Comments
Description
Transcript
APPENDIX A CONNECTION ASSESSMENT
APPENDIX A CONNECTION ASSESSMENT Engineering Study Report Tehrn©nt Connection to Enbndge Pipelines Inc. Proposed Battle Sands 594S Substation Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation AESO P 1558 Revision Date: October 15, 2015 Revision: 4 Name Prepared by: Reviewed Mahmud Rashid, P.Eng AshrafHaque, P.Eng. Ashikur Bhuiya, P.Eng. . Approved by: Data /5/Jo/2.olc CS/1i3 David King, P.Eng. Ashikur Bhuiya, REng. 6067.0O1.000.RevO4 [RevOO Issued: 2015-06-24) Prepared by: Teshmont Consultants LP 1190 Waverley Street Winnipeg, Manitoba, Canada R3T 0P4 www.teshmontcom Teshrnon& PERMIT TO PRACTICE TESHMO SULTANTSLP signature IS PERMIT NUMBER: P 03012 Date The Association of Professional Engineers, Geologists and Geophy’sicists of Alberta Signature 7PLi64 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation Executive Summary This study report describes the engineering connection analysis that was performed on the transmission alternative considered to connect Enbridge’s proposed Battle Sands 594S substation to the Alberta Interconnected Electricity System (AIES) in the Hardisty area. Project Overview Enbridge Pipelines Inc. has submitted a System Access Service Request to the Alberta Electric System Operator (AESO) requesting the reliable connection of Enbridge’s proposed 138/6.9 kV point-of-delivery substation to serve new 6.9 kV load in the Hardisty area (the Project). The proposed Enbridge substation, to be designated the Battle Sands 594S substation, will be located on Enbridge’s Hardisty terminal and will have a peak load of 26 MW. A Demand Transmission Service (DTS) capacity of 26 MW was not requested. Instead, the proposed Battle Sands 594S substation DTS will be totalized with Enbridge’s existing 60.3 MW DTS contract at the nearby Rosyth 296S and Clipper 656S substations. The requested project in-service date is July 1, 2017. Existing System The requested connection to the proposed Battle Sands 594S substation is located in Wainwright area (AESO Planning Area 32) in which the Hardisty 377S, Rosyth 296S, and Clipper 656S substations are located. The Rosyth 296S and Clipper 656S substations only serve Enbridge load. The Rosyth 296S substation is fed radially from the Hardisty 377S substation via the 138 kV transmission line 769L. The Clipper 656S substation is connected to the 138 kV transmission line 769L through a T-tap on the 138 kV transmission line 769AL. The Wainwright area is located in the Central East Sub-Region and consists primarily of 138 kV and 144 kV transmission lines. A 240/138 kV switching substation, the Nilrem 574S substation, located in the Wainwright area, functions as the primary source of supply in the area. The Wainwright area is connected through the transmission system to the Battle River / Alliance (AESO Planning Area 36), Lloydminster (AESO Planning Area 13), and Provost (AESO Planning Area 37) areas. The Central East Sub-Region is impacted by the Central East Region Transmission Development1 and Hanna Region Transmission Development Plan Stage 12 projects. 1 The Central East Region Transmission Development NID, as originally approved by AUC Decision 2011-048 and Approval No. U2011-57 2 The Hanna Region Transmission System Development NID, as originally approved by AUC Decision 2010-188 and Approval No. U2010-135 R(4) 2 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation Study Summary In order to identify existing system constraints, pre-connection power flow, voltage stability, and short-circuit analyses were performed. Short-circuit and motor starting analyses were performed after connection of the Project to identify post-connection system constraints and to evaluate whether the performance requirement of the Alberta Reliability Standards would be met under the studied scenarios. The Project connection will not impact Enbridge’s DTS, so post-connection power flow and voltage stability analyses are expected to yield the same results as the preconnection results. Therefore, the post-connection power flow and voltage stability analyses were not undertaken. The Study Area analyzed included Wainwright, and the nearby Battle River/ Alliance, Lloydminster, Provost, and Hanna areas. The study included all Category A, Category B, and selected Category C5 contingencies within the Study Area and the tie lines from the Study Area to the surrounding areas. All branches in the Study Area and the tie lines to the surrounding areas were monitored for thermal violations. All busses (69 kV and above) within the Study Area were monitored for voltage violations. Connection Alternative Selected for Study Of the four potential transmission connection configurations identified, only one alternative, Alternative 1 was selected for further study. The other three alternatives were ruled out either because of space constraints or because they would require more facilities and hence would result in higher capital costs than Alternative 1. Alternative 1 involves connecting the proposed Battle Sands 594S substation to the existing 138 kV transmission line 769L between the Rosyth 296S substation and the Clipper 656S substation T-tap (the 138 kV transmission line 769AL), by means of a Ttap configuration. Study Results The pre-connection power flow and the voltage stability analyses were performed for the 2017 summer peak (SP) and 2017 winter peak (WP) pre-connection scenarios. Motor starting analysis was performed for the 2017WP post-connection scenario. In addition, short-circuit analysis was performed for 2017WP pre-connection and postconnection scenarios, as well as 2024WP post-connection scenario. The Study results indicate: Pre-connection results: 1. No Category A, Category B, or selected Category C voltage violations were identified. 2. Category B thermal loadings violations were observed for the 2017SP and 2017WP pre-connection scenarios, under several Category B contingencies. R(4) 3 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation These thermal loading violations are existing and known to the AESO. They are currently being mitigated in real time by the AESO and Transmission Facilities Owner (TFO) operating practices. Post-connection results: 1. Short-circuit analysis showed that the Project connection will not negatively impact short-circuit current levels in the Study Area. 2. Motor starting analysis showed that the impact of “across-the-line” starting of one motor, in VFD bypass mode, is acceptable during both system normal and contingency conditions. Recommendation The engineering study indicates that Alternative 1 will not adversely impact the AIES in the Study Area. Based on these results, Teshmont recommends Alternative 1 to connect the proposed Enbridge Battle Sands 594S substation to the AIES. R(4) 4 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation Contents EXECUTIVE SUMMARY ................................................................................................ 2 Project Overview ..................................................................................................................................... 2 Existing System ...................................................................................................................................... 2 Study Summary....................................................................................................................................... 3 Connection Alternative Selected for Study .......................................................................................... 3 Recommendation .................................................................................................................................... 4 1. INTRODUCTION...................................................................................................... 8 1.1. Project .............................................................................................................................................. 8 1.1.1. Project Overview ..................................................................................................................... 8 1.1.2. Load Component ..................................................................................................................... 8 1.1.3. Generation Component ........................................................................................................... 9 1.2. Study Scope ..................................................................................................................................... 9 1.2.1. Study Objectives...................................................................................................................... 9 1.2.2. Study Area ............................................................................................................................... 9 1.2.3. Studies Performed ................................................................................................................. 11 1.3. 2. Report Overview ............................................................................................................................ 12 CRITERIA, SYSTEM DATA, AND STUDY ASSUMPTIONS ................................. 12 2.1. Criteria, Standards, and Requirements .......................................................................................... 12 2.1.1. Transmission Planning Standards and Criteria ..................................................................... 12 2.1.2. AESO Rules .......................................................................................................................... 14 2.2. Load and Generation Assumptions ................................................................................................ 14 2.2.1. Load Assumptions ................................................................................................................. 15 2.2.2. Generation and Intertie Flow Assumptions ........................................................................... 15 2.3. System Projects ............................................................................................................................. 16 2.4. Customer Connection Projects ...................................................................................................... 18 2.5. Additional Projects ......................................................................................................................... 19 2.6. Facility Ratings ............................................................................................................................... 19 2.7. Voltage Profile Assumptions .......................................................................................................... 22 3. STUDY METHODOLOGY ...................................................................................... 23 3.1. Study Objectives ............................................................................................................................ 23 3.2. Study Scenarios ............................................................................................................................. 23 3.3. Connection Studies Performed ...................................................................................................... 24 R(4) 5 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation 3.4. Power Flow Analysis ...................................................................................................................... 24 3.4.1. Contingencies Studied for Power Flow Analysis ................................................................... 24 3.5. Voltage Stability Analysis ............................................................................................................... 25 3.6. Short-Circuit Analysis ..................................................................................................................... 26 3.7. Motor Starting Analysis .................................................................................................................. 26 4. PRE-CONNECTION SYSTEM ASSESSMENT ..................................................... 26 4.1. Pre-Connection Power Flow Analysis ............................................................................................ 26 4.1.1. 2017SP Scenario .................................................................................................................. 26 4.1.2. 2017WP Scenario ................................................................................................................. 28 4.2. 5. 5.1. Voltage Stability Analysis ............................................................................................................... 29 CONNECTION ALTERNATIVES ........................................................................... 30 Overview ........................................................................................................................................ 30 5.2. Evaluation of Connection Alternatives ........................................................................................... 31 5.2.1. Connection Alternatives Eliminated....................................................................................... 31 5.2.2. Connection Alternative Selected for Further Studies ............................................................ 34 6. TECHNICAL ANALYSIS OF THE CONNECTION ALTERNATIVE ........................ 35 6.1. Power Flow Analysis ...................................................................................................................... 35 6.2. Voltage Stability Analysis ............................................................................................................... 36 7. SHORT-CIRCUIT ANALYSIS ................................................................................ 36 7.1. Pre-Connection Short-Circuit Analysis ........................................................................................... 36 7.2. Alternative 1 Post-Connection Short-Circuit Analysis .................................................................... 36 8. MOTOR STARTING ANALYSIS ............................................................................ 38 8.1. Motor Starting Assumptions ........................................................................................................... 39 8.2. Motor Starting Results for Alternative 1 ......................................................................................... 39 9. PROJECT INTERDEPENDENCIES ...................................................................... 40 10. SUMMARY AND CONCLUSION ........................................................................... 41 11. REVISION HISTORY ............................................................................................. 43 R(4) 6 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation Attachments Attachment A Pre-Connection Power Flow Single Line Diagrams Attachment B Pre-Connection Voltage Stability Results Attachment C Post-Connection (Alternative 1) Motor Starting Analysis Results Figures Figure 1-1: Wainwright Area Post-HRTD Stage One and CETD Development...................................................... 11 Figure 5-1: Alternative 2 – Radial Connection from Rosyth 296S (or Clipper 656S) Substation (connection to the Rosyth 296S substation shown) ......................................................................................................................... 32 Figure 5-2: Alternative 3 – In-and-Out Connection to 138 kV Transmission Line 769L ....................................... 33 Figure 5-3: Alternative 4 – In-and-Out Connection to 138 kV Transmission Line 703L ....................................... 34 Figure 5-4: Alternative 1 – T-Tap Connection to the 138 kV Transmission Line 769L ......................................... 35 Figure 8-1: Equivalent Circuit of Induction Motor ................................................................................................... 39 Tables Table 1-1: Study Area Transmission System Summary ...........................................................................................9 Table 2-1: Post-Contingency Voltage Deviation Guidelines .................................................................................. 14 Table 2-2: Studied Load Distribution between the Rosyth 296S, the Clipper 656S, and the proposed Battle Sands 594S Substations ........................................................................................................................................... 14 Table 2-3: Forecast Area Load ................................................................................................................................. 15 Table 2-4: Summary of Local Generators in the Study Case(s) ............................................................................. 15 Table 2-5: CETD Developments Included in the Connection Study ...................................................................... 16 Table 2-6: Summary of HRTD System Projects Not Included in the Connection Study, Stage 2 ........................ 17 Table 2-7: Summary of Relevant Facility Assumption included in the Connection Study, Market Participant Projects past Gate 2................................................................................................................................................... 18 Table 2-8: Summary of Key Transmission Lines in the Study Area. ..................................................................... 19 Table 2-9: Summary of Ratings of Key Transformers in the Study Area .............................................................. 21 Table 2-10: Summary of Key Shunt Elements in the Study Area ........................................................................... 21 Table 2-11: Summary of Voltages at Key Substation in the Study Area ............................................................... 22 Table 3-1: Contingencies Found in the Power Flow and the Voltage Stability Analyses .................................... 25 Table 4-1: 2017SP Pre-Connection Category B Line Loadings .............................................................................. 28 Table 4-2: 2017WP Pre-Connection Category B Transmission Line Loading....................................................... 29 Table 4-3: Worst Contingency Scenarios ................................................................................................................ 29 Table 7-1: Pre-Connection Short-Circuit Current Levels (2017WP) ....................................................................... 36 Table 7-2: Post-Connection Short-Circuit Current Levels for Alternative 1 (2017WP) ......................................... 37 Table 7-3: Post-Connection Short-Circuit Current Levels for Alternative 1 (2024WP) ......................................... 37 Table 8-1: Motor Nameplate and Calculated Data ................................................................................................... 38 Table 8-2: Equivalent Circuit Data ............................................................................................................................ 39 Table 8-3: Motor Starting Performance for Alternative 1 ........................................................................................ 40 R(4) 7 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation Introduction 1. This study report describes the engineering connection analysis that was performed on the transmission alternative considered to connect Enbridge’s proposed Battle Sands 594S substation to the Alberta Interconnected Electricity System (AIES) in the Hardisty area. 1.1. Project Project Overview 1.1.1. Enbridge Pipelines Inc. (the customer) submitted a System Access Service Request (SASR) to the Alberta Electric System Operator (AESO) requesting the connection of the proposed Enbridge 138/6.9 kV point-of-delivery (POD) substation, comprised of two 138/6.9 kV, 25/33.3 MVA transformers, located on Enbridge’s Hardisty terminal. In this report, the requested connection to the Enbridge’s proposed Battle Sands 594S substation will be referred to as “the Project”. The requested in-service date (ISD) for the Project is July 1, 2017. Load Component 1.1.2. The proposed facility includes 26 MW of new motor load. No additional Demand Transmission Service (DTS) has been requested as part of the Project. The AESO agreed to support Enbridge’s request for totalization of the proposed Battle Sands 594S substation DTS with Enbridge’s existing DTS at Rosyth 296S and Clipper 656S substations. 1.1.2.1. R(4) Proposed Battle Sands 594S Substation Project Load Details Existing Hardisty DTS: 60.3 MW totalized from Rosyth 296S and Clipper 656S substation loads. Request for the Hardisty DTS: 60.3 MW totalized from the proposed Battle Sands 594S, Rosyth 296S, and Clipper 656S substation loads. Peak Substation Load: 26 MW @ 0.95 power factor, to be included in the 60.3 MW DTS Load Type: Industrial motor / pump station Number of Motors: 4 @ 7000 HP each Future Allowance for Load Growth: Enbridge does not currently have future expansion plans to increase the load above 26 MW at the proposed Battle Sands 594S substation. 8 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation Generation Component 1.1.3. This project has no generation component. 1.2. Study Scope Study Objectives 1.2.1. The objectives of the study are the following: To assess the impact of connecting the Project on the AIES. To identify any system constraints that would prevent the granting of approval for the Project. To recommend the optimal connection point within the Study Area. 1.2.2. Study Area The Project is located in the Wainwright area (AESO Planning Area 32). The Study Area includes the Wainwright area and the following AESO Planning Areas: Battle River / Alliance (AESO Planning Area 36), Lloydminster (AESO Planning Area 13), Provost (AESO Planning Area 37), and Hanna (AESO Planning Area 42). Table 1-1: Study Area Transmission System Summary Area Number 1.2.2.1. Planning Area Name Voltage Range 32 Wainwright 69 kV to 240 kV 36 Battle River / Alliance 69 kV to 240 kV 13 Lloydminster 69 kV to 240 kV 37 Provost 138 kV to 240 kV 42 Hanna 69 kV to 240 kV Study Area Description The Project will be located approximately 4 km southeast of the Town of Hardisty in the Wainwright area. The Wainwright area is located in the AESO’s Central East SubRegion and consists primarily of 138 kV and 144 kV transmission systems. A 240/138 kV switching substation, the Nilrem 574S substation, functions as the primary source of supply in the Wainwright area. The area is connected to the AESO Planning Areas of Battle River/Alliance, Lloydminster, and Provost. R(4) 9 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation The Study Area is impacted by the Central East Region Transmission Development (CETD)3 and the Hanna Region Transmission Development Plan Stage 1 (HRTD)4 projects. The CETD consists of several 138/144 kV enhancements in the Wainwright and Lloydminster areas intended to serve increasing load and generation, as well as 240 kV and 144 kV enhancements in the Cold Lake area to serve oil sands expansions. Many of these developments are under construction and are expected to enter service by 2017. However, due to changes in forecast assumptions and system conditions, especially those related to the proposed wind generation connections in the eastern part of the region, the AESO has reassessed the need for approved facilities in the CETD as part of its regional plan assessments. The Central East Sub-Regional Plan is a part of the published AESO 2013 Long-term Transmission Plan (2013 LTP).5 Currently, the Hanna region transmission system is being upgraded in accordance with the HRTD to ensure that there is adequate capacity and reliability of supply for the growing load in the area. As part of the HRTD, new 240 kV and 138 kV transmission lines will be built and some existing 138/144 kV and 69/72 kV transmission lines will be decommissioned. All of the facilities included in the HRTD Stage 1 are already in service. The AESO is re-assessing the HRTD Stage 2 and will file necessary components in the future. An area map of the transmission system near the Project (excluding the HRTD Stage 2) is shown in Figure 1-1. The closest existing substations to the Project are Rosyth 296S and Clipper 656S substations, both approximately 1 km to the north of the proposed Battle Sands 594S substation location. The Rosyth 296S substation is fed radially from the Hardisty 377S substation via the 138 kV transmission line 769L. The Clipper 656S substation is connected to the 138 kV transmission line 769L through a T-tap on the 138 kV transmission line 769AL. 1.2.2.2. Existing Constraints The existing constraints in the Study Area are currently managed by the following planned and installed Remedial Action Scheme (RAS): 1. Battle River 7L50 and 7L701 TPS 2. RAS #134: 174L-395S North Holden overload mitigation scheme 3. RAS #138: 7L50 -526S Buffalo Creek overload mitigation scheme 4. RAS #139: 901T-766S Nevis overload mitigation scheme 5. EATL RAS for 912L and 9L20 contingencies 3 The Central East Region Transmission Development NID, as originally approved by AUC Decision 2011-048 and Approval No. U2011-57 4 The Hanna Region Transmission System Development NID, as originally approved by AUC Decision 2010-188 and Approval No. U2010-135 5 Available on the AESO website at: http://www.aeso.ca/downloads/AESO_2013_LongtermTransmissionPlan_Web.pdf R(4) 10 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation 1.2.2.3. AESO Long-Term Plans The system development projects which impact the Study Area are defined in the CETD. More details regarding the CETD projects and their in-service dates are presented in Table 2-5 in Section 2.3. The AESO published its 2013 LTP, which included its Central Region Plan in 2014. The Central Region Plan includes new 240 kV transmission lines and substations to alleviate the existing congestion and to facilitate the new wind generation interest in the Central Region. The AESO will file the related Needs Identification Documents (NID) with the Alberta Utilities Commission (AUC) in 2016. These plans do not impact the Project study results. Figure 1-1: Wainwright Area Post-HRTD Stage One and CETD Development 1.2.3. Studies Performed The following pre-connection analyses were performed: R(4) 11 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation Power flow analysis (Category A, Category B, and selected Category C5 for 2017 Summer Peak (SP) and 2017 Winter Peak (WP) load scenarios) Voltage stability analysis (Category A, Category B, and selected Category C5 for 2017WP load scenarios) Short-circuit analysis (with all generators in service for 2017WP) The following analyses were performed for the post-connection analysis: Short-circuit analysis (with all generators in service for 2017WP and 2024WP) Motor starting analysis (Category A, Category B, and selected Category C5 for 2017WP load scenarios) 1.3. Report Overview The Executive Summary provides a high-level summary of the report and its conclusions. Section 1 provides an introduction of the Engineering Study Report. Section 2 describes the reliability criteria, system data, and other study assumptions used in this report. Section 3 describes the study methodology. Section 4 discusses the pre-connection power flow and voltage stability analysis of the system. Section 5 presents the connection alternatives considered and studied. Section 6 discusses the power flow and voltage stability analysis of the connection alternative selected for further study. Section 7 presents the short-circuit analysis results. Section 8 shows the motor start analysis results. Section 9 discusses project interdependencies. Section 10 presents the summary and conclusions of this engineering study. Criteria, System Data, and Study Assumptions 2. 2.1. 2.1.1. Criteria, Standards, and Requirements Transmission Planning Standards and Criteria The Transmission Planning (TPL) Standards, which are included in the Alberta Reliability Standards, and the AESO’s Transmission Planning Criteria – Basis and Assumptions (Reliability Criteria) were applied to evaluate system performance under Category A system conditions (i.e., all elements in-service) and following Category B contingencies (i.e., single element outage), prior to and following the studied alternatives. Below is a summary of Category A and Category B system conditions as well as a summary of Category C5 system conditions. Category A, often referred to as the N-0 condition, or N-G with the most critical generator out of service, represents a normal system with no contingencies and all facilities in service. Under this condition, the system must be able to supply all firm load R(4) 12 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation and firm transfers to other areas. All equipment must operate within its applicable rating, voltages must be within their applicable range, and the system must be stable with no cascading outages. Category B events, often referred to as an N-1, or N-G-1 with the most critical generator out of service, result in the loss of any single specified system element under specified fault conditions with normal clearing. These elements are a generator, a transmission circuit, a transformer, or a single pole of a DC transmission line. The acceptable impact on the system is the same as Category A. Planned or controlled interruptions of electric supply to radial customers or some local network customers, connected to or supplied by the faulted element or by the affected area, may occur in certain areas without impacting the overall reliability of the interconnected transmission systems. To prepare for the next contingency, system adjustments are permitted, including curtailments of contracted firm (non-recallable reserved) transmission service electric power transfers. Category C5 events result in loss of two circuits of a multiple circuit tower. All equipment must operate within its applicable rating, voltages must be within their applicable range, and the system must be stable with no cascading outages. For Category C5, the controlled interruption of electric supply to customers (load shedding), the planned removal from service of certain generators, and/or the curtailment of contracted firm (non-recallable reserved) transmission service electric power transfers may be necessary to maintain the overall reliability of the interconnected transmission systems. The TPL standards, TPL-001-AB-0, TPL-002-AB-0, and TPL-003-AB-0 reference Applicable Ratings when specifying the required system performance under Category A, Category B, and Category C events. For the purpose of applying the TPL standards to the studies documented in this report Applicable Ratings are defined as follows: Applicable Rating refers to the applicable normal and emergency facility thermal and voltage rating, as applied by the facility owner, or to the system voltage limit, as determined and consistently applied by the ISO. Applicable ratings may include emergency ratings applicable for short durations as required to permit the operating steps necessary to maintain system control. All ratings must be established by the applicable entity consistent with applicable ISO rules addressing facility ratings. For Category A conditions: Voltage range under normal operating condition is in accordance with AESO Information Document ID# 2010-007RS, General Operating Practice – Voltage Control. For Category B conditions: The extreme voltage range, as applicable, is taken from Table 2-1 in the Transmission Planning Criteria – Basis and Assumptions. The acceptable post-contingency voltage change limits for three defined post-event timeframes are as provided in Table 2-1 below. R(4) 13 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation The post-contingency voltage deviations following Category B events were compared with the guidelines in Table 2-1 below. Table 2-1: Post-Contingency Voltage Deviation Guidelines Time Period Parameter and Reference Point Post-Transient Post-Auto Control Post-Manual Control (up to 30 sec) (30 sec to 5 min) (Steady State) ±10% ±7% ±5% Voltage deviation from steady state at POD low voltage bus. 2.1.2. AESO Rules The AESO Information Document ID # 2010-007RS will be applied to establish precontingency voltage profiles in the study region. The Section 302.1 of the ISO rules, Real Time Constraint Management (the TCM Rule) will be followed in setting up the study scenarios and assessment of the connection impact. In addition, due regard will be given to the AESO Customer Connection Study Requirements Document and the Generation and Load Interconnection Standard. The Reliability Criteria is the basis for planning the AIES. The transmission system will normally be designed to meet or exceed the Reliability Criteria under credible worstcase loading and generation conditions. 2.2. Load and Generation Assumptions Studies were conducted for 2017SP and 2017WP scenarios to align with the requested ISD of July 1, 2017. The AESO Planning Base Case Suite was used to develop the study cases. The 2024WP scenario was considered to calculate short-circuit current levels for 2024. Table 2-2 shows the load distribution amoung the Rosyth 296S, the Clipper 656S, and the proposed Battle Sands 594S substations for pre-connection and post-connection scenarios considering the total DTS of 60.3 MW. Table 2-2: Studied Load Distribution between the Rosyth 296S, the Clipper 656S, and the proposed Battle Sands 594S Substations Load @ Scenario Year / Condition Load @ Clipper 656S Load @ Rosyth 296S (MW DTS) (MW DTS) Proposed Battle Sands 594S Total Load (MW DTS) (MW DTS) 2017SP PreConnection* 2017SP 15.1 45.2 0 60.3 2017WP PreConnection* 2017WP 15.1 45.2 0 60.3 2017WP PostConnection* 2017WP 12 22.3 26 60.3 R(4) 14 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation * 2017 Scenarios were considered without the HRTD Stage 2 system developments. 2.2.1. Load Assumptions The forecasted SP and WP load levels for the relevant study years from the AESO 2014 Long-term Outlook is presented in Table 2-3. The ratio of active power to reactive power in the study cases was maintained when scaling of the loads was required. Table 2-3: Forecast Area Load Area Name and Number Central Region* Alberta Internal Load without losses Season Year Forecast Peak Load (MW) Summer 2017 1,602 Winter 2017 1,847 Winter 2024 2,153 Summer 2017 11,440 Winter 2017 12,796 Winter 2024 15,532 *The Central Region comprises of the following AESO Planning Areas: 13, 29, 30, 32, 34, 35, 36, 37, 38, 39, 42, and 56 2.2.2. Generation and Intertie Flow Assumptions One of the major sources of power supply to the Study Area is the Battle River Generation Plant located in the Battle River / Alliance area. Table 2-4 shows the dispatch from the Battle River generators for different seasons and study years. The selection of one Battle River unit out of service was determined as the most critical unit for an N-G condition. This unit is out of service for power flow and voltage stability studies. All the remaining generators were dispatched based on economic merit in accordance with the generation dispatch provided by the AESO. Table 2-4: Summary of Local Generators in the Study Cases Name Units Generation Level Modelled in the Study Case (MW) 2017SP 2017WP Battle River 3 153 153 Battle River 4 163 163 Battle River 5 OFF OFF Power import through the intertie with British Columbia had no impact on this study and therefore the intertie assumptions used were consistent with that in the AESO base cases. The intertie with Saskatchewan was considered at zero. The study case R(4) 15 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation assumed no wind as the most stressed case and consequently all wind generation in the Study Area was set offline. 2.3. System Projects Table 2-5 lists the approved CETD plan, which was considered in the study. Table 2-5: CETD Developments Included in the Connection Study R(4) Subproject Name and Description Scheduled ISD / Complete / Cancelled Project Subproject 811 1 Bourque 970S Substation (Partial Stage 1) Complete 811 1 Bourque 970S Substation (Partial Stage 2) Complete 811 2 138 kV transmission line 7L146 from Bonnyville 700S Substation to Bourque 970S substation Complete 811 3 St. Paul Area Upgrades - Watt Lake 956S substation Complete 811 4 St. Paul Upgrades St. Paul 707S substation and the 138 kV transmission lines 7L139/ 7L70 in and out April 2016 811 5 Vermillion 710S Substation Upgrade Complete 811 6 Heisler Area Upgrades Complete 811 7 Kitscoty 705S substation and 138 kV transmission lines 7L14 and 7L130 in and out Complete 811 9 144 kV transmission line 7L701 Line Clearance Mitigation Complete 811 10 144 kV Transmission Line 7L157 from the Bourque 970S substation to the Mahihkan 837S substation Complete 811 11 138 kV transmission line 7L574 from the Bourque 970S substation to the Wolf Lake 822S substation Complete 811 12 138 kV transmission line 7L583 from Bourque 970S substation to the Leming Lake 715S substation Complete 811 13 144 kV transmission line 7L160 from the Bourque 970S substation to the Mahihkan 837S substation Complete 811 14 St. Paul Area Upgrades – 138 kV transmission line 7LA92 T-tap to Watt Lake 956S substation Complete 811 16 138 kV transmission line 7L24 Termination at the Bonnyville 700S substation Complete 16 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation Scheduled ISD / Complete / Cancelled Project Subproject Subproject Name and Description 811 20 144 kV transmission line 7L587 from the Marguerite Lake 826S substation to the Wolf Lake 822S substation Complete 811 22 138 kV transmission line 7L14 Line Clearance Mitigation Cancelled 811 23 138 kV transmission line 7L53/7L117 Line Clearance Mitigation Cancelled 811 24 St. Paul Area Upgrades - Whitby Lake 819S Circuit Breaker addition June 2014 811 25 Bonnyville 700S substation Transformer addition April 2016 811 26 Kitscoty 69 kV transmission line 6L06 Decommission Complete 811 27 New 138 kV transmission line 408L from the Jarrow 252S substation to the Wainwright 51S substation Cancelled Table 2-6 lists the HRTD Stage 2 system reinforcement project developments. The HRTD Stage 2 developments were not considered in the 2017 study scenarios. Table 2-6: Summary of HRTD System Projects Not Included in the Connection Study, Stage 2 Project Subproject Subproject Name and Description Scheduled ISD 1113 1 Energization 1 - 240 kV D/C transmission line 9L49 from the Cordel 755S substation to the Halkirk 401S substation Q2 2017 1113 2 Energization 2 - 240 kV D/C transmission line 9L31 from the Oakland 946S substation to the Coyote Lake 963S substation - second side strung Q2 2017 1113 3 Energization 3 - 240 kV D/C transmission line 9L65 from the Oakland 946S substation to the Lanfine 959S substation - String second side Q2 2017 1113 4 Energization 4 - Convert the existing 72 kV Hanna 763S substation to a 144 kV substation and add a new 144 kV transmission line 7L108L from the Coyote Lake 963S substation to the upgraded Hanna 763S substation Q2 2017 1113 5 Energization 5 - Pemukan 932S substation – add a second 240/144 kV, 300 MVA transformer Q2 2017 1113 6 Energization 6 - Lanfine 959S substation – add a second 240/144 kV, 300 MVA transformer Q2 2017 1113 7 Energization 7 - Youngstown 772S substation - 5 MVAr Q2 2017 R(4) 17 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation Project Subproject Subproject Name and Description Scheduled ISD Capacitor Bank 1113 9 Energization 9 - Metiskow 648S substation – add one 27 MVAr (138 kV) capacitor bank Q2 2017 1113 10 Energization 10 - Hansman Lake 650S substation – add a second 240/144 kV - 200 MVA transformer Q2 2017 1113 11 Energization 11 - Hansman Lake 650S substation – add two 36 MVAr (240 kV) and one 27 MVAr (138 kV) capacitor banks Q2 2017 1113 12 Energization 12 - Coronation 773S substation- add 2.4 MVAr (25 kV) capacitor bank Q2 2017 1113 13 Energization 13 - Nilrem 574S substation – add two 27 MVAr (138 kV) capacitor banks Q2 2017 Notes: 1. As Part of HRTD Stage 2, 138 kV transmission line 7L224 will be open at Monitor 774S substation, and 144 kV transmission line 7L141 will be energized. Based on the AESO 2013 LTP, 72 kV transmission line 6L56 (between Hanna 763S and Michichi Creek 802S substations) will still be required after HRTD Stage 2. 2. 138 kV transmission Line 7L760 will no longer be open at Oyen 767S substation after HRTD Stage 2. 2.4. Customer Connection Projects Table 2-7 shows the new load connection projects that passed Gate 2 and can be found on the AESO’s website. Table 2-7: Summary of Relevant Facility Assumption included in the Connection Study, Market Participant Projects past Gate 2 Project No Project Name Planning Area Generation (MW) Load (MW) MW Type 851 TransCanada Keystone KXL Pump station #2-Eyre 37-Provost 0.0 25.0 Load 863 TransCanada Keystone KXL Pump station #3Current 42- Hanna 0.0 25.0 Load 864 TransCanada Keystone KXL Pump station #4Armitage 42- Hanna 0.0 25.0 Load 1319 ATCO 774S Monitor Substation Upgrades 42-Hanna 0.0 4.3 Load Feb 10, 2015 1366 Enbridge Sunken Lake 221S Substation Expansion 37-Provost 0.0 14 Load Jun 2014 1284 Nilrem 574S Substation 32- 0.0 24.1 Load Dec 1, R(4) 18 Scheduled/ Actual ISD Jan 1, 2017 (on hold) Jul 2, 2016 (on hold) Jul 1, 2016 (on hold) Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation Project No Planning Area Project Name Expansion (formerly Lagstaff) Generation (MW) Load (MW) MW Type Wainwright Scheduled/ Actual ISD 2014 1390 Fortis Tucuman 478S Substation-25KV Breaker Addition 32Wainwright 0.0 41.7 Load Aug 2014 1454 Fortis Tucuman 478S Substation-T2 25KV Feeder Breaker Addition 32Wainwright 0.0 12.4 Load Nov 2014 1495 Fortis Hayter 277S Substation 42 MVA Transformer and 25 kV Breaker Add. 37-Provost 0.0 0.0 Equipment Change Sep 16, 2015 1311 ATCO Irish Creek 706S Substation Upgrades 13Lloydminster 0.0 7.3 Load Nov 2014 2.5. Additional Projects Apart from those specified in Section 2.4, no other market participant facilities prior to Gate 2 need to be included in the study cases. 2.6. Facility Ratings Table 2-8 shows key transmission lines in the Study Area operating at 69 kV and above. Table 2-8: Summary of Key Transmission Lines in the Study Area Nominal Voltage (kV) Transmission Line 138 769L Hardisty 377S 138 769L 138 769AL 138 703BL 138 703L 138 885L 138 749L R(4) Summer Rate (MVA) Winter Rate (MVA) Emergency Summer Rate (MVA) Emergency Winter Rate (MVA) Clipper Tap Point 86 115 95 127 Rosyth 296S Clipper Tap Point 86 115 95 127 Clipper 656S Clipper Tap Point 122 150 134 165 Express Tap Point 123 150 135 165 83 83 83 83 287 287 287 287 121 148 133 163 From HRT Express 329S Hardisty 377S Metiskow 648S Metiskow 648S To Express Tap Point Hansman Lake 650S Killarney Tap Point 19 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation Nominal Voltage (kV) Transmission Line 138 703L 138 703L 138 703L 138 715L 240 954L 138 703AL 138 748L 138 749AL 138 7L224 240 9L948/948L 240 1047L 240 9L966 138 749L 138 749L/7L749 138 7L749 138 7L42 138 7L14 138 R(4) 7L130 Summer Rate (MVA) Winter Rate (MVA) Emergency Summer Rate (MVA) Emergency Winter Rate (MVA) 122 143 134 162 122 147 134 162 121 145 133 160 98 132 108 145 333 333 499 499 85 90 94 99 Hayter 277S 119 146 131 161 Edgerton 899S 121 148 133 163 109.25 138.9 9 123.63 150.5 PaintEarth 863S 332 332 432 432 Nilrem 574S 499 499 680 748 332 332 432 432 121 149 133 164 88 96 97 140 109.25 138.9 9 123.6 150.45 Hill 751S 94.88 94.88 123.63 123.63 Kitscoty 705S 71.88 86.25 71.88 86.25 Vermilion 710S 71.88 86.25 71.88 86.25 From To Metiskow 648S Hughenden 213S Hughenden 213S Provost 545S Metiskow 648S Sunken Lake 221S Killarney Lake 267S Killarney Lake 267S Hansman Lake 650S Hansman Lake 650S Hansman Lake 650S Hansman Lake 650S Killarnery Ttap Edgerton 899S Briker Tap Point Lloydminster 716S Hill 751S Kitscoty 705S 703AL Tap Point Express Tap Point 703AL Tap Point Hansman Lake 650S Hansman Lake 650S 703AL Tap Point Monitor 774S Pemukan 932S Metiskow 648S Briker Tap Point Lloydminster 716S 20 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation Table 2-9 shows the key transformers in the Study Area. Table 2-9: Summary of Ratings of Key Transformers in the Study Area Transformers Transformer ID Transformer Voltages (kV) Rating (MVA) Metiskow 648S T3 240/138 200 Hansman Lake 650S T1 240/138 200 Nilrem 574S T1 240/138 400 Nilrem 574S T2 240/138 400 T1/T2 138/25 42 Substation Name and Number Tucuman 478S Table 2-10 shows the relevant key shunt elements in the Study Area. Table 2-10: Summary of Key Shunt Elements in the Study Area Capacitors Substation Name and Number Nominal Bus Voltage (kV) Reactors Number of Switched Shunt Blocks Total at Nominal Voltage (MVAr) Number of Switched Shunt Blocks Total at Nominal Voltage (MVAr) Amoco Empress 163S 138 2x24.35 48.70 - - McNeil 840S 138 2x24.80 49.6 - - Tilley 498S 138 1 27.17 - - 138 2x27.55 55.1 - - 34.5 (SVC) 1x200 200 1x-100 -100 Stettler 769S 138 1 13.78 - - Michichi Creek 802S 138 1 9.18 - - Youngstown 772S 69/25 1x4.6+1x2.4 7 - - Hanna 763S 25 1 4.95 - - Sullivan Lake 775S 69 1 9.19 - - Bull Pound 803S 25 2 2x2.4 - - Battle River 757S 69 1x9.19 9.19 - - Three Hills 770S 138/25 1x18.37/1x4.95 - - Lanfine 959S R(4) 21 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation Capacitors Substation Name and Number Nominal Bus Voltage (kV) Reactors Number of Switched Shunt Blocks Total at Nominal Voltage (MVAr) Number of Switched Shunt Blocks Total at Nominal Voltage (MVAr) Hansman Lake 650S 18.0 (SVC) 1x200 200 1x-100 -100 Hardisty 377S 138 1x27+1x44.9 71.9 - - Killarney Lake 267S 138 1x9.1+2x10.9 30.9 - - Tucuman 478S 138 1x27.17 27.17 - - Pemukan 932S 138 2x27.55 55.1 - - Sunken Lake 221S 138 1x18.10 18.10 - - Monitor 774S 138 1x18.38+1x27.55 45.93 - - Hill 751S 138 1x18.12 + 1x22.96 41.08 - - Lloydminster 716S 138 1x18.12 18.12 - - Vermilion 710S 138 1x22.96 22.96 - - 2.7. Voltage Profile Assumptions The typical voltage set-point for Hansman Lake 650S substation Static VAR Compensator (SVC) is 253 kV and the normal operating range is -20 to 20 MVAr. The typical Lanfine 959S substation SVC set-point is 258 kV with the same MVAr range. The AESO Information Document ID# 2010-007RS was used to establish normal system (i.e. pre-contingency) voltage profiles for all busses in the Study Area prior to commencing any studies. All bus voltages in the Study Cases were established in the ‘Desired Range’ column of this document. A selection of the key substation voltage ranges from this ID is listed in Table 2-11. Voltage standards listed in Table 2-11 are applied where the ID does not specify voltage ranges for the study region bus nodes. Table 2-11: Summary of Voltages at Key Substation in the Study Area R(4) Substation Names and Number Nominal Voltage (kV) Minimum Operating Limit (kV) Desired Range (kV) Maximum Operating Limit (kV) Battle River 757S 144 144 146 - 150 155 22 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation Substation Names and Number Nominal Voltage (kV) Minimum Operating Limit (kV) Desired Range (kV) Maximum Operating Limit (kV) Cordel 755S 240 253 254 - 257 260 240 246 248 - 255 265 144 145 149 -152 155 Oyen 767S 144 140 143 - 146 155 Killarney Lake 267S 138 138 138-144 145 240 250 250-260 260 138 140 140-144 145 Hardisty 377S 138 140 140-144 145 Lloydminster 716S 138 137 142 - 149 151 Nevis 766S Metiskow 648S Study Methodology 3. All studies were performed using the PSS/E software Version 33. 3.1. Study Objectives The objective of this study was to analyze the impacts of connecting the Project to the transmission system upon the following parameters: Thermal loading of the branches/transformers in the Study Area under Category A, Category B, and selected Category C5 contingency conditions Voltage profile of the Study Area under Category A, Category B, and selected Category C5 contingency conditions Voltage stability of the Study Area busses under the increased loading condition Short-circuit analysis Maximum voltage dip under “across-the-line” starting of one motor at the proposed Battle Sands 594S substation without a Variable Frequency Drive (VFD) 3.2. Study Scenarios The following load scenarios were selected for the Project analyses: R(4) 2017SP – Pre-connection System 23 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation 2017WP – Pre-connection System 2017WP – Post-connection System 2024WP – Post-connection System The pre-connection system is defined as the 2017 system configuration immediately prior to the connection of the Project. The post-connection system is defined as the 2017 system configuration immediately following the connection of the Project and the post-connection system in 2024. 3.3. Connection Studies Performed The following pre-connection analyses were performed: Power flow analysis (Category A, B, and selected Category C5 for 2017SP preconnection and 2017WP pre-connection scenarios) Voltage stability analysis (Category A, B, and selected Category C5 for 2017WP pre-connection scenarios) Short-circuit analysis (with all generators on, for 2017WP) The following studies were performed for the post-connection analysis: 6 Short-circuit analysis (with all generators on, for 2017WP and 2024WP) Motor starting analysis (Category A, B, and selected Category C5 for 2017WP post-connection scenarios) 3.4. Power Flow Analysis Pre-connection power flow analysis was performed to assess the system performance for Category A, Category B, and selected Category C5 contingencies within the Study Area and for the tie lines from the Study Area to the surrounding areas. All branches in the Study Area at 69 kV and above and all tie lines to the surrounding areas were monitored for thermal violation. All busses within the Study Area at 69 kV and above were monitored for voltage violation. 3.4.1. Contingencies Studied for Power Flow Analysis The study included all Category B and selected Category C5 contingencies (69 kV and above) within the Study Area and for the tie lines from the Study Area to the surrounding areas shown in Table 3-1. 6 The Project connection will not impact the customer DTS; therefore, post-connection power flow analysis was not undertaken. R(4) 24 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation Table 3-1: Contingencies Found in the Power Flow and the Voltage Stability Analyses System Condition Contingency From Substation To Substation Category B (N-1) 7L130 Vermillion 710S Kitscoty 705S Category B (N-1) 7L14 Kitscoty 705S Hill 751S Category B (N-1) 749L Metiskow 648S Edgerton 899S Category B (N-1) Edgerton 899S - T3 Edgerton 899S Edgerton 899S Category B (N-1) 681L Hardisty 377S Tucuman 478S Category B (N-1) 702L/7L702 Hardisty 377S Battle River 757S Category B (N-1) 703L/703BL/703AL Metiskow 648S Sunken Lake 221S/Hardisty 377S Category C5 (N-2) 9L953/953L/1047L Nilrem 574S Hansman Lake 650S/Cordel 755S Category C5 (N-2) 679L/680L Nilrem 574S Tucuman 478S 3.5. Voltage Stability Analysis The objective of the voltage stability analysis is to determine the ability of a power system to maintain acceptable voltages at the busses in the system under normal conditions and after being subjected to a contingency. In the study, PV (Power-Voltage) voltage stability analysis was performed according to the Western Electricity Coordinating Council (WECC) Voltage Stability Assessment Methodology, as described in detail in the AESO Alberta Reliability Standards. The reference load level is the forecasted peak load level. The WECC voltage stability criteria states, “for load areas, post-transient voltage stability is required for the area modelled at a minimum of 105% of the reference load level for the system normal conditions (Category A) and for single contingencies (Category B). For multiple contingencies (Category C), post-transient voltage stability is required with the area modelled at a minimum of 102.5% of the reference load level.”7 The studies were performed using the PV method as follows: The PV analysis was performed by increasing load in the Wainwright area and increasing generation in the areas remote from the Study Area (i.e., AESO Planning Areas 6, 30, 33, 35, 40, 43, 53, 54, 55, 57 and 60). The analysis was performed with all discrete switched capacitors and reactors, LTC transformers and phase shifting transformers locked. 7 System Performance Regional Business Practice, TPL–001–WECC–RBP–2.1, developed by Western Electricity Coordinating Council (WECC), https://www.wecc.biz/Reliability/TPL-001-WECC-RBP-2.1.pdf R(4) 25 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation Results were generated for the Category A, Category B, and selected Category C5 contingencies and the worst-case contingencies as identified by power flow studies. 3.6. Short-Circuit Analysis All generators in Study Area and the neighboring area were switched on to evaluate the maximum fault current under three-phase and single-line-to-ground faults for the shortcircuit analysis. The automatic sequencing fault calculation function in PSS/E 33 was used to perform the study. 3.7. Motor Starting Analysis Motor starting analysis was performed for the proposed motors under system normal (Category A) conditions and worst case contingencies identified in the voltage stability and power flow analyses. The analysis considered the starting of one motor, with its VFD out of service, while the other motors were running at full load. Pre-Connection System Assessment 4. 4.1. Pre-Connection Power Flow Analysis The steady-state performance was assessed under the 2017SP and 2017WP preconnection scenarios. The power flow analyses were based on the Reliability Criteria, System Data and Study Assumptions as described in Section 2. 4.1.1. 2017SP Scenario The steady state performance of the system under normal conditions (Category A), single contingency (Category B), and selected Category C5 contingencies was assessed using the 2017SP pre-connection scenario. Results for System Normal Category A: No thermal loading or voltage violation was observed for the 2017SP pre-connection scenario. Results for System Category B and Selected Category C5: No voltage violation was observed for the 2017SP pre-connection scenario. A number of thermal loadings above the continuous 100% thermal limit were observed for the 2017SP pre-connection scenario under several Category B contingencies and consist of the following: R(4) 26 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation The 2017SP case with the contingency of Metiskow 648S substation transformer T1 did not converge in the PSS/E simulation. There are no breakers separating the AIES from T1. As a result, the transformer contingency will trip the 138 kV transmission lines 749L, 703L, and 885L simultaneously. This contingency would cause loss of load in the local area and is currently managed by the AESO and TFO real time operating practices. The 138 kV transmission line 749L (Metiskow 648S to the Killarney Tap Point) shows a thermal loading of 108.5% for the contingency of 138 kV transmission line 7L130 (from the Vermillion 710S substation to the Kitscoty 705S substation). This is below the emergency rating of the 138 kV transmission line 749L. This thermal loading is mitigated in real time by the AESO and TFO operating practices. The 138 kV transmission line 749L also shows a thermal loading of 105.6% when there is an outage to the 138 kV transmission line 7L14 (from the Kitscoty 705S substation to the Hill 751S substation). This is below the emergency rating of the 138 kV transmission line 749L.This thermal loading is mitigated in real time by the AESO and TFO operating practices. The 138 kV transmission line 7L130 (from the Vermillion 710S substation to the Kitscoty 705S substation) shows a thermal loading of 112.1% for the contingency of the 138 kV transmission line 749L (from the Metiskow 648S substation to the Edgerton 899S substation). This is above the emergency rating of the 138 kV transmission line 7L130. Under this contingency, the area load is fed radially through line 138 kV transmission line 7L130. This thermal loading will be mitigated in real time by the AESO and TFO operating practices. The 138 kV transmission line 7L14 (from the Kitscoty 705S substation to the Hill 751S substation) shows a thermal loading of 105.5% for the contingency of 138 kV transmission line 749L (from the Metiskow 648S substation to the Edgerton 899S substation). This is above the emergency rating of the 138 kV transmission line 7L14. Under this contingency, the area load is fed radially through the 138 kV transmission line 7L14. This thermal loading is mitigated in real time by the AESO and TFO operating practices. The 138 kV transmission lines 7L130 and 7L14 also show thermal loadings of 106.2% and 100.9%, respectively for the contingency Edgerton 899S substation transformer T3. These thermal loadings are above the emergency ratings (see Table 2-8). Under this contingency, the area load is fed radially through line 138 kV transmission lines 7L130 and 7L14. This thermal loading will be mitigated in real time by the AESO and TFO operating practices. The results of the power flow analysis are shown in Table 4-1. The power flow single line diagrams (SLDs) are presented in Attachment A. R(4) 27 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation Table 4-1: 2017SP Pre-Connection Category B Line Loadings 2017SP Pre-Connection Contingency Category B: 138 kV transmission line 7L130 (Vermillion 710S substation to Kitscoty 705S substation) Category B: 138 kV transmission line 7L14 (Kitscoty 705S substation to Hill 751S substation) Category B: 138 kV transmission line 749L (Metiskow 648S substation to Edgerton 899S substation) Category B: Edgerton 899S substation Transformer T3* Branch Nominal Line Rating (MVA) Power Flow (MVA) % Loading 749L (Metiskow 648S substation to Killarney Tap Point) 120.9 131.2 108.5 749L (Metiskow 648S substation to Killarney Tap Point) 120.9 127.7 105.6 71.9 80.6 112.1 71.9 75.9 105.5 71.9 76.4 106.2 71.9 72.6 100.9 7L130 (Vermillion 710S substation to Kitscoty 705S substation) 7L14 (Kitscoty 705S substation to Hill 751S substation) 7L130 (Vermillion 710S substation to Kitscoty 705S substation) 7L14 (Kitscoty 705S substation to Hill 751S substation) * The transformer does not have a high side breaker and will trip the high voltage bus, taking several transmission lines out of service. 4.1.2. 2017WP Scenario The steady state performance of the system under normal conditions, single contingency and selected Category C5 contingency was assessed using the 2017WP pre-connection scenario. Results for System Normal Category A: No thermal loading or voltage violation was observed for the 2017WP pre-connection scenario. Results for System Category B and Selected Category C5: No voltage violation was observed for the 2017WP pre-connection scenario. Thermal loading above the continuous 100% thermal limit was observed for the 2017WP pre-connection scenario and consists of the following: R(4) The 2017WP case with the contingency of Metiskow 648S substation transformer T1 did not converge in the PSS/E simulation. There are no breakers separating the AIES from T1. As a result, the transformer contingency will trip the 138 kV transmission lines 749L, 703L, and 885L simultaneously. This contingency would 28 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation cause loss of load in the local area and is currently managed by the AESO and TFO real time operating practices. The 138 kV transmission line 7L130 (from the Vermillion 710S substation to the Kitscoty 705S substation) shows thermal loading of 103.7% for the contingency of the 138 kV transmission line 749L (from Metiskow 648S substation to Edgerton 899S substation). This line loading is above the emergency rating of the 138 kV transmission line 7L130. Under this contingency the area load is fed radially through the 138 kV transmission line 7L130. This thermal loading is mitigated in real time by the AESO and TFO operating practices. The results of the 2017WP pre-connection scenario power flow analysis are shown in Table 4-2. The power flow SLDs are presented in Attachment A. Table 4-2: 2017WP Pre-Connection Category B Transmission Line Loading 2017WP Pre-Connection Contingency Branch Category B: 138 kV transmission line 749L (from the Metiskow 648S substation to the Edgerton 899S substation) 4.2. 138 kV transmission line 7L130 (from the Vermillion 710S substation to the Kitscoty 705S substation) Nominal Rating (MVA) Power Flow (MVA) % Loading 86.3 89.5 103.7 Voltage Stability Analysis To estimate the maximum load that can be served while meeting the performance requirements of the AESO Reliability Criteria, a PV analysis was conducted using the 2017WP pre-connection scenario to identify the worst-case contingency conditions. The analysis was performed under the following conditions. Pre-connection Under Category B and selected Category C5 contingencies Table 4-3 lists the worst-case contingency scenarios used in the voltage stability analysis. Table 4-3: Worst Contingency Scenarios Contingency Category Transmission Line Line Voltage (kV) 681L B 681L 138 Hardisty 377S Tucuman 478S 9L953 240 Nilrem 574S Cordel 755S From To 9L953 and 1047L C5 1047L 240 Nilrem 574S Hansman Lake 650S 679L and 680L C5 679L 138 Nilrem 574S Tucuman 478S R(4) 29 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation Contingency 702L 703L Category Transmission Line Line Voltage (kV) 680L 138 Nilrem 574S Tucuman 478S 702L 138 Sedgewick 137S Hardisty 377S 702L 138 Sedgewick 137S Battle River 757S 703L 138 703AL Tap Point Metiskow 648S 703L 138 703AL Tap Point Sunken Lake 221S 703L 138 703AL Tap Point Hansman Lake 650S 703L 138 Express Tap Point HRT Express 329S 703L 138 Express Tap Point Hughenden 213S 703L 138 Express Tap Point Hardisty 377S B From B To The initial 2017WP pre-connection load (reference load) in the Wainwright area is 205.50 MW. The sink sub-system included only the loads in the Wainwright area. The source sub-system was chosen to consist of the surrounding and neighbouring generation in the AESO Planning Areas 6, 30, 33, 35, 40, 43, 57, 60, 53, 54, and 55. The PV analysis was performed with the switched capacitors, reactors and transformer taps locked. The results of PV analysis confirm that there is no voltage stability violation prior to the connection of the proposed development. The Wainwright area voltage stability results under Category A, Category B, and selected Category C5 system conditions are given in Attachment B. Connection Alternatives 5. 5.1. Overview Four connection alternatives were identified for the Project. For each of the four alternatives the addition of a 138 kV breaker at Rosyth 296S substation has been included. This breaker will improve reliability by ensuring the isolation of local faults at Rosyth 296S substation from the rest of 138 kV transmission system. Alternative 1: T-Tap Connection to the 138 kV Transmission Line 769L This alternative includes: R(4) Connecting the proposed Enbridge Battle Sands 594S substation to the existing 138 kV transmission line 769L through a T-tap configuration between the Rosyth 30 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation 296S substation and the 138 kV transmission line 769AL T-tap that connects the Clipper 656S substation to 138 kV transmission line 769L. Alternative 2: Radial Connection to the Rosyth 296S or the Clipper 656S Substations This alternative includes: Connecting the proposed Enbridge Battle Sands 594S substation radially to the existing Rosyth 296S or Clipper 656S substation. Adding a new 138 kV bay to the Rosyth 296S or Clipper 656S substation to supply Battle Sands 594S substation. Alternative 3: In-and-Out Connection to the 138 kV Transmission Line 769L This alternative includes: Connecting the proposed Enbridge Battle Sands 594S substation to the existing 138 kV transmission line 769L by an in-and-out configuration through a new switching station. Constructing a new switching station located adjacent to the Battle Sands 594S substation, which will consist of two incoming 138 kV bays to terminate the 138 kV transmission line 769L and one bay to terminate the outgoing 138 kV transmission line to Battle Sands 594S substation. The new switching station will include three 138 kV circuit breakers. Alternative 4: In-and-Out Connection to the 138 kV Transmission Line 703L This alternative includes: Connecting the proposed Enbridge Battle Sands 594S substation to the existing 138 kV transmission line 703L by an in-and-out configuration through a new switching station. Constructing a new switching station located adjacent to the Battle Sands 594S substation, which will consist of two incoming 138 kV bays to terminate the 138 kV transmission line 703L and one bay to terminate the outgoing 138 kV transmission line to the Battle Sands 594S substation. The new switching station will include three 138 kV circuit breakers. 5.2. 5.2.1. Evaluation of Connection Alternatives Connection Alternatives Eliminated As indicated below, Alternatives 2, 3, and 4 were ruled out and were not selected for further studies, as they were either not considered viable due to space constraints or had significantly higher capital costs. R(4) 31 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation Alternative 2 5.2.1.1. Alternative 2 was ruled out because there is no space within the Rosyth 296S or Clipper 656S substation to accommodate an additional circuit breaker bay and there are rightof-way constraints surrounding the existing substations (see Figure 5-1). Figure 5-1: Alternative 2 – Radial Connection from Rosyth 296S (or Clipper 656S) Substation (connection to the Rosyth 296S substation shown) Bus # 73 HARDIST7,138 kV Area 32, WAINWRIG Hardisty 377S Bus # 809 EXPRESTP,138 kV Area 37, PROVOST 703L 769L Bus # 484 CLIPPER7,138 kV Area 32, WAINWRIG Clipper 656S 769AL Bus # 373 IPL HAR7,138 kV Area 32, WAINWRIG Rosyth 296S T1 20/26MVA T3 25/25MVA 769BL Bus # 715 CLIPP_TP2,138kV Area 32, WAINWRIG 769-2a, 3a T2 33.3/33.3MVA T1 33.3/33.3MVA T1 25/33MVA Bus # 2609 BAT SND2, 6.9 kV Area 32, WAINWRIG Bus # 4484 CLIPPER9, 4.16 kV Area 32, WAINWRIG Bus # 609 BAT SND1,138 kV Area 32, WAINWRIG Battle Sands 594S T2 25/33MVA Bus # 3609 BAT SND3, 6.9 kV Area 32, WAINWRIG Bus # 2373 Bus # 3373 Bus # 4373 IPL HAA8, 4.16 kV IPL HAA9, 4.16 kV IPL HAR9, 4.16 kV Area 32, Area 32, Area 32, WAINWRIG WAINWRIG WAINWRIG Existing New 5.2.1.2. Alternative 3 Alternative 3 was ruled out because it would require two circuits and an additional TFO switching station (see Figure 5-2), and hence would result in a higher capital cost than Alternative 1. This in-and-out configuration on the radial 138 kV transmission line 769L would not result in any improvement in reliability for the Customer. R(4) 32 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation Figure 5-2: Alternative 3 – In-and-Out Connection to 138 kV Transmission Line 769L Bus # 73 HARDIST7,138 kV Area 32, WAINWRIG Hardisty 377S Bus # 809 EXPRESTP,138 kV Area 37, PROVOST 703L 769L T3 25/25MVA T2 33.3/33.3MVA 769AL T1 33.3/33.3MVA Bus # 484 CLIPPER7,138 kV Area 32, WAINWRIG Clipper 656S Bus # 609 BAT SND1,138 kV Area 32, WAINWRIG Battle Sands 594S T1 25/33 MVA T1 20/26MVA T2 25/33 MVA 594SM3 Bus # 4484 Bus # 2373 Bus # 3373 Bus # 4373 IPL HAA8, 4.16 kV IPL HAA9, 4.16 kV IPL HAR9, 4.16 kV CLIPPER9, 4.16 kV Area 32, Area 32, Area 32, Area 32, WAINWRIG WAINWRIG WAINWRIG WAINWRIG 594SM2 Bus # 3609 BAT SND3, 6.9 kV Area 32, WAINWRIG 594SD1 Bus # 2609 BAT SND2, 6.9 kV Area 32, WAINWRIG 594SM5 769-2a, 3a 769L Bus # 373 IPL HAR7,138 kV Area 32, WAINWRIG Rosyth 296S Switching Station 769L Bus # 715 CLIPP_TP2,138 kV Area 32, WAINWRIG 594SM4 769L Existing New 5.2.1.3. Alternative 4 Alternative 4 is similar to Alternative 3 in that it would also require two circuits and an additional TFO switching station (see Figure 5-3), and hence would result in a higher capital cost than Alternative 1. An improvement in reliability for the Customer over Alternative 1 is possible because 138 kV transmission line 703L is capable of being fed from both ends. However this advantage is not considered significant due to the overall system configuration in the area, therefore Alternative 4 was rejected. R(4) 33 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation Figure 5-3: Alternative 4 – In-and-Out Connection to 138 kV Transmission Line 703L Bus # 73 HARDIST7,138 kV Area 32, WAINWRIG Hardisty 377S Bus # 809 EXPRESTP,138 kV Area 37, PROVOST 703L 703L 703L 769L Switching Station Bus # 715 CLIPP_TP2,138 kV Area 32, WAINWRIG 703L 703L T3 25/25MVA T2 33.3/33.3MVA 769AL T1 33.3/33.3MVA T1 25/33 MVA T1 20/26MVA T2 25/33 MVA 594SM3 Bus # 4484 Bus # 2373 Bus # 3373 Bus # 4373 IPL HAA8, 4.16 kV IPL HAA9, 4.16 kV IPL HAR9, 4.16 kV CLIPPER9, 4.16 kV Area 32, Area 32, Area 32, Area 32, WAINWRIG WAINWRIG WAINWRIG WAINWRIG 594SM2 Bus # 3609 BAT SND3, 6.9 kV Area 32, WAINWRIG 594SD1 Bus # 2609 BAT SND2, 6.9 kV Area 32, WAINWRIG 594SM5 769-2a, 3a Bus # 609 BAT SND1,138 kV Area 32, WAINWRIG Battle Sands 594S 594SM4 Bus # 373 IPL HAR7,138 kV Area 32, WAINWRIG Rosyth 296S Bus # 484 CLIPPER7,138 kV Area 32, WAINWRIG Clipper 656S Existing New 5.2.2. Connection Alternative Selected for Further Studies The connection alternative selected for further studies was Alternative 1. 5.2.2.1. Alternative 1 Alternative 1 includes connecting the proposed Battle Sands 594S substation to the existing 138 kV transmission line 769L through a T-tap configuration between the Rosyth 296S substation and the 138 kV transmission line 769AL T-tap that connects the Clipper 656S substation to 138 kV transmission line 769L. Figure 5-4 shows the connection diagram for Alternative 1. R(4) 34 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation Figure 5-4: Alternative 1 – T-Tap Connection to the 138 kV Transmission Line 769L Bus # 73 HARDIST7,138 kV Area 32, WAINWRIG Bus # 809 EXPRESTP,138 kV Area 37, PROVOST Hardisty 377S 703L Bus # 860 BATSD_TP,138 kV 769-1a1 Area 32, WAINWRIG 769-1a2 T2 33.3/33.3 MVA 769AL T1 33.3/33.3 MVA Bus # 484 CLIPPER7,138 kV Area 32, WAINWRIG Clipper 656S T1 20/26 MVA Bus # 609 BAT SND1,138 kV Area 32, WAINWRIG Battle Sands 594S T1 25/33 MVA T2 25/33 MVA 594SM3 Bus # 4484 CLIPPER9, 4.16 kV Area 32, WAINWRIG 594SD1 Bus # 3373 Bus # 4373 Bus # 2373 IPL HAA9, 4.16 kV IPL HAR9, 4.16 kV IPL HAA8, 4.16 kV Area 32, WAINWRIG Area 32, WAINWRIG Area 32, WAINWRIG Bus # 3609 BAT SND3, 6.9 kV Area 32, WAINWRIG 594SM2 Bus # 2609 BAT SND2, 6.9 kV Area 32, WAINWRIG 594SM4 594SM5 T3 25/25 MVA 769-2a, 3a 769BL Bus # 373 IPL HAR7,138 kV Area 32, WAINWRIG Roysth 296S »1Km Bus # 715 CLIPP_TP2,138 kV Area 32, WAINWRIG Existing New Figures 5-1 to 5-4 contain simplified versions of the system configuration. Technical detail has been reduced for illustration purposes. It does not indicate geographical location of facilities. 6. Technical Analysis of the Connection Alternative 6.1. Power Flow Analysis The Project connection will not impact the customer DTS. As a result, post-connection power flow analysis is expected to yield the same results as pre-connection; therefore, post-connection power flow analysis was not undertaken. R(4) 35 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation 6.2. Voltage Stability Analysis The Project will not impact the DTS on the radial 138 kV transmission line 769L. As a result, post-connection voltage stability analysis is expected to yield the same results as pre-connection; therefore, post-connection voltage stability analysis was not undertaken. 7. Short-Circuit Analysis The short-circuit analysis involved calculating three-phase and single-line-to-ground fault current levels for the substations in the Study Area.8 7.1. Pre-Connection Short-Circuit Analysis Short-circuit analysis was performed using the 2017WP pre-connection scenario. The results of the short-circuit analysis are shown in Table 7-1. Table 7-1: Pre-Connection Short-Circuit Current Levels (2017WP) Substation / Tap Point Hardisty 377S Rosyth 296S Clipper 656S Clipper Tap Point Express Tap Point Bus Base Voltage (kV) PreFault Voltage (kV) PreFault Voltage (pu) 3Phase Fault (A) Singleline-toground Fault (A) Positive Sequence Impedance (pu) Zero Sequence Impedance (pu) 73 138 143.20 1.0377 6943.1 5950.3 0.02182+j0.05860 0.02247+j0.09117 373 138 143.00 1.0361 6671.9 5602.2 0.02295+j0.06078 0.02485+j0.09918 484 138 143.00 1.0361 6657.3 5582.9 0.02300+j0.06090 0.02499+j0.09971 715 138 143.00 1.0361 6682.7 5615.3 0.02290+j0.06069 0.02478+j0.09890 809 138 143.20 1.0374 6732.0 5662.0 0.02272+j0.06033 0.02433+j0.09815 Note: Pu values have been calculated using base voltage and 100 MVA as base power. 7.2. Alternative 1 Post-Connection Short-Circuit Analysis Short-circuit analysis was performed using 2017WP and 2024WP post-connection scenarios to determine the fault levels after the proposed T-tap connection to line 769L. 8 The information provided in the study should not be used as the sole source of information for electrical equipment specifications or for the design of safety-grounding systems. Short-circuit analysis was based on modelling information provided to the AESO by third parties. The authenticity of the modelling information has not been validated. Fault levels could change as a result of system developments, new customer connections, or additional generation in the area. It is recommended that these changes be monitored and fault levels reviewed to ensure that the fault levels are within equipment operating limits. R(4) 36 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation The results of the short-circuit analysis for Alternative 1 are shown in Table 7-2 and Table 7-3. Table 7-2: Post-Connection Short-Circuit Current Levels for Alternative 1 (2017WP) Substation / Tap Point Hardisty 377S Rosyth 296S Clipper 656S Clipper Tap Point Express Tap Point Battle Sands Bus Base Voltage (kV) Pre-Fault Voltage (kV) PreFault Voltage (pu) 3Phase Fault (A) Singleline-toground Fault (A) 73 138 142.20 1.0306 6960.3 6022.3 0.02143+j0.05813 0.02095+j0.08855 373 138 142.00 1.0292 6684.8 5664.6 0.02257+j0.06033 0.02334+j0.09657 484 138 142.00 1.0292 6670.1 5643.8 0.02263+j0.06046 0.02348+j0.09711 715 138 142.00 1.0293 6695.8 5677.1 0.02253+j0.06023 0.02327+j0.09629 809 138 142.20 1.0306 6746.4 5722.9 0.02234+j0.05986 0.02287+j0.09561 609 138 142.00 1.0288 6445.2 5368.4 0.02362+j0.06246 0.02558+j0.10401 Positive Sequence Impedance (pu) Zero Sequence Impedance (pu) Note: Pu values have been calculated using base voltage and 100 MVA as base power. Table 7-3: Post-Connection Short-Circuit Current Levels for Alternative 1 (2024WP) Substation / Tap Point Hardisty 377S Rosyth 296S Clipper 656S Clipper Tap Express Tap Battle Sands Bus Base Voltage (kV) Pre-Fault Voltage (kV) PreFault Voltage (pu) 3Phase Fault (A) Singleline-toground Fault (A) Positive Sequence Impedance (pu) Zero Sequence Impedance (pu) 73 138 145.08 1.0513 7579.5 6469.7 0.0193+j0.0547 0.0195+j0.0858 373 138 144.89 1.0499 7259.3 6066.3 0.0195+j0.0858 0.0219+j0.0938 484 138 144.89 1.0499 7242.3 6042.9 0.0219+j0.0938 0.0221+j0.0943 715 138 144.89 1.0499 7272 6080.3 0.0204+j0.0569 0.0218+j0.0935 809 138 145.06 1.0511 7333.6 6131.6 0.0202+j0.0565 0.0215+j0.0929 609 138 144.82 1.0495 6982.9 5734.1 0.0215+j0.0591 0.0242+j0.1012 Note: Pu values have been calculated using base voltage and 100 MVA as base power. It can be seen from Table 7-2 and Table 7-3 that Alternative 1 does not negatively impact the short-circuit current levels in the Study Area. R(4) 37 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation 8. Motor Starting Analysis Motor starting analysis was performed to assess the feasibility of the “across-the-line” starting of the 7,000 HP motors at the proposed Battle Sands 594S substation. Although Enbridge has indicated that VFDs will be used to start the motors, the analysis assesses the voltage dip at the transmission busses in the case of a VFD failure (VFD by-pass condition) and to determine if starting restrictions would be imposed. Motor starting analysis was conducted for the start-up of a single motor with all other motors in the station already running at full load. All four motors were supplied by one 138/6.9 kV, 25/33 MVA transformer. The 2017WP post-connection scenario was used in the analysis. The analysis were based on the dynamic analysis method in PSS/E 33. Table 8-1 shows the nameplate data of the 7,000 HP induction motors. Table 8-1: Motor Nameplate and Calculated Data Motor Rating R(4) Value Rated power 7,000 HP Rated voltage 6,600 V Rated current 516 A Rated speed 1780 rpm Rated torque 20,676 lb-ft Nominal power factor 0.92 Nominal efficiency 0.964 Moment of inertia (motor) 4667 lb-ft Moment of inertia (Driven Machine) 400 lb-ft Locked-rotor torque 75.7% Breakdown torque 196.2% Locked-rotor current 650% MVA base 5.889 MVA Rated motor speed pu 0.9889 Driven machine torque pu @ n=ns 0.8 H (combined motor and driven machine) 0.6297 2 38 2 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation Figure 8-1 shows the equivalent circuit that was used to model the motors. Figure 8-1: Equivalent Circuit of Induction Motor Ra La L1 L2 R1 S Lm R2 S Table 8-2 lists the equivalent circuit parameters. Table 8-2: Equivalent Circuit Data 8.1. Equivalent Circuit Parameter Value in Per Unit Ra 0.037 La 0.071 Lm 3.4 R1 0.025 L1 0.07 R2 0.0195 L2 0.024 Motor Starting Assumptions The following assumptions were used in conducting motor starting analysis: The transient voltage dip at the 138 kV transmission bus should not exceed 5% when starting a single motor. The motors will not start simultaneously. Only one motor will be allowed to start in VFD bypass mode while the other motors are running at full load. Motor starting was investigated for the following system scenario: o 2017WP Post-connection Alternative 1 8.2. Motor Starting Results for Alternative 1 Motor starting analysis was conducted for the 2017WP post-connection Alternative 1 configuration. The analysis was conducted under system normal Category A and critical contingency conditions extracted from the power flow analysis. Table 8-3 shows the summary for Alternative 1. R(4) 39 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation Table 8-3: Motor Starting Performance for Alternative 1 Substation Condition Contingency From To Proposed Battle Sands 594S Substation Nominal Voltage (kV) Before Motor Start (kV) After Motor Start (kV) Voltage Dip (kV) % Voltage Dip Category A (N-0) Normal N/A N/A 138 142.83 139.66 3.17 2.22 Category B (N-1) 681L Hardisty 377S Tucuman 478S 138 129.38 123.86 5.52 4.27 Category C5 (N-2) 679L and 680L Nilrem 574S Tucuman 478S 138 129.38 123.86 5.52 4.27 Category C5 (N-2) 953L and 1047L Nilrem 574S 138 126.01 120.57 5.44 4.31 Category B (N-1) 702L Hardisty 377S 138 129.38 123.86 5.52 4.27 138 129.38 123.86 5.52 4.27 Category B (N-1) 703L Metiskow 648S Hansman Lake 650S/ Cordel 755S Battle River 757S Sunken Lake 221S/ Hardisty 377S The motor starting results show that the voltage dip caused by “across-the-line” motor starting at the proposed Battle Sands 594S substation 138 kV bus is below 5% under both system normal and contingency conditions. The simulation results suggest that the impact on the voltage due to “across-the-line” starting of one motor is acceptable. The induction motor curves and the voltages at the proposed Battle Sands 594S substation busses are provided in Attachment C. 9. Project Interdependencies The Project is not dependent on any other planned developments in the Study Area. R(4) 40 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation 10. Summary and Conclusion Enbridge submitted a SASR to the AESO requesting the connection of the proposed Enbridge Battle Sands 594S substation. The substation DTS will be totalized with the DTS at the Rosyth 296S and Clipper 656S substations. The requested ISD for the connection to the proposed Battle Sands 594S substation is July 1, 2017. The Project to connect the proposed Battle Sands 594S substation is located in the Wainwright area, near the Hardisty 377S, Rosyth 296S, and Clipper 656S substations. The Rosyth 296S and Clipper 656S substations only serve Enbridge load. The Rosyth 296S substation is fed radially from the Hardisty 377S substation via the 138 kV transmission line 769L. The Clipper 656S substation is connected to the 138 kV transmission line 769L through a T-tap, designated 138 kV transmission line 769AL. Four possible alternatives were identified to meet the needs of the Project. Only one of the four alternatives, Alternative 1, was selected for further study. Three of the alternatives were eliminated either due to space constraints or because they would require more facilities and hence result in higher capital costs than Alternative 1. Alternative 1 consists of a tapped connection, designated 138 kV transmission line 769BL, from the existing 138 kV transmission line 769L to the proposed Battle Sands 594S substation between Rosyth 296S substation and Clipper 656S substation T-tap, 138 kV transmission line 769AL. This Engineering Study Report details the system performance studies undertaken to assess the impact of the connection of the proposed Battle Sands 594S substation on the AIES. In order to identify the existing system constraints, pre-connection power flow and voltage stability analyses were performed. No voltage violation was observed in the power flow analysis for the 2017SP and 2017WP pre-connection scenarios. A number of thermal loadings above the continuous 100% thermal limit were observed for the 2017SP and 2017WP pre-connection scenarios, under several Category B contingencies. These thermal loadings are existing and known to the AESO. They are currently being mitigated in real time by the AESO and TFO operating practices. The results of voltage stability analysis confirm that there is no voltage stability violation prior to the connection of the proposed development. The connection of the Battle Sands 594S substation will not impact the customer’s DTS. As a result, post-connection power flow and voltage stability analyses are expected to yield the same results as the pre-connection analyses. Therefore, post-connection power flow and voltage stability analyses were not undertaken. The post-connection short-circuit and motor starting analyses were performed in order to identify post-connection system constraints of Alternative 1. The short-circuit analysis showed that Alternative 1 does not negatively impact shortcircuit current levels. The motor starting analysis results show that the impact of R(4) 41 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation “across-the-line” starting of one motor, in VFD bypass mode, is acceptable during both system normal (Category A) and contingency (Category B and C5) conditions. The results of the engineering study indicate that Alternative 1, a tapped connection to radial 138 kV transmission line 769L, will not adversely impact the AIES in the Study Area. Based on these results, Teshmont recommends Alternative 1 to meet the request for a connection to Enbridge’s proposed Battle Sands 594S substation. R(4) 42 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation 11. Revision History R(4) Revision Issue Date Author Change Tracking Revision 04 2015-10-15 Ashraf Haque Final Draft Revision 03 2015-10-08 Ashraf Haque Fourth Draft Revision 02 2015-09-25 Ashraf Haque Third Draft Revision 01 2015-08-07 Ashraf Haque Second Draft Revision 00 2015-06-24 Mahmud Rashid First Draft 43 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation Attachment A Power Flow Single Line Diagrams Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation Table A-1: SLD List for Thermal Loadings Scenario System Condition Thermal Loadings Category A : Normal Operation None Category B: 138 kV Transmission Line 7L130 Contingency (from the Vermillion 710S substation to the Kitscoty 705S substation) Category B: 138 kV Transmission Line 7L14 Contingency (from the Kitscoty 705S substation to the Hill 751S substation) 2017SP PreConnection Category B: 138 kV Transmission Line 749L (from the Metiskow 648S substation to the Edgerton 899S substation) Category B: Edgerton 899S substation transformer T3* Category B: Edgerton 899S substation transformer T3* 2017WP PreConnection R(4) % of Overload Figure in Attachment A -- A-1 138 kV Transmission Line 749L (from the Metiskow 648S substation to the Killarney 267S substation T-tap) 108.5 A-2 138 kV Transmission Line 749L (from the Metiskow 648S substation to the Killarney 267S substation T-tap) 105.6 A-3 138 kV Transmission Line 7L130 (from the Vermillion 710S substation to the Kitscoty 705S substation) 138 kV Transmission Line 7L14 (from the Kitscoty 705S substation to the Hill 751S substation) 138 kV Transmission Line 7L130 (from the Vermillion 710S substation to the Kitscoty 705S substation) 138 kV Transmission Line 7L14 (from the Kitscoty 705S substation to the Hill 751S substation) Category A: Normal Operation None Category B: 138 kV Transmission Line 749L (from the Metiskow 648S substation to the Edgerton 899S substation) 138 kV Transmission Line 7L130 (from the Vermillion 710S substation to the Kitscoty 705S substation) A-1 112.1 A-4 105.5 106.2 A-5 100.9 -- A-6 103.7 A-7 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation Figure A-1: 2017SP Pre-Connection, Category A: Normal Operation 1047 DRURY_138 1383 VERMILO7 30.6 16.3 16.2 1387 KITSCOT7 7L130 24.0 29.8 26.1 22.1 23.1 1393 HILL 7 7L14 25.8 SW 21.9 44.7 9.58.8 1.0 141.3 1.0 143.1 SW 1377 IRISH C7 7L129 7.0 0.0 11.2 19.3 44.3 7L129 15.7 1.0 141.3 72 JARROW 7 704L 8.4 2.2 1.0 142.0 36 4.4 153.0 3 13.9R 9.6R 11.1 36 5.5 9L16 100.6 144.2 143.5 18.3 34.2 151.9 151.1 15.1 34.4 1.0 16.3 13.8 22.3 23.4 39.6 702L 45.2 5.2 9L79 88.6 88.7 45.2 41.0 37.9 19427 NILREM5 52.6 1469 1427 BAT RV79 NILREM3 33.8 99.6 4.4 13.7 13.7 10.5 679L 0.1 60.6 43.7 43.6 373 IP L HAR7 29.9 1.0 142.0 954L 1.0 142.5 17.8 15.4 15.3 10.1 8.9 15.0 10.1 8.5 19.9 19.8 0.1 0.0 34.7 63.3 63.2 19.8 22.2 27.9 27.9 28.4 1.0 18.5 17.9 9L966 885L 1.0 1451 EYRE7 1.1 257.3 68.1 7L967L79 1477 RIB STON1 7.8 10.7 2.6 4.2 1.1 145.0 10.8 2.3 10.8 2.4 1.1 145.6 Enbridge Battle Sands Subs tation Connec tion P1558 2017 Summer Peak Pre-Connec tion 7L79 2.7 814 KILRY TP 89.2 749L 87.4 29.1 31.7 749L 41.9 19.3 219 KILLARN7 749A L 1410 CURR_TAP 27.2 26.9 12.9 14.8 45.5 45.1 11.9 1.0 141.7 11.6 1446 CURRANT7 7L111 9.5 9.5 1.0 143.0 4.4 5.1 7L127 57.2 8.1 8.5 7L110 25.2 1.1 145.6 19.2 SW 31.0 1.1 9.6 4.1 4.4 1.1 145.8 1.1 145.9 0.0 1.1 146.4 10471 774S 701T 2.8 2.8 1.1 1.1 146.3 1.1 Enbridge Battle Sands Subs tation Pre-Connec tion - Diagram A-1 N-0: Normal Operation 1458 LOYALIS7 7L110 9.6 SW 10.9 41.3 19.9 7L224 25.2 1470 VETERA N7 6.6 2.4 9.5 19.2 716 LAK ESEN7 6.6 1.0 142.3 1.0 142.4 6.9 57.2 1.0 144.3 10.8 1471 MONITOR7 1.1 254.4 4.5 11.5 68.1 7.0 2.4 4.0 19419 932_LV 1.1 257.1 68.1 7.8 17.3 7L224 1.0 142.6 68.2 5.1 1425 EYRE_TAP 17.3 5.0 10419 932S901T 7.0 6.6 1.0 25.9 9.5 22.0 7L749 4361 EDGERTO9 7.1 7L224 1.1 255.6 111.6 99 59.9 1.1 149.1 Bus - Voltage (k V/pu) Branc h - M W/M v ar Equipm ent - M W/M v ar 100.0% Rate A k V: >0.000<=20.000 <=50.000<=100.000<=200.000<=300.000<=500.000>500.000 1 R(4) A-2 362 EDGERTO7 1.0 142.3 34.6 20.9 2.5 21.4 0.0 9.7 1.0 142.3 1.0 142.9 43.4 4.0 17.5 9.7 60.3 4.6 17.5 33.7 33.9 7.1 43.4 SW 26.4 862 PV-TAP7 648 HANSMAN9 59.9 60.3 112 SUNK EN7 1.6 11.2 11.2 703L703L 1.0 18.8 8.4 99 8.5 1.0 4.1 9.0 74 ME TIS647 26.4 SW 33.9 98.2 1419 932_HV A 2373 IPL HAA8 15.0 989 703ALTAP 1.1 2648 255.6 HA NSMSV 948L 99.1 703L 99 15.0 6.3 27.9 112.2 9L46 8.5 1.0 3373 4.1 IPL HAA9 63.3 1047L 99 8.5 87 METIS 644 649 HANSMAN7 63.3 99 4373 IPL HAR9 15.0 15.0 1.0 142.0 1.1 255.8 0.0 11.6 1.0 4.0 1.0 4.1 1.0 142.2 SW 1.0 142.2 58.5 1.1 255.0 1438 959S _HV 4484 CLIPPER9 15.1 11.6 60.7 29.9 61.1 10.5 9L27 110.7 110.3 0.0 3.4 769L 45.4 45.4 61.2 681L 4.3 3.2 1403 PAINTRT4 SW 9.0 15.0 0.1 52.5 13.1 22.2 7.3 52.5 3.2 58.6 4.4 1.1 255.6 15.2 15.1 13.7 1.0 142.0 27.1 680L 58.7 17.7 17438 LANFSV 3.6 484 CLIP PER7 769L 15.2 15.2 769L 483 TUCUMAN7 0.2 58.8 1.1 255.6 101.2 9L953 715 CLIPP_TP 0.0 9.9 20.3 27.6 1.6 1.0 142.2 9.7 1.1 146.3 19.3 27.8 702L 10.8 42.2 1.1 253.7 5.3 SW 1.0 143.0 1.1 255.6 9.8 9L20 99 15.8 38.1 0.2 52.6 42.4 2.0 1.0 4.2 SW 78 SEDGEWI7 1489 BA T RV80 9L80 19.3 4037 HRT EXP 9 3.9 1.0 141.7 76.4 88.6 45.1 1422 NEVIS 4 3.9 20.1 8.7 88.6 1.1 256.2 2.1 1.0 142.0 100.4 10.6 64.4 7L50LN 78.9 74.0 14.4 1499 CORDEL 4 1431 S WITCH_H 65.6 1.0 141.4 1.0 16.3 1496 BAT #4 163.0 4 9.2 3.8 8.4 703L 5.3 703L 9.2 16.1 7L50 2.0 1491 BAT. RV7 1495 BAT #3 8.8 3.9 2.3 2.3 75 HUGHEND7 73 HARDIST7 44.7 1.0 1490 141.2 JAROW TP 1.0 141.4 3.9 2.3 1.0 142.2 3.6 79 1.0 BUFFALO7 141.2 37.4 18.8 6.7 1113 BAUER1 3.9 703L 3.9 7.0 3.6 7L129 37.0 7L117 11.1 3.0 1.0 144.0 766 B AUERTAP 37 HRT EXP7 809 EXPRESTP SW 32.3 1.0 141.2 1.0 141.8 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation Figure A-2: 2017SP, Pre-Connection, Category B: 7L130 (Vermillion 710S to Kitscoty 705S) Contingency 1047 DRURY_138 1383 VE RMILO7 1393 HILL 7 1387 KITS COT7 7L130 7.5 7L14 3.7 7.5 1.0 3.7 SW 1.0 45.4 2.51.8 1.0 140.1 1377 IRIS H C7 7.2 28.5 11.1 7L129 3.6 1.0 140.4 72 JARROW 7 704L 17.3 17.3 2.6 2.6 1.0 141.6 36 4.4 153.0 3 12.5R 4 8.3R 11.1 36 5.5 9L16 101.2 144.2 143.5 16.9 32.8 151.9 151.1 13.8 33.1 1.0 16.3 14.1 41.5 702L 47.1 38.9 99.4 99.5 47.1 41.9 9L79 105.4 5.8 50.7 50.6 66.1 12.9 679L 1.1 50.6 1.1 60.7 60.6 43.7 43.6 5.5 4.3 56.6 56.5 681L 15.2 15.1 13.7 13.7 13.7 1.0 142.4 8.0 29.9 29.9 1.0 141.8 15.0 15.0 9.7 8.5 15.4 15.3 10.1 8.9 15.0 15.0 10.1 8.5 19.6 0.0 26.6 76.5 76.4 19.6 23.0 26.5 26.5 27.0 1.0 18.5 18.5 9L966 885L 1451 EYRE7 1.1 257.3 1.0 144.4 31.6 11.3 13.0 1.0 143.0 19.2 7L967L79 1477 RIBSTON1 7.8 10.7 2.6 4.2 2.3 1.1 145.1 Enbridge Battle Sands Subs tation C onnec tion P1 2017 Summer Peak Pre-C onnec tion 10.8 2.4 1.1 145.7 7L127 62.1 23.7 1470 VETERAN7 10.8 7L79 749L 77.0 33.8 219 KILLARN7 45.5 45.1 11.6 1.0 141.2 11.3 1446 CURRANT7 7L111 9.5 9.5 4.4 5.1 8.1 8.5 7L110 23.7 1.1 145.7 19.2 SW 31.1 1.1 9.6 9.6 4.1 4.4 1.1 145.9 1.1 146.0 0.0 1.1 146.5 10471 774S701T 2.8 2.8 1.1 1.1 146.4 1.1 Enbridge Battle Sands Subs tation Pre-C onnec tion - D iagram A-2 N -1: 7L130 (Vermillion 710S to Kits c oty 705S) C ontingenc y 1458 LOYA LIS7 7L110 SW 10.9 75.0 31.2 7L224 62.1 4.5 1410 CURR_TA P 32.1 1.1 254.6 7.8 42.8 9.5 8.5 716 LAKE SEN7 122.5 36.3 1.0 142.3 1471 MONITOR7 73.0 8.6 2.7 814 K ILRY TP 4.0 19419 932_LV 1.1 257.1 73.0 6.6 2.4 749AL 7L224 1.0 142.6 73.1 6.6 Overload 9.1 1.0 142.4 9.5 6.4 2.4 749L 126.1 22.1 5.0 73.0 1425 EY RE_TAP 7L224 10419 932S901T 8.6 6.6 1.0 25.7 9.7 2.5 36.5 7L749 4361 EDGERTO9 4.5 22.1 1.1 255.6 120.1 99 77.1 1.1 149.2 Bus - Voltage (k V/pu) Branc h - M W/M v ar Equipm ent - M W/M v ar 100.0% Rate A k V: >0.000<=20.000 <=50.000<=100.000<=200.000<=300.000<=500.000>500.000 Note: Dashed black lines mark the contingencies and solid red lines mark the thermal loadings. 1 R(4) A-3 362 EDGE RTO7 1.0 142.3 68.3 41.0 1.7 21.2 0.0 9.7 1.0 142.3 1.0 142.6 46.9 4.0 17.5 9.7 72.6 4.7 17.5 64.9 26.1 4.5 47.0 SW 19.9 862 PV-TAP7 648 HANSMAN9 77.1 72.7 112 S UNKEN7 5.3 15.0 15.0 703L703L 1.0 18.9 12.5 99 2.4 74 METIS647 19.9 SW 26.1 110.5 1419 932_HVA 8.5 1.0 4.1 989 703ALTAP 76.5 19.8 0.1 948L 703L 87 METIS644 954L 99 99 2373 IPL HAA8 15.0 1.0 141.8 1.1 255.7 120.7 9L46 8.5 1.0 3373 4.1 IPL HAA9 1.1 2648 255.6 HANSMSV 30.8 99 4373 IPL HAR9 15.0 1.0 4.1 1.0 142.0 SW 1047L 111.6 11.6 1.0 4.0 373 IPL HA R7 2.8 1.1 254.8 1438 959S_HV 4484 CLIPPE R9 15.1 11.6 13.0 76.5 9L27 123.3 122.8 0.0 7.2 1.0 141.8 66.1 649 HANSMAN7 5.4 4.3 1403 PA INTRT4 0.0 2.4 769L 45.4 45.4 1.0 142.1 16.7 SW 0.2 484 CLIPPER7 769L 15.2 15.2 769L 28.8 8.3 680L 56.7 8.0 25.1 702L 483 TUCUMAN7 1.0 56.8 1.1 255.5 1.1 255.5 715 CLIPP _TP 0.0 9.9 34.3 29.5 19427 NILREM5 1469 1427 BAT RV79 NILRE M3 19.3 107.2 9L953 17438 LANFSV 2.1 1.0 142.0 SW 78 SEDGEWI7 6.0 1.1 146.1 21.5 29.9 11.8 15.7 11.7 49.4 1.1 253.6 99 1.0 141.6 1.0 142.8 1.1 255.5 9.8 9L20 11.7 39.8 1.0 50.7 49.6 7L50 1489 BAT RV 80 9L80 19.3 703L SW 76.2 99.4 47.0 1422 NE VIS 4 0.2 14.4 9.2 99.4 1.1 256.0 11.8 1.0 141.6 101.0 10.9 2.0 1.0 4.2 48.3 7L50LN 70.2 66.3 11.0 1499 CORDEL 4 1431 SWITCH_H 15.8 0.1 1.0 140.8 1.0 16.3 1496 BAT #4 163.0 4037 HRT EX P9 3.9 1491 BAT. RV7 1495 BAT #3 8.8 2.0 11.9 703L 15.8 4.5 49.0 3.9 2.3 2.3 75 HUGHEND7 73 HARDIST7 28.6 1.0 1490 140.3 JAROW TP 1.0 140.1 3.9 2.3 1.0 142.0 3.6 79 1.0 BUFFALO7 140.3 21.5 6.2 1113 BAUER1 3.9 703L 3.9 7.0 3.6 7L129 21.4 17.5 7.8 7L129 7.0 0.0 7L117 17.3 1.1 145.0 766 BAUERTAP 1.0 144.9 SW 37 HRT EXP7 809 EXPRESTP SW 32.1 1.0 140.7 1.0 141.0 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation Figure A-3: 2017SP, Pre-Connection, Category B: 7L14 (Kitscoty 705S to Hill 751S) Contingency 1047 DRURY_138 1383 VE RMILO7 8.5 1387 KITSCOT7 7L130 3.7 8.5 1393 HILL 7 7L14 3.7 2.6 46.5 3.32.5 1.0 140.3 1.0 140.1 SW 1377 IRISH C7 7L129 7.0 0.0 16.7 8.5 30.4 7L129 4.9 1.0 140.5 72 JA RROW 7 704L 16.2 2.1 1.0 141.6 4.4 153.0 3 12.7R 8.5R 11.1 36 5.5 143.5 17.1 33.0 9L16 151.9 151.1 14.0 33.3 1.0 16.3 14.1 46.9 41.2 9L79 98.2 98.3 46.9 41.8 702L 39.6 5.9 38.8 50.8 1469 1427 BA T RV79 NILREM3 1.1 255.5 34.3 104.7 1.0 141.9 43.7 43.6 373 IPL HAR7 29.9 65.4 681L 65.4 13.1 13.1 679L 5.1 4.0 29.9 1.0 141.9 9.1 15.0 15.0 9.7 8.5 15.4 15.3 10.1 8.9 954L 21.2 0.1 0.0 31.2 15.0 8.5 75.0 74.9 21.2 24.5 0.0 26.9 26.9 0.0 27.4 1.0 18.5 119.6 9L46 18.6 9L966 46.6 885L 2.5 1451 EYRE7 1.1 257.3 7L967L79 1477 RIBSTON1 7.8 10.7 2.6 4.2 1.1 145.1 10.8 2.3 10.8 2.4 1.1 145.7 Enbridge Battle Sands Subs tation Connec tion P1558 2017 Summer Peak Pre-Connec tion 7L79 2.7 814 K ILRY TP 749L 121.5 39.3 118.2 45.3 Overload 749L 72.7 1410 CURR_TAP 35.8 219 KILLARN7 11.1 45.5 45.1 11.8 1.0 141.6 11.6 1446 CURRANT7 7L111 31.0 9.5 9.5 12.8 4.4 5.1 7L224 1.0 143.1 7L127 61.4 8.1 8.5 7L110 23.4 1.1 145.7 19.2 SW 31.1 1.1 9.6 4.1 4.4 1.1 145.9 1.1 146.1 0.0 1.1 146.6 10471 774S701T 2.8 2.8 1.1 1.1 146.4 1.1 Enbridge Battle Sands Subs tation Pre-Connec tion - Diagram A-3 N-1: 7L14 (Kits c oty 705S to Hill 751S) Contingenc y 1458 LOYALIS7 7L110 9.6 SW 10.9 70.8 33.5 749AL 31.4 23.4 1470 VETERAN7 6.6 2.4 9.5 19.2 716 LAKESE N7 6.6 1.0 142.5 1.0 142.5 8.8 61.4 1.0 144.4 8.9 1471 MONITOR7 1.1 254.6 4.5 9.5 72.3 8.9 2.4 4.0 19419 932_LV 1.1 257.1 72.3 7.8 21.4 7L224 1.0 142.7 72.4 6.7 1425 E YRE_TAP 21.4 5.0 72.3 6.6 1.0 25.9 9.5 10419 932S 901T 8.9 64.1 38.5 2.9 7L224 1.1 255.6 119.0 99 75.0 1.1 149.2 Bus - Voltage (k V/pu) Branc h - M W/M v ar Equipm ent - M W/M v ar 100.0% Rate A k V: >0.000<=20.000 <=50.000<=100.000<=200.000<=300.000<=500.000>500.000 Note: Dashed black lines mark the contingencies and solid red lines mark the thermal loadings. 1 R(4) A-4 362 EDGERTO7 1.0 142.4 7L749 4361 EDGERTO9 0.3 21.5 0.0 9.7 61.0 42.3 46.5 4.2 17.5 1.0 142.4 71.2 3.2 17.5 9.7 1.0 144.1 2.9 1419 932_HVA SW 20.8 862 P V-TAP7 648 HANSMAN9 75.0 71.3 112 SUNKEN7 5.3 14.9 14.9 703L703L 30.5 1.1 255.7 99 8.5 1.0 4.1 3.3 74 METIS 647 20.8 1.0 18.8 12.0 1438 959S_HV 2373 IPL HAA8 15.0 989 703ALTAP SW 30.5 109.0 30.4 703L 10.1 75.0 21.4 99 99 15.0 1.1 2648 255.6 HANSMSV 948L 110.1 4373 IPL HAR9 15.0 87 ME TIS644 1047L 9L27 121.8 121.3 99 8.5 1.0 3373 4.1 IPL HA A9 3.5 1.1 254.9 11.6 1.0 4.0 1.0 141.9 75.0 1.0 142.4 4484 CLIP PER9 15.1 1.0 4.1 1.0 142.1 SW 649 HANSMA N7 56.7 5.1 4.0 1403 PAINTRT4 SW 7.2 769L 45.4 45.4 0.8 50.7 16.0 17438 LANFSV 3.3 11.6 60.6 1.0 142.1 9.1 24.7 13.7 13.7 769L 8.2 50.7 0.8 15.2 15.1 13.7 60.7 28.5 680L 56.9 56.8 5.8 1.1 255.5 702L 483 TUCUMA N7 0.7 56.9 21.4 29.6 0.1 484 CLIPPER7 769L 15.2 15.2 0.0 9.9 106.5 9L953 29.3 19427 NILREM5 1.1 146.2 19.3 715 CLIPP_TP 78 SE DGEWI7 11.6 48.5 1.1 253.6 2.0 1.0 142.1 SW 1.0 142.8 1.1 255.5 9.8 9L20 10.9 15.7 76.2 0.7 50.8 48.7 0.3 15.1 1489 BAT RV 80 9L80 19.3 703L SW 13.0 99 1.0 141.7 1.0 140.8 98.2 46.8 1422 NEVIS 4 7L50 9.1 98.2 1.1 256.1 2.0 1.0 4.2 50.3 1.0 141.6 100.9 10.9 13.0 14.9 0.2 7L50LN 71.2 67.2 11.4 1499 CORDEL 4 1431 SWITCH_H 101.1 144.2 1.0 16.3 1496 BAT #4 163.0 4 2.1 4037 HRT EX P9 3.9 1491 BAT. RV7 1495 BAT #3 8.8 36 51.0 2.0 11.0 703L 14.9 5.8 16.2 3.9 2.3 2.3 75 HUGHEND7 73 HA RDIS T7 30.6 1.0 1490 140.4 JA ROW TP 1.0 140.2 3.9 2.3 1.0 142.1 3.6 79 1.0 B UFFALO7 140.4 23.5 7.6 10.6 1113 B AUER1 3.9 703L 3.9 7.0 3.6 7L129 23.3 7L117 16.5 7.3 1.1 146.8 766 BAUE RTAP 37 HRT EX P7 809 E XPRES TP SW 1.0 SW 32.3 1.0 141.1 1.0 141.9 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation Figure A-4: 2017SP, Pre-Connection, Category B: 749L (Metiskow 648S to Edgerton 899S) Contingency 1047 DRURY_138 1383 VERMILO7 28.6 28.2 9.08.5 1.0 137.3 1387 KITSCOT7 7L130 75.3 28.7 Overload 71.4 67.7 33.4 34.4 Overload 40.6 7L129 23.6 7L129 19.9 1.0 138.1 72 JARROW 7 704L 3.5 36 4.4 153.0 3 11.3R 4 7.3R 11.1 36 5.5 9L16 93.9 144.2 143.5 15.7 31.6 151.9 151.1 12.8 32.1 1.0 16.3 16.3 47.0 35.4 32.4 72.7 72.7 47.0 43.8 702L 9L79 3.1 702L 4.8 1.1 255.5 83.9 55.1 680L 679L 55.0 50.1 681L 5.2 2.5 SW 7.1 5.8 43.6 373 IP L HAR7 29.9 29.9 1.0 141.6 50.1 1.0 142.2 38.5 15.4 15.3 10.1 8.9 15.0 15.0 10.1 8.5 13.1 0.0 27.7 31.0 13.1 13.7 1419 932_HV A 0.0 29.8 29.8 0.0 30.3 1.0 18.5 88.1 9L46 15.1 9L966 31.5 10.8 10.1 885L 1.1 255.6 87.8 3.8 1451 EYRE7 1.1 257.3 56.2 0.4 7L967L79 7.8 10.7 2.6 4.2 1.0 144.6 31.1 1470 VETERA N7 10.8 2.3 10.8 2.4 1.1 145.2 Enbridge Battle Sands Subs tation Connec tion P1558 2017 Summer Peak Pre-Connec tion 7L79 749L 219 KILLARN7 749A L 9.5 SW 1.0 141.7 1410 CURR_TAP 15.3 15.1 18.8 20.9 1.0 142.5 19.2 1477 RIB STON1 2.7 814 KILRY TP 1446 CURRANT7 7L111 9.5 9.5 4.4 5.1 7L224 45.3 1.0 143.9 1.0 141.8 0.8 716 LAK ESEN7 6.6 2.4 1.0 141.8 1471 MONITOR7 1.1 253.6 4.5 16.9 56.2 0.9 6.6 4.0 19419 932_LV 1.1 256.9 56.2 7.8 5.5 17.6 7L224 1.0 142.1 56.3 2.4 749L 1425 EYRE_TAP 5.5 5.1 0.9 6.6 1.0 24.7 9.5 10419 932S901T 7L127 45.3 8.1 8.5 7L110 31.1 1.1 145.2 19.2 30.9 SW 1.0 9.6 4.1 4.4 1.1 145.4 1.1 145.5 0.0 1.1 146.1 10471 774S 701T 2.8 2.8 1.1 1.1 145.9 1.1 Enbridge Battle Sands Subs tation Pre-Connec tion - Diagram A-4 N-1: 749L (Metis k ow 648S to Edgerton 899S) Contingenc y 1458 LOYALIS7 7L110 9.6 SW 10.9 2.7 7L749 4361 EDGERTO9 20.9 7L224 21.0 99 17.9 1.1 148.7 Bus - Voltage (k V/pu) Branc h - M W/M v ar Equipm ent - M W/M v ar 100.0% Rate A k V: >0.000<=20.000 <=50.000<=100.000<=200.000<=300.000<=500.000>500.000 Note: Dashed black lines mark the contingencies and solid red lines mark the thermal loadings. 1 R(4) A-5 362 EDGERTO7 1.0 141.8 6.6 0.2 31.5 3.3 0.0 9.7 6.6 20.8 30.0 17.5 1.0 141.8 1.0 136.4 648 HANSMAN9 17.9 30.1 17.5 9.7 862 PV-TAP7 27.2 1.1 255.7 SW 41.4 4.4 4.4 703L703L 1.0 18.8 1.8 112 SUNK EN7 5.3 74 ME TIS647 41.4 SW 27.2 68.2 99 8.5 1.0 4.1 24.0 31.1 1.1 2648 255.6 HA NSMSV 23.7 2373 IPL HAA8 15.0 989 703ALTAP 31.1 13.2 703L 99 1.0 4.1 6.0 948L 1438 959S _HV 8.5 1.0 3373 4.1 IPL HAA9 87 METIS 644 954L 99 8.5 1.0 141.6 1047L 1.1 254.7 99 4373 IPL HAR9 15.0 15.0 769L 45.4 45.4 1.0 141.8 31.1 68.7 1.1 255.5 60.6 43.7 11.6 1.0 4.0 5.1 0.1 18.0 4484 CLIPPER9 15.1 11.6 60.7 649 HANSMAN7 61.0 7.0 5.7 9L27 79.9 13.7 13.7 1.0 141.6 1.0 141.9 13.0 24.3 15.2 15.1 13.7 15.0 2.5 55.0 61.1 61.0 1403 PAINTRT4 484 CLIP PER7 769L 15.2 15.2 769L 23.4 483 TUCUMAN7 2.4 61.2 1.2 80.1 715 CLIPP_TP 0.0 9.9 9L953 23.9 19427 NILREM5 38.4 SW 23.8 3.8 9.7 1469 1427 BAT RV79 NILREM3 19.3 30.3 17438 LANFSV 10.9 SW 78 SEDGEWI7 34.2 1.1 146.0 14.1 85.0 9.0 1.0 141.8 15.1 8.8 18.0 1.1 253.6 11.3 9.5 SW 25.6 99 1.0 141.2 1.0 142.7 1.1 255.5 9.8 9L20 11.2 75.9 2.4 55.1 18.0 7L50 1489 BA T RV80 9L80 19.3 5.6 18.3 72.7 47.0 1422 NEVIS 4 2.0 1.0 4.2 89.3 7.2 72.7 1.1 256.0 19.0 1.0 139.4 93.8 13.0 21.8 2.0 703L 9.5 703L 5.6 7L50LN 91.0 84.6 9.1 1499 CORDEL 4 1431 S WITCH_H 3.5 2.3 4037 HRT EXP9 3.9 75 HUGHEND7 73 HARDIST7 69.6 1.0 138.0 1.0 16.3 1496 BAT #4 163.0 91.7 3.9 1491 BAT. RV7 1495 BAT #3 8.8 7.1 2.3 3.9 1.0 141.8 1.0 1490 137.4 JAROW TP 1.0 137.2 7.1 1.0 139.4 2.3 1113 BAUER1 3.7 79 1.0 BUFFALO7 137.4 68.7 7.8 3.9 703L 3.9 7.0 61.7 24.5 37 HRT EXP7 809 EXPRESTP 1.0 137.2 3.6 7L129 60.8 2.7 4.2 SW 36.6 7.0 0.0 7L117 2.6 65.8 766 B AUERTAP 1.0 136.7 SW 1377 IRISH C7 1393 HILL 7 7L14 1.0 141.2 1.0 135.6 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation Figure A-5: 2017SP, Pre-Connection, Category B: Edgerton 899S Transformer T3 Contingency 1047 DRURY_138 1383 VERMILO7 27.1 35.0 11.911.4 1.0 139.3 1387 KITS COT7 7L130 67.8 27.2 Overload 64.4 60.7 38.8 39.8 Overload 43.4 7L129 25.4 7L129 21.8 1.0 139.7 72 JA RROW 7 704L 2.6 2.6 4.0 4.0 1.0 140.5 36 4.4 153.0 3 12.6R 8.5R 11.1 36 5.5 9L16 100.1 144.2 143.5 17.0 32.9 14.5 151.9 151.1 14.0 33.3 1.0 16.3 45.5 35.8 9L79 76.0 45.5 42.1 702L 4.1 702L 55.3 680L 0.8 55.3 679L 55.2 6.0 55.2 681L 0.9 55.2 7.4 0.9 SW 93.2 61.4 5.5 4.2 61.3 61.2 1.0 142.4 29.6 20.4 13.7 13.7 43.7 43.6 373 IPL HAR7 15.0 15.0 9.7 8.5 29.9 29.9 1.0 141.8 55.2 15.4 15.3 10.1 8.9 15.0 15.0 10.1 8.5 15.6 0.0 47.7 15.6 17.0 28.4 28.4 28.9 1.0 18.5 16.6 9L966 885L 62.8 1.1 255.6 1451 EYRE7 1.1 257.0 1.0 142.0 1410 CURR_TAP 21.9 21.6 15.9 1477 RIBSTON1 10.7 2.6 4.2 1.0 144.7 2.3 10.8 2.4 1.1 145.4 Enbridge Battle Sands Subs tation C onnec tion P1558 2017 Summer Peak Pre-C onnec tion 7L127 51.9 28.2 1470 VETERAN7 10.8 7L79 11.7 749L 219 K ILLARN7 17.9 45.1 11.7 1.0 141.4 11.4 1446 CURRANT7 7L111 9.5 9.5 1.0 142.7 4.4 5.1 8.1 8.5 7L110 28.2 1.1 145.4 19.2 SW 30.9 9.6 4.1 4.4 1.1 145.6 1.1 145.7 0.0 1.0 1.1 146.2 10471 774S 701T 2.8 2.8 1.1 1.1 146.1 1.1 Enbridge Battle Sands Subs tation Pre-C onnec tion - D iagram A-5 N -1: Edgerton 899S Trans former T3 C ontingenc y 1458 LOYALIS7 7L110 9.6 SW 10.9 45.5 7L224 19.2 7.8 12.0 749AL 62.8 51.9 7L967L79 814 KILRY TP 45.5 9.5 3.8 716 LAKE SEN7 749L 1.0 142.0 1471 MONITOR7 1.1 254.0 1.0 144.1 13.9 46.0 4.0 19419 932_LV 3.9 4.5 12.1 14.6 7L224 1.0 142.3 62.9 62.8 7.8 12.1 9.5 2.3 7L749 4361 EDGERTO9 1.0 25.9 5.1 3.9 1.1 148.9 Bu s - Vo l ta g e (k V/p u ) Bra n c h - M W /M v a r Eq u i p m e n t - M W /M v a r 1 0 0 .0 % Ra te A k V: >0 .0 0 0 <=2 0 .0 0<=5 0 0 .0 0 0<=1 00 .0 0 0< =2 0 0 .0 0 0<=3 0 0 .0 0 0< =5 0 0 .0 0 0> 5 0 0 .0 0 0 Note: Dashed black lines mark the contingencies and solid red lines mark the thermal loadings. 1 R(4) 362 EDGERTO7 1.0 142.0 99 40.1 1425 EYRE_TAP 7L224 20.9 10419 932S901T 0.0 9.7 15.0 39.3 1.1 257.3 17.5 1.0 142.0 7.2 1.1 17.5 9.7 45.7 8.5 3.4 112 SUNKEN7 SW 7.2 7.2 703L703L 1.0 141.5 14.9 102.3 99 2.4 34.4 862 PV-TAP7 648 HANS MAN9 40.1 39.4 74 METIS647 34.4 28.4 1.1 255.7 102.7 9L46 8.5 1.0 4.1 16.9 47.8 1.0 18.8 5.4 1419 932_HVA 2373 IPL HAA8 15.0 SW 28.4 45.8 703L 989 703ALTAP 47.8 15.7 99 99 1.0 4.1 87 METIS644 954L 83.9 26.1 4373 IPL HAR9 15.0 1.0 141.8 28.9 99 8.5 1.0 3373 4.1 IPL HAA9 1.1 2648 255.6 HA NSMSV 948L 11.6 1.0 4.0 769L 45.4 45.4 1047L 84.6 1438 959S _HV 4484 CLIPPER9 15.1 11.6 1.0 141.8 1.0 142.0 0.1 95.8 15.2 15.1 13.7 6.2 9L27 0.0 16.8 0.7 7.4 47.8 1.1 1403 254.8 PAINTRT4 26.3 60.6 649 HA NSMAN7 5.5 4.2 13.0 96.1 60.7 1.0 142.0 29.6 0.0 7.8 484 CLIPPER7 769L 15.2 15.2 769L 25.2 483 TUCUMAN7 0.8 61.4 2.1 1.1 255.5 715 CLIPP_TP 0.0 9.9 9L953 25.8 19427 NILREM5 1469 1427 BA T RV79 NILRE M3 1.1 255.5 17438 LA NFSV 5.8 1.0 142.0 SW 78 SEDGEWI7 36.1 1.1 146.1 19.3 32.3 SW 2.6 15.4 9.8 75.9 17.9 94.6 28.2 99 1.0 141.4 1.0 142.9 34.1 1.1 253.6 37.4 1.1 255.5 9.8 9L20 34.2 7L50 1489 BA T RV80 9L80 19.3 703L SW 76.2 75.9 45.4 1422 NE VIS 4 8.1 21.1 7.9 75.9 1.1 256.1 25.0 1.0 140.6 100.0 11.3 2.0 1.0 4.2 83.6 7L50LN 89.3 83.1 12.4 1499 CORDE L 4 1431 SWITCH_H 1.4 8.0 1.0 139.6 1.0 16.3 1496 B AT #4 163.0 4 4037 HRT EXP9 3.9 1491 BAT. RV7 1495 B AT #3 8.8 2.0 2.6 703L 1.4 21.2 85.7 3.9 2.3 2.3 75 HUGHEND7 73 HARDIST7 63.9 1.0 1490 139.2 JAROW TP 1.0 139.3 3.9 2.3 1.0 142.0 3.6 79 1.0 BUFFA LO7 139.2 63.1 5.5 1113 BA UER1 3.9 703L 3.9 7.0 56.2 26.0 37 HRT EXP 7 809 EXPRE STP 1.0 141.8 3.6 7L129 55.4 3.3 1.8 SW 41.4 7.0 0.0 7L117 3.3 59.1 766 BAUE RTAP 1.0 140.5 SW 1377 IRIS H C7 1393 HILL 7 7L14 A-6 SW 32.2 1.0 140.9 1.0 141.8 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation Figure A-6: 2017WP, Pre-Connection, Category A: Normal Operation 1047 DRURY_138 1383 VERMILO7 32.3 20.6 20.5 1387 KITSCOT7 7L130 20.6 31.5 26.2 18.6 19.9 1393 HILL 7 7L14 25.9 SW 18.6 44.9 17.316.6 1.0 142.4 1.0 143.6 SW 1377 IRISH C7 24.5 54.6 7L129 23.2 1.0 140.5 72 JARROW 7 704L 5.5 3.1 1.0 143.0 4.4 153.0 3 11.0R 7.0R 11.1 36 5.5 9L16 148.7 144.2 143.5 15.4 31.2 151.9 151.1 12.5 31.7 1.0 16.4 4.6 42.5 702L 31.9 38.5 67.6 67.6 31.9 29.6 9L79 29.0 19427 NILREM5 113.1 7.9 65.6 13.7 13.7 60.6 1.0 143.6 43.5 43.5 373 IP L HAR7 769L 63.1 681L 6.9 679L 7.9 65.5 7.9 SW 2.1 3.9 72.5 72.4 29.8 29.8 1.0 143.7 63.1 1.0 144.1 32.0 15.4 15.3 10.1 8.9 15.0 10.0 8.5 954L 77.2 6.9 77.1 6.9 0.1 0.0 18.7 948L 3.6 862 PV-TAP7 885L 0.0 13.0 13.0 0.0 13.2 1.0 18.6 146.0 9L46 19.0 9L966 82.0 1425 EYRE_TAP 36.2 1451 EYRE7 1.1 256.8 63.2 17.6 4.8 1.0 136.9 1410 CURR_TAP 33.5 11.1 3.1 3.6 1.0 137.7 18.4 1470 VETERA N7 11.1 1.9 11.1 2.0 1.0 138.3 Enbridge Battle Sands Subs tation Connec tion P1558 2017 Winter Peak Pre-Connec tion 7L79 30.7 749L 21.4 219 KILLARN7 50.3 49.8 9.4 1.0 142.0 9.3 1446 CURRANT7 7L111 10.1 10.0 32.3 4.8 5.4 1.0 142.1 7L127 51.9 10.7 11.0 7L110 18.4 1.0 138.4 23.3 SW 0.0 1.1 6.2 13.3 6.5 1.0 138.5 1.0 138.8 0.0 1.0 139.2 10471 774S 701T 3.3 3.3 1.3 1.0 139.2 1.3 Enbridge Battle Sands Subs tation Pre-Connec tion - Diagram A-6 N-0: Normal Operation 1458 LOYALIS7 7L110 13.3 SW 11.2 50.9 21.3 21.9 23.4 1477 RIB STON1 102.2 7L224 51.9 8.3 749L 26.9 10.0 22.5 63.1 1.0 241.9 7L967L79 104.6 749A L 7L224 19.5 716 LAK ESEN7 3.1 814 KILRY TP 1.0 143.2 1471 MONITOR7 19419 932_LV 1.1 256.6 19.6 8.2 2.7 4.3 1.0 141.6 63.1 8.2 51.9 36.6 5.3 63.1 2.7 11.8 1.0 143.2 10.0 10419 932S901T 8.3 7L224 11.7 6.0 19.6 8.2 4.3 1.1 254.2 145.1 1.0 141.6 Bus - Voltage (k V/pu) Branc h - M W/M v ar Equipm ent - M W/M v ar 100.0% Rate A k V: >0.000<=20.000 <=50.000<=100.000<=200.000<=300.000<=500.000>500.000 1 R(4) A-7 362 EDGERTO7 24.5 7L749 4361 EDGERTO9 1.1 26.8 27.2 19.5 1.0 143.2 38.9 81.7 11.6 99 65.1 38.9 1419 932_HV A 9.3 42.7 24.4 73.9 7.5 18.1 9.3 1.0 143.2 1.0 142.9 648 HANSMAN9 65.1 74.0 18.1 41.4 18.4 1.1 254.9 SW 28.8 11.811.7 703L703L 1.0 18.8 5.1 2.4 74 ME TIS647 28.8 SW 18.4 104.4 112 SUNK EN7 10.7 77.2 6.8 99 8.5 1.0 4.1 989 703ALTAP 1.1 2648 254.1 HA NSMSV 23.9 2373 IPL HAA8 15.0 87 METIS644 1047L 105.4 703L 99 15.0 15.4 9L27 118.6 118.2 SW 8.5 1.0 3373 4.2 IPL HAA9 1.0 143.6 649 HANSMAN7 99 8.5 1.0 4.2 1.0 143.9 99 4373 IPL HAR9 15.0 15.0 6.9 77.2 1.1 254.2 1438 959S _HV 11.6 1.0 4.0 769L 45.4 45.4 1.0 143.9 2.13.9 1403 PAINTRT4 4484 CLIPPER9 15.1 11.6 15.0 65.5 3.6 18.0 15.2 15.1 13.7 60.7 28.3 8.6 680L 72.6 32.0 1.1 255.0 702L 483 TUCUMAN7 7.7 72.6 1.1 255.0 34.9 484 CLIP PER7 769L 15.2 15.2 29.6 9.9 115.2 9L953 17438 LANFSV 10.6 0.5 9.7 1469 1427 BAT RV79 NILREM3 19.3 715 CLIPP_TP 78 SEDGEWI7 6.4 1.1 147.8 20.9 23.1 7.9 SW 12.1 37.2 1.1 252.9 5.9 1.0 143.8 16.1 1.0 144.5 1.1 255.0 9.8 9L20 99 5.0 SW 30.0 40.8 7.7 65.6 37.3 3.5 1.0 4.2 1.0 142.9 78.2 1489 BA T RV80 9L80 19.3 9.8 24.6 67.6 31.9 1422 NEVIS 4 7L50 9.6 67.6 1.1 255.5 4037 HRT EXP 9 4.0 76.9 1.0 143.0 148.4 2.3 27.7 9.1 9.7 7L50LN 90.4 84.1 15.9 1499 CORDEL 4 1431 S WITCH_H 3.0 703L 5.0 703L 9.1 23.1 1.0 142.6 1.0 16.4 1496 BAT #4 163.0 4 78.7 3.5 1491 BAT. RV7 1495 BAT #3 8.8 36 5.5 4.0 3.9 3.9 75 HUGHEND7 73 HARDIST7 55.2 1.0 1490 142.5 JAROW TP 1.0 142.7 4.1 3.9 1.0 143.8 1.3 79 1.0 BUFFALO7 142.5 47.4 24.5 0.1 1113 BAUER1 4.1 703L 4.1 7.2 1.3 7L129 46.8 21.9 3.3 7L129 7.2 24.5 7L117 21.6 1.0 144.3 766 B AUERTAP 37 HRT EXP7 809 EXPRESTP SW 32.4 1.0 141.2 1.0 141.9 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation Figure A-7: 2017WP, Pre-Connection, Category B: Edgerton 899S Transformer T3 Contingency 1047 DRURY_138 1383 VERMILO7 35.9 17.8 13.212.9 1.0 135.3 1387 KITSCOT7 7L130 87.8 36.1 Overload 82.8 77.4 25.7 27.0 37.2 7L129 26.9 24.9 84.0 7L129 72 JARROW 7 704L 13.7 2.0 1.0 138.7 36 4.4 153.0 3 5.9R 4 143.5 10.3 26.0 27.0 1.0 16.4 8.4 37.4 702L 36.3 31.6 48.4 48.4 36.3 34.8 3.9 9L79 30.6 SW 702L 5.7 94.9 68.6 680L 679L 68.5 2.3 49.1 681L 1.8 3.7 SW 0.4 2.3 0.4 43.5 373 IP L HAR7 29.8 29.8 1.0 143.0 49.0 1.0 143.6 56.4 15.4 15.3 10.1 8.9 15.0 15.0 10.0 8.5 11.7 0.0 13.9 948L 40.0 39.9 11.7 10.7 1419 932_HV A SW 0.0 16.6 16.6 0.0 16.8 1.0 18.6 118.6 9L46 17.0 9L966 68.4 12.0 11.0 885L 29.5 0.9 1451 EYRE7 1.1 256.8 49.6 49.6 12.4 4.8 1.0 136.6 8.3 11.1 3.1 3.7 1.0 137.3 11.1 1.9 11.1 12.5 2.0 1.0 137.9 Enbridge Battle Sands Subs tation Connec tion P1558 2017 Winter Peak Pre-Connec tion 7L79 SW 1.0 142.0 1410 CURR_TAP 27.5 1446 CURRANT7 7L111 8.7 10.1 10.0 25.7 4.8 5.4 1.0 141.7 23.4 7L967L79 219 KILLARN7 7L224 38.4 1470 VETERA N7 749L 10.0 9.0 49.6 1.0 241.2 1477 RIB STON1 3.2 814 KILRY TP 749A L 7L224 13.5 716 LAK ESEN7 8.2 2.7 1.0 142.8 1471 MONITOR7 19419 932_LV 1.1 256.5 13.6 8.2 4.3 1.0 141.2 49.6 8.3 30.0 5.3 13.6 2.7 1.3 1.0 142.8 10.0 10419 932S901T 8.2 749L 1425 EYRE_TAP 7L224 1.4 1.1 254.2 118.0 99 16.6 7L127 38.4 10.7 11.0 7L110 12.5 1.0 138.0 23.3 0.0 SW 1.0 13.3 6.2 6.5 1.0 138.2 1.0 138.4 0.0 1.0 138.8 10471 774S 701T 3.3 3.3 1.3 1.0 138.8 1.3 Enbridge Battle Sands Subs tation Pre-Connec tion - Diagram A-7 N-1: 749L (Metis k ow 648S to Edgerton 899S) Contingenc y 1458 LOYALIS7 7L110 13.3 SW 11.2 1.0 141.2 Bus - Voltage (k V/pu) Branc h - M W/M v ar Equipm ent - M W/M v ar 100.0% Rate B k V: >0.000<=20.000 <=50.000<=100.000<=200.000<=300.000<=500.000>500.000 Note: Dashed black lines mark the contingencies and solid red lines mark the thermal loadings. 1 R(4) A-8 362 EDGERTO7 3.2 7L749 4361 EDGERTO9 1.0 24.3 27.8 19.4 1.0 142.8 25.5 68.2 11.5 9.2 8.2 0.6 25.5 38.5 18.1 9.2 1.0 142.8 0.9 130.0 648 HANSMAN9 16.6 38.6 18.1 8.3 13.7 1.1 254.7 SW 47.7 862 PV-TAP7 1.0 18.9 1.5 112 SUNK EN7 8.8 18.018.0 703L703L SW 13.7 69.6 99 8.5 1.0 4.1 29.5 74 ME TIS647 47.7 1.1 2648 254.1 HA NSMSV 20.1 2373 IPL HAA8 15.0 989 703ALTAP 40.0 11.6 703L 99 1.0 4.2 12.6 70.0 1438 959S _HV 8.5 1.0 3373 4.2 IPL HAA9 87 METIS 644 954L 99 8.5 1.0 143.0 1047L 1.1 253.6 99 4373 IPL HAR9 15.0 15.0 769L 45.4 45.4 1.0 143.2 0.1 14.2 60.6 43.6 11.6 1.0 4.0 1.7 40.0 9L27 82.8 4484 CLIPPER9 15.1 11.6 60.7 649 HANSMAN7 75.4 5.6 20.5 13.7 13.7 1.0 143.0 1.0 143.3 56.2 83.0 15.2 15.1 13.7 15.0 3.7 68.5 75.6 75.5 1403 PAINTRT4 484 CLIP PER7 769L 15.2 15.2 769L 23.8 483 TUCUMAN7 3.5 75.7 0.9 1.1 254.7 715 CLIPP_TP 29.3 9.9 9L953 24.3 19427 NILREM5 1469 1427 BAT RV79 NILREM3 19.3 1.1 254.6 17438 LANFSV 29.2 7.5 9.7 1.1 147.2 13.4 96.4 14.9 14.8 9.7 9.2 1.1 252.7 13.2 1.0 143.2 1.0 142.4 1.0 143.9 1.1 254.6 9.8 9L20 99 13.6 SW 27.1 36.1 3.5 68.6 9.3 17.1 78 SEDGEWI7 1489 BA T RV80 9L80 19.3 17.0 77.4 48.4 36.3 1422 NEVIS 4 9.4 18.9 7.9 48.4 1.1 255.2 7L50 151.1 141.1 5.9 20.9 3.5 1.0 4.2 107.1 1.0 138.7 1499 CORDEL 4 9L16 21.6 7L50LN 105.2 96.8 5.2 7.9 5.5 1431 S WITCH_H 141.4 144.2 151.9 2.4R 11.1 36 2.0 4037 HRT EXP9 4.0 75 HUGHEND7 703L 13.5 703L 9.4 1.0 136.6 1.0 16.4 1496 BAT #4 163.0 110.5 3.5 3.9 1491 BAT. RV7 1495 BAT #3 8.8 13.7 4.0 3.9 73 HARDIST7 85.4 1.0 1490 135.8 JAROW TP 1.0 135.2 4.1 3.9 1.0 143.1 1.3 79 1.0 BUFFALO7 135.8 23.6 1.0 134.7 1113 BAUER1 4.1 703L 4.1 7.2 76.7 4.0 37 HRT EXP7 809 EXPRESTP 1.0 131.3 1.3 7L129 75.3 10.3 0.6 SW 30.4 7.2 22.0 7L117 10.3 75.1 766 B AUERTAP 1.0 131.9 SW 1377 IRISH C7 1393 HILL 7 7L14 1.0 141.2 0.9 128.9 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation Attachment B Pre-Connection Voltage Stability Results Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation Table B-1: 2017WP Pre-Connection PV Results From To 2017WP PreConnection Reference Load (MW) Substation Condition Contingency Margin (MW) Nose Point (MW) Voltage Criteria Category A (N-0) Normal N/A N/A 205.50 215.78 (105%) 475 Meets voltage stability criteria Category B (N-1) 681L Hardisty 377S Tucuman 478S 205.50 215.78 (105%) 421 Meets voltage stability criteria Category C5 (N-2) 679L and 680L Nilrem 574S Tucuman 478S 205.50 210.64 (102.5%) 294 Meets voltage stability criteria 205.50 210.64 (102.5%) 273 Meets voltage stability criteria 205.50 215.78 (105%) 471 Meets voltage stability criteria 205.50 215.78 (105%) 471 Meets voltage stability criteria Category C5 (N-2) 953L and 1047L Nilrem 574S Category B (N-1) 702L Hardisty 377S Category B (N-1) 703L Metiskow 648S Hansman Lake 650S/ Cordel 755S Battle River 757S Sunken Lake 221S/ Hardisty 377S Table B-2: Figure Description of Voltage Stability Analysis R(4) Figure Number PV Curve Description Figure B-1 PV curve at the Hardisty 377S substation for 2017WP preconnection Figure B-2 PV curve at the Clipper 656S substation T-tap for 2017WP preconnection Figure B-3 PV curve at the Express 329S substation T-tap for 2017WP preconnection B-1 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation Figure B-1: 2017WP Pre-Connection PV Curve for the Hardisty 377S Substation 2017WP Pre: At Hardisty 377S Bus Voltage (PU) 1.000 0.500 0.000 25.000 50.000 75.000 100.000 125.000 150.000 175.000 N-0: Normal Operation N-2: 9L953_1047L N-2: 679L_680L N-1: 681L N-1: 702L N-1: 703L 0.000 Incremental Load Addition (MW) in Area 32 R(4) 200.000 B-2 225.000 250.000 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation Figure B-2: 2017WP Pre-Connection PV Curve for the Clipper Tap Bus 2017WP Pre: At Clipper Tap Bus Voltage (PU) 1.000 0.500 0.000 25.000 50.000 75.000 100.000 125.000 150.000 175.000 N-0: Normal Operation N-2: 9L953_1047L N-2: 679L_680L N-1: 681L N-1: 702L N-1: 703L 0.000 Incremental Load Addition (MW) in Area 32 R(4) B-3 200.000 225.000 250.000 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation Figure B-3: 2017WP Pre-Connection PV Curve for Express Tap Bus 2017WP Pre: At Express Tap Bus Voltage (PU) 1.000 0.500 0.000 25.000 50.000 75.000 100.000 125.000 150.000 175.000 N-0: Normal Operation N-2: 9L953_1047L N-2: 679L_680L N-1: 702L N-1: 681L 0.000 R(4) Incremental Load Addition (MW) in Area 32 B-4 200.000 225.000 250.000 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation Attachment C Motor Starting Analysis Results for Post-Connection (Alternative 1) Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation Table C-1: Figure Description of Motor Starting Analysis R(4) Figure Number Contingency Description Figure C-1 Induction Motor Curve Figure C-2 Bus voltages during motor start under system normal condition for the Alternative 1 configuration Figure C-3 Bus voltages during motor start under a contingency of the 138 kV transmission line 681L for Alternative 1 configuration Figure C-4 Bus voltages during motor start under a contingency of the 138 kV transmission lines 679L and 6807L for the Alternative 1 configuration Figure C-5 Bus voltages during motor start under a contingency of the 138 kV transmission lines 953L and 1427L for the Alternative 1 configuration Figure C-6 Bus voltages during motor start under a contingency to the 138 kV transmission line 702L for the Alternative 1 configuration Figure C-7 Bus voltages during motor start under a contingency to the 138 kV transmission line 703L for the Alternative 1 configuration C-1 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation Figure C-1: Induction Motor Curve, Torque, Current and Power Factor (in per unit) R(4) C-2 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation Figure C-2: Voltage at the Proposed Battle Sands 594S Substation for 2017WP Alternative 1, Category A R(4) C-3 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation Figure C-3: Voltage at the Proposed Battle Sands 594S Substation for 2017WP Alternative 1, for the 138 kV Transmission Line 681L Contingency R(4) C-4 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation Figure C-4: Voltage at the Proposed Battle Sands 594S Substation for 2017WP Alternative 1, for the 138 kV Transmission Line 679L and 680L Contingencies R(4) C-5 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation Figure C-5: Voltage at the proposed Battle Sands 594S Substation for 2017WP Alternative 1, Category C5, for the 138 kV Transmission Line 953L and 1047L Contingencies R(4) C-6 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation Figure C-6: Voltage at the proposed Battle Sands 594S Substation for 2017WP Alternative 1, for the 138 kV Transmission Line 702L Contingency R(4) C-7 Engineering Study Report Connection to Enbridge Pipelines Inc. Proposed Battle Sands 594S Substation Figure C-7: Voltage at the Proposed Battle Sands 594S Substation for 2017WP Alternative 1, for the 138 kV Transmission Line 703L Contingency R(4) C-8