Draft Information Documents Supporting the Proposed ISO OPP 500 Series... The following four (4) draft information documents have been developed... OPP 500 Series Removals.

by user

on
Category: Documents
8

views

Report

Comments

Transcript

Draft Information Documents Supporting the Proposed ISO OPP 500 Series... The following four (4) draft information documents have been developed... OPP 500 Series Removals.
Draft Information Documents Supporting the Proposed ISO OPP 500 Series OPP Removals.
The following four (4) draft information documents have been developed to support the proposed ISO
OPP 500 Series Removals.
1. Information Document # 2012-014R Joffre Area Transmission Constraint Management
Information Document # 2012-014R Joffre Area Transmission Constraint Management (“ID# 2012-014R”) has
been created to complement Section 302.1 of the ISO rules, Real Time Transmission Constraint Management
(“TCM Rules”), by providing useful information and additional clarity to market participants on how the AESO
intends to manage transmission constraints in the Joffre Area.
ID# 2012-014R has been created to set out the transmission constraint conditions and the limits resulting
from those conditions. As well, ID# 2011-014R provides information on each of the transmission constraint
management procedure steps, and includes additional information regarding the unique operating
characteristics and resulting transmission constraint conditions and limits in the Joffre Area.
Click here to view ID# 2012-014R. Please submit any questions or comments regarding this draft
information document to [email protected].
2. Information Document # 2012-015R Cold Lake Area Transmission Constraint Management
Information Document # 2012-015R Cold Lake Area Transmission Constraint Management (“ID# 2012015R”) has been created to complement the TCM Rules, by providing useful information and additional clarity
to market participants on how the AESO intends to manage transmission constraints in the Cold Lake Area..
ID# 2012-015R has been created to set out the transmission constraint conditions and the limits resulting
from those conditions. As well, ID# 2011-015R provides information on each of the transmission constraint
management procedure steps, and includes additional information regarding the unique operating
characteristics and resulting transmission constraint conditions and limits in the Cold Lake Area.
Click here to view ID# 2012-015R. Please submit any questions or comments regarding this draft information
document to [email protected].
3. Information Document # 2012-016R Fort Saskatchewan Area Transmission Constraint Management
Information Document 2012-016R Fort Saskatchewan Area Transmission Constraint Management (“ID#
2012-016R”) has been created to complement the TCM Rules, by providing useful information and additional
clarity to market participants on how the AESO intends to manage transmission constraints in the Fort
Saskatchewan Area..
ID# 2012-016R has been created to set out the transmission constraint conditions and the limits resulting
from those conditions. As well, ID# 2011-016R provides information on each of the transmission constraint
management procedure steps, and includes additional information regarding the unique operating
characteristics and resulting transmission constraint conditions and limits in the Fort Saskatchewan Area.
Click here to view ID# 2012-016R. Please submit any questions or comments regarding this draft information
document to [email protected].
4. Information Document # 2012-017R Crossfield Area Transmission Constraint Management
Information Document # 2012-017R Crossfield Area Transmission Constraint Management (“ID# 2012-017R”)
has been created to complement the TCM Rules, by providing useful information and additional clarity to
market participants on how the AESO intends to manage transmission constraints in the Crossfield Area.
Issued for Stakeholder Consultation: 2012-10-09
ID# 2012-017R has been created to set out the transmission constraint conditions and the limits resulting
from those conditions. As well, ID# 2011-017R provides information on each of the transmission constraint
management procedure steps, and includes additional information regarding the unique operating
characteristics and resulting transmission constraint conditions and limits in the Crossfield Area.
Click here to view ID# 2012-017R. Please submit any questions or comments regarding this draft information
document to [email protected].
Issued for Stakeholder Consultation: 2012-10-09