Comments
Transcript
APPENDIX E DFO DISTRIBUTION DEFICIENCY REPORT
APPENDIX E DFO DISTRIBUTION DEFICIENCY REPORT Contents 1 EXECUTIVE SUMMARY .............................................................................................................................. 2 2 EXISTING DISTRIBUTION AND TRANSMISSION SYSTEM ASSESSMENT ..................................... 3 Figure 2.0-1, Substations in the Vicinity of Load Requests ............................................................................. 3 Table 2.0-1, Distances between Substations and Customer Sites.................................................................... 3 2.1 DOME CUTBANK 810S.............................................................................................................................. 4 Figure 2.1-1 – Simplified SLD of Dome Cutbank 810S................................................................................... 4 2.2 SIMONETTE 733S ...................................................................................................................................... 4 Figure 2.2-1 – Simplified SLD of Simonette 733S ........................................................................................... 4 2.3 EXISTING DISTRIBUTION SYSTEM ............................................................................................................. 5 Figure 2.3-1 – Simplified SLD of Simonette 733S ........................................................................................... 5 3 NEED FOR DEVELOPMENT ........................................................................................................................ 6 Table 3.0-1 – Load Requests ........................................................................................................................... 6 4 ALTERNATIVES ............................................................................................................................................. 6 4.1 ALTERNATIVE 1: SERVE THE LOADS WITH A DISTRIBUTION-BASED SOLUTION ......................................... 7 4.2 ALTERNATIVE 2: UPGRADE EXISTING TRANSFORMER AT SIMONETTE 733S ............................................ 7 Figure 4.2-1 – Simplified SLD of Simonette 733S, Alternative 2 .................................................................... 7 4.3 ALTERNATIVE 3: INSTALL SECOND TRANSFORMER AT SIMONETTE 733S ................................................ 8 Figure 4.3-1 – Simplified SLD of Simonette 733S, Alternative 3 .................................................................... 8 5 RECOMMENDATION .................................................................................................................................... 9 APPENDIX A – LOAD FORECASTS .................................................................................................................... 10 Table A-1 - Dome Cutbank 810S Current Load Forecast excluding requested loads................................... 10 Table A-2 –Simonette 733S Current Load Forecast excluding requested loads ........................................... 10 Table A-3 –Simonette 733S Load Forecast including Requested Loads ....................................................... 11 Table A-4 – Simonette 733S Alternative 2 Load Forecast............................................................................. 11 Table A-5 – Simonette 733S Alternative 3 Load Forecast............................................................................. 11 Revision History: R0 Original R1 Implement comments R2 Implementing AESO DDR Author’s Guide R3 Implement AESO Comments Erin Ebbers Julian Tong Sonya Wallbank Septemper 16, 2014 February 9, 2015 September 11, 2015 Matt Sv. November 4, 2015 1 1 Executive Summary Simonette 733S is located approximately 60 km west of the Town of Fox Creek. This POD has a single 10/13 MVA, 144 – 25 kV transformer. ATCO Electric Distribution Division (AE DFO) has received requests for approximately 7.1 MW of new load in the Simonette area. Substation loading is forecast to exceed the nameplate rating of the transformer in 2015. To serve the requested loads, AE DFO has considered the following Distribution alternative: Alternative 1 Serve the loads with a distribution-based solution AE DFO also considered the following Transmission alternatives: Alternative 2 Upgrade Existing Transformer at Simonette 733S Alternative 3 Install Second Transformer at Simonette 733S Based on the analysis outlined in this report, a distribution based solution cannot serve these requests. Both Alternative 2 and Alternative 3 are technically acceptable. AE DFO prefers Alternative 2 to address the distribution deficiency. The requested in-service date (ISD) for this upgrade is December 31, 2016. 2 2 Existing Distribution and Transmission System Assessment Figure 2.0-1 shows the existing Transmission system near the load requests. The closest substations to the customer sites are Simonette 733S and Dome Cutbank 810S. Distances between each substation and customer site are provided in Table 2.0-1. Kakwa Ridge 857S was not considered because it is not a distribution POD. Figure 2.0-1, Substations in the Vicinity of Load Requests Table 2.0-1, Distances between Substations and Customer Sites Site Site #1 Site #2 Site #3 Total Requested Load 4.3 MW 2.6 MW 0.2 MW Distance from Simonette 733S 31 km 11 km 13 km 3 Distance from Dome Cutbank 810S 42 km 80 km 82 km 2.1 Dome Cutbank 810S Table A-1, in Appendix A, shows the load forecast for Dome Cutbank 810S with existing customer loading and forecasts. The simplified single-line diagram (SLD) is shown in Figure 2.1-1. Figure 2.1-1 – Simplified SLD of Dome Cutbank 810S 2.2 Simonette 733S Simonette 733S has one 10/13 MVA 144/25 kV transformer (702T) and one 10/13 MVA voltage regulator (502VR). Figure 2.2-1 shows the simplified SLD for Simonette 733S. Table A-2, in Appendix A, shows the load forecast for Simonette 733S with existing customer loading and forecasts. Figure 2.2-1 – Simplified SLD of Simonette 733S 4 2.3 Existing Distribution System All sites identified in Table 2.0-1 are within the existing Simonette 733S distribution system. Figure 2.3-1 shows the distribution system configuration emanating from Simonette 733S. No interconnections to other distribution systems exist. Figure 2.3-1 – Simplified SLD of Simonette 733S Industrial sites constitute 97.3% of the load at Simonette 733S, with the remaining 2.7% of load being residential and commercial. Critical load is defined as all non-industrial loads, as well as 10% of industrial load (to allow for basic heating and lighting in a contingency scenario). Using this definition, the critical load served from Simonette 733S is calculated to be 12% of the current substation loading. In the event of a POD transformer contingency at Simonette 733S, there is currently no capability to serve critical load. AE DFO does not deem this critical load as a deficiency and this is not driving the need for development. 5 3 Need for Development The need for development at Simonette 733S is driven by new customer load additions and existing customer load increase requests. AE DFO has received multiple industrial load requests near Simonette 733S. Table 3.01 summarizes these requests. Table 3.0-1 – Load Requests Site Site #1 LSD 1-21-63-2-W6M Site #2 5-31-62-24-W5M Site #3 1-16-63-24-W5M Load Description Liquid Transfer Gas Plant Expansion Site Expansion Site Expansion Pump Total Requested Load 0.6 MW 3.7 MW 1.1 MW 1.5 MW 0.2 MW 7.1 MW Requested ISD Q3 2014 Q4 2015 Q2 2014 Q3 2014 Q4 2014 No major distribution system development is required to connect the load requests to the Simonette 733S distribution system. Table A-3, in Appendix A, shows the load forecast for Simonette 733S after connecting all load requests shown in Table 3.0-1. In 2015, the loading at the POD exceeds the total nameplate capacity of transformer 702T and voltage regulator 502VR. Due to this identified deficiency, alternatives have been evaluated to serve the load requests. 4 Alternatives The following alternatives were considered and are described in Sections 4.1, 4.2, and 4.3. Distribution alternative: Alternative 1 Serve the loads with a distribution-based solution Transmission alternatives: Alternative 2 Upgrade Existing Transformer at Simonette 733S Alternative 3 Install Second Transformer at Simonette 733S 6 4.1 Alternative 1: Serve the loads with a distribution-based solution A. Load Shifting Dome Cutbank 810S is the nearest adjacent POD to the Simonette 733S distribution system. AE DFO investigated shifting load from Simonette feeder 5L175 to Dome Cutbank’s distribution system, in order to serve the requested loads identified in Table 3.0-1. Shifting feeder 5L175’s load to Dome Cutbank 810S would involve constructing approximately 42 km of 25 kV distribution line. AE DFO modelled this scenario in a load flow simulation. Minimum acceptable voltage levels (0.97 Vpu) cannot be obtained at Site #1 in this scenario. Distribution line lengths are too long to support any load shifting. This alternative is not technically feasible and has been rejected. No further analysis was completed. 4.2 Alternative 2: Upgrade Existing Transformer at Simonette 733S Alternative 2 involves increasing the POD capacity at Simonette 733S by replacing the existing 10/13 MVA transformer and 10/13 MVA voltage regulator with a larger capacity unit. The assumed transmission development at 733S Simonette substation may include: Discontinuing use of the existing 10/13 MVA transformer; Discontinuing use of the existing 10/13 MVA voltage regulator; Installing one (1) 30/40/50 MVA, 144-25 kV LTC transformer; and Installing associated protection and metering. Figure 4.2-1 – Simplified SLD of Simonette 733S, Alternative 2 7L80 H.R. Milner 701 7L80D1 701A 503 5L283 503A 702TCS 7L40 Little Smoky 702T 30/40/50 MVA 702 H 7L40D1 702A 500D4 N.O. 502 X 502TD 5L175 502A 500D6 500D3 N.O. 501 5L390 501A Legend ATCO Electric Development 701TD N.O. 4.2.1 Assessment After the assumed transmission development is completed, the POD capacity at Simonette 733S will increase by 37 MVA. A load forecast is shown in Table A-4, in Appendix A. The upgraded transformer will provide adequate capacity for the requested 7 loads as well as for load growth in the area for the foreseeable future. As described in Section 2.3, the critical load at Simonette 733S is not the driver of the need for development; therefore, the redundancy offered by installation of a second transformer is not required. This alternative is technically acceptable. 4.3 Alternative 3: Install Second Transformer at Simonette 733S Alternative 3 involves increasing the POD capacity at Simonette 733S by installing a second transformer at Simonette 733S. The assumed transmission development at 733S Simonette substation may include: Installing one (1) new 30/40/50 MVA LTC transformer; Installing one (1) new 144 kV breaker and associated disconnect switch; Installing one (1) 144 kV motorized disconnect switch; Installing one (1) 25 kV motorized disconnect switches; Installing associated protection and metering; and Changing 500D6 to be a normally open switch. Figure 4.3-1 – Simplified SLD of Simonette 733S, Alternative 3 703T 30/40/50 MVA 7L80 H.R. Milner 144 kV 701 7L80D1 703 701A H M 503 X 500D4 N.O. 502VR 10/13 MVA 700D1 502 702TCS 702T 10/13 MVA 500D3 N.O. 501 702 7L40D1 5L175 502A M 7L40 Little Smoky 144 kV 5L283 503A 503TD 703TD 702A 502TD 500D6 N.O. 5L390 501A Legend ATCO Electric Development 701TD N.O. 4.3.1 Assessment After the assumed transmission development is completed, the POD capacity at Simonette 733S will increase by 50 MVA. A load forecast is shown in Table A-5, in Appendix A. The second transformer will provide adequate capacity for the requested loads as well as for load growth in the area for the foreseeable future. This alternative is technically acceptable. 8 5 Recommendation Both Alternative 2 and Alternative 3 are technically acceptable from a distribution standpoint. AE DFO prefers Alternative 2 to address the capacity concerns at Simonette 733S for the following reasons: The redundancy offered by installation of a second transformer is not required, and Alternative 2 is assumed to require less transmission development compared to Alternative 3. The requested in-service date (ISD) for this upgrade is December 31, 2016. 9 Appendix A – Load Forecasts Table A-1 - Dome Cutbank 810S Current Load Forecast excluding requested loads Existing System Sub No. 810S 810S Feeder Dome Cutbank 5L318 5L724 Total Station Capacity 701T/702T 20/26 MVA PF 92% 94% 90% 92% Peak MW 2010 9.8 10.0 0.0 9.8 Peak MW 2011 18.2 9.8 9.7 18.2 Recorded Peak MW 2012 19.6 10.1 10.5 19.6 Peak MW 2013 21.1 9.9 12.0 21.1 Peak MW 2014 21.2 10.0 12.8 21.2 Peak MW 2015 22.9 10.2 14.4 22.9 Peak MW 2016 23.4 10.6 14.6 23.4 Peak MW 2017 23.6 10.7 14.7 23.6 Peak MW 2018 23.8 10.8 14.8 23.8 Peak MW 2019 24.1 10.9 15.0 24.1 Predicted Peak MW 2020 24.3 11.0 15.1 24.3 Peak MW 2021 24.5 11.1 15.2 24.5 Peak MW 2022 24.7 11.2 15.3 24.7 Peak MW 2023 24.9 11.3 15.5 24.9 Peak MW 2024 25.1 11.4 15.6 25.1 Peak MW 2025 25.3 11.5 15.7 25.3 Notes: A feeder coincidence factor of 0.93 was applied to the feeders Tranformer capacity violations Capacity constraints at Dome Cutbank 810S are being addressed under AESO project 1634 Table A-2 –Simonette 733S Current Load Forecast excluding requested loads Existing System Sub No. 733S 733S Feeder Simonette 5L390 5L175 5L283 Total Station Capacity 702T 10/13 MVA PF 96% 92% 90% 98% 96% Peak MW 2010 7.3 1.1 4.6 1.5 7.3 Peak MW 2011 8.1 1.1 5.0 1.6 8.1 Recorded Peak MW 2012 8.4 1.2 5.5 2.0 8.4 Peak MW 2013 9.4 1.2 5.6 3.1 9.4 Peak MW 2014 11.2 1.2 6.7 4.0 11.2 Peak MW 2015 11.2 1.2 6.7 4.0 11.2 Notes: A coincidence factor of 0.94 was applied to the feeders Transformer capacity violations 10 Peak MW 2016 11.2 1.2 6.7 4.0 11.2 Peak MW 2017 11.2 1.2 6.7 4.0 11.2 Peak MW 2018 11.2 1.2 6.7 4.0 11.2 Predicted Peak Peak MW MW 2019 2020 11.2 11.2 1.2 1.2 6.7 6.7 4.0 4.0 11.2 11.2 Peak MW 2021 11.2 1.2 6.7 4.0 11.2 Peak MW 2022 11.2 1.2 6.7 4.0 11.2 Peak MW 2023 11.2 1.2 6.7 4.0 11.2 Peak MW 2024 11.2 1.2 6.7 4.0 11.2 Table A-3 –Simonette 733S Load Forecast including Requested Loads Sub No. 733S 733S Feeder Simonette 5L390 5L175 5L283 Total Station Capacity 702T 10/13 MVA Peak MW 2010 7.3 1.1 4.6 1.5 7.3 PF 96% 92% 90% 98% 96% Peak MW 2011 8.1 1.1 5.0 1.6 8.1 Recorded Peak MW 2012 8.4 1.2 5.5 2.0 8.4 Peak MW 2013 9.4 1.2 5.6 3.1 9.4 Peak MW 2014 11.2 1.2 6.7 4.0 11.2 Peak MW 2015 14.4 1.2 9.5 4.6 14.4 Peak MW 2016 17.8 1.2 9.5 8.3 17.8 Peak MW 2017 17.8 1.2 9.5 8.3 17.8 Peak MW 2018 17.8 1.2 9.5 8.3 17.8 Predicted Peak Peak MW MW 2019 2020 17.8 17.8 1.2 1.2 9.5 9.5 8.3 8.3 17.8 17.8 Peak MW 2021 17.8 1.2 9.5 8.3 17.8 Peak MW 2022 17.8 1.2 9.5 8.3 17.8 Peak MW 2023 17.8 1.2 9.5 8.3 17.8 Peak MW 2024 17.8 1.2 9.5 8.3 17.8 Peak MW 2023 17.8 1.2 9.5 8.3 17.8 Peak MW 2024 17.8 1.2 9.5 8.3 17.8 Notes: Transformer capacity violations A coincidence factor of 0.94 was applied to the feeders Table A-4 – Simonette 733S Alternative 2 Load Forecast Sub No. 733S 733S Feeder Simonette 5L390 5L175 5L283 Total Station Capacity 702T 30/40/50 MVA PF 96% 92% 90% 98% 96% Peak MW 2010 7.3 1.1 4.6 1.5 7.3 Peak MW 2011 8.1 1.1 5.0 1.6 8.1 Recorded Peak MW 2012 8.4 1.2 5.5 2.0 8.4 Peak MW 2013 9.4 1.2 5.6 3.1 9.4 Peak MW 2014 11.2 1.2 6.7 4.0 11.2 Peak MW 2015 14.4 1.2 9.5 4.6 14.4 Peak MW 2016 17.8 1.2 9.5 8.3 17.8 Peak MW 2017 17.8 1.2 9.5 8.3 17.8 Peak MW 2018 17.8 1.2 9.5 8.3 17.8 Predicted Peak Peak MW MW 2019 2020 17.8 17.8 1.2 1.2 9.5 9.5 8.3 8.3 17.8 17.8 Peak MW 2021 17.8 1.2 9.5 8.3 17.8 Peak MW 2022 17.8 1.2 9.5 8.3 17.8 Notes: Transformer capacity violations A coincidence factor of 0.94 was applied to the feeders A new transformer would take approximately 3 years to be ordered and installed. This load forecast assumes that a new transformer will be installed for 2016. Table A-5 – Simonette 733S Alternative 3 Load Forecast Recorded Sub No. 733S Feeder Simonette 733S Simonette 5L390 5L175 5L283 Total Station 733S Capacity 702T 10/13 703T 30/40/50 MVA PF 96% 96% 92% 90% 98% 96% Predicted Peak MW Peak MW Peak MW Peak MW Peak MW Peak MW Peak MW Peak MW Peak MW Peak MW Peak MW Peak MW Peak MW Peak MW Peak MW 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 7.3 8.1 8.4 9.4 11.2 14.4 17.8 1.1 4.6 1.5 7.3 1.1 5.0 1.6 8.1 1.2 5.5 2.0 8.4 1.2 5.6 3.1 9.4 1.2 6.7 4.0 11.2 1.2 9.5 4.6 14.4 1.2 9.5 8.3 17.8 17.8 1.2 9.5 8.3 17.8 17.8 1.2 9.5 8.3 17.8 Notes: Transformer capacity violations A coincidence factor of 0.94 was applied to the feeders A new transformer would take approximately 3 years to be ordered and installed. This load forecast assumes that a new transformer will be installed for 2016. 11 17.8 1.2 9.5 8.3 17.8 17.8 1.2 9.5 8.3 17.8 17.8 1.2 9.5 8.3 17.8 17.8 1.2 9.5 8.3 17.8 17.8 1.2 9.5 8.3 17.8 17.8 1.2 9.5 8.3 17.8