, assist the Independent System Operator in any manner to enable the Independent System Operator to carry out its duties, responsibilities and functions. (3) Each owner of a transmission facility must (a) establish, in conjunction with owners of electric distribution systems, procedures and systems for load shedding in emergencies; (b) provide the Independent System Operator in a timely manner with descriptions, ratings and operating restrictions relating to their transmission facility; Page 10 (c) inform the Independent System Operator in a timely manner of anticipated changes in their transmission facility that could affect the Independent System Operator in carrying out its duties, responsibilities and functions, including (i) the capability of the transmission facility, (ii) the status and availability of the transmission facility, including maintenance schedules, and (iii) additions to, alterations to or decommissioning of transmission facilities or any part of them; (c.1) install and remove meters and perform metering, including verifying meter readings and verifying accuracy of meters that are directly connected to the owner’s transmission facility; (d) comply with standards and practices established by the Independent System Operator to enable the Independent System Operator to carry out its duties, responsibilities and functions; (e) provide the Independent System Operator with use of the owner’s transmission facility for the purpose of carrying out the Independent System Operator’s duties, responsibilities and functions. 2003 (4) The owner of a transmission facility may refuse to comply with a direction from the Independent System Operator only if the owner notifies the Independent System Operator that the owner considers that (a) a real and substantial risk of damage to its transmission facility could result if the direction were complied with; (b) a real and substantial risk to the safety of its employees or the public could result if the direction were complied with; (c) a real and substantial risk of undue injury to the environment could result if the direction were complied with. Owner’s right to provide electric distribution service 101(1) A person wishing to obtain electricity for use on property must make arrangements for the purchase of electric distribution service from the owner of the electric distribution system in whose service area the property is located. (2) If the person has an interval meter and receives electricity directly from the transmission system, the person may, with the prior approval of (a) the owner of the electric distribution system in whose service area the person’s property is located, if any, and (b) the Independent System Operator, enter into an arrangement directly with the Independent System Operator for the provision of system access service. Hydro Electric and Energy Act Permit 14(1) No person shall construct a transmission line or any part of a transmission line unless the person is the holder of a permit issued by the Commission. (2) No person shall make a significant extension or alteration of a transmission line unless the Commission has amended the person’s permit or issued a new permit to cover the extension or alteration. Combining application and submission 15.4 If a person makes an application under this Part and the Independent System Operator has submitted a needs identification document to the Alberta Utilities Commission under section 34 of the Electric Utilities Act in respect of the same transmission line or part of a transmission line, the application and submission may be combined and considered by the Commission. Exemption 16(1) Unless the Commission otherwise directs, sections 14 and 15 do not apply (a) to a person transmitting or proposing to transmit electric energy over the person’s own land solely for the person’s own use by means of a line that does not cross a public highway, or (b) to the owner of an industrial system transmitting or proposing to transmit electric energy (i) over land of which the owner of the industrial system is the owner or tenant, or (ii) across a public highway dividing land that is owned or leased by the owner of the industrial system for use solely by that industrial system. Page 11 Transmission Regulation Assistance to the ISO 14(1) As part of the duties of a TFO under section 39 of the Act, the TFO must, as directed by the ISO, assist the ISO in (a) preparing and updating forecasts, (b) preparing, maintaining and updating the transmission system plan, and (c) preparing and updating needs identification documents. (2) In addition to the duties of a DFO under the Act, the DFO must, as directed by the ISO, assist the ISO in (a) preparing and updating forecasts, (b) preparing, maintaining and updating the transmission system plan, (c) evaluating the relative merits of transmission and distribution options, and (d) preparing and updating needs identification documents. (3) In providing assistance to the ISO, the TFO and DFO must, in accordance with the directions of the ISO, respect the confidentiality of information of market participants. Local interconnection costs 28 (3) The owner of a generating unit that interconnects with the transmission system, and who has paid local interconnection costs, may not prohibit interconnection or access to the interconnection facilities by other market participants. Recovery of assistance costs 40(1) A TFO may include in its transmission tariff (a) costs and expenses incurred by the owner in assisting the ISO in preparing forecasts, the transmission system plan, needs identification documents and updates to any or all of them, and (b) the costs incurred by the owner to assist the Market Surveillance Administrator in preparing reports made under section 23(2). Recovery of other secondary costs 41(1) A TFO or DFO may include in its tariff any one or more of the following, as applicable: (a) costs or expenses incurred as a consequence of a direction given by the ISO under this Regulation or any other enactment; (b) costs and expenses (i) of a maintenance upgrade, enhancement or other modification to a transmission facility referred to in section 11(6), (ii) incurred in implementing an expansion or enhancement to the transmission system access service interconnection or a transmission facility project referred to in section 12, (iii) incurred in order to implement the standards and rules under section 5, or (iv) incurred in order to implement the reliability standards. Page 12 Appendix 2 – ISO Rules 9.3, Transmission Facility Projects 9.1 Transmission Facility Projects 9.1.1 Eligible TFO 9.1.1.1 Eligibility by Service Area Subject to rule 9.1.1.2 b), c), d), and e) each service area shall have one TFO eligible to apply for the construction or operation, or both, of transmission facilities in such area. For purposes of this rule 9.1.1.1, the following TFOs are eligible for the referenced service area: TFO Service area AltaLink L.P. FortisAlberta Inc. ATCO Electric Ltd. ATCO Electric ENMAX Power Corporation ENMAX Corp. EPCOR Distribution & Transmission Inc. EPCOR Distribution & Transmission Inc. City of Red Deer City of Red Deer City of Lethbridge City of Lethbridge 9.1.1.2 Directions a) Subject to rules 9.1.1.2 b), c), d), and e), i) the ISO will issue a Direction to the TFO eligible in the service area where the Project is located; ii) with respect to a Project located in more than one service area, the ISO will issue a Direction to each TFO for that part of the Project located in its service area; b) With respect to transmission facilities that exist as of August 12, 2004, the owner of such facilities, or its successors and assigns, shall be the TFO eligible to receive a Direction with respect to any enhancements or upgrades to such facilities, subject to the ISO being satisfied that the operation of such facilities will result in the safe, reliable and efficient operation of the facilities. For purposes of this rule 9.1.1.2 b), owners include the following: Owners AltaLink L.P. TransAlta Utilities Corp ATCO Electric Ltd. ENMAX Power Corporation EPCOR Distribution & Transmission Inc. City of Red Deer City of Lethbridge c) The ISO may issue a Direction to a TFO other than the TFO that is eligible pursuant to rule 9.1.1.1. if such TFO and the TFO in whose service area the Project is located, have entered into an arrangement or agreement which would result in the safe, reliable and efficient operation of the transmission system and such arrangement or agreement has been filed with the Commission; d) With respect to a Project that is located in more than one service area, where the TFOs in those service areas have entered into an arrangement or agreements, with respect to the Project, Page 13 i) ii) whereby the Project is to be constructed or operated or both by one or more of the TFOs or by a separate entity created for the purpose of the Project and wholly owned, directly or indirectly, by one or more of: (A) the TFOs; (B) the direct or indirect owners of the TFOs; and (C) entities that are directly or indirectly wholly owned by the owners of the TFOs; and which would result in the safe, reliable and efficient operation of the transmission system and such arrangement or agreement has been filed with the Commission. the ISO may issue a Direction in respect of the Project to one or more of the TFOs in accordance with such arrangement or agreement, and one or more of the TFOs, or the entity created for the purpose of the Project, is eligible to apply for the construction or operation, or both, of the transmission facilities. e) with respect to a Project all but a small portion of which is located in one service area with the small portion located in an adjacent service area, the ISO may issue a Direction to the TFO in whose service area the largest portion of the Project is located, if, in the ISO’s opinion, acting reasonably, such Direction will result in the safe, reliable, efficient and economic operation of the interconnected electric system. 9.1.1.3 Directions - Interconnections to Jurisdictions outside Alberta a) If the ISO has obtained approval of a NID for a Project contemplated by the T-Reg: i) the ISO may issue a Direction to the TFO eligible in the service area where the connection of the Project to the interconnected electric system will be located if the proponent of the Project has submitted an application under the HEEA for a permit and license for the remainder of the Project; or ii) the ISO may issue a Direction to the TFO eligible in accordance with rule 9.1.1.1 if the Project is proposed by the ISO. 9.1.2 TFO Obligation to Provide Estimates and Proposals 9.1.2.1 Request for a NID Estimate a) The ISO may request a NID Estimate with respect to a Project from the Designated TFO. b) The ISO shall provide to the Designated TFO with such request, information required regarding the Project which the Designated TFO would reasonably require from the ISO to complete a NID Estimate. 9.1.2.2 Obligation to Provide NID Estimate A Designated TFO to whom a request for a NID Estimate has been made must prepare and submit the NID Estimate to the ISO on or before the date mutually agreed to by the ISO and the Designated TFO, acting reasonably. The NID Estimate must include, without limitation, the following: a) a cost estimate for the Project within the accuracy range of plus 30% to minus 30% of the final costs; b) assumptions used; and c) the period of time the estimate is valid. 9.1.2.3 Requirement for a Service Proposal a) The ISO may request a Service Proposal with respect to a Project from the Designated TFO. b) The ISO shall not issue a Direction to a Designated TFO with respect to a Project unless: i) it has received a Service Proposal from the Designated TFO for such Project, or ii) a Transmission Customer has agreed, in writing, to forgo the Service Proposal review by the ISO and to support the ISO’s issuance of such Direction on the basis of a NID Estimate for such Project, or Page 14 iii) the Direction contains conditions requiring the ISO’s receipt of a Service Proposal for such Project in advance of the Designated TFO’s submission of the Transmission Facility Proposal for the Project (c) The ISO shall provide to the Designated TFO with such request or to a Designated TFO referred to in the forgoing rule b), information regarding the Project which the Designated TFO reasonably requires to prepare a Service Proposal and a Service Proposal Estimate. 9.1.2.4 Obligation to Provide Service Proposal and Service Proposal Estimate A Designated TFO to whom a request for a Service Proposal has been made must prepare and submit the Service Proposal and a Service Proposal Estimate to the ISO on or before the date mutually agreed to by the ISO and the Designated TFO, acting reasonably. The Service Proposal Estimate must include, without limitation, the following: a) b) c) d) a cost estimate for the Project within the accuracy range of plus 20% to minus 10% of the final costs: assumptions used; the period of time the estimate is valid; and identify any proposed capital maintenance costs included within any Commission approval. 9.1.2.5 Obligation to Provide Service Proposal Estimate Update A Designated TFO who has submitted a Service Proposal Estimate pursuant to rule 9.1.2.4 must prepare an update of such Service Proposal Estimate. The Designated TFO must submit such update to the ISO on or before 180 days from the date that the Commission has issued to the Designated TFO all permits and granted all licences pursuant to the HEEA required for the facilities associated with the Project. Such update must include an updated cost estimate for the Project within the accuracy range of plus 10% to minus 10% of the final costs. 9.1.3 Project Reporting by Designated TFOs 9.1.3.1 Monthly Reporting Unless agreed otherwise, each Designated TFO with respect to a Project, the cost of which is estimated to be more than one million dollars, shall provide to the ISO on or before the 15th Business Day of each month commencing the month after the ISO has issued a Direction to such Designated TFO(s), a Project Progress Report. 9.1.3.2 Project Variance Reporting In addition to any other obligations it has with respect to a Project, the Designated TFO shall notify the ISO as soon as reasonably practical in the event of any of the following: a) if the in service date of the Project is forecast by it to be delayed from the in service date specified in the Direction; or b) if the forecast costs of the Project are expected to vary by more than 10% from the amount specified in the Direction or if applicable, the amount agreed to by the ISO in an amendment to the Direction; or c) if the TFO has determined that a material amendment to the scope of the Project is required to meet the need identified with respect to the Project. 9.1.3.3 Project Variance Explanation The Designated TFO shall include with the notice given in rule 9.1.3.2, the reason or reasons for any or all of the variances, including schedule delays, cost trends and scope change. 9.1.3.4 Project Change Proposal Page 15 The Designated TFO shall prepare and submit to the ISO a Project Change Proposal to address the delay, cost trends, or scope change, as the case may be, identified in a notice pursuant to rule 9.1.3.2. The Designated TFO shall prepare and submit such proposal to the ISO as soon as reasonably practical and in any event no later than 15 days from the date of the notice pursuant to rule 9.1.3.2. 9.1.3.5 Project Change Proposal Review The ISO shall review the Project Change Proposal submitted by the Designated TFO pursuant to rule 9.1.3.4. As soon as reasonably practical, and no later than 15 days following receipt of the Project Change Proposal, the ISO must do one or more of the following: a) approve such proposal, with or without amendments, in which event the Project shall be deemed amended; b) reject such proposal with or without requesting a revised Project Change Proposal; c) cancel the Project; and/or d) recommend that the TFO apply to the Commission for an amendment to any approval it may have obtained pursuant to the HEEA. 9.1.3.6 Final Cost Report Unless agreed otherwise, a Designated TFO shall provide to the ISO; a) on or before the 60th day from the last day of the month after the Project Energization of the Project, an estimate of the final cost of the Project substantially in the form of the Final Cost Report and specifying the accuracy range of the estimate, as a plus % to a minus % of the final costs; and b) as soon as practical, and in no event later than the first day of the sixth full month after the Project Energization of the Project, a Final Cost Report of the Project. 9.1.3.7 Notification – Transmission Customer Projects Notwithstanding any other provision within this rule 9.1.3, if a Transmission Customer has made an application for system access service for a specific Project, or portion of a Project, the ISO shall notify the Designated TFO in that regard. Subject to such notification; a) the Designated TFO shall provide to the Customer at the same time it is required to provide or submit to the ISO, any and all notifications and documents it is required to provide or to submit pursuant to this rule 9.1.3; and b) the ISO and the TFO shall review any Project Change Proposal with the Customer, and thereafter the ISO acting reasonably, must do one of the things identified in rule 9.1.3.5. 9.1.4 ISO Projects Reporting No later than the last day of the month following each Quarter, the ISO shall make available on its website the Quarterly Projects Report. 9.1.5 Project Procurement 9.1.5.1 Project Material Procurement by Designated TFO A Designated TFO, shall, in carrying out the construction of the transmission facilities, comply with the procurement requirements contained in this rule. 9.1.5.2 Major acquisitions Where the cost of a specific item or type of any Project Material required for a Project is forecast by the Designated TFO, acting reasonably, to exceed $50,000, the Designated TFO shall solicit written bids to provide such material from not less than 3 arm’s length suppliers. Page 16 9.1.5.3 Minor acquisitions Where the cost of all of any specific item or type of any Project Material required for a Project is forecast by the Designated TFO, acting reasonably, to exceed $10,000 but be less than $50,000, the Designated TFO shall solicit written bids, including short form written bids, to provide such material from not less than 3 arm’s length suppliers. 9.1.5.4 Standing Bids The Designated TFO may obtain from a supplier a written bid, including a short form written bid, that is in effect for a specified period of time and utilize such bid for purpose of making a determination in accordance with the following rule 9.1.5.5. 9.1.5.5 Lowest Priced Compliant Bid Subject to rule 9.1.5.6 a), in the event the Designated TFO receives one or more compliant bid pursuant to rule 9.1.5.2 or 9.1.5.3, it shall award the contract to the party that has submitted the lowest priced, fully compliant bid. 9.1.5.6 Exceptions a) In the event the Designated TFO has awarded a contract to a party from whom it has received a bid pursuant to rules 9.1.5.2 or 9.1.5.3, and such party did not submit the lowest priced, fully compliant bid such TFO shall; i) demonstrate to the ISO, if requested, that it was commercially reasonable to do so; ii) with respect to a contract awarded where bids were received pursuant to rule 9.1.5.2 include in the next Project Progress Report for the Project, its reasons for not awarding such contract in compliance with rule 9.1.5.5; and iii) with respect to all such contracts, include in its books and records its reasons for not awarding such contracts in compliance with rule 9.1.5.5. b) A Designated TFO may award a contract to a party without obtaining a bid pursuant to rule 9.1.5.2 or 9.1.5.3 if the Designated TFO can demonstrate to the ISO that it was reasonable not to obtain competitive bids, based on any of the following: i) that the party awarded the contract was the only entity capable to provide the Project Material; ii) that given reasonable Project schedule requirements, there was insufficient time to solicit bids; or iii) that there was insufficient information on which to base a bid. 9.1.5.7 Maintenance of Procurement Books and Records Subject to any other obligation or duty a Designated TFO has, including without limitation any obligations it has pursuant to the ISO Tariff or the terms and conditions contained in the current version of the Commission approved tariff of such TFO, the Designated TFO shall maintain all written bids relating to the procurement of Project Material for each Project regarding which it has been issued a Direction for not less than one year from the date that the ISO has received the completed Final Cost Report for the Project. 9.1.5.8 Compliance Review Right of ISO The ISO shall have the right exercisable upon reasonable prior notice to the Designated TFO to examine the books and records of the Designated TFO, including all written bids relating to the procurement of Project Material, to the extent reasonably necessary to verify, with respect to any Project compliance by the TFO with this rule 9.1.5; provided, that such right shall only continue for a period of one year from the date it has delivered the Final Cost Report of such Project to the ISO. Page 17 9.1.5.9 Reasons for non-compliance In addition to any other provisions in these rules, in the event the ISO, acting reasonably, determines that a Designated TFO has not complied with this rule 9.1.5 regarding procurement, it shall advise the Designated TFO and give it the reasons for such non-compliance. 9.1.5.10 Project Procurement Report The Designated TFO shall include in the Final Cost Report details regarding the level of competitive procurement with respect to the acquisitions for a Project made pursuant to rule 9.1.5.2. 9.1.6 Confidentiality 9.1.6.1 Data and Information Included Subject to rule 9.1.6.2, all data and information either the ISO or Designated TFO provides to the other with respect to rule 9.1 shall be treated by the party receiving such data and information in accordance with the confidentiality provisions in the ISO rules or the terms and conditions contained in the current version of the Commission approved tariff of the TFO. 9.1.6.2 Data and Information Excluded All NID Estimates and all Quarterly Projects Reports shall not be confidential. 9.1.7 Interpretation In the event of any conflict or inconsistency between this rule 9.1 and any tariff approved by the Commission, or Commission order or directive, the latter shall prevail. Page 18