Comments
Description
Transcript
APPENDIX A CONNECTION ASSESSMENT
APPENDIX A CONNECTION ASSESSMENT ATCO Electric Connection Engineering Study Report for AUC Application ATCO Bauer 91 8S Transformer Addition AESO P1 554 Revision: 2 Revision Date: 2016-02-08 Name Prepared by: Amanda Robertson, P. Eng Date Signature 9o I APEGA Permit to Practice P0850 Connection Engineering Study Report for AUC Application Connection Engineering Study Report for AUC Application: ATCO Bauer 918S Transformer Addition Executive Summary Project Overview ATCO Electric Ltd. (ATCO), in its capacity as the legal owner of distribution facilities (DFO), has received a request for a 13 MW load increase at a customer site in the vicinity of the Town of Vermilion. The DFO has submitted a system access service request (SASR) to the Alberta Electric System Operator (AESO) to serve industrial load growth in the area. The SASR includes a request for a Rate DTS, Demand Transmission Service, contract capacity increase from 18 MW to 31 MW for the system access service provided at the existing Bauer 918S substation, and a request for transmission development (collectively, the Project). The DFO also requested upgrades to the existing Bauer 918S substation. The scheduled in-service date (ISD) for the Project is February 1, 2017. This report details the system performance studies undertaken to assess the impact of the Project on the Alberta Interconnected Electric System (AIES). Existing system The Project is geographically located in the AESO planning area of Lloydminster (Area 13), which is part of the Central East sub-region (CE sub-region) within the AESO Central Region. The Lloydminster area is located adjacent to the planning areas of Cold Lake (Area 28), Vegreville (Area 56), and Wainwright (Area 32). From a transmission system perspective, the CE sub-region mainly consists of 72 kV and 138/144 kV transmission systems. It is also supported by the 240 kV network through the Marguerite Lake 826S, Battle River 757S, Nilrem 574S, and Hansman Lake 650S substations. The CE sub-region is primarily supplied by the Battle River generation station in the Alliance/Battle River area (Area 36), as well as generation resources in the Cold Lake area. There are a number of existing constraints in the study area that are mitigated by remedial action schemes (RASs). Following RAS activation, these constraints are managed in accordance with the procedures set out in Section 302.1 of the ISO rules, Real Time Constraint Management. Study Summary Study Area for the Project The study area for the Project consists of the AESO planning areas that constitute the CE subregion, namely the Lloydminster (Area 13), Cold Lake (Area 28), Wainwright (Area 32), Alliance/Battle River (Area 36), Provost (Area 37), and Vegreville (Area 56) areas. The study area also includes the tie lines connecting these planning areas to neighbouring planning areas. All transmission facilities within the study area were studied and monitored to assess the impact ATCO Electric February, 2016 2 R2 Connection Engineering Study Report for AUC Application: ATCO Bauer 918S Transformer Addition of the Project on the AIES, including any violations of the Reliability Criteria (as defined in Section 2.1.1). Studies Performed for the Project Load flow analysis was performed for the 2016 winter peak (WP) and 2017 summer peak (SP) pre- and post-connection scenarios. Voltage stability analysis was performed only for the 2016 WP post-connection scenario. Short-circuit analysis was performed for the 2016 WP pre- and post-connection scenarios, and for the 2024 WP post-connection scenario to determine the short-circuit current levels in the vicinity of the Project. Results of the Pre-Connection Studies The following is a brief summary of the pre-connection studies results. The pre-connection studies results and applicable mitigation measures are shown in greater detail in Table E-1 below. Category A (N-G-0) Conditions Under Category A conditions, no Reliability Criteria violations were observed for any of the preconnection scenarios. Category B (N-G-1) Contingency Conditions The pre-connection load flow analysis identified a number of system performance issues under Category B contingency conditions, including thermal criteria violations and voltage criteria violations. ATCO Electric February, 2016 3 R2 Connection Engineering Study Report for AUC Application: ATCO Bauer 918S Transformer Addition Table E-1: Overview of Pre-Connection Studies Results Condition Scenario Results Mitigation Measure Contingency Result 2016 WP -- -- -- 2017 SP -- -- -- Category A 2016 WP Loss of the 138/25 kV transformer at Metiskow 648S substation1 Area voltage collapse Currently managed by real time operational practices Loss of the 138/25 kV transformer at Metiskow 648S substation Area voltage collapse Currently managed by real time operational practices Thermal criteria violation on the 144 kV transmission line 7L130 Currently managed by real time operational practices Thermal criteria violation on the 144 kV transmission line 7L14 Currently managed by real time operational practices Loss of the 144 kV transmission line 7L50 Thermal criteria violation on a segment of the 144 kV transmission line 7L53 Currently managed by real time operational practices Loss of one of the Vegreville 709S substation 2 transformers Thermal criteria violation on a segment of the 144 kV transmission line 7L53 Currently managed by real time operational practices Loss of the 144 kV transmission line 7L130 Thermal criteria violation on a segment of the 138 kV transmission line 749L Currently managed by real time operational practices Loss of the 144 kV transmission line 7L14 Thermal criteria violation on a segment of the 138 kV transmission line 749L Currently managed by real time operational practices Loss of the 138 kV transmission line 749L Category B 2017 SP 1 While the loss of the 138/25 kV transformer at Metiskow 648S substation is considered a Category B (NG-1) event, this event would result in the simultaneous loss of the 138 kV bus and the 138 kV transmission lines 749L, 703L, and 885L, due to the Metiskow 138 kV bus configuration. 2 While the loss of one of the Vegreville 709S substation transformers is considered a Category B (N-G-1) event, this event would result in the simultaneous loss of the 144 kV bus at Vegreville 709S substation and the 144 kV transmission lines 7L92, 7L77, and 7L65, due to the Vegreville 144kV bus configuration. ATCO Electric February, 2016 4 R2 Connection Engineering Study Report for AUC Application: ATCO Bauer 918S Transformer Addition Connection Alternative Examined for the Project ATCO, as the DFO in the area southwest of the Town of Vermilion, examined and ruled out the use of a distribution-based solution to serve the industrial load increase request. One transmission alternative was identified for the Project and was studied to evaluate the impact of the Project on the AIES. The connection alternative involves upgrading the existing Bauer 918S substation, including adding a 144/4.16 kV transformer with a minimum transformation capacity of 17.2 MVA, a 144 kV circuit breaker, and a 4.16 kV circuit breaker. For this connection alternative, a transformer size of 15/20/25 MVA would be recommended based on good electric industry practice and under advisement from the legal owner of transmission facilities (TFO) regarding its asset management and inventory practices. Results of the Post-Connection Studies The following is a brief summary of the post-connection studies results. The post-connection studies results and applicable mitigation measures are shown in greater detail in Table E-2, below. Category A (N-G-0) Conditions Under Category A conditions, no Reliability Criteria violations were observed for any of the postconnection scenarios. Category B (N-G-1) Contingency Conditions The post-connection load flow analysis identified several Reliability Criteria violations in addition to the system performance issues that were observed in the pre-connection studies. Under Category B contingency conditions, exacerbated thermal criteria violations were observed for the 2017 SP post-connection study scenarios. These violations were observed on a segment of the 144 kV transmission line 7L53 (between the Bonnyville 700S substation and the Lindbergh 969S substation tap). The incremental thermal criteria violations on transmission line 7L53 were as follows: 6.8% increase over the pre-connection loading following the loss of the 144 kV transmission line 7L50 (between the Battle River 757S and Buffalo Creek 526S substations); and 4.8% increase over the pre-connection loading following the loss of one of the Vegreville 709S substation transformers. Thermal criteria violations on transmission line 7L53 were also observed under the following additional contingencies: Loss of a 138/25 kV transformer at Buffalo Creek 526S; or Loss of the 144 kV transmission line 7L65 (between the Vegreville 709S substation and Vermilion 710S substations). ATCO Electric February, 2016 5 R2 Connection Engineering Study Report for AUC Application: ATCO Bauer 918S Transformer Addition The voltage stability criterion was met for all studied contingencies for the 2016 WP postconnection scenario. Short-Circuit Analysis The short-circuit analysis show that short-circuit current levels will not significantly increase with the Project. Table E-2: Overview of Post-Connection Studies Results Results Condition Scenario Contingency Mitigation Measure Impact after Project Result 2016 WP -- -- -- -- 2017 SP -- -- -- -- 2016 WP Loss of the 138/25 kV transformer at Metiskow 648S substation Area voltage collapse N/A Continue to be managed by real time operational practices Loss of the 138/25 kV transformer at Metiskow 648S substation Area voltage collapse Category A N/A Continue to be managed by real time operational practices Thermal criteria violation on the 144 kV transmission line 7L130 No Continue to be managed by real time operational practices Thermal criteria violation on the 144 kV transmission line 7L14 No Continue to be managed by real time operational practices Loss of the 144 kV transmission line 7L50 Thermal criteria violation on a segment of the 144 kV transmission line 7L53 Yes: 6.8% increase over pre-connection loading Continue to be managed by real time operational practices Loss of one of the Vegreville 709S substation transformers Thermal criteria violation on a segment of the 144 kV transmission line 7L53 Yes: 4.8% increase over pre-connection loading Continue to be managed by real time operational practices Loss of the 144 kV transmission line 7L130 Thermal criteria violation on a segment of the 138 kV transmission line No Continue to be managed by real time operational practices Loss of the 138 kV transmission line 749L Category B 2017 SP ATCO Electric February, 2016 6 R2 Connection Engineering Study Report for AUC Application: ATCO Bauer 918S Transformer Addition Results Condition Scenario Contingency Result Impact after Project Mitigation Measure 749L Loss of the 144 kV transmission line 7L14 Thermal criteria violation on a segment of the 138 kV transmission line 749L Loss of a 138/25 kV transformer at Buffalo Creek 3 526S Thermal criteria violation on a segment of the 144 kV transmission line 7L53 Loss of the 144 kV transmission line 7L65 Thermal criteria violation on a segment of the 144 kV transmission line 7L53 No Continue to be managed by real time operational practices Yes Continue to be managed by real time operational practices Yes Continue to be managed by real time operational practices Mitigation Measures As indicated in Table E-1, Reliability Criteria violations that were identified in the pre-connection studies are currently managed by real time operational practices. As indicated in Table E-2, Reliability Criteria violations that were identified in the postconnection studies, including exacerbated thermal criteria violations, will continue to be managed by real time operational practices. Existing RASs in the area will not need to be modified and no new RASs will be required. Conclusions and Recommendation The connection assessment identified a number of pre-connection and post-connection system performance issues. Real time operational practices are being used to manage the identified pre-connection system performance issues, and will continue to be used to manage the identified post-connection system performance issues. It is recommended that the Project be connected using the identified connection alternative, and to continue the use of real time operational practices to manage the system performance issues. 3 While the loss of a 138/25 kV transformer at Buffalo Creek 526S is considered a Category B (N-G-1) event, this event would result in the simultaneous loss of the 138 kV bus at Buffalo Creek 526S substation and the 144 kV transmission lines 7L129 and 7L50, due to the Buffalo Creek 138 kV bus configuration. ATCO Electric February, 2016 7 R2 Connection Engineering Study Report for AUC Application: ATCO Bauer 918S Transformer Addition Contents Executive Summary .................................................................................................................................... 2 1. Introduction ....................................................................................................................................... 10 1.1. Project ......................................................................................................................................... 10 1.1.1. Project Overview.................................................................................................................. 10 1.1.2. Load Component ................................................................................................................. 10 1.1.3. Generation Component ....................................................................................................... 10 1.2. Study Scope ................................................................................................................................ 10 1.2.1. Study Objectives .................................................................................................................. 10 1.2.2. Study Area ........................................................................................................................... 11 1.2.3. Studies Performed ............................................................................................................... 15 1.3. Report Overview .......................................................................................................................... 15 2. Criteria, System Data, and Study Assumptions ............................................................................. 16 2.1. Criteria, Standards, and Requirements ....................................................................................... 16 2.1.1. Transmission Planning Standards and Criteria ................................................................... 16 2.1.2. Authoritative Documents (ADs) ....................................................................................... 17 2.2. Load and Generation Assumptions ............................................................................................. 17 2.2.1. Load Assumptions ............................................................................................................... 17 2.2.2. Generation Assumptions ..................................................................................................... 17 2.2.3. Intertie Flow Assumptions ................................................................................................... 18 2.3. System Projects........................................................................................................................... 18 2.4. Customer Connection Projects.................................................................................................... 18 2.5. Facility Ratings and Shunt Elements........................................................................................... 20 2.6. Voltage Profile Assumptions ....................................................................................................... 22 3. Study Methodology ........................................................................................................................... 23 3.1. Study Objectives.......................................................................................................................... 23 3.2. Study Scenarios .......................................................................................................................... 23 3.3. Connection Studies Carried Out.................................................................................................. 24 3.4. Load flow Analysis ....................................................................................................................... 24 3.4.1. Contingencies Studied ......................................................................................................... 25 3.5. Voltage Stability (P-V) Analysis ................................................................................................... 25 3.5.1. Contingencies Studied ......................................................................................................... 26 3.6. Short-Circuit Analysis .................................................................................................................. 26 4. Pre-Connection System Assessment ............................................................................................. 26 4.1. Pre-Connection Load Flow Analysis ........................................................................................... 26 5. Connection Alternative ..................................................................................................................... 30 5.1. Overview ...................................................................................................................................... 30 5.2. Connection Alternative Examined ............................................................................................... 30 6. Technical Analysis of the Connection Alternative ........................................................................ 31 6.1. Alternative 1 ................................................................................................................................. 31 6.1.1. Load flow Analysis (Alternative 1) ....................................................................................... 32 6.1.2. Voltage Stability Analysis .................................................................................................... 35 6.1.3. Mitigation Measures............................................................................................................. 35 6.2. Conclusions and Recommendations ........................................................................................... 37 7. Short-Circuit Analysis....................................................................................................................... 37 ATCO Electric February, 2016 8 R2 Connection Engineering Study Report for AUC Application: ATCO Bauer 918S Transformer Addition 7.1. Pre-Connection............................................................................................................................ 37 7.2. Post-Connection .......................................................................................................................... 38 8. Project Interdependencies ............................................................................................................... 39 9. Summary and Conclusion ................................................................................................................ 40 Attachments Attachment A Pre-Connection Load Flow Plots (2016WP and 2017SP) Attachment B Post Connection Load Flow Plots (2016WP and 2017SP) Attachment C Voltage Stability Curves Figures Figure 1-1: Existing CE Sub-Region Transmission Network ........................................................................................ 12 Figure 1-2: Project Area ............................................................................................................................................... 13 Tables Table E-1: Overview of Pre-Connection Studies Results ............................................................................................... 4 Table E-2: Overview of Post-Connection Studies Results ............................................................................................. 6 Table 1-1: Summary of CETD Developments Not Yet In-Service ................................................................................ 14 Table 2-1: Post Contingency Voltage Deviations Guidelines for Low Voltage Busses ................................................. 17 Table 2-2: Forecast Area Load..................................................................................................................................... 17 Table 2-3: Local Generators in the Study Cases.......................................................................................................... 18 Table 2-4: Summary of System Projects Included in the Study Cases ........................................................................ 18 Table 2-5: Summary of Customer Connection Projects in Study Area ......................................................................... 19 Table 2-6: Summary of Key Transmission Line Ratings (MVA on a 138 kV base)....................................................... 20 Table 2-7: Summary of Key Shunt Elements in the Study Area ................................................................................... 22 Table 2-8: Summary of Voltage at Key Nodes in the Study Region ............................................................................. 23 Table 3-1: List of the Connection Study Scenarios ...................................................................................................... 24 Table 3-2: Summary of Studies Performed .................................................................................................................. 24 Table 3-3: Summary of Monitored Areas and Contingency Areas for Load Flow Analysis .......................................... 25 Table 4-1 Overview of pre-connection studies results.................................................................................................. 26 Table 4-2: Scenario 1, 2016 WP Pre-Connection: N-G-1 Voltage Criteria Violations and POD bus Deviations .......... 28 Table 4-3: Scenario 2, 2017 SP Pre-Connection: N-G-1 Line Loading Above Rate A (Continuous Summer Rating) .. 29 Table 4-4: Scenario 2, 2017 SP Pre-Connection: N-G-1 Voltage Criteria Violations and POD bus Deviations ........... 29 Table 6-1 Overview of post-connection studies results ................................................................................................ 31 Table 6-2: Scenario 3, 2016 WP Post-Connection: N-G-1 Voltage Criteria Violations and POD bus Deviations ......... 33 Table 6-3: Scenario 4, 2017 SP Post-Connection: N-G-1 Line Loading Above Rate A (Continuous Summer Rating) 34 Table 6-4: Scenario 4, 2017 SP Post-Connection: N-G-1 Voltage Criteria Violations and POD bus Deviations .......... 35 Table 6-5: Scenario 3, 2016 WP Post-Connection: Voltage Stability Results .............................................................. 35 Table 6-6: Scenario 3, 2016 WP Post-Connection: Voltage Criteria Violations and Mitigation ....................................36 Table 6-7: Scenario 4, 2017 SP Post-Connection: N-G-1 Line Loading Above Rate A and Mitigation ........................ 36 Table 6-8: Scenario 4, 2017 SP Post-Connection: N-G-1 Voltage Criteria Violations and Mitigation ........................... 37 Table 7-1: Summary of Short-Circuit Current Levels – Pre-Connection (2016 WP) ..................................................... 38 Table 7-2: Summary of Short-Circuit Current Levels – Post-Connection (2016 WP) ................................................... 38 Table 7-3: Summary of Short-Circuit Current Levels – Post-Connection (2024 WP) ................................................... 38 ATCO Electric February, 2016 9 R2 Connection Engineering Study Report for AUC Application: ATCO Bauer 918S Transformer Addition 1. Introduction This Engineering Study Report presents the results of the study conducted to assess the impact of the Project (as defined below) on the performance of the Alberta Interconnected Electric System (AIES). 1.1. Project 1.1.1. Project Overview ATCO Electric Ltd. (ATCO), in its capacity as the legal owner of distribution facilities (DFO), has received a request for a 13 MW load increase at a customer site in the vicinity of the Town of Vermilion. The DFO has submitted a system access service request (SASR) to the Alberta Electric System Operator (AESO) to serve industrial load growth in the area. The SASR includes a request for a Rate DTS, Demand Transmission Service, contract capacity increase from 18 MW to 31 MW for the system access service provided at the existing Bauer 918S substation, and a request for transmission development (collectively, the Project). The DFO also requested upgrades to the existing Bauer 918S substation. The scheduled in-service date (ISD) for the Project is February 1, 2017. 1.1.2. Load Component The load increase associated with the Project is driven by new pump station load. The requested 13 MW load addition at Bauer 918S has been studied using a 0.9 lagging power factor, and is comprised of four 5750 HP motors started using a variable frequency drive (VFD) at a pump station facility. When the VFD is not available, the motors will not be started. 1.1.3. Generation Component There is no generation component associated with the Project. 1.2. Study Scope 1.2.1. Study Objectives The objectives of the study are the following: • Assess the impact of the Project on the performance of the AIES. • Identify any violations of the relevant criteria, standards or requirements of the AESO, both pre- and post-connection of the Project. ATCO Electric February, 2016 10 R2 Connection Engineering Study Report for AUC Application: ATCO Bauer 918S Transformer Addition • Recommend mitigation measures, if required, to enable the reliable connection of the Project to the AIES. 1.2.2. Study Area 1.2.2.1. Study Area Description The Project is geographically located in the AESO planning area of Lloydminster (Area 13), which is part of the Central East sub-region (CE sub-region) within the AESO Central Region. The Lloydminster area is located adjacent to the planning areas of Cold Lake (Area 28), Vegreville (Area 56), and Wainwright (Area 32). From a transmission system perspective, the CE sub-region mainly consists of 72 kV and 138/ 144 kV transmission systems. It is also supported by the 240 kV network through the Marguerite Lake 826S, Battle River 757S, Nilrem 574S, and Hansman Lake 650S substations. The CE subregion is primarily supplied by the Battle River generation station in the Alliance/Battle River area (Area 36), as well as generation resources in the Cold Lake area. Figure 1-1 shows the existing CE sub-region transmission network. Figure 1-2 shows the transmission network surrounding the Project area. The study area for the Project consists of the AESO planning areas that constitute the CE subregion, namely the Lloydminster, Cold Lake, Wainwright, Alliance/Battle River, Provost (Area 37), and Vegreville areas. The study area also includes the tie lines connecting these planning areas to neighbouring planning areas. All transmission facilities within the study area were studied and monitored to assess the impact of the Project on the AIES, including any violations of the Reliability Criteria (as defined in Section 2.1.1). ATCO Electric February, 2016 11 R2 Connection Engineering Study Report for AUC Application: ATCO Bauer 918S Transformer Addition Figure 1-1: Existing CE Sub-Region Transmission Network Coal Generator 69/72 kV Gas Generator 138/144 kV Wind Generator 138/144 kV Double Circuit 69 or 72 kV Substation 240 kV 138 or 144 kV Substation 240 kV Double Circuit 240 kV Substation 500 kV Central East Area This diagram contains a simplified version of the system configuration. Technical detail has been simplified for illustration purposes. It does not indicate geographical locations of facilities. ck Bla ) t o 4S L ( 15 15 e 11 pruc S AESO Planning Areas Currency Date: 2016-01-27 25 Fort McMurray PIKE 170S L 445 Foster Creek (EC04) UNDERWOOD 183S FOSTER CREEK 1200S 27 Athabasca / Lac La Biche 7 3 7L IOR2 Nabiye 7L 7 7L587 6 14 7L 7L91 9L36 7L 5 Mahkeses (IOR1) LEMING LAKE 715S ETHEL LAKE 717S 7L 8 9 7L28 7L66 7L24 7L70 BONNYVILLE 700S 9 GRAND CENTRE 846S 7LA24 3 7L1 NORBERG 936S MAHKESES 889S 5 7L9 83 LACOREY 721S 7LA139 4 7L79 WHITEFISH LAKE 825S 7L 1 16 7L 5 10 MAHIHKAN 837S 7L157 9L37 61 9L960/9L9 (to Whitefish Lake 825S) MAHNO 909S 4 7L160 BOURQUE 970S MARGUERITE LAKE 826S 794L (to Lac La Biche 157S) PRIMROSE 859S 5 NABIYE 942S 4 57 7L 9L22/9L81 (to Heart Lake 898S) WOLF LAKE 822S 28 Cold Lake Primrose #1 (PR1) 6 L8 BEARTRAP 940S WHITBYLAKE 819S 7L92 7LA53 7L53 ST. PAUL 707S VILNA 777S LINDBERGH 969S WATT LAKE 956S 7LA92 IRISH CREEK 706S 56 Vegreville 13 Lloydminster 7 7L11 VEGREVILLE 709S 7L130 7L14 7L77 7L65 7L A BAUER 918S 12 9 7L 9 12 KITSCOTY 705S HILL 751S 7L42 NORTH HOLDEN 395S VERMILION 710S 174L (to Bardo 197S) JARROW 252S 749L METISKOW 648S HAYTER 277S 715L HANSMAN LAKE 650S 948L 42 Hanna ATCO Electric PROVOST 545S 7L224 (to Monitor 774S) 948L 748L KILLARNEY LAKE 267S 885L SUNKEN LAKE 221S 954L 769L 679 L 680 L Bull Creek #1-2 749AL HUGHENDEN 213S 1047L 37 Provost EDGERTON 899S HRT EXPRESS 329S 966L (to Pemukan 932S) HALKIRK 615S PAINTEARTH 863S 9L59 (to Anderson 801S) 9L93 TINCHEBRAY 972S 13L50 (to Newell 2075S) 6L02 (to Marion Lake 873S) 6L03 (to Sullivan Lake 775S) BIGFOOT 756S L 9L948 9L16 CORDEL 755S NILREM 574S 953L 6L08 9L20 (to Nevis 766S) B 703 70 3L ROSYTH 296S 9L27 9L953 9 74 7L WAINWRIGHT 51S 953L 1047L Battle River #3-5 (BR3-5) 79 9L L80 9 7LB 749 681L TUCUMAN 478S CLIPPER 656S 50 704AL 36 Alliance / Battle River BATTLE RIVER 757S 05 6L 9L80 (to Mannix Mine 765S) 7L701 7L 70 2 6L05 7LA701 BIG KNIFE CREEK 7L HARDISTY 377S 704L 702AL 702L BRIKER 880S 61L SEDGEWICK 137S 13L50 (to Heathfield 2029S) LLOYDMINSTER 716S COCHIN PIPELINE FABYAN 968S 703AL STROME 223S HEISLER 764S BUFFALO CREEK 526S 61AL 701L 32 Wainwright February, 2016 12 R2 Connection Engineering Study Report for AUC Application: ATCO Bauer 918S Transformer Addition Figure 1-2: Project Area 7L139 7L70 (to Bonnyville 700S) WHITBYLAKE 819S 69 or 72 kV Substation 240 kV Substation 138 or 144 kV Substation 69/72 kV 138/144 kV 138/144 kV Double Circuit This diagram contains a simplified version of the system configuration. Technical detail has been simplified for illustration purposes. It does not indicate geographical locations of facilities. 7L53 ST. PAUL 707S VILNA 777S P1554 Area Transmission System 7L53 (to Bonnville 700S) 7LA139 4 (to 7L79 La Lac 7S e 15 Bich NORBERG 936S 7LA53 240 kV Double Circuit P1554 Project Area LINDBERGH 969S AESO Planning Areas Currency Date: 2015-08-13 7L92 28 - Cold Lake 56 - Vegreville IRISH CREEK 706S 13 - Lloydminster 7L117 7LA92 WATT LAKE 956S 7L130 VEGREVILLE 709S 7L14 BAUER 918S 7L A NORTH HOLDEN 395S BIG KNIFE CREEK 843S 1.2.2.2. 681L 704AL TUCUMAN 478S 702L 36 - Alliance / Battle River 769L CLIPPER 656S ttle Ba ) (to 57S 50 er 7 L 7 iv R (to 9L y t h 76 os S ) R 96 2 NILREM 574S B 703 953L/1047L (to Junction) BRIKER 880S 7LB 749 L LLOYDMINSTER 716S 9 74 7L 61L 704L HARDISTY 377S 679 L 680 L 7L702 (to Battle River 757S) 7L701 (to Battle River 757S) 702AL 701L 6L05 7LA701 COCHIN PIPELINE FABYAN 968S JARROW 252S SEDGEWICK 137S HILL 751S 9 BUFFALO CREEK 526S STROME 223S HEISLER 764S 1 7L 61AL 32 - Wainwright 12 KITSCOTY 705S 7L42 174L (to Bardo 197S) VERMILION 710S 29 WAINWRIGHT 51S HRT EXPRESS 329S 703L HUGHENDEN 213S 703 L Meti skow (to 64 8 S) EDGERTON 899S 749L (to Metiskow 648S) 7L77 7L65 37 - Provost KILLARNEY LAKE 267S 749AL 748L (to Hayter 277S Existing Constraints There are a number of existing constraints in the study area that are mitigated by remedial action schemes (RASs). Following RAS activation, these constraints are managed in accordance with the procedures set out in Section 302.1 of the ISO rules, Real Time Constraint Management (TCM Rule). As discussed in Section 6.1.3 of this report, the Project does not affect the effectiveness of existing RASs in the study area, nor does the Project create the need for new RASs in the study area. 1.2.2.3. AESO Long-Term Plans Transmission developments are planned as part of the approved Central East Transmission Development (CETD) project to address constraints in the CE sub-region. The CETD developments in/around the study area that are not in service yet are shown in Table 1-1. ATCO Electric February, 2016 13 R2 Connection Engineering Study Report for AUC Application: ATCO Bauer 918S Transformer Addition Table 1-1: Summary of CETD Developments Not Yet In-Service Project Project Name ISD 811-4 St. Paul 707S & 7L139/7L70 Aug. 2016 811-25 Bonnyville 700S Transformer addition Oct. 2016 In addition to the CETD, the AESO 2015 Long-term Plan (2015 LTP)4 also includes the following system developments in the CE sub-region in the near term (by 2020)5: Add voltage reinforcement at Strome substation east of Camrose, Irish Creek substation north of Kitscoty and Whitby Lake substation near Vilna; Add new 240/144 kV substation near Vermilion; Add new 240 kV line from Tinchebray substation northeast of Halkirk to new substation near Vermilion energized at 144 kV; Reconfigure 144 kV lines in vicinity of Vermilion to terminate at new substation; Add new 240 kV line from Hansman Lake substation southeast of Hughenden to Edgerton substation energized at 144 kV; Rebuild 144 kV line from Vermilion to Irish Creek to higher capacity; Add voltage reinforcement in the Cold Lake area. 4 The 2015 LTP document is available on the AESO website. 5 The 2015 LTP identifies the near-term transmission developments in the CE sub-region on pages 44-45. ATCO Electric February, 2016 14 R2 Connection Engineering Study Report for AUC Application: ATCO Bauer 918S Transformer Addition 1.2.3. Studies Performed The following studies were performed for the pre-connection analysis: • Load flow analysis (Category A conditions and Category B contingencies) • Short-circuit analysis (Category A conditions) The following studies were performed for the post-connection analysis: 1.3. • Load flow analysis (Category A conditions and Category B contingencies) • Voltage stability analysis (Category A conditions and Category B contingencies) • Short-circuit analysis (Category A conditions) Report Overview The Executive Summary provides a high-level summary of the report and its conclusions. Section 1 provides an introduction of the Project. Section 2 describes the criteria, system data, and study assumptions used in this study. Section 3 presents the study methodology used in this study. Section 4 discusses the pre-connection system assessment. Section 5 presents the connection alternatives examined. Section 6 provides a technical analysis of the postconnection system assessment for the alternatives selected for further study. Section 7 provides a short-circuit analysis for the pre- and post-connection as well as the future post-connection information. Section 8 discusses project interdependencies. Section 9 presents the conclusions and recommendations of this study. ATCO Electric February, 2016 15 R2 Connection Engineering Study Report for AUC Application: ATCO Bauer 918S Transformer Addition 2. Criteria, System Data, and Study Assumptions 2.1. Criteria, Standards, and Requirements 2.1.1. Transmission Planning Standards and Criteria The Transmission Planning (TPL) Standards, which are included in the Alberta Reliability Standards, and the AESO’s Transmission Planning Criteria – Basis and Assumptions6 (collectively, the Reliability Criteria) were applied to evaluate system performance under Category A system conditions (i.e., all elements in-service) and following Category B contingencies (i.e., single element outage), prior to and following the studied alternatives. Below is a summary of Category A and Category B system conditions. Category A, often referred to as the N-0 condition, represents a normal system with no contingencies and all facilities in service. Under this condition, the system must be able to supply all firm load and firm transfers to other areas. All equipment must operate within its applicable rating, voltages must be within their applicable range, and the system must be stable with no cascading outages. Category B events, often referred to as an N-1 or N-G-1 with the most critical generator out of service, result in the loss of any specified single system element under specified fault conditions with normal clearing. These elements are a generator, a transmission circuit, a transformer or a single pole of a DC transmission line. The acceptable impact on the system is the same as Category A. Planned or controlled interruptions of electric supply to radial customers or some local network customers, connected to or supplied by the faulted element or by the affected area, may occur in certain areas without impacting the overall reliability of the interconnected transmission systems. To prepare for the next contingency, system adjustments are permitted, including curtailments of contracted firm (non-recallable reserved) transmission service electric power transfers. The TPL standards, TPL-001-AB-0 and TPL-002-AB-0, have referenced Applicable Ratings when specifying the required system performance under Category A and Category B events. For the purpose of applying the TPL standards to the studies documented in this report, Applicable Ratings are defined as follows: 6 Seasonal continuous thermal rating of the line’s loading limits. Highest specified loading limits for transformers. For Category A conditions: Voltage range under normal operating condition per AESO Information Document ID# 2010-007RS. For the busses not listed in ID#2010-007RS, Table 2-1 in the Transmission Planning Criteria – Basis and Assumptions applies. Filed under a separate cover. ATCO Electric February, 2016 16 R2 Connection Engineering Study Report for AUC Application: ATCO Bauer 918S Transformer Addition For Category B conditions: the extreme voltage range values per Table 2-1 in the Transmission Planning Criteria – Basis and Assumptions. Desired post-contingency voltage change limits for three defined post event timeframes as provided in Table 2-1, below. Table 2-1: Post Contingency Voltage Deviations Guidelines for Low Voltage Busses Parameter and Reference Point Post Transient (Up to 30 sec.) Time Period Post Auto Control (30 sec. to 5 min.) Post Manual Control (Steady State) ± 10% ± 7% ± 5% Voltage deviation from steady state at low voltage bus 2.1.2. Authoritative Documents (ADs) AESO Information document ID# 2010-007RS, General Operating Practices - Voltage Control, which relates to Section 304.4 of the ISO rules, Maintaining Network Voltage, was used to establish system normal (i.e., pre-contingency) voltage profiles for the study area. The TCM Rule will be followed to assess any criteria violations identified as a result of the connection studies. 2.2. 2.2.1. Load and Generation Assumptions Load Assumptions The study area load forecast used for this connection study is reflected in Table 2-2 and is at CE sub-region peak, which was based on the AESO 2014 Long-term Outlook (2014 LTO). Table 2-2: Forecast Area Load Forecast Peak Load Area Name and Number Season Year (MW) CE sub-region Total (Area 13, 28, 32, 36, 37, 56) AIL without Losses 2.2.2. Winter 2016 979.4 Summer 2017 922.5 Winter 2016 12,154.5 Summer 2017 11,440.4 Generation Assumptions The study scenarios will assume the credible worst condition for the network, which is a no wind scenario. Wind projects in the study area will be dispatched to zero in this study. Table 2-3 provides the list of non-wind generators and their dispatch levels in the study scenarios. Battle River unit #5 is considered to be the critical generating unit in the CE sub-region, and will be turned off in the load flow and voltage stability analysis. ATCO Electric February, 2016 17 R2 Connection Engineering Study Report for AUC Application: ATCO Bauer 918S Transformer Addition Table 2-3: Local Generators in the Study Cases Generator Name Units Symbol Maximum Capacity (MW) Dispatch Level in the Study Scenarios (MW) 2016 WP 2017 SP 1 FCG1 49 47 45 2 FCG2 49 47 45 1 MAHKE-G1 100.8 88 69 2 MAHKE-G2 100.8 88 69 1 NABIYE-2 90 64 56 2 NABIYE-3 90 64 56 1 PRIM 94.5 88 77 3 BAT3 162.6 149 149 4 BAT4 166.3 155 155 5 BAT5 407 Off Off Foster Creek Mahkeses Nabiye Primrose Battle River 2.2.3. Intertie Flow Assumptions The Alberta-BC and Alberta-Montana intertie points are deemed to be too far away to have any material impact on the assessment of the requested connection. Therefore the intertie flows were dispatched the same as in the published AESO’s base cases. The Alberta-Saskatchewan intertie will be set to zero. The HVDC systems are blocked in the study scenarios, since they are not expected to have any material impact on the assessment of the requested connection. 2.3. System Projects Only the system projects in or near the study area that have an earlier ISD than the Project were modelled in the study scenarios. These future system projects are shown in Table 2-4. Table 2-4: Summary of System Projects Included in the Study Cases System Facility Name 2.4. Project ISD CETD EN-4 - St. Paul Upgrades St. Paul 707S, 7L139/7L70 Aug. 2016 CETD EN-25 - Bonnyville 700S Transformer addition Oct. 2016 Customer Connection Projects Table 2-5 identifies customer connection projects in the study area. ATCO Electric February, 2016 18 R2 Connection Engineering Study Report for AUC Application: ATCO Bauer 918S Transformer Addition Table 2-5: Summary of Customer Connection Projects in Study Area Planning Area Queue Position* Project Number Project Name ISD Modelled** in the Study cases 13 72 1554 ATCO Bauer 918S Transformer Addition Feb. 1, 2017 Yes 37 6 851 TransCanada Keystone KXL Pumpstation #2-Eyre (Phase 1) Jul 1, 2016 Yes 37 7 851 TransCanada Keystone KXL Pumpstation #2-Eyre (Phase 2) Jan. 1, 2017 Yes 28 N/A 901 Imperial Oil Cold Lake Expansion Nabiye Plant (Phase 2) Energized Yes 32 17 937 Mainstream Wainwright Wind Project Jan. 3, 2018 Yes 32 N/A 1284 Nilrem 574S Expansion (formerly Lagstaff) Energized Yes 28 N/A 1280 ATCO Bear Trap 940S Substation Capacity Addition Energized Yes 13 N/A 1311 ATCO Irish Creek 706S Upgrades (Load Addition) Energized Yes 32 N/A 1390 Fortis Tucuman 478S-25 kV Breaker Addition Energized Yes 28 N/A 1240 ATCO Pengrowth Lindbergh 969S Breaker Add Energized Yes 37 N/A 1366 Enbridge Sunken Lake Substation Expansion Energized Yes 56 N/A 1350 Strome 223S Transformer Addition Energized Yes 28 N/A 1364 La Corey Area Capacity Increase Energized Yes 13 28 1250 E. ON Grizzly Bear Wind Facility Dec. 15, 2017 Yes 36 37 1472 Fortis Genalta Bellshill DG May 2, 2016 Yes 32 N/A 1454 Fortis Tucuman 478S-T2 25 kV Feeder Breaker Addition Energized Yes 56 38 1410 ATCO Heartland Pump Station Connection Nov. 1, 2017 Yes 28 40 1492 Cenovus Kodiak New Substation and Transmission Line May 31, 2017 Yes 37 N/A 1495 Fortis Hayter 277S 42 MVA Transformer and 25 kV Breaker Addition Energized Yes 28 N/A 1514 Imperial Oil Mahkeses G1&G2 Control And Exciter System Repairs Energized Yes 37 58 1516 Enbridge Sunken Lake 221S Transformer Change July 1, 2017 No# 28 61 1524 AltaGas Kent Generation New POS June. 1, 2017 No# ATCO Electric February, 2016 19 R2 Connection Engineering Study Report for AUC Application: ATCO Bauer 918S Transformer Addition Planning Area Queue Position* Project Number Project Name ISD Modelled** in the Study cases 28 63 1571 ATCO Mahihkan Load Increase-25 KV Breaker Addition Jan. 1, 2017 No# Notes: * Per the AESO Connection Queue posted in January 2016. The projects in the study area that have lower queue positions than Project 1554 have not been listed in this table and were not modelled in the study cases. ** These projects are dispatched per the load and generation levels set out in Section 2.2.1 and Section 2.2.2. # These projects had not yet passed Gate 2 of the AESO Connection Process at the beginning of this study; therefore, they were not modelled in this study. These connection projects will not affect the results of this connection assessment or the conclusions and recommendations contained in this report. 2.5. Facility Ratings and Shunt Elements Table 2-6 provides the ratings of the key existing transmission lines in the study area. Table 2-7 provides a summary of the shunt elements modelled in the study area. Table 2-6: Summary of Key Transmission Line Ratings (MVA on a 138 kV base) Line Number From To Voltage (kV) Summer Rating (MVA) Winter Rating (MVA) 174L Bardo 197S Holden 395S 138 85 90 7L794 Whitby Lake 819S Lac La Biche 157S 144 94 94 701L North Holden 395S Strome 223S 138 119 146 749L Metiskow 648S Killarney Lake Tap 138 121 149 749L Edgertson 899S Killarney Lake Tap 138 88 96 749AL Killarney Lake 267S Killarney Lake Tap 138 121 148 7L130 Vermillion 710S Kitscoty 705S 144 72 86 7L14 Kitscoty 705S Hill 751S 144 72 86 7L24 Bonnyville 700S Grande Centre 846S 144 109 139 7L28 Ethel Lake 717S Grande Centre 846S 144 109 139 7L35 Primrose Tap Primrose 859S 144 140 143 7L42 Hill 751S Lloydminster 716S 144 95 95 7L129 Vermillion 710S Buffalo Creek 526S 144 109 139 7L50 Buffalo Creek 526S Jarrow Tap 144 109 139 7L50 Jarrow tap Battle River 757S 144 109 139 704L Jarrow Tap Jarrow 252S 138 85 90 704L Tucuman 478S Wainwright 515S 138 75 79 704AL Wainright 515S 704L tap 138 121 148 7L53 Bonnyville 700S Irish Creek 706S 144 72 86 7L117 Irish Creek 706S Vermillion 710S 144 95 95 7L65 Vegreville 709S Vermillion 710S 144 95 95 7L66 Leming Lake 715S Ethel Lake 717S 144 109 139 7L139 St. Paul 707S Whitby lake 819S 144 109 139 7L70 Bonnyville 700S St. Paul 707S 144 109 139 ATCO Electric February, 2016 20 R2 Connection Engineering Study Report for AUC Application: ATCO Bauer 918S Transformer Addition Line Number From To Voltage (kV) Summer Rating (MVA) Winter Rating (MVA) 701L/7L701 Strome 223S Battle River 757S 144 140 169 702L Hardisty 377S Sedgewick Tap 137S 139 87 135 7L702 Sedgewick Tap 137S Battle River 757S 144 109 118 7L574 Wolf Lake 822S Bourque 970S 144 247 286 748L Killarney Lake 267S Hayter 277S 138 119 146 749L Edgerton 899S PV Tap 138 88 96 7LB749 PV tap Briker 880S 144 109 139 7L749 PV tap Lloydminster 144 109 139 715L Hansman Lake 650S Provost 545S 138 98 132 7L77 North Holden 395S Vegreville 709S 144 96 96 7L583 Bourque 970S Leming Lake 715S 144 178.3 218.5 7L86 Wolf Lake 822S Foster Creek 877S 144 139 143 7L587 Wolf Lake 822S Marguerite Lake 826S 144 191.7 191.7 7L89 La Corey 721S Bonnyville 700S 144 109 139 7L91 Leming Lake 715S Marguerite Lake 826S 144 109 139 7L92 Whitby lake 819S Vegreville 709S 144 94 94 7L95 Mahkeses 889S Leming Lake 715S 144 190 190 7L105 Mahihkan 837S MahNo 909S 144 109 139 7L146 Bourque 970S Bonnyville 700S 144 191 191 7L157/7L160 Mahihkan 837S Bourque 970S 144 178.3 218.5 7LA129 Bauer 918S 7L129 Tap 144 109 139 Note: Emergency line ratings will be provided, where applicable, for the pre- and post-connection study results. ATCO Electric February, 2016 21 R2 Connection Engineering Study Report for AUC Application: ATCO Bauer 918S Transformer Addition Table 2-7: Summary of Key Shunt Elements in the Study Area Substation Name and Number Nominal Number of Bus Voltage Switched Shunt (kV) Blocks Capacitors Total at Nominal Voltage (MVAr) Reactors Status in Study Number of Switched Shunt Blocks Total at Nominal Voltage (MVAr) Status in Study (on or off) Marguerite Lake 826S 25 - - 3 20 Switch as required Whitefish 825S 240 1 100 - - - Bonnyville 700S 144 3 15 - - - Vermillion 710S 144 1 25 - - - Buffalo Creek 526S 138 1 15 - - - Tucuman 478S 138 1 27 - - - Hardisty 377S 138 1 44.9 - - - - - - Hill 751S 144 - - - Lloydminster 716S 144 St. Paul 707S 25 Sunken Lake 221S 138 Killarney Lake 267S 138 Battle River 757S 72 2.6. Switch as required 1 27 1 20 1 25 - - - 1 20 - - - 1 2.4 - - - 1 4.8 - - - 1 18.1 - - - 1 9.1 - - - 2 10.9 - - - 1 9.19 - - - Off Voltage Profile Assumptions The AESO Voltage Control Practice ID# 2010-007RS is used to establish normal system (i.e., pre-contingency) voltage profiles for key area busses prior to commencing any studies. Table 21 of the Transmission Planning Criteria – Basis and Assumptions applies for all the busses not included in the ID# 2010-007RS. These voltages will be utilized to set the voltage profile for the study base cases prior to load flow analysis. The key bus voltages for the study area for the project are shown in Table 2-8. ATCO Electric February, 2016 22 R2 Connection Engineering Study Report for AUC Application: ATCO Bauer 918S Transformer Addition Table 2-8: Summary of Voltage at Key Nodes in the Study Region AESO ID# 2010-007RS Substation Minimum Nominal Operating Voltage Limit (kV) (kV) Whitefish Lake 825S Pre-connection Post-connection Desired Range (kV) Maximum Operating Limit (kV) 2016 WP 2017 SP 2016 WP 2017 SP 240 253 255-265 275 264.4 266.6 264.4 266.6 Marguerite Lake 826S 240 252 255-268 275 259.6 261.2 259.6 261.2 144 141 148-151 155 150.8 150.8 150.9 150.8 Hill 751S 144 137 143-149 151 147.4 146.9 146.2 145.6 Lloydminster 716S 144 137 142-149 151 147.3 146.8 146.2 145.5 240 250 250-260 260 256.8 256.5 256.8 257.3 Metiskow 648S 3. Voltage in the Study Case (kV) 138 140 140-144 145 143.9 142.1 143.9 142.3 Hardisty 377S 138 140 140-144 145 143.4 140.5 143.3 140.6 Bonnyville 700S 144 140 147-150 155 147.9 148.7 147.8 148.5 Leming Lake 715S 144 140 144-150 155 145.7 146.4 145.8 146.3 Battle River 757S 144 144 146-150 155 147.0 147.9 146.9 147.0 Killarney Lake 267S 138 138 138-144 145 142.8 140.9 142.7 140.9 Study Methodology All the studies were completed using PTI PSS/E version 33. 3.1. Study Objectives The objectives of the study are the following: • Assess the impact of the Project on the performance of the AIES. • Identify any violations of the relevant criteria, standards or requirements of the AESO, both pre- and post-connection of the Project. Recommend mitigation measures, if required, to enable the reliable integration of the project to the AIES. • 3.2. Study Scenarios The scheduled ISD for the Project is February 1, 2017. Hence, the study was conducted for the 2016 WP and 2017 SP. Short-circuit analysis was also completed for the 2024 WP. The study ATCO Electric February, 2016 23 R2 Connection Engineering Study Report for AUC Application: ATCO Bauer 918S Transformer Addition cases were derived from the published AESO’s 2014 Planning Base Case Suite and related auxiliary data files. Table 3-1 lists the scenario and load development considered for the Project in this study. The new load power factor used for this study was 0.9 lagging. Table 3-1: List of the Connection Study Scenarios Scenario Number Study Scenario Project Load (MW) Pre-Connection System 1 2016 WP 18 2 2017 SP 18 Post-Connection System 3.3. 3 2016 WP 31 4 2017 SP 31 Connection Studies Carried Out The following studies were carried out for this connection study: Table 3-2: Summary of Studies Performed Scenario(s) Studied 3.4. Studies Performed System Conditions Studied 3, 4 Load Flow Category A and B -- 3 Voltage Stability Category B 1 3, 2024 WP7 Short-Circuit Category A PreConnection PostConnection 1, 2 Load flow Analysis Load flow analysis was conducted on all study scenarios to identify any thermal overloads or transmission voltage violations as per the Reliability Criteria, and to identify any deviations from the desired limits in Table 2-1. The purpose of the load flow analysis is to quantify any incremental violations in the study area after the Project is connected. Point-of-delivery (POD) low voltage bus deviations were assessed by first locking all tap changers and area capacitors to identify any post-transient voltage deviations above 10%. Tap 7 For the 2024 WP short circuit studies, Battle River unit #3 was switched off because it is expected to retire by 2019. ATCO Electric February, 2016 24 R2 Connection Engineering Study Report for AUC Application: ATCO Bauer 918S Transformer Addition changers were then allowed to move while capacitors remained locked to determine if any voltage deviations above 7% were found in the area. Once all taps and capacitor controls were allowed to adjust, voltage deviations above 5% were reported for both the pre-connection and post-connection networks. 3.4.1. Contingencies Studied For the load flow analysis, the study area was monitored for voltage criteria and thermal criteria violations under Category A conditions and under Category B contingency conditions. The studied contingencies include all transmission single outages (Category B contingencies) within the CE sub-region, as well as the tie lines connecting the study area to surrounding planning area, as shown in Table 3-3. Table 3-3: Summary of Monitored Areas and Contingency Areas for Load Flow Analysis 3.5. Area Number Area Name Voltage Range 13 Lloydminster 69 kV and above 28 Cold Lake 69 kV and above 32 Wainwright 69 kV and above 36 Alliance/Battle River 69 kV and above 37 Provost 69 kV and above 56 Vegreville 69 kV and above Voltage Stability (P-V) Analysis The objective of the voltage stability analysis is to determine the ability of the network to maintain voltage stability at all the busses in the system under normal and abnormal system conditions. The Power-Voltage (PV) curve is a representation of voltage change as a result of increased power transfer between two systems. The reported incremental transfers will be to the collapse point. As per the AESO requirements, no assessment based upon other criteria such as minimum voltage will be made at the PV minimum transfer. Voltage stability analysis for post-connection scenarios will be performed. For load connection projects, the load level modelled in post-connection scenarios are the same or higher than in pre-connection scenarios. Therefore, voltage stability analysis for pre-connection scenarios will only be performed if postconnection scenarios show voltage stability criteria violations. The voltage stability analysis was performed according to the Western Electricity Coordinating Council (WECC) Voltage Stability Assessment Methodology. WECC voltage stability criteria states, for load areas, post-transient voltage stability is required for the area modeled at a minimum of 105% of the reference load level for system normal conditions (Category A) and for single contingencies (Category B). For this standard, the reference load level is the maximum established planned load. Typically, voltage stability analysis is carried out assuming the worst case scenarios in terms of loading. The voltage stability analysis was performed by increasing load in the CE sub-region, and increasing the corresponding generation in the following AESO Planning Areas: Calgary (Area 6) ATCO Electric February, 2016 25 R2 Connection Engineering Study Report for AUC Application: ATCO Bauer 918S Transformer Addition Sheerness (Area 43) Fort McLeod (Area 53) 3.5.1. Contingencies Studied Voltage stability analysis was performed for the Category A condition and all Category B contingencies in the study area for the 2016 WP post-connection scenario to determine the system voltage stability margin in this winter peaking area. 3.6. Short-Circuit Analysis The short-circuit analysis was performed prior to and following the Project connection for the 2016 WP scenario, as well the long-term assessment using the post-connection 2024 WP study scenario. The short-circuit analysis includes three-phase and single-line-to-ground faults. Fault levels, in the form of currents in kilo amperes and per unit positive and zero sequence impedances, are provided for all buses near the Project with all area generators on (except wind generation). 4. Pre-Connection System Assessment 4.1. Pre-Connection Load Flow Analysis Table 4-1 provides an overview of the pre-connection load flow analysis and applicable mitigation measures. Please refer to Attachment A for load flow diagrams. Table 4-1 Overview of pre-connection studies results Condition Category A Category B Results Scenario Contingency Mitigation Measure Result 2016 WP -- -- -- 2017 SP -- -- -- 2016 WP Loss of the 138/25 kV transformer at Metiskow 648S 8 substation Area voltage collapse Currently managed by real time operational practices 2017 SP Loss of the 138/25 kV transformer at Metiskow 648S substation Area voltage collapse Currently managed by real time operational practices 8 While the loss of the 138/25 kV transformer at Metiskow 648S substation is considered a Category B (NG-1) event, this event would result in the simultaneous loss of the 138 kV bus and the 138 kV transmission lines 749L, 703L, and 885L, due to the Metiskow 138 kV bus configuration. ATCO Electric February, 2016 26 R2 Connection Engineering Study Report for AUC Application: ATCO Bauer 918S Transformer Addition Condition Scenario Results Contingency Result Loss of the 138 kV transmission line 749L 4.1.1.1. Mitigation Measure Thermal criteria violation on the 144 kV transmission line 7L130 Currently managed by real time operational practices Thermal criteria violation on the 144 kV transmission line 7L14 Currently managed by real time operational practices Loss of the 144 kV transmission line 7L50 Thermal criteria violation on a segment of the 144 kV transmission line 7L53 Currently managed by real time operational practices Loss of one of the Vegreville 709S substation 9 transformers Thermal criteria violation on a segment of the 144 kV transmission line 7L53 Currently managed by real time operational practices Loss of the 144 kV transmission line 7L130 Thermal criteria violation of a segment of the 138 kV transmission line 749L Currently managed by real time operational practices Loss of the 144 kV transmission line 7L14 Thermal criteria violation of a segment of the 138 kV transmission line 749L Currently managed by real time operational practices Scenario 1 – 2016 WP No Reliability Criteria violations were observed under Category A conditions. No thermal criteria violations were observed under Category B contingency conditions. Under the studied Category B contingency conditions, the following voltage criteria violations were observed: Area voltage collapse following the loss of the 138/25 kV transformer at Metiskow 648S substation. Please see Table 4-2: below and refer to Attachment A for load flow diagrams. 9 While the loss of one of the Vegreville 709S substation transformers is considered a Category B (N-G-1) event, this event would result in the simultaneous loss of the 144 kV bus at Vegreville 709S substation and the 144 kV transmission lines 7L92, 7L77, and 7L65, due to the Vegreville 144kV bus configuration. ATCO Electric February, 2016 27 R2 Connection Engineering Study Report for AUC Application: ATCO Bauer 918S Transformer Addition Table 4-2: Scenario 1, 2016 WP Pre-Connection: N-G-1 Voltage Criteria Violations and POD bus Deviations Substation Name and Number Contingency Bus Number Base kV 138/25 kV transformer at Metiskow 648S substation Initial Voltage (kV) Voltage Deviations for POD Busses Only Post Transient (kV) % Change Post Auto (kV) % Change Post manual (kV) % Change for POD Busses Only Area Voltage Collapse 4.1.1.2. Scenario 2 – 2017 SP No Reliability Criteria violations were observed under Category A conditions. Under the studied Category B contingency conditions the following Reliability Criteria violations were observed. Voltage Criteria Violations: Area voltage collapse following the loss of the 138/25 kV transformer at Metiskow 648S substation, as previously noted in scenario 1. Thermal Criteria Violations: Line loading above emergency line ratings were observed on the 144 kV lines 7L130 (between the Vermilion 710S and Kitscoty 705S substations) and 7L14 (between the Kitscoty 705S and Hill 751S substations) following the loss of the 138 kV line 749L (between the Metiskow 648S and Edgerton 899S substations). Line loading above the emergency line rating was observed on a segment of the 144 kV line 7L53 (between the Bonnyville 700S substation and the Lindbergh 969S substation tap) following two Category B contingencies: Loss of transformer 701T at the Vegreville 709S substation, resulting in the simultaneous loss of the 144 kV bus and the 144 kV transmission lines 7L92, 7L77, and 7L65; or o Loss of the 144 kV line 7L50 (between the Battle River 757S and Buffalo Creek 526S substations). Line loading below the emergency line rating was observed on a segment of the 138 kV line 749L (between the Metiskow 648S substation and the Killarney Lake 267S substation tap) following two Category B contingencies: o Loss of the 144 kV line 7L14 (between the Kitscoty 705S and Hill 751S substations); or o Loss of the 144 kV line 7L130 (between the Vermilion 710S and Kitscoty 705S substations). o Please see Table 4-3 and Table 4-4 below and refer to Attachment A for load flow diagrams. ATCO Electric February, 2016 28 R2 Connection Engineering Study Report for AUC Application: ATCO Bauer 918S Transformer Addition Table 4-3: Scenario 2, 2017 SP Pre-Connection: N-G-1 Line Loading Above Rate A (Continuous Summer Rating) Line Pre-Contingency Post-Contingency Rating % Loading Load Load Contingency Limiting Branch Normal/ % % Difference Flow Flow Emergency Loading Loading (MVA)* (MVA)* (MVA)* 7L130 (Vermilion 710S to Kitscoty 705S) 72 / 72 43.5 60.4 80.9 112.3 51.9 7L14 (Kitscoty 705S to Hill 751S) 72 / 72 38.7 53.7 76.2 105.8 52.1 Vegreville 709S Transformer 7L53 segment (Bonnyville 700S to Lindbergh 969S tap) 72 / 72 59.0 82.0 72.2 100.3 18.3 7L50 (Battle River 757S to Buffalo Creek 526S) 7L53 segment (Bonnyville 700S to Lindbergh 969S tap) 72 / 72 59.0 82.0 77.3 107.3 25.3 7L14 (Kitscoty 705S to Hill 751S) 749L segment (Metiskow 648S to Killarney Lake 267S tap) 121 / 133 87.0 71.9 125.7 103.8 31.9 7L130 (Vermilion 710S to Kitscoty 705S) 749L segment (Metiskow 648S to Killarney Lake 267S tap) 121 / 133 87.0 71.9 129.7 107.2 35.3 749L (Metiskow 648S to Edgerton 899S) *MVA using 138 kV base. Table 4-4: Scenario 2, 2017 SP Pre-Connection: N-G-1 Voltage Criteria Violations and POD bus Deviations Contingency Substation Name and Number 138/25 kV transformer at Metiskow 648S substation Bus Number Base kV Initial Voltage (kV) Voltage Deviations for POD Busses Only Post Transient (kV) % Change Post Auto (kV) % Change Post manual (kV) % Change for POD Busses Only Area Voltage Collapse ATCO Electric February, 2016 29 R2 Connection Engineering Study Report for AUC Application: ATCO Bauer 918S Transformer Addition 5. Connection Alternative 5.1. Overview ATCO, as the DFO in the area southwest of the Town of Vermilion, examined and ruled out the use of a distribution-based solution to serve the industrial load increase request.10 One transmission alternative was identified for the Project, and was studied to evaluate the impact of the Project on the performance of the AIES. 5.2. Connection Alternative Examined Below is a description of the developments associated with the transmission alternative that was examined for the Project.11 Add a transformer at the Bauer 918S substation This connection alternative involves upgrading the existing Bauer 918S substation by adding a second 144/4.16 kV transformer, and by adding a 144 kV breaker. This alternative includes the following: Add one 144/4.16 kV transformer with a minimum transformation capacity of 17.2 MVA; Add a 144 kV circuit breaker; and Add a 4.16 kV circuit breaker and associated equipment. For this connection alternative, a transformer size of 15/20/25 MVA would be recommended based on good electric industry practice and under advisement from the legal owner of transmission facilities (TFO) regarding its asset management and inventory practices. This connection alternative was studied to evaluate the impact of the Project on the performance of the AIES. 10 The DFO’s analysis is reported in sections 5 and 6 of the ATCO Distribution Deficiency Report, Bauer 918S Transformer Addition, which is filed under a separate cover. 11 This alternative reflects more up to date engineering design than the alternative identified in the ATCO Distribution Deficiency Report, Bauer 918S Transformer Addition, which is filed under a separate cover. ATCO Electric February, 2016 30 R2 Connection Engineering Study Report for AUC Application: ATCO Bauer 918S Transformer Addition 6. Technical Analysis of the Connection Alternative 6.1. Alternative 1 Table 6-1 provides an overview of the post-connection analysis. Mitigation measures, where applicable, are discussed in Section 6.1.3. Please refer to Attachment B for load flow diagrams. Table 6-1 Overview of post-connection studies results Results Condition Scenario Contingency Mitigation Measure Impact after Project Result 2016 WP -- -- -- -- 2017 SP -- -- -- -- 2016 WP Loss of the 138/25 kV transformer at Metiskow 648S substation Area voltage collapse N/A Continue to be managed by real time operational practices Loss of the 138/25 kV transformer at Metiskow 648S substation Area voltage collapse Category A Continue to be managed by real time operational practices Thermal criteria violation on the 144 kV transmission line 7L130 No Continue to be managed by real time operational practices Thermal criteria violation on the 144 kV transmission line 7L14 No Continue to be managed by real time operational practices Loss of the 144 kV transmission line 7L50 Thermal criteria violation on a segment of the 144 kV transmission line 7L53 Yes: 6.8% increase over pre-connection loading Continue to be managed by real time operational practices Loss of one of the Vegreville 709S substation transformers Thermal criteria violation on a segment of the 144 kV transmission line 7L53 Yes: 4.8% increase over pre-connection loading Continue to be managed by real time operational practices Loss of the 138 kV transmission line 749L Category B N/A 2017 SP ATCO Electric February, 2016 31 R2 Connection Engineering Study Report for AUC Application: ATCO Bauer 918S Transformer Addition Results Condition 6.1.1. Scenario Contingency Result Impact after Project Mitigation Measure Loss of the 144 kV transmission line 7L130 Thermal criteria violation of a segment of the 138 kV transmission line 749L No Continue to be managed by real time operational practices Loss of the 144 kV transmission line 7L14 Thermal criteria violation of a segment of the 138 kV transmission line 749L No Continue to be managed by real time operational practices Loss of a 138/25 kV transformer at Buffalo Creek 12 526S Thermal criteria violation on a segment of the 144 kV transmission line 7L53 Loss of the 144 kV transmission line 7L65 Thermal criteria violation on a segment of the 144 kV transmission line 7L53 Yes Continue to be managed by real time operational practices Yes Continue to be managed by real time operational practices Load flow Analysis (Alternative 1) 6.1.1.1. Scenario 3: 2016 WP Post-Connection No Reliability Criteria violations were observed under Category A conditions. No thermal criteria violations were observed under Category B contingency conditions. Under the studied Category B contingency conditions, voltage criteria violations that were identified in the pre-connection analysis were also observed in the post-connection analysis: Area voltage collapse following the loss of the 138/25 kV transformer at Metiskow 648S substation. Please refer to Table 6-2 and Attachment B for load flow diagrams. 12 While the loss of a 138/25 kV transformer at Buffalo Creek 526S is considered a Category B (N-G-1) event, this event would result in the simultaneous loss of the 138 kV bus at Buffalo Creek 526S substation and the 144 kV transmission lines 7L129 and 7L50, due to the Buffalo Creek 138 kV bus configuration. ATCO Electric February, 2016 32 R2 Connection Engineering Study Report for AUC Application: ATCO Bauer 918S Transformer Addition Table 6-2: Scenario 3, 2016 WP Post-Connection: N-G-1 Voltage Criteria Violations and POD bus Deviations Substation Name and Number Contingency 138/25 kV transformer at Metiskow 648S substation Bus Number Base kV Initial Voltage (kV) Voltage Deviations for POD Busses Only Post Transient (kV) % Change Post Auto (kV) % Change Post manual (kV) % Change for POD Busses Only Area Voltage Collapse 6.1.1.2. Scenario 4: 2017 SP Post-Connection No Reliability Criteria violations were observed under Category A conditions. Under the studied Category B contingency conditions, Reliability Criteria violations that were identified in the pre-connection analysis were also observed in the post-connection analysis. Voltage Criteria Violations Also Identified in the Pre-Connection Analysis (Scenario 2): Area voltage collapse following the loss of the 138/25 kV transformer at Metiskow 648S substation. Thermal Criteria Violations Also Identified in the Pre-Connection Analysis (Scenario 2): Line loading above emergency line ratings were observed on the 144 kV lines 7L130 (between the Vermilion 710S and Kitscoty 705S substations) and 7L14 (between the Kitscoty 705S and Hill 751S substations) following the loss of the 138 kV line 749L (between the Metiskow 648S and Edgerton 899S substations). The loading on each of these transmission lines does not increase after this post-connection contingency. Line loading above the emergency line rating was observed on a segment of the 144 kV line 7L53 (between the Bonnyville 700S substation and the Lindberg 969S substation tap) following two Category B contingencies. The loading on transmission line 7L53 increased after each these post-connection contingencies: o Loss of transformer 701T at the Vegreville 709S substation, resulting in the simultaneous loss of the 144 kV bus and the 144 kV transmission lines 7L92, 7L77, and 7L65; or o Loss of the 144 kV line 7L50 (between the Battle River 757S and Buffalo Creek 526S substations). Line loading below emergency line rating was observed on a segment of 138 kV line 749L (between the Metiskow 648S and the Killarney Lake 267S tap) following two Category B contingencies. The loading due to these contingencies does not increase after this post-connection contingency. o Loss of the 144 kV line 7L14 (between the Kitscoty 705S and Hill 751S substations); or o Loss of the 144 kV line 7L130 (between the Vermilion 710S and Kitscoty 705S substations). ATCO Electric February, 2016 33 R2 Connection Engineering Study Report for AUC Application: ATCO Bauer 918S Transformer Addition Thermal Criteria Violations Not Identified in the Pre-Connection Analysis: Line loading exceeding the emergency line ratings on the 144 kV transmission line 7L53 (between the Bonnyville 700S substation and Lindbergh 979S substation tap) were observed following two additional Category B contingencies, as follows: o Loss of transformer 701T at the Buffalo Creek 526S substation, which results in the simultaneous loss of the 138 kV bus at Buffalo Creek 526S substation and the 144 kV transmission lines 7L129 and 7L50; o Loss of the 144 kV transmission line 7L65 (between the Vegreville 709S and Vermilion 710S substations) Please refer to Table 6-3, Table 6-4, and to Attachment B. Table 6-3: Scenario 4, 2017 SP Post-Connection: N-G-1 Line Loading Above Rate A (Continuous Summer Rating) Line Pre-Connection Post-Connection Rating % Loading Load Load Contingency Limiting Branch Normal/ % % Difference Flow Flow Emergency Loading Loading (MVA)* (MVA)* (MVA)* 7L130 (Vermilion 710S to Kitscoty 705S) 72 / 72 80.9 112.3 80.5 111.8 -0.5 7L14 (Kitscoty 705S to Hill 751S) 72 / 72 76.2 105.8 75.8 105.3 -0.5 Vegreville 709S Transformer 701T13 7L53 segment (Bonnyville 700S to Lindbergh 969S tap) 72 / 72 72.2 100.3 75.7 105.1 4.8 Buffalo Creek 526S 14 Transformer 701T 7L53 segment (Bonnyville 700S to Lindbergh 969S tap) 72 / 72 69.1 96.0 73.6 102.2 6.2 7L14 (Kitscoty 705S to Hill 751S) 749L segment (Metiskow 648S to Killarney Lake 267S tap) 121 / 133 125.7 103.8 124.8 103.1 -0.7 7L130 (Vermilion 710S to Kitscoty 705S) 749L segment (Metiskow 648S to Killarney Lake 267S tap) 121 / 133 129.7 107.2 128.7 106.4 -0.8 7L50 (Battle River 757S to Buffalo Creek 526S) 7L53 segment (Bonnyville 700S to Lindbergh 969Stap) 72 / 72 77.3 107.3 82.2 114.1 6.8 7L65 (Vegreville 709S to Vermilion 710S) 7L53 segment (Bonnyville 700S to Lindbergh 969S tap) 72 / 72 69.0 95.9 72.2 100.2 4.3 749L (Metiskow 648S to Edgerton 899S) *MVA using 138 kV base. 13 Loss of transformer 701T at the Vegreville 709S substation would result in the simultaneous loss of the 144 kV bus and the 144 kV transmission lines 7L92, 7L77, and 7L65. 14 Loss of transformer 701T at the Buffalo Creek 526S substation would result in the simultaneous loss of the 138 kV bus at Buffalo Creek 526S substation and the 144 kV transmission lines 7L129 and 7L50. ATCO Electric February, 2016 34 R2 Connection Engineering Study Report for AUC Application: ATCO Bauer 918S Transformer Addition Table 6-4: Scenario 4, 2017 SP Post-Connection: N-G-1 Voltage Criteria Violations and POD bus Deviations Substation Name and Number Contingency Bus Number Base kV Initial Voltage (kV) 138/25 kV transformer at Metiskow 648S substation Voltage Deviations for POD Busses Only Post Transient (kV) % Change Post Auto (kV) % Change Post manual (kV) % Change for POD Busses Only Area Voltage Collapse 6.1.2. Voltage Stability Analysis Voltage stability analysis was conducted for the post-connection 2016 WP scenario. The voltage stability margins were met. The PV graphs for the worst three contingencies are provided in Attachment C. 6.1.2.1. Scenario 3: 2016 Winter Peak (2016 WP) Post Connection The 2016 WP reference load in the study area is 979.4 MW. For the Category B contingency condition, the minimum incremental MW transfer required to meet the 105% load criterion is 49.0 MW (0.05 x 979.4 = 49.0 MW). The average power factor 0.93 for the study area was used for this analysis. Table 6-5 provides the voltage stability analysis results for system normal (N-0) conditions and for the three worst contingencies. The voltage stability criterion was met for all contingencies. Table 6-5: Scenario 3, 2016 WP Post-Connection: Voltage Stability Results Contingency N-0 749L 7L50 7L95* From To System Normal Category B (Minimum Transfer = 49.0 MW) Metiskow 648S Edgerton 899S Battle River 757S Buffalo Creek 526S Leming Lake 715S Mahkeses 889S Maximum Meets Incremental Criteria? Transfer (MW) 481.25 Yes 250.0 275.0 337.5 Yes Yes Yes *Tripping of the plant at Mahkeses 889S results in the same maximum incremental transfer as the loss of the 144 kV transmission line 7L95. 6.1.3. Mitigation Measures The connection assessment identified a number of pre-connection and post-connection system performance issues. Real time operational practices are being used to manage the identified pre-connection system performance issues. Real time operational practices will continue to be used to manage the identified postconnection system performance issues. ATCO Electric February, 2016 35 R2 Connection Engineering Study Report for AUC Application: ATCO Bauer 918S Transformer Addition The Project does not affect the effectiveness of existing RASs in the study area, nor does the Project create the need for new RASs in the study area. Table 6-6, Table 6-7 and Table 6-8 summarize the applicable mitigation measures to manage the post-connection system performance issues. Table 6-6: Scenario 3, 2016 WP Post-Connection: Voltage Criteria Violations and Mitigation Substation Contingency Name and Number Bus Number Base kV Initial Voltage (kV) 138/25 kV transformer at Metiskow 648S substation Voltage Deviations for POD Busses Only Post Transient (kV) % Change Post Auto (kV) % Change Post manual (kV) % Change for POD Busses Only Mitigation Continue to be managed by real time operational practices Area Voltage Collapse Table 6-7: Scenario 4, 2017 SP Post-Connection: N-G-1 Line Loading Above Rate A and Mitigation Line Rating Contingency Limiting Branch Normal/ Emergency (MVA)* Post-Connection Load Flow % (MVA)* Loading 7L130 (Vermilion 710S to Kitscoty 705S) 72 / 72 80.5 111.8 7L14 (Kitscoty 705S to Hill 751S) 72 / 72 75.8 105.3 Vegreville 709S Transformer 701T 7L53 segment (Bonnyville 700S to Lindbergh 969S tap) 72 / 72 75.7 105.1 Buffalo Creek 526S Transformer 701T 7L53 segment (Bonnyville 700S to Lindbergh 969S tap) 72 / 72 73.6 102.2 7L14 (Kitscoty 705S to Hill 751S) 749L segment (Metiskow 648S to Killarney Lake 267S tap) 121 / 133 124.8 103.1 7L130 (Vermilion 710S to Kitscoty 705S) 749L segment (Metiskow 648S to Killarney Lake 267S tap) 121 / 133 128.7 106.4 7L50 (Battle River 757S to Buffalo Creek 526S) 7L53 segment (Bonnyville 700S to Lindbergh 969Stap) 72 / 72 82.2 114.1 7L65 (Vegreville 709S to Vermilion 710S) 7L53 segment (Bonnyville 700S to Lindbergh 969S tap) 72 / 72 72.2 100.2 749L (Metiskow 648S to Edgerton 899S) ATCO Electric Mitigation Continue to be managed by real time operational practices Continue to be managed by real time operational practices February, 2016 36 R2 Connection Engineering Study Report for AUC Application: ATCO Bauer 918S Transformer Addition Table 6-8: Scenario 4, 2017 SP Post-Connection: N-G-1 Voltage Criteria Violations and Mitigation Substation Contingency Name and Number Bus Noumber Initial Base Voltage kV (kV) 138/25 kV transformer at Metiskow 648S substation 6.2. Voltage Deviations for POD Busses Only Post Transient (kV) % Change Post Auto (kV) Area Voltage Collapse % Change Post manual (kV) % Change for POD Busses Only Mitigation Continue to be managed by real time operational practices Conclusions and Recommendations Only one connection alternative was examined for the Project, and was studied to evaluate the impact of the Project on the performance of the AIES. The connection assessment identified a number of pre-connection and post-connection system performance issues. Real time operational practices are being used to manage the identified pre-connection system performance issues and will continue to be used to manage the identified post-connection system performance issues. It is recommended that the Project be connected using the identified connection alternative, and to continue the use of real time operational practices to manage the system performance issues. 7. Short-Circuit Analysis Short-circuit analysis was performed pre- and post-connection using the 2016 WP scenario with all generation in service, except wind generation, in order to provide the maximum short-circuit levels15 in the CE sub-region. The 2024 WP scenario was used for the long-term short-circuit outlook analysis. Single-phase and three-phase fault currents were calculated as provided in the following tables. 7.1. Pre-Connection Table 7-1 provides the 2016 WP short-circuit levels without the Project addition at Bauer 918S substation. 15 Short-circuit current studies were based on modeling information provided to the AESO by third parties. The authenticity of the modeling information has not been validated. Fault levels could change as a result of system developments, new customer connections, or additional generation in the area. It is recommended that these changes be monitored and fault levels reviewed to ensure that the fault levels are within equipment operating limits. The information provided in this study should not be used as the sole source of information for electrical equipment specifications or for the design of safety-grounding systems. ATCO Electric February, 2016 37 R2 Connection Engineering Study Report for AUC Application: ATCO Bauer 918S Transformer Addition Table 7-1: Summary of Short-Circuit Current Levels – Pre-Connection (2016 WP) PrePositive Sequence Base 3-Φ 1-Φ Fault Thevenin Source Voltage Fault Fault Voltage Impedance (R1+jX1) (kV) (kA) (kA) (kV) (pu) Zero Sequence Thevenin Source Impedance (R0+jX0) (pu) Substation Bus Bauer 918S 1113 144 142.2 3.7 0.056002+j0.102466 3.6 0.026860+j0.124441 Buffalo Creek 526S 79 144 142.3 3.8 0.052327+j0.099384 3.1 0.055350+j0.179337 Drury 2007S 1047 144 143.0 3.5 0.060065+j0.110379 3.5 0.027118+j0.123025 Vermilion 710S 1383 144 143.0 3.9 0.055409+j0.096757 4.9 0.003378+j0.045074 7.2. Post-Connection Short-circuit levels are provided in Table 7-2, and Table 7-3 for the 2016 WP and 2024 WP scenarios with the Project addition in service. Table 7-2: Summary of Short-Circuit Current Levels – Post-Connection (2016 WP) Substation PreBase 3-Φ Fault Bus Voltage Fault Voltage (kV) (kA) (kV) Positive Sequence Thevenin Source Impedance (R1+jX1) (pu) 1-Φ Fault (kA) Zero Sequence Thevenin Source Impedance (R0+jX0) (pu) Bauer 918S 1113 144 141.2 3.7 0.057891+j0.101675 3.9 0.016079+j0.101755 Buffalo Creek 526S 79 144 141.5 3.8 0.054421+j0.099915 3.3 0.039105+j0.162776 Drury 2007S 1047 144 142.6 3.4 0.061386+j0.109622 3.5 0.026904+j0.121484 Vermilion 710S 1383 144 142.6 3.9 0.056911+j0.096005 4.9 0.003203+j0.043331 Table 7-3: Summary of Short-Circuit Current Levels – Post-Connection (2024 WP) Substation PreBase 3-Φ Fault Bus Voltage Fault Voltage (kV) (kA) (kV) Positive Sequence Thevenin Source Impedance (R1+jX1) (pu) 1-Φ Fault (kA) Zero Sequence Thevenin Source Impedance (R0+jX0) (pu) Bauer 918S 1113 144 145.5 5.1 0.033011+j0.080577 4.7 0.017701+j0.105244 Buffalo Creek 526S 79 144 144.0 4.5 0.039125+j0.089878 3.5 0.044498+j0.172069 Drury 2007S 1047 144 148.2 7.0 0.022253+j0.060292 7.2 0.010236+j0.057225 ATCO Electric February, 2016 38 R2 Connection Engineering Study Report for AUC Application: ATCO Bauer 918S Transformer Addition Substation Vermilion 710S 8. PreBase 3-Φ Fault Bus Voltage Fault Voltage (kV) (kA) (kV) 1383 144 147.9 Positive Sequence Thevenin Source Impedance (R1+jX1) (pu) 1-Φ Fault (kA) Zero Sequence Thevenin Source Impedance (R0+jX0) (pu) 0.026488+j0.067575 7.2 0.003664+j0.042007 6.2 Project Interdependencies No project interdependencies were identified. ATCO Electric February, 2016 39 R2 Connection Engineering Study Report for AUC Application: ATCO Bauer 918S Transformer Addition 9. Summary and Conclusion The DFO has received a request for a 13 MW load increase at a customer site in the vicinity of the Town of Vermilion. The DFO has submitted a SASR to the AESO to serve industrial load growth in the area. The SASR includes a request for a Rate DTS, Demand Transmission Service, contract capacity increase from 18 MW to 31 MW for the system access service provided at the existing Bauer 918S substation, and a request for transmission development (collectively, the Project). The DFO also requested upgrades to the existing Bauer 918S substation. The scheduled in-service date (ISD) for the Project is February 1, 2017. This report detailed the system performance studies undertaken to assess the impact of the Project on the Alberta Interconnected Electric System (AIES). The connection assessment identified a number of pre-connection and post-connection system performance issues. Real time operational practices are being used to manage the identified pre-connection system performance issues and will continue to be used to manage the identified post-connection system performance issues. It is recommended that the Project be connected using the identified connection alternative, and to continue the use of real time operational practices to manage the system performance issues. ATCO Electric February, 2016 40 R2 ATTACHMENT A Pre-Connection Load Flow Diagrams (2016WP and 2017SP) ATCO Electric R1 A‐1Pre‐ConnectionSystemLoadFlowDiagramsfor2016WPand 2017SP The steady-state power flow diagrams for Category A, and B contingencies are provided in this section. The following table presents the list of load flow diagrams. Load flow diagrams for contingencies that resulted in voltage collapse are not shown. Scenario 1 2 Table A‐1: List of Pre‐connection Power Flow Diagrams Description System Condition Normal (N-0) N-1, Loss of 749L (899S to 648S) N-1, Loss of 701T at 709S 2016WP N-1, Loss of 7L50 N-1, Loss of 7L14 N-1, Loss of 7L130 Normal (N-0) N-1, Loss of 749L (899S to 648S) N-1, Loss of 701T at 709S 2017SP N-1, Loss of 7L50 N-1, Loss of 7L14 N-1, Loss of 7L130 Page Number A-1 / A-2 A-3 / A-4 A-5 / A-6 A-7 / A-8 A-9 / A-10 A-11 / A-12 A-13 / A-14 A-15 / A-16 A-17 / A-18 A-19 / A-20 A-21 / A-22 A-23 / A-24 ATCO Electric R1 ATTACHMENT B Post-Connection Load Flow Diagrams (2016WP and 2017SP) ATCO Electric R1 B‐1Post‐ConnectionSystemLoadFlowDiagramsfor2016WPand 2017SP The steady-state power flow diagrams for Category A, and B contingencies are provided in this section. The following table presents the list of power flow diagrams. Load flow diagrams for contingencies that resulted in voltage collapse are not shown. Scenario 3 4 ATCO Electric Table B‐1: List of Post‐Connection Load Flow Diagrams Description System Condition Normal (N-0) N-1, Loss of 749L (899S to 648S) N-1, Loss of 701T at 709S N-1, Loss of 7L50 2016WP N-1, Loss of 701T at 526S N-1, Loss of 7L65 N-1, Loss of 7L14 N-1, Loss of 7L130 Normal (N-0) N-1, Loss of 749L (899S to 648S) N-1, Loss of 701T at 709S N-1, Loss of 7L50 2017SP N-1, Loss of 701T at 526S N-1, Loss of 7L65 N-1, Loss of 7L14 N-1, Loss of 7L130 Page Number B-1 / B-2 B-3 / B-4 B-5 / B-6 B-7 / B-8 B-9 / B-10 B-11 / B-12 B-13 / B-14 B-15 / B-16 B-17 / B-18 B-19 / B-20 B-21 / B-22 B-23 / B-24 B-25 / B-26 B-27 / B-28 B-29 / B-30 B-31 / B-32 R1 ATTACHMENT C Voltage Stability Curves (2016WP) ATCO Electric R1 C‐12016WPPost‐ConnectionSystemVoltageStabilityAnalysisResults The following figures show the PV curves for the most severe contingencies of 7L50, 7L95, and 749L. These contingencies were run for scenario 3: post-connection 2016WP. There is no plot for the contingency of 648ST1, because this contingency resulted in voltage collapse. Figure 1: Loss of 7L50 145 140 144 kV Bus Voltage (kV) 135 130 125 120 115 110 105 100 95 0.000 50.000 100.000 150.000 200.000 250.000 300.000 Incremental Load Transfer (MW) Bauer ATCO Electric Vermilion Buffalo Creek Minimum Transfer (B) = 49 MW R1 Figure 2: Loss of 749L 144 kV Bus Voltage (kV) 140 130 120 110 100 90 0.000 50.000 100.000 150.000 200.000 250.000 300.000 Incremental Load Transfer (MW) Bauer Vermilion Buffalo Creek Minimum Transfer (B) = 49 MW Figure 3: Loss of 7L95 145 144 kV Bus Voltage (kV) 140 135 130 125 120 115 0.000 50.000 100.000 150.000 200.000 250.000 300.000 350.000 400.000 Incremental Load Transfer (MW) Bauer ATCO Electric Vermilion Buffalo Creek Minimum Transfer (B) = 49 MW R1