...

APPENDIX A CONNECTION ASSESSMENT

by user

on
Category: Documents
13

views

Report

Comments

Transcript

APPENDIX A CONNECTION ASSESSMENT
APPENDIX A
CONNECTION ASSESSMENT
ATCOiiecrric
Connection Engineering Study
Report for AUC Application
Bohn 931 S Transformer Addition
File No. 7570
Revision: 1
Revision Date: 2016-02-09
APEGA Permit to Practice P0850
Connection Engineering Study Report for AUC Application: Bohn 931S Transformer Addition
Executive Summary
Project Overview
ATCO Electric Ltd., in its capacity as the legal owner of distribution facilities (DFO), has
received a request from Enbridge (Athabasca) Pipeline (Enbridge) to expand the electric service
to its Enbridge Janvier surface pump station (Facility) in the Janvier South area for its Wood
Buffalo Pipeline Extension project. The DFO has submitted a System Access Service Request
(SASR) to the Alberta Electric System Operator (AESO), which includes a Rate DTS, Demand
Transmission Service, contract capacity increase from 12 MW to 19 MW. The existing load at
the Facility is served by the Bohn 931S substation. The Bohn 931S substation currently includes
one 15/20/25 MVA 144/4.16 kV transformer and one 4.16 kV breaker dedicated to serving the
Facility load.
The new load includes three new motor/pump sets that will be used to increase the flowrate of
the Enbridge pipeline that runs through the Facility. To meet Enbridge’s operational
requirements, which stipulate that a maximum of four motor/pump sets be connected to one
feeder, at minimum Enbridge needs a dedicated 4.16 kV breaker to serve the new load.
Although the transformer that currently serves the Facility has enough spare capacity available
to connect a new dedicated 4.16 kV breaker, Enbridge has asked that the new dedicated
breaker be connected to a second transformer to improve the reliability of electrical service to
the Facility. The Facility provides pumping support to a key Enbridge pipeline and operates
continuously. A second transformer ensures that the Enbridge pipeline will continue to operate
should there be an outage to one of the transformers.
The requested in-service date (ISD) for the Project is February 1, 2017.
This report presents the results of the study that assesses the impact of the Project on the
Alberta interconnected electric system (AIES).
Existing System
The Facility is located in the Fort McMurray area (AESO planning area 25), which is part of the
AESO Northeast region. The Fort McMurray area occupies the northeast corner of Alberta. The
transmission system in the Fort McMurray area is comprised of 240 kV, 144 kV and 72 kV.
Currently, the Fort McMurray area connects to the AIES through four long 240 kV transmission
lines. Two of these 240 kV lines, 9L55 and 9L930, are part of the 240 kV path connecting Fort
McMurray Area to the Edmonton area (AESO planning area 60) while the third line, 9L56, is part
of the path connecting Fort McMurray area to the High Prairie area (AESO planning area 21)
and 9L15 which connects Fort McMurray area with Peace River area (AESO planning area 19).
The existing constraints in the Northeast region are managed in accordance with Section 302.1
of the ISO rules, Real Time Transmission Constraint Management.1
1
Available on the AESO website
ATCO Electric
1
February 2016
R1
Connection Engineering Study Report for AUC Application: Bohn 931S Transformer Addition
Study Summary
Study Area for the Project
The Study Area for the Project consists of the south-east portion of the Fort McMurray area
(AESO planning area 25).
Studies performed for the Project
Power flow analysis was performed for the 2016 winter peak (2016WP) pre- and postconnection scenarios and the 2017 summer peak (2017SP) post-connection scenario. Voltage
stability analysis was completed for the 2016WP post-connection scenario.
The analyses included all Category A and Category B conditions.
All transmission facilities within the Study Area were studied and monitored to assess the
impact of the Project on the AIES, including any violations of the Reliability Criteria (as defined
in Section 2.1.1).
Results of the pre-connection studies
No Reliability Criteria violations were observed for the pre-connection study scenario.
Connection alternatives examined for the Project
The Project is located close to one point-of-delivery (POD), the Bohn 931S substation. All other
PODs in the area are too far away to effectively serve the requested load addition.
Therefore, the only connection alternative considered for the Project included the addition of a
second 15/20/25 MVA 144/4.16 kV transformer with a dedicated 4.16 kV breaker to the Bohn
931S substation to supply the requested load addition.
Results of the post-connection studies
Category A (N-G-0) conditions
Under Category A conditions, no Reliability Criteria violations were observed for any of the
studied scenarios with the examined alternative.
Category B (N-G-1) contingency conditions
Under Category B contingency conditions, no Reliability Criteria violations were observed for
any of the studied scenarios with the examined alternative.
Conclusions and Recommendation
The study confirmed that the AIES is not adversely impacted by upgrading the Bohn 931S
substation and increasing its DTS. It also confirmed that this alternative is technically viable and
that there are no Reliability Criteria violations. Therefore, it is recommended to proceed with the
addition of a second transformer at the Bohn 931S substation.
ATCO Electric
2
February 2016
R1
Connection Engineering Study Report for AUC Application: Bohn 931S Transformer Addition
Contents
Executive Summary ................................................................................................................................... 1 1. Introduction ......................................................................................................................................... 5 1.1. Project ........................................................................................................................................... 5 1.1.1. Project Overview.................................................................................................................... 5 1.1.2. Load Component ................................................................................................................... 5 1.1.3. Generation Component ......................................................................................................... 6 1.2. Study Scope .................................................................................................................................. 6 1.2.1. Study Objectives .................................................................................................................... 6 1.2.2. Study Area ............................................................................................................................. 6 1.2.3. Studies Performed ................................................................................................................. 9 1.3. Report Overview ............................................................................................................................ 9 2. Criteria, System Data, and Study Assumptions ............................................................................. 10 2.1. Criteria, Standards, and Requirements ....................................................................................... 10 2.1.1. Transmission Planning Standards and Criteria ............................................................. 10 2.1.2. AESO Rules ........................................................................................................................ 11 2.2. Load and Generation Assumptions ............................................................................................. 11 2.2.1. Load Assumptions ............................................................................................................... 11 2.2.2. Generation Assumptions ..................................................................................................... 11 2.2.3. Intertie Flow and High Voltage Direct Current (HVDC) Line Flow Assumptions ................. 13 2.3. System Projects........................................................................................................................... 13 2.4. Customer Connection Projects.................................................................................................... 13 2.5. Facility Ratings and Shunt Elements........................................................................................... 13 2.6. Voltage Profile Assumptions ....................................................................................................... 14 3. Study Methodology ........................................................................................................................... 16 3.1. Study Objectives.......................................................................................................................... 16 3.2. Study Scenarios .......................................................................................................................... 16 3.3. Connection Studies Carried Out.................................................................................................. 16 3.4. Power flow Analysis .................................................................................................................. 17 3.4.1. Contingencies Studied ...................................................................................................... 17 3.5. Voltage Stability Analysis ............................................................................................................ 17 3.5.1. Contingencies Studied ......................................................................................................... 17 4. Pre-Connection System Assessment ............................................................................................. 18 4.1. Pre-Connection Power flow Analysis .......................................................................................... 18 4.1.1. Scenario 1: 2016WP Pre-Connection.................................................................................. 18 5. Connection Alternatives ................................................................................................................... 18 5.1. Connection Alternative Identified................................................................................................. 18 5.1.1. Connection Alternatives Selected for Further Studies .................................................. 19 5.1.2. Connection Alternatives Not Selected for Further Studies .................................................. 19 6. Post-Connection System Assessment ........................................................................................... 20 6.1. Post-Connection Power Flow Analysis........................................................................................ 20 6.1.1. Scenario 2: 2016WP Post-Connection ................................................................................ 20 6.1.2. Scenario 3: 2017SP Post-Connection ................................................................................. 20 6.2. Post-Connection Voltage Stability Analysis................................................................................. 20 6.2.1. Scenario 2: 2016WP Post-Connection ................................................................................ 20 ATCO Electric
3
February 2016
R1
Connection Engineering Study Report for AUC Application: Bohn 931S Transformer Addition
6.3. Mitigation Measures for Identified Issues .................................................................................... 21 6.4. Conclusions and Recommendations ........................................................................................... 21 7. Project Interdependencies ............................................................................................................... 21 8. Conclusions and Recommendations .............................................................................................. 21 Attachments
Attachment A
Pre-Connection System Power Flow Plots
Attachment B
Post-Connection System Power Flow Plots
Attachment C
Post-Connection System Voltage Stability Analysis Results
Figures
Figure 1-1: Fort McMurray Area Transmission Network................................................................................................. 7 Figure 1-2: The Transmission Network in the Study Area .............................................................................................. 8 Figure 5-1: Alternative 1 - Serve load from the existing Bohn 931S Substation ........................................................... 19 Tables
Table 1-1: Summary of Recently Energized System Projects in the Study Area ........................................................... 9 Table 2-1: Post-Contingency Voltage Deviation Guidelines for Low Voltage Busses .................................................. 11 Table 2-2: Fort McMurray Area Coincident 2014 LTO Peak Load Forecasted ............................................................ 11 Table 2-3: Key Generation Facilities by Study Scenarios ............................................................................................ 12 Table 2-4: Summary of Customer Connection Projects Assumptions .......................................................................... 13 Table 2-5: Key Transmission Line Ratings in the Study Area (MVA) ........................................................................... 13 Table 3-1: Study Scenarios Analyzed .......................................................................................................................... 16 Table 3-2: Summary of Studies Performed .................................................................................................................. 16 Table 6-1: Scenario 2 - 2016WP Post-Connection (Voltage Stability Analysis Results) .............................................. 20
ATCO Electric
4
February 2016
R1
Connection Engineering Study Report for AUC Application: Bohn 931S Transformer Addition
1.
Introduction
This Engineering Study Report presents the results of the study that assesses the impact of the
Project (as defined below) on the AIES.
1.1. Project
1.1.1. Project Overview
ATCO, in its capacity as the DFO in the Janvier South area, has received a request from
Enbridge to expand the electric service to its Facility for the Wood Buffalo Pipeline Extension
project. The DFO has submitted a SASR to the AESO, which includes a Rate DTS, Demand
Transmission Service, contract capacity increase from 12 MW to 19 MW. The existing load at
the Facility is served by the Bohn 931S substation. The substation currently includes one
15/20/25 MVA 144/4.16 kV transformer and one 4.16 kV breaker dedicated to serving the
Facility load.
The new load includes three new motor/pump sets that will be used to increase the pipeline
flowrate of the Enbridge pipeline that runs through the Facility. To meet Enbridge’s operational
requirements, which stipulate that a maximum of four motor/pump sets be connected to one
feeder, at minimum Enbridge needs a dedicated 4.16 kV breaker to serve the new load.
Although the transformer that currently serves the Facility has enough spare capacity available
to connect a new dedicated 4.16 kV breaker, Enbridge has asked that the new dedicated
breaker be connected to a second transformer to improve the reliability of electrical service to
the Facility. The Facility provides pumping support to a key Enbridge pipeline and operates
continuously. A second transformer ensures that the Enbridge pipeline will continue to operate
should there be an outage to one of the transformers.
In this report, connecting the load addition at the Facility will be referred to as the Project. The
requested ISD for the Project is February 1, 2017.
1.1.2. Load Component
Existing DTS contract capacity: 12 MW.
Requested DTS contract capacity: 19 MW.
Power Factor Studied: 0.9 lagging.
Load Type: Industrial motor/ pump station.
Existing Number of Motors: 3.
Number of Motors with new load: 6.
Future Allowance for Load Growth: Enbridge does not currently have future expansion plans to
increase the load above 19 MW at its Facility.
ATCO Electric
5
February 2016
Connection Engineering Study Report for AUC Application: Bohn 931S Transformer Addition
1.1.3. Generation Component
There is no generation component associated with the Project.
1.2. Study Scope
1.2.1. Study Objectives
The objectives of the study are as follows:



Assess the impact of the Project on the performance of the AIES.
Identify any violations of the Reliability Criteria, standards or requirements of the AESO
both pre- and post-connection of the Project.
Mitigation measures, if required, to enable the reliable connection of the Project to the
AIES.
1.2.2.
Study Area
1.2.2.1.
Study Area Description
The Project is located within the Fort McMurray area which is part of the Northeast region.
The Study Area for the Project consists of the south-east portion of the Fort McMurray area
(AESO planning area 25).
The transmission system in the Fort McMurray Area is comprised of 240 kV, 144 kV and 72 kV.
Currently, the Fort McMurray area connects to the AIES through four long 240 kV transmission
lines. Two of these 240 kV lines, 9L55 and 9L930, are part of the 240 kV path connecting Fort
McMurray Area to the Edmonton area (AESO planning area 60) while the third line, 9L56, is part
of the path connecting Fort McMurray area to the Wabamun area (AESO planning area 40) and
9L15 which connects Fort McMurray area with Peace River area (AESO planning area 19).
Figure 1-1 shows transmission network of the Fort McMurray Area. Figure 1-2 shows the
transmission network of the Study Area.
ATCO Electric
6
February 2016
Connection Engineering Study Report for AUC Application: Bohn 931S Transformer Addition
Figure 1-1: Fort McMurray Area Transmission Network
CNRL Horizon
(CNR5)
HORIZON
UPGRADING
842S
9L101
9L
69
AURORA
9L32
KVAL-1
KVAL-2
9L84
STEEPBANK
836S
29EDD-55
9L2
7L
47
RUTH
LAKE
848S
7L
71
DOG RIB
2082S
74
7L165
9L
29PL9-14
29PL9-15
29PL6-24
29EDD-93
29EDD-9
HORSESHOE
737S
29EDD-8
29EDD-10
29EDD-19
29EDD-45
29EDD
-0020
29EDD-33
29EDD-19
3
29PL6-28
29EDD-62
29EDD-31
29EDD-46
29EDD-64
29EDD-84
29EDD-83
7
A9
7L
7L126
9L85
GREGOIRE
883S
7
18
L
3
7LA183
ENGSTROM
2060S
MEADOW
CREEK 2081S
MEG1 Christina
Lake (MEG1)
BOHN
931S
957
QUIGLEY
989S
SUNDAY
CREEK 539S
CHRISTINA
LAKE 723S
CONKLIN
762S
1118L
971L
05
90
7L
9L9
LEISMER
72S
9L55 (to
Round
Hill 852S)
MCMILLAN
885S
7L1
14
7LA114
CROW
860S
9L930 (to
Heart Lake
898S)
7L02
7L02
45
KETTLE
RIVER
2049S
9L
7L121
9L89
7L
MARIANA
833S
5
7L104
HORSE
RIVER
917S
240 kV Double Circuit
P1570 Project Area
AESO Planning Areas
7L1
KINOSIS
856S
7LA121
LONG
LAKE
841S
LONG LAKE
COGEN 864S
BLACK
SPRUCE
154S
1115L
(to Pike
170S)
7L38
ALGAR
875S
Nexen Inc
#2 (NX02)
7
7L155
16
7L182
7L194
CHARD
658S
240 kV
SALT CREEK
977S
7L36
WILLOW
LAKE 2009S
LIVOCK
939S
138/144 kV
138/144 kV Double Circuit
7L1
35
HANGINGSTONE
820S
7L
9L89
7L97
AHS 01
279S
7
9L5
9L
M 56 (
73 itsu to
2S e
)
ATCO Electric
29EDD-67
HALFWAY
2014S
WADDEL
907S
Currency Date: 2016-01-29
29
EDD-7
29PL6-16
29PL6-29
29PL6-26
9L07
29PL6-7
29PL6-14
29EDD
-0056
29PL9-6
29EDD
-32
ATHABASCA
CROSSING
EDD200
SCR1
29PL6-23
29PL6-22
29PL6-05
29PL6-06
SCR1
6L
32
SCR5
29EDD-5
TOWER
ROAD 933S
WABASCA
720S
Gas Generator
69 or 72 kV Substation
138 or 144 kV Substation
240 kV Substation
69/72 kV
9
29PL6-01
9L01
FIREBAG
29EDD-18
29EDD-0063
29PL6-27
BRINTNELL
876S
PL
4
29PL9-5
29PL6-04
9- 2
1
PL
29 L 9 P
29
MACKAY
RIVER 874S
BIRCHWOOD
CREEK 960S
9L10
56
29
/
-3
PARSONS
CREEK 718S
7L170
9L
29EDD-3
MILLENIUM
29EDD-1
RL1
RL2
6LML2
6LML1
SCR1
29PL6-20
PLANT
30-2
UE-1
SCR6
DAWES
2011S
9L15 (to Wesley
Creek 834S)
SUNCOR
FACILITY
SCR1
29EDD-22
29EDD-2
29PL6-02
9L74
9L58
9L43
9L0
1
9L0
7
SCR1
29PL7-1
29PL6-03
9L08
9L09
East
Mine
DML
MacKay
River (MKRC)
9L 28
9L19
JACK
PINE
920S
29EDD-71
29PL7-3
29PL7-4
Muskeg
River (MKR1)
MILDRED
LAKE
9L58
AMR02
937S
29EDD-65
9LJH1
9LJH2
D05
DOVER
888S
9L39
MUSKEG
RIVER
847S
9L66
GREEN
STOCKING
925S
9L77
BLACK FLY
934S
Syncrude #1
(SCL1)
Syncrude #1
(SCL1)
25 - Fort McMurray
KEARL
9900S
L9900
29PL7-5
75_PLH-902
MCCLELLAND
957S
9L32
JOSLYN
CREEK
849S
This diagram contains a simplified
version of the system configuration.
Technical detail has been simplified
for illustration purposes. It does not
indicate geographical locations of facilities.
IOR3 Kearl
(IOR3)
BITUMOUNT
941S
29PL7-2
75-PLH-3
29PL6-23
75-PLH-4
29PL9-12
29PL9-13
HORIZON
MINING
838S
75_PLH-901
Project 1570 Area
Transmission System
1099L
1090L
JACKFISH
698S
February 2016
Connection Engineering Study Report for AUC Application: Bohn 931S Transformer Addition
AHS 01
279S
9L84 (to Black
Fly 934S)
7L1
35
HANGINGSTONE
820S
SALT
CREEK
977S
7L126
7L182
9L07 (to
Dover 888S)
7LA97
HALFWAY
2014S
9L23 (to Ruth
Lake 848S)
Project 1570 Area
Transmission System
7L97 (to Tower
Road 933S)
Figure 1-2: The Transmission Network in the Study Area
7L36
4
7L19
Nexen Inc
#2 (NX02)
GREGOIRE
883S
7L155
ALGAR
875S
7L38
KINOSIS
856S
7LA183
KETTLE
RIVER
2049S
7L02
7L1
14
7LA114
CROW
860S
WADDEL
907S
9L9
90
CHARD
658S
LEISMER
72S
MCMILLAN
885S
BOHN
931S
957
L
MEADOW
CREEK
2081S
SUNDAY
CREEK
539S
MEG1 Christina
Lake (MEG1)
1118L
CONKLIN
762S
1099L
9L55 (to
Round Hill
852S)
CHRISTINA
LAKE 723S
9L930 (to Heart
Lake 898S)
Gas Generator
138 or 144 kV Substation
240 kV Substation
7L
05
ENGSTROM
2060S
971L
9L
45
7L
18
3
MARIANA
833S
7LA121
This diagram contains a simplified
version of the system configuration.
Technical detail has been simplified
for illustration purposes. It does not
indicate geographical locations of facilities.
QUIGLEY
989S
7L104
25 - Fort McMurray
7L121
9L89
LONG
LAKE
841S
5
7L1
HORSE
RIVER
917S
Currency Date: 2016-01-11
LONGLAKE
COGEN 864S
7L
16
7
7L170
9L
85
DAWES
2011S
WILLOW LAKE
2009S
138/144 kV
240 kV
P1570 Project Area
AESO Planning Areas
BLACK
SPRUCE
154S
1090L
JACKFISH
698S
27 - Athabasca / Lac La Biche
1
Pi 115
ke L
17 (to
0S
)
28 Cold
Lake
1.2.2.2. Existing Constraints
The Northeast region is currently managed by the AESO Rule 302.1 Information Document
ID#2011-008(R) - Real Time Transmission Constraint Management (TCM Rule). This AESO ID
specifies the Fort McMurray Export Cutplane Transfer-out-Limits (710 MW) and the Fort
McMurray Import Cutplane Transfer-In-Limits (593 MW (Voltage) / 512 MW (Thermal)). These
transfer levels are based on the existing transmission network configuration and represent the
system normal condition (all transmission elements in service).
ATCO Electric
8
February 2016
Connection Engineering Study Report for AUC Application: Bohn 931S Transformer Addition
1.2.2.3.
AESO Long-Term Plans
The AESO published the AESO 2015 Long Term Plan (2015 LTP) in November 2015. There
are no transmission developments proposed for the Study Area in the near-term.2 Table 1-1
shows system reinforcements in the Fort McMurray area recently energized.
Table 1-1: Summary of Recently Energized System Projects in the Study Area
Project Name
Whitefish 825S 100 MVAr capacitor bank addition
Dover 888S 100 MVAr capacitor bank addition
Leismer 72S 60 MVAr capacitor bank addition
Winefred 818S 42 MVAR capacitor bank addition
Kettle River 2049S 60 MVAr capacitor bank addition
Kinosis area 60 MVAr capacitor bank addition
Algar Area System Reinforcement Project
Christina Lake Area Transmission Development project
1.2.3.
Studies Performed
The following studies were performed for both the pre-connection and post-connection analysis:
•
Power flow analysis (Category A and B).
The following studies were performed for the post-connection analysis:
•
Voltage stability analysis (Category A and B).
For load connection projects, the load level modelled in post-connection scenarios is the same
or higher than in pre-connection scenarios. Therefore, voltage stability analysis for preconnection scenarios will only be performed if post-connection scenarios show voltage stability
criteria violations.
1.3.
Report Overview
The Executive Summary provides a high-level summary of the report and its conclusions.
Section 1 provides an introduction of the Project. Section 2 describes the Reliability Criteria,
system data, and other study assumptions used in this report. Section 3 describes the study
methodology used. Section 4 discusses the pre-connection assessment of the system. Section
5 presents the connection alternatives identified. Section 6 provides a technical analysis of the
connection alternative selected for further study. Section 7 discusses project interdependencies.
Section 8 presents a conclusions and recommendations of this study.
2
Refer to: AESO 2015 Long-term Transmission Plan available on the AESO website.
ATCO Electric
9
February 2016
Connection Engineering Study Report for AUC Application: Bohn 931S Transformer Addition
2.
2.1.
Criteria, System Data, and Study Assumptions
Criteria, Standards, and Requirements
2.1.1.
Transmission Planning Standards and Criteria
The Transmission Planning (TPL) Standards, which are included in the Alberta Reliability
Standards, and the AESO’s Transmission Planning Criteria – Basis and Assumptions3
(collectively, the Reliability Criteria) were applied to evaluate system performance under
Category A system conditions (i.e., all elements in-service) and following Category B
contingencies (i.e., single element outage), prior to and following the studied alternatives. Below
is a summary of Category A and Category B system conditions.
Category A, often referred to as the N-0 condition, represents a normal system with no
contingencies and all facilities in service. Under this condition, the system must be able to
supply all firm load and firm transfers to other areas. All equipment must operate within its
applicable rating, voltages must be within their applicable range, and the system must be stable
with no cascading outages.
Category B events, often referred to as an N-1 or N-G-1 with the most critical generator out of
service, result in the loss of any single specified system element under specified fault conditions
with normal clearing. These elements are a generator, a transmission circuit, a transformer, or a
single pole of a DC transmission line. The acceptable impact on the system is the same as
Category A. Planned or controlled interruptions of electric supply to radial customers or some
local network customers, connected to or supplied by the faulted element or by the affected
area, may occur in certain areas without impacting the overall reliability of the interconnected
transmission systems. To prepare for the next contingency, system adjustments are permitted,
including curtailments of contracted firm (non-recallable reserved) transmission service electric
power transfers.
The TPL standards, TPL-001-AB-0 and TPL-002-AB-0 have referenced Applicable Rating when
specifying the required system performance under Category A and Category B events. For the
purpose of applying the TPL standards to the studies documented in this report Applicable
Ratings are defined as follows:
•
Seasonal continuous thermal rating of the line’s loading limits.
•
Highest specified loading limits for transformers.
•
For Category A conditions: Voltage range under normal operating condition per AESO
Information Document ID# 2010-007RS, General Operating Practice – Voltage Control.
•
For Category B conditions: The extreme voltage range as applicable from Table 2-1 in the
Transmission Planning Criteria – Basis and Assumptions.
•
Desired post-contingency voltage deviations for three defined post event timeframes as
provided in Table 2-1 below.
3
Filed under a separate cover
ATCO Electric
10
February 2016
Connection Engineering Study Report for AUC Application: Bohn 931S Transformer Addition
The post contingency voltage deviations following Category B events were compared with
the guidelines in Table 2-1.
Table 2-1: Post-Contingency Voltage Deviation Guidelines for Low Voltage Busses
Time Period
Post-Transient
(Up to 30 sec)
Post-Auto Control
(30 sec to 5 min)
Post-manual Control
(Steady State)
Voltage Deviation from
Steady State at POD
Low Voltage Bus
± 10%
± 7%
± 5%
2.1.2.
AESO Rules
ISO rules Section 304.4 ID #2010-007RS4 was used to set the system pre-contingency voltages
at critical busses to be within the desired range. The Northeast region constraints are outlined in
AESO ID#2011-008R5.
The AESO Voltage Control Practice ID # 2010-007RS, which relates to Section 304.4 of the ISO
Rules, Maintaining Network Voltage will be applied to establish pre-contingency voltage profiles
in the study region. The TCM Rule will be followed in setting up the study scenarios and
assessment of the connection impact. In addition, due regard will be given to the AESO
Customer Connection Study Requirements Document and the Generation and Load
Interconnection Standard.
2.2.
2.2.1.
Load and Generation Assumptions
Load Assumptions
The Fort McMurray area load forecast used for this connection study is reflected in Table 2-2
and is based on the AESO 2014 Long-Term Outlook (LTO).
Table 2-2: Fort McMurray Area Coincident 2014 LTO Peak Load Forecasted
Area Name
2016WP
Forecast Peak Load
(MW)
2017SP
Forecast Peak Load
(MW)
Fort McMurray area
2614.9
2363.5
Alberta Internal Load (AIL) without Losses
12154.5
11441
2.2.2. Generation Assumptions
The generation within the Northeast region contains natural gas-fired generation from industrial
sites in the Fort Saskatchewan (AESO planning area 33), Fort McMurray and Cold Lake areas,
and biomass generation in the Athabasca/Lac La Biche area (AESO planning area 27).
4
5
Available on the AESO website
Available on the AESO website
ATCO Electric
11
February 2016
Connection Engineering Study Report for AUC Application: Bohn 931S Transformer Addition
Table 2-3 provides the area generation assumptions used in this engineering study. The MEGConklin generator is defined as the Study Area critical generator and its status is off on all
analyses.
Table 2-3: Key Generation Facilities by Study Scenarios
Area
Capacity
(MW)
2016WP
Unit Net
Generation
(MW)
2017SP
Unit Net
Generation (MW)
13249
25
80
80
78
LONGLAKE G2
12249
25
80
80
78
Existing
LONGLAKE G3
11241
25
11.5
11
11
Existing
LONGLAKE G4
11241
25
11.5
11
11
Existing
MEG-Conklin
2405
25
85
Offline
0ffline
Existing
MEG-Conklin 2B
3405
25
85
85
70
Future
Project 1245
23754
25
50
44
38
Future
Project 1245
23755
25
50
44
38
Existing
Mackay
18274
25
185
181
153
Existing
Syncrude G1
19209
25
53
42
37
Existing
Syncrude-UE-1-G11
17233
25
22
18
15
Existing
Syncrude-UE-1-G12
16233
25
86
69
61
Existing
Syncrude G2
18209
25
53
42
37
Existing
Syncrude G20
18206
25
100
80
70
Existing
Syncrude G21
18207
25
100
80
70
Existing
Syncrude G3
17209
25
28.8
23
20
Existing
Syncrude G4
17210
25
53
42
37
Existing
Syncrude G5
18210
25
28.8
23
20
Existing
Syncrude G6
19210
25
67.5
54
48
Existing
Suncor 1
16218
25
34.4
31
27
Existing
Suncor 2
18218
25
34.4
31
27
Existing
Millennium 3
16219
25
68.8
62
54
Existing
Millennium 4
18223
25
81
73
63
Existing
Millennium 5
18208
25
130.5
118
102
Existing
Millennium 6
19208
25
130.5
118
102
Existing
Suncor
3273
25
86.8
79
68
Existing
Firebag 3 G1
19297
25
85
77
66
Existing
Firebag 3 G2
18297
25
85
77
66
Existing
Firebag 4 G1
17297
25
95
86
74
Existing
Firebag 4 G2
16297
25
95
86
74
Future
Project 1404
(Cenovus Narrows
Lake)
4733
25
50
0
41
Existing/
Future
Plant name
Bus
Number
Existing
LONGLAKE G1
Existing
ATCO Electric
12
February 2016
Connection Engineering Study Report for AUC Application: Bohn 931S Transformer Addition
2.2.3. Intertie Flow and High Voltage Direct Current (HVDC) Line Flow
Assumptions
The intertie points are deemed to be too far away to have an effect on the assessment of the
proposed connection. The flows in the Study Area are not influenced by the AIES HVDC
facilities. As a result, the intertie and HVDC assumptions are consistent with that in the AESO
planning base cases.
2.3. System Projects
No additional system projects were identified to be included in the study aside from those listed
in Table 1-1.
2.4. Customer Connection Projects
Table 2-4 lists the customer connection projects included in all study scenarios unless noted
otherwise.
Table 2-4: Summary of Customer Connection Projects Assumptions
AESO Project
Number
Project Description
Generation
(MW)
Load (MW)
Projected inservice date
1245
Cenovus Sunday Creek BTF
30
50
March 1, 2016
1482
ATCO Grand Rapids MacKay Pumpstation
0
1.5
May 6, 2016
1491
ATCO Wabasca 720S-Breaker Addition
0
8
July 1, 2016
1287
Fortis Alberta CNRL - Edwards Lake Substation
0
50
March 1, 2017
1258
Fortis Alberta Grist Lake (Pike) Substation
0
29.2
March 1, 2017
1404*
Cenovus Narrows Lake Substation (Boreal)
0
35
June 1, 2017
1348*
Fort Hills Switching Station
0
20
June 1, 2017
1104*
AOC Dover West Leduc Insitu Bitumen Extraction Facility
0
120
November 20, 2017
*Projects P1404, P1348 and P1104 are included in 2017SP scenario only.
2.5. Facility Ratings and Shunt Elements
Table 2-5 provide the summer and winter ratings of key transmission lines for the Project in the
Study Area.
Table 2-5: Key Transmission Line Ratings in the Study Area (MVA)
Transmission
Line
From Substation
To Substation
Nominal
Voltage
(kV)
Summer
Rating
(MVA)
Winter
Rating
(MVA)
971L
Conklin 762S
Black Spruce 154S
240
624
764
1099L
Black Spruce 154S
Jackfish 698S
240
624
764
1090L
Jackfish 698S
Christina Lake 723S
240
594
713
ATCO Electric
13
February 2016
Connection Engineering Study Report for AUC Application: Bohn 931S Transformer Addition
Transmission
Line
From Substation
To Substation
Nominal
Voltage
(kV)
Summer
Rating
(MVA)
Winter
Rating
(MVA)
9L930
Leismer 72S
Heart Lake 898S
240
592
713
9L45
Kettle River 2049S
Kinosis 856S
240
332
332
9L990
Kinosis 856S
Leismer 72S
240
332
332
1115L
Black Spruce 154S
Pike 170S
240
931
1117
1116L
Pike 170S
Ipiatik 167S
240
874
1103
1117L
Ipiatik 167S
Heart Lake 898S
240
874
1103
Table 2-6 provides the summary of key shunt elements for the Project in the Study Area.
Table 2-6: Key Shunt Elements in the Study Area
Bus Name
Nominal
Bus
Voltage
(kV)
Block
1
Steps
Block 1
Bstep
(Mvar)
Block
2
Steps
Block 2
Bstep
(Mvar)
Block
3
Steps
Block 3
Bstep
(Mvar)
1402
SALTCR1
240
1
-34.96
0
0
0
0
17218
SUNC_R67
13.8
1
8.17
0
0
0
0
18200
RUTH LA9
14.4
3
-5
0
0
0
0
18224
HANGSTO1
25
2
5
0
0
0
0
19200
RUTH LB9
14.4
1
-20
0
0
0
0
19218
SUNC_R68
13.8
1
8.17
0
0
0
0
19224
HANGSTO9
25
2
5
0
0
0
0
468
LEISMER7
138
2
27.19
0
0
0
0
1242
KINOSIS2
138
2
30
0
0
0
0
17204
MCMILLA9
25
1
-20
0
0
0
0
18291
KR03
138
2
27.55
0
0
0
0
19242
KINOSIS3
25
1
-20
0
0
0
0
Bus
Number
2.6. Voltage Profile Assumptions
The voltages at the key Fort McMurray area substations in the study scenarios for the Project
are shown in Table 2-7. The desired voltage ranges as provided in the AESO ID# 2010-007RS
were utilized to set the study scenarios voltages prior to power flow analysis.
Table 2-7: Summary of Voltages at Key Substations in Fort McMurray Area
AESO ID# 2010-007RS
Substation
Whitefish 825S
ATCO Electric
Nominal
Voltage
(kV)
Minimum
Operating
Limit (kV)
Desired
Range (kV)
240
253
255-265
14
Voltage in the Study Scenarios N-G (kV)
Maximum
Operating
Limit (kV)
275
Preconnection
Post-connection
2016WP
2016WP
2017SP
261.6
261.4
265.2
February 2016
Connection Engineering Study Report for AUC Application: Bohn 931S Transformer Addition
AESO ID# 2010-007RS
Substation
Ruth Lake 848S
Dover 888S
Heart Lake 898S
Leismer 72S
Salt Creek 977S
ATCO Electric
Nominal
Voltage
(kV)
Minimum
Operating
Limit (kV)
Desired
Range (kV)
240
248
263– 269
144
141
240
Voltage in the Study Scenarios N-G (kV)
Maximum
Operating
Limit (kV)
Preconnection
Post-connection
2016WP
2016WP
2017SP
275
263.4
263.4
263.5
144-153
155
149.4
149.6
150.6
263
264-271
275
266.7
266.7
266.2
240
258
260-269
275
265.5
265.3
267.7
144
138
140-144
145
143.8
143.7
143.4
240
248
262-271
280
265.4
264.8
264.5
144
138
140-146
150
144.7
144.7
144.8
240
246
258-269
275
263.9
263.4
262.2
144
144
147-152
155
150.3
150.6
150.5
15
February 2016
Connection Engineering Study Report for AUC Application: Bohn 931S Transformer Addition
3.
Study Methodology
All the following analysis was completed using PTI PSS/E version 33.
3.1.
Study Objectives
The objectives of the study are as follows:



Assess the impact of the Project on the performance of the AIES.
Identify any violations of the Reliability Criteria, standards or requirements of the AESO
both pre- and post-connection of the Project.
Recommend mitigation measures, if required, to enable the reliable connection of the
Project into the AIES.
3.2.
Study Scenarios
The study was conducted using the 2016WP and 2017SP scenarios. The study scenarios were
derived from the published AESO’s 2014 Planning Base Case Suite and related auxiliary data
files.
Table 3-1 lists the scenarios considered for the project study. A power factor of 0.9 lagging was
used for the new Facility load.
Table 3-1: Study Scenarios Analyzed
Study
Scenario
Study Scenarios for Alternative
Identified
Facility Load (MW)
System Generation
Dispatch Conditions
2016WP pre-connection
12
Economic
2016WP post-connection
19
Economic
2017SP post-connection
19
Economic
1
2
3
Note that the critical generator identified for this study was the MEG-Conklin unit. The power
flow and voltage stability analyses were performed with this generator out-of-service.
3.3. Connection Studies Carried Out
The following studies were carried out for this connection study:
Table 3-2: Summary of Studies Performed
Study Scenarios
Critical Generator Status
Studies Performed
Conditions Studied
1,2,3
OFF
Power flow
Category A and B
2
OFF
Voltage stability
Category B
ATCO Electric
16
February 2016
Connection Engineering Study Report for AUC Application: Bohn 931S Transformer Addition
3.4.
Power flow Analysis
Power flow analysis was completed to identify any thermal or transmission voltage violations as
per the Reliability Criteria. The purpose of the power flow analysis is to quantify any incremental
violations that are observed following the connection of the Project.
PODs low voltage bus deviations were also assessed by first locking all tap changers and area
capacitors to identify any post transient voltage deviations above 10%. Tap changers were then
allowed to move while capacitors remained locked to determine if any voltage deviations above
7% were found in the area. Once all taps and capacitor controls were allowed to adjust, voltage
deviations above 5% were reported for both the pre-connection and post-connection networks.
3.4.1.
Contingencies Studied
The contingencies studied include all lines and transformers in Study Area as well as ties into it.
The Study Area was monitored for voltage and thermal violations during contingency analysis.
3.5. Voltage Stability Analysis
Voltage stability analysis was performed according to the Western Electricity Coordinating
Council (WECC) Voltage Stability Assessment Methodology. WECC voltage stability criteria
states, “for load areas, post-transient voltage stability is required for the area modelled at a
minimum of 105% of the reference load level for system normal conditions (Category A) and for
single contingencies (Category B)”. For this standard, the reference load level is the maximum
established planned load.
The reference load level is the maximum forecasted load for the Fort McMurray area. The
Wabamun area (AESO planning area 40) was used as the remote generation source for the
voltage stability analysis.
The objective of the Power-Voltage (PV) curve is to determine the ability of the network to
maintain voltage stability at all the busses in the system under normal and abnormal system
conditions. The PV curve is a representation of voltage change as a result of increased power
transfer between two systems. The reported incremental transfers will be to the collapse point.
As per the AESO requirements, no assessment based upon other criteria such as minimum
voltage will be made at the PV minimum transfer.
As per the voltage stability criteria, post-transient techniques (all tap changers, all discrete
capacitors locked, but SVCs were allowed to adjust) were used in applying the criteria and this
information is reflected in all tables and graphs. Also for this analysis, no limits were selected for
the generation sources and non-negative active power constant MVA loads was enforced.
3.5.1.
Contingencies Studied
Voltage stability analysis was performed for the Category A condition and all Category B
contingencies in the study area for the 2016WP post-connection scenario to determine the
system voltage stability margin.
ATCO Electric
17
February 2016
Connection Engineering Study Report for AUC Application: Bohn 931S Transformer Addition
4.
Pre-Connection System Assessment
4.1. Pre-Connection Power flow Analysis
No Reliability Criteria violation was observed for Category A conditions and Category B
contingencies studied in the 2016WP pre-connection scenario within the study area. Please
refer to Attachment A for pre-connection power flow plots for the Study Area.
4.1.1. Scenario 1: 2016WP Pre-Connection
No thermal overloads, voltage violations or POD bus voltage deviations were found for the
Category A condition or the Category B contingencies analyzed.
5.
5.1.
Connection Alternatives
Connection Alternative Identified
Bohn 931S substation is supplying the existing Facility load. The requested load addition is at
the Facility site.
The new load includes three new motor/pump sets that will be used to increase the flowrate of
the Enbridge pipeline that runs through the Facility. To meet Enbridge’s operational
requirements, which stipulate that a maximum of four motor/pump sets be connected to one
feeder, at minimum Enbridge needs a dedicated 4.16 kV breaker to serve the new load.
Although the transformer that currently serves the Facility has enough spare capacity available
to connect a new dedicated 4.16 kV breaker, Enbridge has asked that the new dedicated
breaker be connected to a second transformer to improve the reliability of electrical service to
the Facility. The Facility provides pumping support to a key Enbridge pipeline and operates
continuously. A second transformer ensures that the Enbridge pipeline will continue to operate
should there be an outage to one of the transformers.
ATCO Electric DFO6 concluded that there are no other PODs in the vicinity of the customer site
technically capable of supplying the proposed load effectively. Therefore, only one alternative
was evaluated for this connection project:
6
Please refer to: ATCO Electric 2016 Distribution Deficiency Report Bohn 931S Transformer Addition, which has
been filed under a separate cover.
ATCO Electric
18
February 2016
Connection Engineering Study Report for AUC Application: Bohn 931S Transformer Addition
Alternative 1: Install a second 15/20/25 MVA 144/4.16 kV transformer at the Bohn 931S
substation with a dedicated 4.16 kV breaker
This alternative includes the following work at Bohn 931S:

Installing 1 (one) 15/20/25 MVA 144/4.16 kV LTC transformer.

Installing 1 (one) grounding resistor. Size to be defined by Enbridge.

Installing 1 (one) 144 kV breaker and associated disconnect switch and instrument
transformers.

Installing 1 (one) 4.16 kV breaker and associated disconnect switches.
5.1.1.
Connection Alternatives Selected for Further Studies
Only Alternative 1 was evaluated. The red elements in Figure 5-1 show the proposed
developments in Bohn 931S substation for the connection alternative evaluated.
Figure 5-1: Alternative 1 - Serve load from the existing Bohn 931S Substation
5.1.2.
Connection Alternatives Not Selected for Further Studies
N/A
ATCO Electric
19
February 2016
Connection Engineering Study Report for AUC Application: Bohn 931S Transformer Addition
6.
Post-Connection System Assessment
No transmission criteria violation was found for the contingencies studied in the 2016WP and
2017SP post-connection scenarios within the Study Area. Please refer to Attachment B for postconnection power flow plots. Also, no voltage stability margin problems were found in the Study
Area for this connection project.
6.1. Post-Connection Power Flow Analysis
6.1.1. Scenario 2: 2016WP Post-Connection
No thermal overloads, voltage violations or POD bus voltage deviations were found for any
Category A conditions or Category B contingencies within the Study Area.
6.1.2. Scenario 3: 2017SP Post-Connection
No thermal overloads, voltage violations or POD bus voltage deviations were found for any
Category A or B or selected C5 contingencies within the Study Area.
6.2. Post-Connection Voltage Stability Analysis
The voltage stability analysis was conducted for the 2016WP post-connection scenario.
6.2.1. Scenario 2: 2016WP Post-Connection
In the 2016WP post-connection scenario, the reference load level for the Fort McMurray area is
2614.9MW. The minimum incremental load transfer for the Category B contingencies is 5.0% of
the reference load or 130.75 MW to meet the voltage stability criteria (0.05 x 2614.9MW =
130.75MW). All contingencies met the minimum criteria.
The five worst contingencies for Categories B contingencies are shown in Table 6-1. The PV
curves for the 240 kV transmission line 9L10, the MacKay generator’s transformer, the 240 kV
transmission line 9L43, the 240 kV transmission line 9L57, and the 240 kV transmission line
9L930 contingencies in the Study Area in the 2016WP post-connection scenario are included in
Attachment C.
Table 6-1: Scenario 2 - 2016WP Post-Connection (Voltage Stability Analysis Results)
Contingency
From Substation
To Substation
System Normal (N-G)
Maximum
incremental
transfer (MW)
Meets transfer criteria?
560
YES
Category B (Min Transfer = 130.75 MW)
9L10
Brintnell 876S
Livock 939S
MacKay Generator’s Transformer
9L43
ATCO Electric
Dover 888S
MacKay 874S
20
410
YES
430
YES
440
YES
February 2016
Connection Engineering Study Report for AUC Application: Bohn 931S Transformer Addition
Contingency
From Substation
To Substation
Maximum
incremental
transfer (MW)
Meets transfer criteria?
9L57
Livock 939S
Birchwood Creek 960S
460
YES
9L930
Edwards Lake 89S
Heart Lake 898S
470
YES
6.3. Mitigation Measures for Identified Issues
No Reliability Criteria violations were found in the Study Area for the 2016WP pre- and postconnection scenarios and the 2017SP post-connection scenario for the conditions studied. No
mitigation measures are, therefore, required.
6.4. Conclusions and Recommendations
There were no Reliability Criteria violations found within the Study Area or on the tie lines that
connect it to the AIES for the evaluated connection alternative. Hence, the evaluated connection
alternative is recommended to proceed based on the technical assessment presented in
Section 6.
7.
Project Interdependencies
No project interdependencies were identified.
8.
Conclusions and Recommendations
ATCO, in its capacity as DFO, in the Janvier South area, has received a request from Enbridge
to expand the electric service to its Facility. The DFO has submitted a SASR to the AESO,
which includes a Rate DTS, Demand Transmission Service, contract capacity increase from 12
MW to 19 MW. In addition to increased capacity, Enbridge has asked for a second transformer
to serve its Facility to improve the reliability of the electricity service to its Facility. The existing
load at the Facility is served by the Bohn 931S substation. The ISD requested for the Project is
February 1, 2017.
This report presented the results of the study that assesses the impact of the Project on the
AIES.
The Project is located within the Fort McMurray area, which is part of the Northeast region. The
existing constraints in the Northeast region are managed in accordance Section 302.1 of the
ISO rules, Real Time Transmission Constraint Management.
ATCO Electric
21
February 2016
Connection Engineering Study Report for AUC Application: Bohn 931S Transformer Addition
Study Area
The Study Area chosen was defined as south-east portion of the Fort McMurray area (AESO
planning area 25).
Studies performed for the Project
Power flow analysis was performed for the 2016WP pre- and post-connection scenarios and
2017SP post-connection scenario.
Voltage stability analysis was completed for the 2016WP post-connection scenario.
Results of the pre-connection studies
No Reliability Criteria violations were observed for the pre-connection study scenario.
Connection alternatives examined for the Project
The only alternative considered and evaluated includes adding a second 15/20/25 MVA
144/4.16 kV transformer with a dedicated 4.16 kV breaker at the Bohn 931S substation to
supply the additional Enbridge load. All other PODs in the area are too far away to effectively
serve the requested load addition.
Results of the post-connection studies
Category A (N-G-0) conditions
Under Category A conditions, no Reliability Criteria violations were observed for any of the
studied scenarios with the examined alternative.
Category B (N-G-1) contingency conditions
Under Category B contingency conditions, no Reliability Criteria violations were observed for
any of the studied scenarios with the examined alternative.
Recommendations
The study confirmed that the AIES is not adversely impacted by upgrading the Bohn 931S
substation and increasing its DTS. It also confirmed that this alternative is technically viable and
that there are no Reliability Criteria violations. Therefore, it is recommended to proceed with the
addition of a second transformer at the Bohn 931S substation.
ATCO Electric
22
February 2016
ATTACHMENT A
Pre-Connection System Power Flow Plots
ATCO Electric
A-1
R1
A-1 System Power Flow Results
Power Flow Diagrams
The pre-connection power flow diagrams for Categories A and B contingencies are provided in
this section. The following table presents the list of the power flow diagrams.
Table A-1: List of Pre-Connection Power Flow Diagrams
Scenario
Scenario 1
(2016WP-Pre Project)
Power Flow Diagram
Page
Number
N-G-0, System Normal Condition
A-3
N-G-1, Loss of 9L45
A-4
N-G-1, Loss of 9L990
A-5
N-G-1, Loss of 9L85
A-6
N-G-1, Loss of 9L47
A-7
NOTES: Other power flow diagrams will be provided upon request.
ATCO Electric
A-2
R1
1.1
267.9
9L69
1.1
148.4
1625
DAWES138
42.3
-13.2
-9.4
-9.4
8.8
3.8
10204
885ST1
309
MCMILLA7
6.9
13.2
-98.3
8.0
1.0
143.7
9L56
-29.4
9L22
-65.2
-16.5
-16.5
-65.2
22.7
118.4
22.8
-7.3
180.8
180.8
-7.3
21.8
-62.1
-39.1
21.8
-62.1
14.3
-18.4
19.4
17.2
-46.3
46.3
-22.1
1.1
149.9
1.1
260.5
11245
KINOSIS6
9L81
51.9
1292
MEAD_144
23.1
-0.0
1.1
149.1
-69.9
1.1
266.3
1.0
26.0
SW
1.0
4.3
60.7
24.7
5.9
1242
KINOSIS2
-64.1
-12.0
12.0
99
-12.0
12.0
-5.9
6.6
-6.6
-6.0
1.1
260.5
9L45
29.8
-32.1
-50.3
10291
KR02
6.0
1687
BOHN_01
19687
BOHN_02
-29.8
1245
KINOSIS1
-6.0
-10.3
10.4
-10.2
10282
898ST1
-98.5
144.0
47.0
-21.0
-101.9
1.1
263.7
SW
10.3
-10.3
-9.4
9.4
19.0
17282
HEARTLAK
-78.5
957L
1090L
971L
-129.1
369
CHRISLK1
-93.4
348
LEISMER4
38.7
25.0
24.4
-40.0
879
539S_240
50.5
1.1
264.9
405
CONKLIN1
-37.7
1.1
263.8
1.1
263.9
1.0
144.3
-0.0
SW
39.1
-39.0
-29.1
30.4
428L
-13.9
43.8
1949
ILAKE_01
457L
1.1
261.6
2949
ILAKE_02
CATEGORY A, N-0
2016WP PRE-CONNECTION
MON, JAN 25 2016 14:45
306
WINEFRE7
974
PIKE_01
SW
-45.9
3.0
1.1
264.4
1.0
143.9
-25.1
-13.6
2974
PIKE_02
36
1.5
2405
CONKLIN2
1.0
14.1
-49.6
49.7
-29.9
33.5
71.6
44.4H
282
HEARTLAK
1.1
264.6
-1.5
435
1134L_TP
1118L
1.0
144.1
38.7
1
-3.0
1.6
-8.0
1116
2.6
1.1
264.8
1.0
14.0
3.1
-13.8
434
189_240
-129.4
1099L
878
JFISH01
27.4
321
HEARTLAK
902
BCKSP_01
10.8
52.3
1291
KR01
1.1
264.9
1.1
263.7
9L930
1117L
10295
KR05
9L990
-50.8
19.3
10.3
-32.0
1.0
24.6
48.1
1348
WHITFISH
19291
KR04
0.0
-29.8
44.4
1.1
265.5
9L913
18.4
10245
KINOSIS5
6.0
1.1
147.3
21.1
1.0
143.8
-104.3
P1570 - Bohn 931S Transformer Addition
39.7
SW
7L104
-21.0
1.1
259.8
SW
1.1
261.5
-39.7
18291
KR03
45.8
9L47
14.6
-134.0
1.1
265.1
28.0
-17.2
1.1
148.4
1.1
265.5
1.1
265.6
1228
MITS E.4
-28.0
7L183
1046
21.0
7L114
2.3
1.1
266.8
468
LEISMER7
21.3
-27.8
-7.5
39.7
29.8
799
CHARD_TP
-63.0
25.0
-59.9
12.3
920
ROUND01
9L40
-62.4
7L15
-52.5
-94.1
9L85
1402
SALTCR1
1.1
268.8
1241
LONGLK1
56.8
1.1
263.1
1.0
25.8
9L929
9L56
1409
QUIGL1
-0.0
1.1
148.9
56.1
1.1
148.5
1.0
144.0
1411
WADDELL7
1.1
265.8
9L15
16.3
15241
LONGLK15
179
MARIANA7 1623
ENGSTRM1
SW
8.7
7LA114
1226
WABASCA4
page A-3
15.0
-15.7
7L167
9L55
1010
CHARD_01
20.3
-56.8
-0.9
24.5
1.0
144.8
1.0
144.0
0.0
-0.0
-18.5
-14.9
2.8
1.1
266.4
1260
LOU CR.4
-14.9
-15.7H
SW
-39.7
5.6
1.0
141.9
138
N BARRH4
16.3
19242
KINOSIS3
G2
33.3R
12249
LNGLKCG2
1.1
15.2
6.3
1227
CROWLK7
1.0
142.1
1280
BRINT02
15.0
-15.7
80.0
-26.4
1277
BLK_FLY1
-0.0
1.1
268.7
-79.8
-10.8
9L84
SW
1.1
14.6
1246
LNGLKC02
1276
S-SHINE1
15.0
-13.9
0.7
-79.8
-14.9
-9.1
7L121
-22.5
1249
LNGLKC01
-26.4
M2
1.1
147.2
-8.3
7L02
1.1
147.3
-79.8
-22.7
-5.5
17.8
-25.1
-20.7
4.3
1.1
147.7
1.1
147.3
9.4
1.1
267.0
60.3
-13.9
1008
SALE01
8.1
144
ALGAR 7
1.1
147.2
-11.8
-0.0
-23.2
1.1
265.9
17241
LONGLK17
1.1
148.0
-22.5
5.8
-20.2
-15.9
-15.7H
7L38
1290
HORSERV7
-79.8
30.1R
-14.9
M1
-1.8
5.9
80.0
13249
LNGLKCG1
1.1
15.2
-8.5
1256
SWEETHE7
-8.8
1006
GERMAIN1
9L10
4.6
3.6
13.4
1.0
142.7
1.1
147.9
1286
S-SHINE4
9L39
1.1
261.0
1405
SALTCR2
1.1
147.3
1.1
147.3
3.5
1.1
265.9
16.6
28.9
-42.3
1.0000
18288
LIVOCK03
1602
LIVOCKPS
204
MCMILLA4
1.1
267.7
1.1
14.5
G1
7L36
1.1
267.0
1.6
11402
977S901T
-60.3
7L135
1.1
149.9
1282
WILL01
1.1
148.4
SW
1.1
265.5
21.1
42.3
-18.0
PST
-9.9
10288
LIVOCK02
1288
LIVOCK01
1.1
150.4
1.1
149.9
1.1
149.9
1.1
9L89
20.2
22.7 9L77
10200
848S901T
1201
RUTH LK8
-25.1
-20.2
1224
HANGSTO7
7L194
1.1
267.2
-18.4
13.6
17288
LIVOCK05
-11.7
-34.6
-16.4
-5.9
-43.6
11.7
1.1
264.2
7.5
-51.0
5.7
43.6
-11.8
-16.4
28.4
51.0
1.1
258.9
-43.6
1673
HALF_01
-60.2
10655
DAWE701T
5.6
-28.6
-5.6
-5.7
-11.5
1622
TWR_RD1
21.9
6.8
1.0
24.8
-0.0
-42.3
-51.0
7L170
-0.1
1.1
-0.1
265.8
9L57
9L144
51.1
30.9
7L165
1.1
257.6
-43.0
9L23
-4.2
-9.1
-0.5
1.1
148.4
7
0.0
1462
-15.5
1.1
149.1
1627
7LA97_TP
1.0
247.7
16.9
1239
GREGOIRE
-5.1
-4.6
7L155
-20.2
1.1
148.5
-1.1
1.1
265.8
1670
BWC01
-14.1
48.7
71.1
-51.9
-70.7
1.0
20.9
11.5
11200
848S902T
2.6 -5.9
1.0
143.5
-1.5
1.1
150.0
7L47
43.0
-11.6
7.7
11201
848S703T
23.0 -30.8
1202
RUTH LA7
-23.0
1.1
148.9
-43.0
32.2
4.7 -8.1
1.0
143.9
7L97
9L19
1222
PARS CR7
10201
848S704T
24.4 -32.2
3.5 -3.5
1.1
149.6
6.5
-13.0
13.1
1.1
266.9
1.1
268.0
-11.8
1.1
265.8
1203
RUTH LK7
24.3 -24.3
7L71
1200
RUTH LK4
1.1
263.7
1.1
258.9
43.7
-41.2R
88.0
-87.5
SW
70107
GENCOG7
1655
DAWES240
9L74
1686
DOGRIB01
1.0
20.8
666
DOVER
46.3
9L43
-29.9
3.4
9L07
46.6
1.0
71.7
1.1
149.2
-31.0
-165.7
9L09
9L28
-11.8
1.1
265.8
1626
AMRBUS04
-22.4
62.9
52.0
154.4
1669
AMRBUS01
-22.4
-22.6
9L08
70159
GENCOG59
1.1
262.9
9L58
59
-5.3
-25.9
-22.1
-5.6
-26.0
1.1
267.5
1
60.8R
60.8
14.1
182.2
18274
MACKAY2
1.1
267.2
1208
MILLENN4
9L01
182.2
-123.7
-27.7
82.7
-25.9
-22.1
9L76
1800
ER_01
1.1
267.4
1.1
258.4
167.4
1.0
18.7
-181.2
1.1
266.3
1295
1206
AURORA 4
1212
MIL_G5 4
1205
SYNC_D04
43.1
1274
MACKAY
-39.2
1263
JOSLYN4
1.1
263.9
-32.7
-86.5
1236
MUSKEG1
13.1
6.8
1251
HORMIN1
1.1
264.0
1610
MCCLE_01
-6.0
9L66
1213
MIL_G6 4
-2.5
1603
KEARL240
-51.3
-6.0L
-16.9
33.2
1612
SECORD01
1.1
262.7
9L32
6.8
1.1
264.0
-28.9
-90.2
-16.9
1214
EDD34
118.4
1.1
264.0
-63.5
6.5
1.1
267.9
32.5
6.5
-63.6
109.5
1.1
266.3
1.1
266.8
1.1
266.7
109.5
1680
BITUMONT
1.0
140.8
1483
KIRBY1
Bus - Voltage (kV/pu)
Branch - MW/Mvar
Equipment - MW/Mvar
100.0%Rate B
kV: <=72.000 <=144.000 <=240.000 <=500.000 >500.000
21.9
10.9
3405
CONKLIN4
2
37
1.1
265.7
9L69
1625
DAWES138
42.3
-13.2
1.1
147.3
-13.3
-13.2
-12.2
8.3
10204
885ST1
309
MCMILLA7
7LA114
7.9
1.1
145.7
468
LEISMER7
9L56
-64.9
-16.5
-16.5
-64.9
26.3
118.4
26.4
56.8
-62.5
25.1
-27.9
-23.7
9L22
27.9
-10.2
10.2
180.7
2.0
21.8
-59.8
-12.8
-59.8
15.9
-45.1
39.7
-39.7
39.7
12.6
10245
KINOSIS5
-12.6
13.5
-46.3
46.3
-15.1
1.1
149.9
1.1
260.5
11245
KINOSIS6
1.0
144.9
9L81
-0.0
1.1
149.1
1.1
271.4
1.0
26.0
SW
1.0
4.3
60.7
24.9
1.0
143.7
16.1
-29.8
-66.6
7L104
5.9
1242
KINOSIS2
-64.1
-12.0
12.0
99
-12.0
12.0
-5.9
6.6
-6.6
9L45
29.8
6.0
1687
BOHN_01
19687
BOHN_02
-6.0
1.1
260.5
10291
KR02
-29.8
1245
KINOSIS1
-6.0
11.2
-11.2
11.3
-11.1
10282
898ST1
123.8
51.7
-36.0
-98.8
4.3
53.6
-67.3
9L990
-52.5
1.0
24.7
1.1
266.5
SW
11.2
-11.2
-8.8
8.7
31.4
17282
HEARTLAK
-66.2
957L
1090L
971L
-116.9
369
CHRISLK1
-73.6
348
LEISMER4
38.7
18.0
17.4
-27.7
879
539S_240
50.5
1.1
267.9
405
CONKLIN1
-52.2
1.1
266.2
1.1
266.3
1.1
145.4
-0.0
SW
39.1
-39.0
-29.8
31.1
428L
-13.9
44.5
1949
ILAKE_01
457L
1.1
262.8
2949
ILAKE_02
CATEGORY B, LOSS OF 9L45
2016WP PRE-CONNECTION
MON, JAN 25 2016 14:45
306
WINEFRE7
974
PIKE_01
SW
-46.7
3.0
1.1
266.7
1.1
145.1
-25.1
-13.6
2974
PIKE_02
36
1.5
2405
CONKLIN2
1.0
14.1
-49.6
49.7
-22.9
26.1
71.6
36.9R
282
HEARTLAK
1.1
264.4
-1.5
435
1134L_TP
1118L
1.1
145.3
38.7
1
-3.0
1.6
16.2
1116
7.1
1.1
267.0
1.0
14.2
3.1
-10.9
434
189_240
-117.0
1099L
878
JFISH01
39.8
321
HEARTLAK
902
BCKSP_01
35.0
76.7
1291
KR01
1.1
267.1
1.1
266.4
9L930
1117L
10295
KR05
12.2
19.6
-95.5
53.0
1348
WHITFISH
19291
KR04
0.0
6.0
SW
1046
1.1
267.6
9L913
-27.9
7L183
1292
MEAD_144
-126.1
9L85
1402
SALTCR1
7L15
-36.4
1241
LONGLK1
21.1
1.0
144.7
-105.7
P1570 - Bohn 931S Transformer Addition
1.0
25.2
1.1
262.4
56.1
1.0
144.9
-21.0
1.1
261.3
SW
1.1
261.3
2.0
180.7
16.4
1.1
256.2
18291
KR03
67.3
9L47
14.9
20.5
-137.5
1.1
264.7
-0.0
1.1
145.4
1.1
269.1
1.1
267.3
1228
MITS E.4
-67.3
-15.7
21.0
7L114
2.2
1.1
267.8
0.0
-0.0
29.8
799
CHARD_TP
9L40
15.0
-61.5
6.9
13.7
-106.1
1409
QUIGL1
SW
-12.7
-14.9
15241
LONGLK15
179
MARIANA7 1623
ENGSTRM1
SW
8.7
12249
LNGLKCG2
9L929
9L56
-14.9
-15.7H
19242
KINOSIS3
G2
39.7H
-39.7
7L167
9L55
1010
CHARD_01
21.1
-64.6
-0.6
36.1
9L15
1.1
146.8
1.1
146.0
12.3
920
ROUND01
page A-4
16.4
80.0
-32.2
1277
BLK_FLY1
-0.0
1.1
262.4
-79.8
1246
LNGLKC02
-3.1
9L84
SW
1.0
14.4
1.1
14.9
1.1
146.0
1411
WADDELL7
1.1
265.2
1260
LOU CR.4
15.0
-15.7
2.8
1226
WABASCA4
138
N BARRH4
-14.9
5.6
1.0
141.5
1.1
265.8
-79.8
-32.2
5.9
1227
CROWLK7
-31.9
1249
LNGLKC01
-12.9
7L121
1.0
141.6
1280
BRINT02
21.8
7L165
-2.0
7.7
1.0
144.5
-79.8
1276
S-SHINE1
25.6
-13.8
-4.1
13249
LNGLKCG1
M2
1.0
143.6
-8.0
7L02
-31.9
-22.7
-5.5
11.1
-25.1
-42.0
8.1
1.1
147.4
1.1
147.3
13.2
1.1
264.3
51.1
-13.8
1008
SALE01
-0.0
-23.2
1.1
266.0
144
ALGAR 7
17241
LONGLK17
1.1
147.6
-79.8
40.2H
5.9
-20.3
-11.6
-15.7H
7L38
1290
HORSERV7
80.0
-14.9
M1
-5.6
5.6
1286
S-SHINE4
9L39
1.1
257.7
1405
SALTCR2
1.0
144.4
1.0
144.5
1.1
14.9
-6.9
1256
SWEETHE7
-8.3
1006
GERMAIN1
9L10
22.2
3.6
13.4
1.0
142.3
1.1
147.4
1.0
14.4
3.5
1.1
265.1
16.6
28.9
1602
LIVOCKPS
-42.3
1.0000
18288
LIVOCK03
204
MCMILLA4
1.1
267.8
1.1
264.3
1.7
11402
977S901T
-51.1
7L135
G1
7L36
SW
1.1
264.7
21.1
42.3
-6.4
PST
-10.0
10288
LIVOCK02
1288
LIVOCK01
1.1
148.5
1.1
148.1
1.1
148.1
4.9
9L89
20.2
22.7 9L77
-42.3
1.1
148.1
1282
WILL01
1.1
147.9
1.1
264.4
10200
848S901T
1201
RUTH LK8
-25.1
-20.2
1224
HANGSTO7
7L194
17288
LIVOCK05
-13.1
-29.2
-10.2
-8.5
-44.1
13.1
1.1
260.2
4.9
-55.7
8.4
44.1
-13.2
1673
HALF_01
9.8
27.5
55.7
7.1
1.1
257.0
-44.1
-10.1
18.1
10655
DAWE701T
1.1
147.9
-13.0
1622
TWR_RD1
-51.0
-8.4
31.4
-36.9
-13.9
9.7
1.0
24.7
-0.0
-42.3
-55.7
7L170
-0.1
1.1
-0.1
264.9
9L57
9L144
55.7
-43.5
9L23
-1.6
-8.2
-1.8
1.1
147.5
1.1
147.1
7
1.1
256.7
0.0
1462
-14.2
1239
GREGOIRE
-5.1
1627
7LA97_TP
1.0
246.9
20.8
7L155
-19.3
1.1
147.2
-1.1
1.1
264.9
1670
BWC01
-14.5
50.6
73.7
-44.9
-61.0
1.0
20.8
13.0
11200
848S902T
4.0 -7.4
1.0
142.5
-2.9
1.1
148.6
7L47
43.5
-13.1
9.2
11201
848S703T
23.5 -31.3
1202
RUTH LA7
-23.5
1.1
147.3
-43.5
32.6
6.2 -9.6
1.0
142.9
7L97
9L19
1222
PARS CR7
10201
848S704T
24.8 -32.6
4.9 -4.9
1.1
148.1
6.5
-13.0
13.1
1.1
265.9
1.1
267.4
-11.8
1.1
264.8
1203
RUTH LK7
24.8 -24.8
7L71
1200
RUTH LK4
1.1
262.4
1.1
257.1
44.2
-33.7R
88.0
-87.5
SW
70107
GENCOG7
1655
DAWES240
9L74
1686
DOGRIB01
1.0
20.8
666
DOVER
38.4
9L43
-31.4
3.4
9L07
33.7
1.0
71.2
1.1
147.7
-36.9
-165.7
9L09
9L28
-11.8
1.1
264.8
1626
AMRBUS04
-22.4
51.3
54.0
160.2
1669
AMRBUS01
-22.4
-20.0
9L08
70159
GENCOG59
1.1
261.6
9L58
59
2.0
-26.9
-23.0
-6.7
-26.9
1.1
266.2
1
67.2R
67.2
15.7
182.2
18274
MACKAY2
1.1
266.1
1208
MILLENN4
9L01
182.2
-122.7
-17.8
90.4
-26.9
-23.0
9L76
1800
ER_01
1.1
266.0
1.1
257.1
183.3
1.0
18.7
-181.2
1.1
264.8
1295
1206
AURORA 4
1212
MIL_G5 4
1205
SYNC_D04
43.6
1274
MACKAY
-45.2
1263
JOSLYN4
1.1
262.7
-29.4
-83.5
1236
MUSKEG1
13.1
6.0
1251
HORMIN1
1.1
262.8
1610
MCCLE_01
-6.0
9L66
1213
MIL_G6 4
-0.2
1603
KEARL240
-51.4
-6.0L
-16.9
23.6
1612
SECORD01
1.1
261.4
9L32
6.0
1.1
262.8
-28.9
-77.9
-16.9
1214
EDD34
118.4
1.1
262.9
-71.2
10.6
1.1
265.7
22.8
10.6
-71.3
109.5
1.1
264.9
1.1
265.1
1.1
265.0
109.5
1680
BITUMONT
1.0
142.1
1483
KIRBY1
Bus - Voltage (kV/pu)
Branch - MW/Mvar
Equipment - MW/Mvar
100.0%Rate B
kV: <=72.000 <=144.000 <=240.000 <=500.000 >500.000
21.9
10.9
3405
CONKLIN4
2
37
1.1
268.1
9L69
1625
DAWES138
42.3
-13.2
1.1
147.2
-13.9
-13.9
-9.7
10.8
10204
885ST1
309
MCMILLA7
7LA114
8.0
1.0
142.5
468
LEISMER7
9L56
-65.2
-16.5
-16.5
-65.2
22.6
118.4
22.7
-34.9
9L22
-94.2
42.6
-62.4
24.9
-27.7
7L15
-56.7
1241
LONGLK1
56.8
-28.0
28.0
-19.2
19.2
7L183
180.8
-7.7
21.8
-62.1
-45.5
-62.1
14.4
11.7
39.7
-39.7
39.8
20.1
10245
KINOSIS5
-20.1
21.1
-46.3
46.3
-24.1
1.1
149.6
1.1
260.0
11245
KINOSIS6
1.1
148.9
9L81
-97.4
43.5
1292
MEAD_144
-0.0
1.1
148.8
-70.3
1.1
268.3
24.7
1.1
147.8
1.0
26.0
SW
1.0
4.3
60.7
7L104
25.2
-29.6
12.0
99
5.9
1242
KINOSIS2
-63.9
-12.0
-12.0
12.0
-5.9
6.6
-6.6
9L45
29.6
12.3
-73.2
10291
KR02
6.0
1687
BOHN_01
19687
BOHN_02
-6.0
1.1
260.0
-29.6
1245
KINOSIS1
-6.0
4.3
50.8
-49.8
1.0
24.5
1.1
261.8
SW
19.2
11.0
-11.0
9.3
-9.2
10282
898ST1
36.3
17282
HEARTLAK
11.0
-11.0
-66.3
-10.4
10.4
10.1
116.4
-61.3
957L
1.1
261.9
1090L
971L
24.4
1.1
263.1
-0.0
SW
39.1
-39.0
-28.6
29.9
428L
-13.9
43.3
405
CONKLIN1
-28.2
1.1
262.2
457L
1.1
261.1
2949
ILAKE_02
CATEGORY B, LOSS OF 9L990
2016WP PRE-CONNECTION
MON, JAN 25 2016 14:45
306
WINEFRE7
974
PIKE_01
SW
-45.5
3.0
1.1
262.3
1.1
263.0
1.0
143.2
-25.1
-13.6
2974
PIKE_02
36
1.5
2405
CONKLIN2
1.0
14.0
-49.6
49.7
-29.8
33.5
71.6
44.4H
1.0
143.6
1949
ILAKE_01
-1.5
435
1134L_TP
1118L
1.0
143.4
38.7
24.9
-22.8
879
539S_240
50.5
1116
-4.4
38.7
1
-3.0
1.6
-20.4
434
189_240
-112.1
1.1
263.2
1.0
14.0
3.1
-24.1
9L930
1117L
1099L
878
JFISH01
348
LEISMER4
-6.3
902
BCKSP_01
-111.9
369
CHRISLK1
1291
KR01
1.1
263.3
-5.3
36.4
321
HEARTLAK
10295
KR05
9L990
282
HEARTLAK
1.1
264.4
1348
WHITFISH
19291
KR04
0.0
6.0
SW
1046
1.1
264.3
9L913
1.1
269.7
56.1
1.1
149.0
-138.5
9L85
1402
SALTCR1
21.1
1.0
143.4
-103.7
P1570 - Bohn 931S Transformer Addition
-7.7
180.8
16.3
-21.0
1.1
259.1
SW
1.1
261.3
1.0
25.9
18291
KR03
74.7
9L47
15.8
21.6
-139.2
1.1
264.8
-69.3
-15.7
1.1
264.1
1.1
149.4
1.1
263.3
1.1
264.7
1228
MITS E.4
-0.0
21.0
7L114
2.3
1.1
266.1
0.0
-0.0
29.6
799
CHARD_TP
9L40
15.0
-58.8
6.9
16.3
-109.8
1409
QUIGL1
SW
-20.2
-14.9
15241
LONGLK15
179
MARIANA7 1623
ENGSTRM1
SW
8.7
12249
LNGLKCG2
9L929
9L56
-14.9
-15.7H
19242
KINOSIS3
G2
31.0R
-39.7
7L167
9L55
1010
CHARD_01
23.7
-68.2
-4.6
41.5
9L15
1.0
143.5
1.0
142.7
12.3
920
ROUND01
page A-5
16.3
80.0
-24.3
1277
BLK_FLY1
-0.0
1.1
269.6
-79.8
1246
LNGLKC02
0.5
9L84
SW
1.1
14.6
1.1
15.2
1.0
142.7
1411
WADDELL7
1.1
265.5
1260
LOU CR.4
15.0
-15.7
2.8
1226
WABASCA4
138
N BARRH4
-14.9
5.6
1.0
141.9
1.1
266.2
-79.8
-24.3
8.5
1227
CROWLK7
-20.4
1249
LNGLKC01
-13.6
7L121
1.0
142.0
1280
BRINT02
21.8
7L165
-4.8
8.3
1.1
147.6
-79.8
1276
S-SHINE1
11.9
-13.9
8.5
13249
LNGLKCG1
M2
1.1
147.7
-10.5
7L02
-20.4
-22.7
-5.5
22.2
-25.1
-49.3
8.1
1.1
147.6
1.1
147.2
13.9
1.1
267.3
49.3
-13.9
1008
SALE01
-0.0
-23.2
1.1
265.8
144
ALGAR 7
17241
LONGLK17
1.1
148.0
-79.8
27.8R
5.9
-20.2
-21.6
-15.7H
7L38
1290
HORSERV7
80.0
-14.9
M1
-6.3
8.1
1286
S-SHINE4
9L39
1.1
261.0
1405
SALTCR2
1.1
147.6
1.1
147.6
1.1
15.2
-10.7
1256
SWEETHE7
-10.8
1006
GERMAIN1
9L10
28.8
3.6
13.4
1.0
142.6
1.1
147.9
1.1
14.5
3.5
1.1
265.7
16.6
28.9
1602
LIVOCKPS
-42.3
1.0000
18288
LIVOCK03
204
MCMILLA4
1.1
267.3
1.1
267.3
1.6
11402
977S901T
-49.3
7L135
G1
7L36
SW
1.1
265.4
21.1
42.3
-1.0
PST
-14.0
10288
LIVOCK02
1288
LIVOCK01
1.1
150.5
1.1
149.9
1.1
149.9
5.5
9L89
20.2
22.7 9L77
-45.9
1.1
149.9
1282
WILL01
1.1
148.4
1.1
267.4
10200
848S901T
1201
RUTH LK8
-25.1
-20.2
1224
HANGSTO7
7L194
17288
LIVOCK05
-11.6
-15.3
-21.3
-4.1
-44.4
11.6
1.1
264.6
7.7
-56.6
4.0
44.4
-11.7
1673
HALF_01
18.1
27.0
56.6
5.6
1.1
258.9
-44.4
-21.2
26.6
10655
DAWE701T
1.1
148.4
-11.5
1622
TWR_RD1
-49.2
-4.0
31.6
-38.3
-15.2
5.3
1.0
24.8
-0.0
-42.3
-56.6
7L170
-0.1
1.1
-0.1
265.8
9L57
9L144
56.6
-43.8
9L23
-4.4
-7.7
-0.4
1.1
149.1
1.1
148.4
7
1.1
257.6
0.0
1462
-15.6
1239
GREGOIRE
-5.1
1627
7LA97_TP
1.0
247.6
22.6
7L155
-18.8
1.1
148.5
-1.1
1.1
265.8
1670
BWC01
-14.8
46.3
67.6
-41.7
-56.6
1.0
20.9
11.5
11200
848S902T
2.5 -5.9
1.0
143.5
-1.4
1.1
150.0
7L47
43.8
-11.6
7.7
11201
848S703T
23.7 -31.5
1202
RUTH LA7
-23.7
1.1
148.9
-43.8
32.9
4.7 -8.0
1.0
143.9
7L97
9L19
1222
PARS CR7
10201
848S704T
25.1 -32.9
3.4 -3.4
1.1
149.6
6.5
-13.0
13.1
1.1
267.0
1.1
267.8
-11.8
1.1
265.8
1203
RUTH LK7
25.0 -25.0
7L71
1200
RUTH LK4
1.1
263.8
1.1
259.0
44.4
-41.3R
88.0
-87.5
SW
70107
GENCOG7
1655
DAWES240
9L74
1686
DOGRIB01
1.0
20.8
666
DOVER
46.4
9L43
-26.0
7.1
9L07
27.9
1.0
71.8
1.1
149.2
-30.9
-165.7
9L09
9L28
-11.8
1.1
265.8
1626
AMRBUS04
-22.4
45.9
54.9
162.9
1669
AMRBUS01
-22.4
-23.0
9L08
70159
GENCOG59
1.1
262.9
9L58
59
-6.6
-27.4
-21.8
-5.4
-27.4
1.1
267.5
1
60.7R
60.7
14.2
182.2
18274
MACKAY2
1.1
267.2
1208
MILLENN4
9L01
182.2
-123.7
-30.1
94.1
-27.3
-21.8
9L76
1800
ER_01
1.1
267.4
1.1
258.5
190.4
1.0
18.7
-181.2
1.1
266.3
1295
1206
AURORA 4
1212
MIL_G5 4
1205
SYNC_D04
43.8
1274
MACKAY
-39.2
1263
JOSLYN4
1.1
263.9
-39.4
-86.6
1236
MUSKEG1
13.1
6.8
1251
HORMIN1
1.1
264.0
1610
MCCLE_01
-6.0
9L66
1213
MIL_G6 4
-2.6
1603
KEARL240
-51.3
-6.0L
-16.9
36.1
1612
SECORD01
1.1
262.8
9L32
6.8
1.1
264.0
-28.9
-72.9
-16.9
1214
EDD34
118.4
1.1
264.1
-74.8
6.4
1.1
268.1
35.1
6.4
-74.9
109.5
1.1
266.4
1.1
266.9
1.1
266.7
109.5
1680
BITUMONT
1.0
140.1
1483
KIRBY1
Bus - Voltage (kV/pu)
Branch - MW/Mvar
Equipment - MW/Mvar
100.0%Rate B
kV: <=72.000 <=144.000 <=240.000 <=500.000 >500.000
21.9
10.9
3405
CONKLIN4
2
37
1.1
268.4
9L69
42.3
-13.2
1.1
146.3
0.5
0.5
-13.9
6.4
1008
SALE01
39.8
10204
885ST1
-3.6
309
MCMILLA7
-62.5
25.1
-27.9
9L56
12.0
-123.7
-24.8
9L22
-65.1
-16.5
-16.5
-65.1
21.9
118.4
22.0
-9.6
180.8
-9.6
180.8
21.8
-62.5
-41.0
-62.5
13.7
42.3
41.7
13.5
39.7
-39.7
39.7
12.4
10245
KINOSIS5
-12.4
13.3
27.9
-10.0
10.0
-46.2
46.3
-14.9
1.1
149.2
1.1
259.4
11245
KINOSIS6
19291
KR04
1292
MEAD_144
15.8
0.0
-0.0
1.1
262.6
6.0
SW
1.0
25.9
-29.5
1.1
148.4
-67.8
SW
1.0
4.3
60.7
24.9
1.1
145.1
12.0
99
5.9
1242
KINOSIS2
-63.6
-12.0
-12.0
12.0
-5.9
6.6
-6.6
9L45
29.5
-126.1
-44.5
6.0
1687
BOHN_01
19687
BOHN_02
-6.0
1.1
259.4
10291
KR02
-29.5
1245
KINOSIS1
-6.0
4.3
50.5
-7.9
9.9
-9.8
10282
898ST1
-108.5
203.7
43.5
-17.6
9L81
-112.1
44.4
-30.2
9L990
-49.4
1.0
24.4
1.1
261.0
SW
19.0
7.9
7.9
-7.9
-9.5
9.5
-17.7
17282
HEARTLAK
-115.3
957L
1090L
971L
-165.9
369
CHRISLK1
-151.7
348
LEISMER4
-0.0
SW
39.1
-39.0
-28.2
29.5
1.1
262.0
428L
-13.9
42.9
457L
2949
ILAKE_02
CATEGORY B, LOSS OF 9L85
2016WP PRE-CONNECTION
MON, JAN 25 2016 14:45
405
CONKLIN1
-23.5
1.1
261.4
306
WINEFRE7
974
PIKE_01
SW
-45.1
3.0
1.1
261.5
1.1
262.0
1.0
142.6
-25.1
-13.6
2974
PIKE_02
36
1.5
2405
CONKLIN2
1.0
13.9
-49.6
49.7
-29.8
33.5
71.6
44.4H
1.0
143.0
1949
ILAKE_01
1.1
260.1
24.4
-1.5
435
1134L_TP
879
539S_240
50.5
282
HEARTLAK
1.1
265.0
38.7
24.9
-76.9
1118L
1.0
142.8
38.7
1
-3.0
1.6
-17.5
1116
3.7
1.1
262.4
1.0
13.9
3.1
-9.9
434
189_240
-166.3
1099L
878
JFISH01
33.0
321
HEARTLAK
902
BCKSP_01
1.5
43.3
1291
KR01
1.1
262.5
1.1
261.1
9L930
1117L
10295
KR05
139.4
1.1
263.1
9L913
-27.9
1.1
146.2
7L104
21.1
1.0
142.7
-102.7
P1570 - Bohn 931S Transformer Addition
9L85
1402
SALTCR1
7L183
1046
-21.0
1.1
257.8
SW
1.1
261.8
1.0
25.5
7L15
-37.3
1241
LONGLK1
56.8
1.1
258.5
18291
KR03
-14.7
9L47
1348
WHITFISH
-0.0
1.1
264.8
1.1
262.4
1.1
263.5
1.1
265.7
20.3
21.8
7L165
8.0
1.0
142.0
7.3
-75.4
1409
QUIGL1
0.0
-0.0
1.1
146.7
56.1
1.1
146.2
21.0
7L114
2.2
1.1
265.1
12249
LNGLKCG2
SW
29.5
468
LEISMER7
1228
MITS E.4
-50.3
16.4
7L167
9L55
6.9
12.3
920
ROUND01
9L40
-15.7
1277
BLK_FLY1
-0.0
19242
KINOSIS3
G2
39.7H
9L929
9L56
15.0
-58.5
799
CHARD_TP
9L15
-14.9
-15.7H
80.0
-12.5
-14.9
-34.0
9L84
SW
-32.3
1276
S-SHINE1
14.5
1.1
264.7
-79.8
1246
LNGLKC02
-22.7
-5.5
15.7
-39.7
1.0
142.2
1411
WADDELL7
1.1
266.4
page A-6
16.3
179
MARIANA7 1623
ENGSTRM1
SW
8.7
7LA114
13.9
-34.0
6.3
-9.6
1.0
143.1
1.0
142.3
1.1
267.7
84.8
1.1
14.5
1.1
15.0
5.6
1010
CHARD_01
1226
WABASCA4
138
N BARRH4
15.0
-15.7
2.8
1.1
266.9
-79.8
-14.9
3.9
1227
CROWLK7
-32.0
-32.3
0.8
7L121
1.1
145.7
-79.8
1249
LNGLKC01
15241
LONGLK15
-5.9
7L02
-32.0
13249
LNGLKCG1
M2
1.1
144.9
-6.1
1.1
146.4
-0.5
1.0
142.0
1260
LOU CR.4
8.1
1.1
147.0
1.0
142.2
1280
BRINT02
-0.0
-23.2
1.1
264.3
144
ALGAR 7
17241
LONGLK17
1.1
147.5
-79.8
40.2H
5.8
-20.2
-13.7
-15.7H
7L38
1290
HORSERV7
80.0
-14.9
M1
8.1
3.5
1286
S-SHINE4
9L39
1.1
262.3
1405
SALTCR2
1.1
145.7
1.1
145.7
1.1
15.0
-5.2
1256
SWEETHE7
-6.4
1006
GERMAIN1
9L10
-45.8
3.6
13.4
1.0
142.8
1.1
147.5
1.1
14.5
3.5
1.1
266.3
16.6
28.9
1602
LIVOCKPS
-42.3
1.0000
18288
LIVOCK03
204
MCMILLA4
1.1
266.3
1.1
267.7
1.6
11402
977S901T
-84.7
7L135
G1
7L36
SW
1.1
265.6
21.1
42.3
-52.1
PST
-2.6
10288
LIVOCK02
1288
LIVOCK01
1.1
151.1
1.1
150.6
1.1
150.6
-8.8
9L89
20.1
22.7 9L77
10200
848S901T
1201
RUTH LK8
-11.4
1.1
150.6
1282
WILL01
1.1
148.0
1.1
267.8
-13.9
1625
DAWES138
-20.1
1224
HANGSTO7
7L194
17288
LIVOCK05
-11.2
-17.9
-12.7
-6.1
-42.2
11.2
1.1
265.2
8.1
-39.1
6.1
42.2
-11.3
1673
HALF_01
9.5
31.2
39.1
5.2
1.1
259.4
-42.2
-13.1
17.7
10655
DAWE701T
1.1
148.0
-11.1
1622
TWR_RD1
-84.5
-6.1
29.5
-7.1
16.0
6.7
1.0
24.8
-0.0
-42.3
-39.1
7L170
-0.1
1.1
-0.1
266.0
9L57
9L144
39.1
-41.7
9L23
-4.8
-11.8
-0.2
1.1
148.7
7
1.1
257.0
0.0
1462
-15.1
1.1
149.6
1627
7LA97_TP
1.0
247.9
5.6
1239
GREGOIRE
-5.1
-5.2
7L155
-23.0
1.1
148.8
-1.1
1.1
266.0
1670
BWC01
-12.7
73.8
-99.8
50.3
-73.0
1.0
20.9
11.1
11200
848S902T
2.1 -5.5
1.0
143.7
-1.2
1.1
150.4
7L47
41.7
-11.2
7.3
11201
848S703T
21.6 -29.4
1202
RUTH LA7
-21.6
1.1
149.4
-41.7
30.8
4.2 -7.6
1.0
144.1
7L97
9L19
1222
PARS CR7
10201
848S704T
23.0 -30.8
3.1 -3.1
1.1
150.0
6.5
-13.0
13.1
1.1
267.1
1.1
267.4
-11.8
1.1
265.9
1203
RUTH LK7
22.9 -22.9
7L71
1200
RUTH LK4
1.1
264.0
1.1
259.4
-25.1
-42.4R
88.0
-87.5
SW
70107
GENCOG7
1655
DAWES240
9L74
1686
DOGRIB01
1.0
20.8
666
DOVER
47.6
9L43
-28.6
-2.1
9L07
85.7
1.0
71.9
1.1
149.6
-30.0
-165.7
9L09
9L28
-11.8
1.1
265.9
1626
AMRBUS04
-22.4
97.4
46.1
136.8
1669
AMRBUS01
-22.4
-23.2
9L08
70159
GENCOG59
1.1
263.2
9L58
59
-6.9
-23.0
-22.1
-5.5
-23.0
1.1
267.8
1
59.7R
59.7
-13.9
182.2
18274
MACKAY2
1.1
267.3
1208
MILLENN4
9L01
182.2
-123.9
-28.8
59.4
-23.0
-22.0
9L76
1800
ER_01
1.1
267.7
1.1
258.7
119.8
1.0
18.7
-181.2
1.1
266.6
1295
1206
AURORA 4
1212
MIL_G5 4
1205
SYNC_D04
-25.1
1274
MACKAY
-38.2
1263
JOSLYN4
1.1
264.2
-29.8
-87.2
1236
MUSKEG1
13.1
7.0
1251
HORMIN1
1.1
264.2
1610
MCCLE_01
-6.0
9L66
1213
MIL_G6 4
-3.0
1603
KEARL240
-51.3
-6.0L
-16.9
33.6
1612
SECORD01
1.1
263.0
9L32
7.0
1.1
264.2
-28.9
-127.1
-16.9
1214
EDD34
118.4
1.1
264.3
-40.3
5.6
1.1
268.4
33.2
5.6
-40.3
109.5
1.1
266.6
1.1
267.3
1.1
267.0
109.5
1680
BITUMONT
1.0
139.5
1483
KIRBY1
Bus - Voltage (kV/pu)
Branch - MW/Mvar
Equipment - MW/Mvar
100.0%Rate B
kV: <=72.000 <=144.000 <=240.000 <=500.000 >500.000
21.9
10.9
3405
CONKLIN4
2
37
1.1
267.9
9L69
42.3
-13.2
1.1
147.3
-2.6
-2.6
-14.9
5.7
1008
SALE01
25.0
-12.2
10204
885ST1
309
MCMILLA7
-5.1
8.0
15.9
-108.5
9L56
-62.5
25.0
-27.8
-65.2
-16.5
-16.5
-65.2
22.7
118.4
22.8
-7.3
180.8
-7.3
21.8
-62.1
-36.7
-62.1
14.1
43.8
13.9
43.2
28.0
-16.5
16.5
-17.5
39.7
-39.7
39.7
17.9
10245
KINOSIS5
-17.9
18.8
-46.3
46.3
-21.4
1.1
149.5
1.1
259.8
11245
KINOSIS6
1.1
148.3
19291
KR04
-0.0
1.1
265.5
1.1
148.6
SW
1.0
4.3
60.7
24.7
1.1
147.2
1.0
26.0
-29.6
-69.7
7L104
22.4
0.0
6.0
SW
1046
5.9
1242
KINOSIS2
-63.8
-12.0
12.0
99
-12.0
12.0
-5.9
6.6
-6.6
9L45
29.6
-62.3
-39.1
6.0
1687
BOHN_01
19687
BOHN_02
-6.0
1.1
259.8
10291
KR02
-29.6
1245
KINOSIS1
-6.0
4.3
51.4
-10.9
9.0
-8.9
10282
898ST1
9L22
-94.6
162.9
40.9
-26.6
-97.8
41.9
9L990
-50.4
1.1
262.8
SW
10.9
-10.9
-10.6
10.6
7.1
17282
HEARTLAK
-90.4
957L
1090L
-112.0
971L
348
LEISMER4
-0.0
SW
39.1
-39.0
-28.6
29.9
1.1
263.8
428L
-13.9
43.4
457L
2949
ILAKE_02
CATEGORY B, LOSS OF 9L47
2016WP PRE-CONNECTION
MON, JAN 25 2016 14:45
405
CONKLIN1
-32.5
1.1
262.9
306
WINEFRE7
974
PIKE_01
SW
-45.5
3.0
1.1
263.0
1.1
263.4
1.0
143.2
-25.1
-13.6
2974
PIKE_02
36
1.5
2405
CONKLIN2
1.0
14.0
-49.6
49.7
-29.8
33.5
71.6
44.4H
1.0
143.6
1949
ILAKE_01
1.1
260.8
24.4
-1.5
435
1134L_TP
1118L
1.0
143.5
38.7
25.0
-51.9
879
539S_240
50.5
1116
7.2
38.7
1
-3.0
1.6
-8.2
434
189_240
-141.3
1.1
263.9
1.0
14.0
3.1
-7.4
9L930
1117L
1099L
878
JFISH01
35.7
321
HEARTLAK
902
BCKSP_01
-141.0
282
HEARTLAK
1.1
264.4
1.1
262.8
369
CHRISLK1
1291
KR01
1.1
264.0
11.5
53.1
1.1
264.3
9L81
-41.7
1.0
24.5
19.2
10.9
10295
KR05
74.8
21.1
1.0
143.2
-103.2
9L913
-28.0
7L183
1292
MEAD_144
-63.8
9L85
1402
SALTCR1
7L15
-51.1
1241
LONGLK1
56.8
1.1
262.7
1.0
25.8
1.1
268.5
56.1
1.1
148.3
-21.0
1.1
258.6
SW
P1570 - Bohn 931S Transformer Addition
-0.0
18291
KR03
9L47
15.7
-138.6
180.8
16.3
21.0
7L114
1.0
143.2
1348
WHITFISH
0.0
-0.0
1.1
148.8
1.1
264.6
1.1
264.2
1.1
261.3
12249
LNGLKCG2
SW
29.6
2.3
1.1
268.0
1.1
264.8
21.6
21.8
7L165
6.9
468
LEISMER7
1228
MITS E.4
-68.6
-15.7
-59.4
799
CHARD_TP
9L40
15.0
1277
BLK_FLY1
-0.0
19242
KINOSIS3
G2
34.0R
9L929
9L56
1409
QUIGL1
80.0
-17.9
-14.9
-17.0
9L84
SW
-27.1
1276
S-SHINE1
16.1
1.1
268.4
-79.8
1246
LNGLKC02
-22.7
-5.5
14.0
-39.7
7L167
9L55
7LA114
23.3
-66.9
-4.2
39.6
-14.9
-15.7H
179
MARIANA7 1623
ENGSTRM1
SW
8.7
12.3
920
ROUND01
page A-7
16.3
1.0
143.4
1411
WADDELL7
1.1
265.5
9L15
1.0
144.3
1.0
143.5
1.1
267.0
71.9
1.1
14.6
1.1
15.2
5.6
1010
CHARD_01
1226
WABASCA4
138
N BARRH4
15.0
-15.7
2.8
1.1
266.2
-79.8
-14.9
3.1
1227
CROWLK7
-23.2
-27.1
-2.4
7L121
1.1
147.2
-79.8
1249
LNGLKC01
15241
LONGLK15
-5.1
7L02
-23.2
13249
LNGLKCG1
M2
1.1
147.0
-2.9
1.1
147.4
2.6
1.0
141.9
1260
LOU CR.4
8.1
1.1
147.7
1.0
142.0
1280
BRINT02
-0.0
-23.2
1.1
266.0
144
ALGAR 7
17241
LONGLK17
1.1
148.1
-79.8
30.8R
5.8
-20.2
-6.1
-15.7H
7L38
1290
HORSERV7
80.0
-14.9
M1
4.9
2.7
1286
S-SHINE4
9L39
1.1
261.4
1405
SALTCR2
1.1
147.2
1.1
147.2
1.1
15.2
-5.4
1256
SWEETHE7
-5.7
1006
GERMAIN1
9L10
-34.2
3.6
13.4
1.0
142.7
1.1
147.9
1.1
14.5
3.5
1.1
265.7
16.6
28.9
1602
LIVOCKPS
-42.3
1.0000
18288
LIVOCK03
204
MCMILLA4
1.1
268.2
1.1
267.0
1.6
11402
977S901T
-71.9
7L135
G1
7L36
SW
1.1
265.4
21.1
42.3
-2.9
PST
-13.5
10288
LIVOCK02
1288
LIVOCK01
1.1
150.6
1.1
150.1
1.1
150.1
-5.6
9L89
20.2
22.7 9L77
10200
848S901T
1201
RUTH LK8
-28.4
1.1
150.1
1282
WILL01
1.1
148.5
1.1
267.1
-13.9
1625
DAWES138
-20.2
1224
HANGSTO7
7L194
17288
LIVOCK05
-11.4
-19.6
-11.9
-7.2
-43.7
11.4
1.1
264.1
8.0
-45.8
7.1
43.7
-11.5
1673
HALF_01
8.7
28.2
45.8
5.3
1.1
259.0
-43.7
1622
TWR_RD1
-71.7
10655
DAWE701T
1.1
148.5
-11.3
-12.1
6.1
-7.1
31.0
-16.9
16.9
8.0
1.0
24.8
-0.0
-42.3
-45.8
7L170
-0.1
1.1
-0.1
265.8
9L57
9L144
45.8
-43.1
9L23
-4.7
-8.9
-0.2
1.1
149.2
1.1
148.5
7
1.1
257.7
0.0
1462
-15.6
1239
GREGOIRE
-5.1
1627
7LA97_TP
1.0
247.6
21.9
7L155
-20.0
1.1
148.7
-1.1
1.1
265.8
1670
BWC01
-14.2
49.6
72.5
-57.3
-78.1
1.0
20.9
11.3
11200
848S902T
2.3 -5.7
1.0
143.5
-1.3
1.1
150.1
7L47
43.1
-11.3
7.5
11201
848S703T
23.1 -30.9
1202
RUTH LA7
-23.1
1.1
149.0
-43.1
32.3
4.4 -7.8
1.0
143.9
7L97
9L19
1222
PARS CR7
10201
848S704T
24.5 -32.3
3.2 -3.2
1.1
149.7
6.5
-13.0
13.1
1.1
266.9
1.1
268.2
-11.8
1.1
265.8
1203
RUTH LK7
24.4 -24.4
7L71
1200
RUTH LK4
1.1
263.7
1.1
259.0
-25.1
-41.2R
88.0
-87.5
SW
70107
GENCOG7
1655
DAWES240
9L74
1686
DOGRIB01
1.0
20.8
666
DOVER
46.3
9L43
-35.9
6.6
9L07
80.7
1.0
71.8
1.1
149.3
-31.0
-165.7
9L09
9L28
-11.8
1.1
265.8
1626
AMRBUS04
-22.4
47.8
50.4
149.7
1669
AMRBUS01
-22.4
-22.5
9L08
70159
GENCOG59
1.1
262.9
9L58
59
-4.9
-25.1
-22.2
-5.7
-25.2
1.1
267.5
1
60.8R
60.8
-13.9
182.2
18274
MACKAY2
1.1
267.2
1208
MILLENN4
9L01
182.2
-123.7
-26.8
76.5
-25.1
-22.2
9L76
1800
ER_01
1.1
267.4
1.1
258.4
154.5
1.0
18.7
-181.2
1.1
266.3
1295
1206
AURORA 4
1212
MIL_G5 4
1205
SYNC_D04
-25.1
1274
MACKAY
-39.2
1263
JOSLYN4
1.1
263.9
-27.5
-86.5
1236
MUSKEG1
13.1
6.8
1251
HORMIN1
1.1
264.0
1610
MCCLE_01
-6.0
9L66
1213
MIL_G6 4
-2.4
1603
KEARL240
-51.3
-6.0L
-16.9
32.1
1612
SECORD01
1.1
262.7
9L32
6.8
1.1
264.0
-28.9
-102.1
-16.9
1214
EDD34
118.4
1.1
264.0
-57.3
6.5
1.1
267.9
31.5
6.5
-57.4
109.5
1.1
266.3
1.1
266.8
1.1
266.6
109.5
1680
BITUMONT
1.0
140.3
1483
KIRBY1
Bus - Voltage (kV/pu)
Branch - MW/Mvar
Equipment - MW/Mvar
100.0%Rate B
kV: <=72.000 <=144.000 <=240.000 <=500.000 >500.000
21.9
10.9
3405
CONKLIN4
2
37
ATTACHMENT B
Post-Connection System Power Flow Plots
ATCO Electric
B-1
R1
B-1 System Power Flow Results
Power Flow Diagrams
The post-connection power flow diagrams for Categories A and B contingencies are provided in
this section. The following table presents the list of the power flow diagrams.
Table B-1: List of Post-Connection Power Flow Diagrams
Scenario
Scenario 2
(2016WP-Post Project)
Scenario 3
(2017SP-Post Project)
Power Flow Diagram
Page
Number
N-G-0, System Normal Condition
B-3
N-G-1, Loss of 9L45
B-4
N-G-1, Loss of 9L990
B-5
N-G-1, Loss of 9L85
B-6
N-G-1, Loss of 9L47
B-7
N-G-0, System Normal Condition
B-8
N-G-1, Loss of 9L45
B-9
N-G-1, Loss of 9L990
B-10
N-G-1, Loss of 9L85
B-11
N-G-1, Loss of 9L47
B-12
NOTES: Other power flow diagrams will be provided upon request.
ATCO Electric
B-2
R1
1.1
267.7
9L69
1239
GREGOIRE
1.1
149.3
-5.1
1625
DAWES138
42.1
-13.2
-9.2
-9.2
9.0
3.6
309
MCMILLA7
7.9
1.0
143.7
13.1
-97.9
1046
9L56
14.5
-133.9
-30.2
9L22
51.9
-64.5
-15.7
-15.7
-64.5
23.0
117.6
23.1
-4.8
181.3
-4.8
181.3
-10.2
10.2
-10.1
5.9
19687
BOHN_02
10282
898ST1
-98.8
145.5
46.2
-18.5
-10.2
9.5
9L81
-102.2
47.3
-80.2
957L
-63.0
-34.0
13.6
9L23
-12.0
12.0
-5.9
6.6
-7.1
7.1
3.4
18687
BOHN9
-3.4
1687 3.7
-63.6
-10.3
-27.5
-0.0
SW
1348
WHITFISH
39.1
-39.0
-28.9
30.2
1.1
902
264.4
BCKSP_01
1.1
263.2
1090L
-130.7
971L 38.8
38.8
25.0
24.4
1099L
43.6
-40.9
457L
1.1
261.4
2949
ILAKE_02
CATEGORY A, N-0
2016WP POST-CONNECTION
MON, JAN 25 2016 14:48
306
WINEFRE7
1.0
14.0
1
-3.0
1.6
-1.5
3.0
-35.2
1.1
263.4
-49.6
49.8
-29.9
33.5
974
PIKE_01
21.8
1.1
263.5
1.1
264.1
1.0
143.7
-25.1
-13.6
2974
PIKE_02
71.6
44.4H
405
CONKLIN1
1118L
36
1.5
2405
CONKLIN2
1.0
14.0
435
1134L_TP
879
539S_240
51.1
SW
-45.8
1291
KR01
-14.7
1.1
264.4
-13.9
1245
KINOSIS1
3.1
-11.3
1.0
144.1
428L
-51.7
-9.6
1.1
264.5
878
JFISH01
1949
ILAKE_01
-28.5
10295
KR05
282
HEARTLAK
1.1
264.6
9L45
27.5
27.5
18291
KR03
1116
1.0
143.9
-9.6
1.1
259.4
10291
KR02
BOHN_01
25.0
434
189_240
1.7
1.0
25.9
SW
-19.2
7.4
348
LEISMER4
1.1
265.4
9.6
7.1
369
CHRISLK1
-95.1
26.2
-27.5
9L990
48.7
19291
KR04
0.0
-0.0
-26.1
17.2
17282
HEARTLAK
-130.0
1.1
259.4
9.6
1.1
263.2
321
HEARTLAK
46.2
1.1
149.2
1.1
147.9
9L930
1117L
21.9
4.3
1242
KINOSIS2
SW
10.2
-20.9
-25.1
-50.8
-9.5
39.7
20.9
10245
KINOSIS5
P1570
- Bohn Transformer Addition
1.0
19.3
10.2
22.3
-63.0
22.3
99
60.7
1.0
24.6
1.1
265.2
9L913
-69.2
47.9
1.0
143.7
-39.7
-46.2
12.0
1.1
146.6
21.0
44.6
9L47
-104.1
P1570 - Bohn 931S Transformer Addition
1292
MEAD_144
-11.8
39.7
11245
KINOSIS6
1.0
4.3
SW
24.8
-20.9
1.1
259.5
SW
1.1
261.5
20.2
1.1
147.7
7L104
20.9
7L114
2.2
1.1
266.6
1.1
265.1
21.2
-27.8
27.9
-20.2
7L183
1.1
264.9
1.1
265.3
1228
MITS E.4
-62.7
25.0
-27.9
1
468
LEISMER7
9L40
-62.5
7L15
-57.1
-97.6
9L85
1402
SALTCR1
1.1
267.5
1241
LONGLK1
56.8
1.1
262.2
1.0
25.7
9L929
9L56
1409
QUIGL1
-0.0
1.1
148.2
56.3
1.1
147.8
7L167
9L55
6.8
12.2
920
ROUND01
page B-3
16.4
-59.8
799
CHARD_TP
1260
LOU CR.4
-15.7
15241
LONGLK15
179
MARIANA7 1623
ENGSTRM1
SW
8.6
7LA114
1226
WABASCA4
138
N BARRH4
15.0
1.0
143.9
1411
WADDELL7
1.1
265.8
9L15
1010
CHARD_01
20.2
-56.6
-0.7
24.2
1.0
144.7
1.0
143.9
0.0
-0.0
-21.0
-14.9
2.8
1.1
266.4
-15.5
-14.9
-15.7H
SW
-39.7
5.6
1.0
141.9
16.7
16.3
19242
KINOSIS3
G2
8.4R
12249
LNGLKCG2
1.1
15.1
6.5
1227
CROWLK7
1.0
142.1
1280
BRINT02
15.0
-15.7
80.0
-2.5
1277
BLK_FLY1
-0.0
1.1
267.5
-79.8
1246
LNGLKC02
-9.5
9L84
SW
1.1
14.6
-13.8
10204
885ST1
-79.8
-14.9
-8.9
7L121
-28.7
1249
LNGLKC01
-2.5
M2
1.1
146.5
-8.5
7L02
1.1
146.4
-79.8
1276
S-SHINE1
17.1
-25.0
1.5
8.0
1.1
147.7
1.1
147.2
9.2
-28.7
-22.6
-5.5
20.1
-13.8
-19.6
28.2
144
ALGAR 7
1.1
147.2
-11.6
-0.0
-23.1
1.1
265.9
-15.7H
17241
LONGLK17
1.1
148.0
-79.8
36.6R
-14.9
7L38
1290
HORSERV7
80.0
13249
LNGLKCG1
1.1
15.1
M1
-1.6
1.1
266.7
60.3
-25.0
1008
SALE01
-60.2
-8.7
6.1
1286
S-SHINE4
9L39
1.1
261.5
1405
SALTCR2
1.1
146.3
1.1
146.4
G1
7L36
1.1
266.7
1.6
11402
977S901T
-60.3
7L135
5.8
-42.1
-16.5
22.6 9L77
1.1
150.7
1.1
150.2
1282
WILL01
1256
SWEETHE7
1.1
266.8
10200
848S901T
1201
RUTH LK8
1.1
150.2
-18.6
-9.0
1006
GERMAIN1
9L10
3.8
3.6
13.3
1.0
142.7
1.1
147.9
-11.0
-35.8
3.5
1.1
265.9
204
MCMILLA4
1.1
267.6
-20.1
21.0
-18.1
42.1
1.0000
18288
LIVOCK03
28.8
1602
LIVOCKPS
1.1
265.4
16.6
PST
-9.6
10288
LIVOCK02
1288
LIVOCK01
-43.5
11.0
-20.5
1.1
150.2
1.0
9L89
20.1
1224
HANGSTO7
1.1
148.4
43.5
-11.1
1.1
263.6
8.7
7L194
17288
LIVOCK05
-20.1
4.5
1.1
14.5
-5.3
-4.9
30.8
1.1
259.1
-43.5
1673
HALF_01
23.0
-50.7
4.8
-10.9
-18.6
SW
-42.1
50.7
11201
848S703T
22.9 -30.7
1.5 -4.8
1.0
143.5
14.8
7L170
-0.1
1.1
-0.1
265.8
9L57
9L144
10655
DAWE701T
0.0
-43.0
11200
848S902T
-28.3
1.1
148.4
-4.8
1.0
24.8
0.0
1462
1.0000
5.9
1.0375
1.0
247.7
-0.5
1.1
150.1
10.9
1622
TWR_RD1
1627
7LA97_TP
-50.7
7L47
4.2
1.1
148.6
7
-5.8
7L155
-20.1
1.1
148.7
1.1
257.7
50.7
1202
RUTH LA7
-22.9
43.0
-10.9
7.5
7L165
-5.4
-9.0
-0.3
-14.2
48.8
71.4
-52.1
-70.9
6.5
-13.1
13.2
1.0
20.9
-1.1
1.1
265.8
1670
BWC01
1.1
149.0
-43.0
32.2
4.5 -7.8
1.0
144.0
3.3 -3.3
1.1
149.7
7L97
9L19
1222
PARS CR7
10201
848S704T
24.4 -32.2
1200
RUTH LK4
1.1
263.6
1.1
259.1
43.6
-40.9R
88.5
88.5
SW
1.1
266.9
1.1
268.0
-11.7
1.1
265.8
1203
RUTH LK7
24.4 -24.4
7L71
-40.9
9L43
70107
GENCOG7
1655
DAWES240
9L74
1686
DOGRIB01
1.0
20.8
1.1
149.3
-31.5
-164.6
-30.2
47.1
1.0
71.8
666
DOVER
9L07
3.0
70159
GENCOG59
1.1
262.8
9L58
59
9L09
9L28
-11.7
1.1
265.8
1626
AMRBUS04
-22.3
62.9
51.9
154.1
1669
AMRBUS01
-22.3
-22.3
9L08
1
61.0R
61.0
13.4
181.0
18274
MACKAY2
1.1
267.1
-4.3
-25.9
-22.3
-5.8
-25.9
1.1
267.4
1208
MILLENN4
9L01
181.0
-123.7
-25.8
83.0
-25.9
-22.2
9L76
1800
ER_01
1.1
267.3
1.1
258.4
169.6
1.0
18.7
-180.1
1.1
266.2
1295
1206
AURORA 4
1212
MIL_G5 4
1205
SYNC_D04
43.0
1274
MACKAY
-39.7
1263
JOSLYN4
1.1
263.8
-33.5
-85.8
1236
MUSKEG1
13.2
6.7
1251
HORMIN1
1.1
263.9
1610
MCCLE_01
-6.0
9L66
1213
MIL_G6 4
-2.2
1603
KEARL240
-51.7
-6.0L
-16.4
31.3
1612
SECORD01
1.1
262.6
9L32
6.7
1.1
263.9
-28.1
-90.9
-16.4
1214
EDD34
117.6
1.1
264.0
-63.9
8.4
1.1
267.7
30.6
8.4
-64.0
111.0
1.1
266.2
1.1
266.7
1.1
266.5
111.0
1680
BITUMONT
1.0
142.6
1483
KIRBY1
Bus - Voltage (kV/pu)
Branch - MW/Mvar
Equipment - MW/Mvar
100.0%Rate B
kV: <=72.000 <=144.000 <=240.000 <=500.000 >500.000
10.9
3405
CONKLIN4
2
37
1.1
265.7
9L69
1239
GREGOIRE
1.1
147.8
-5.1
1625
DAWES138
42.1
-13.2
1.1
147.3
-12.6
-12.6
-12.1
8.5
7.0
309
MCMILLA7
-27.9
1046
7L167
9L55
13.6
-104.8
7.8
1.1
145.8
9L56
-24.4
9L22
-11.0
11.2
-11.1
53.8
-64.5
-15.7
-15.7
-64.5
26.1
117.6
26.2
3.6
181.3
3.6
181.3
10282
898ST1
-96.2
127.6
51.5
-34.9
9L81
-99.4
52.7
99
5.9
60.7
19687
BOHN_02
8.8
-69.4
957L
-61.2
-10.5
15.0
9L23
-12.0
12.0
-5.9
6.6
-7.1
7.1
3.4
18687
BOHN9
-3.4
1687 3.7
-65.0
-10.3
-28.3
1090L
1.1
902
266.9
BCKSP_01
-119.8
-0.0
SW
1348
WHITFISH
971L 38.8
38.8
18.6
18.0
1099L
-30.0
39.1
-39.0
-29.8
31.1
44.5
-51.1
1.1
266.0
457L
1.1
262.7
2949
ILAKE_02
CATEGORY B, LOSS OF 9L45
2016WP POST-CONNECTION
MON, JAN 25 2016 14:48
306
WINEFRE7
974
PIKE_01
SW
-46.6
-1.5
3.0
-49.6
49.8
-23.4
26.7
21.8
1.1
266.2
1.1
266.5
1.1
145.0
-25.1
-13.6
2974
PIKE_02
71.6
37.5R
405
CONKLIN1
1118L
36
1.5
2405
CONKLIN2
1.0
14.1
435
1134L_TP
879
539S_240
51.1
1.1
267.7
-13.9
1
-3.0
1.6
-11.0
1.1
145.4
428L
1.0
14.1
3.1
14.3
878
JFISH01
1949
ILAKE_01
1291
KR01
1.1
266.9
1.1
266.2
1245
KINOSIS1
-9.6
10295
KR05
282
HEARTLAK
1.1
264.4
9L45
28.3
28.3
18291
KR03
1116
1.1
145.2
-9.6
1.1
262.2
10291
KR02
BOHN_01
39.1
434
189_240
6.9
1.0
26.2
SW
-19.2
33.0
348
LEISMER4
1.1
270.9
9.6
7.1
369
CHRISLK1
-77.5
16.3
-28.3
9L990
74.6
19291
KR04
0.0
-0.0
-64.3
28.2
17282
HEARTLAK
-119.1
1.1
262.2
9.6
1.1
266.3
321
HEARTLAK
46.2
1.1
150.9
4.3
1242
KINOSIS2
SW
-11.0
13.7
-15.4
-52.7
11.0
-12.8
1.1
149.5
9L930
1117L
22.3
-61.2
22.3
-66.5
1.0
24.7
-8.8
39.6
12.8
10245
KINOSIS5
P1570
- Bohn Transformer Addition
1.0
19.5
11.0
-39.6
-46.2
12.0
1.0
143.6
1.1
267.5
9L913
1292
MEAD_144
-45.4
39.6
11245
KINOSIS6
1.0
4.3
SW
19.4
1.0
144.6
-105.5
P1570 - Bohn 931S Transformer Addition
10.4
1.0
144.8
7L104
21.0
1.1
261.2
SW
1.1
261.3
27.9
-10.5
24.9
-20.9
63.7
9L47
14.8
-136.9
20.6
25.1
-27.9
7L183
1.1
268.8
1.1
267.1
1.1
264.8
-66.5
-62.5
20.9
7L114
2.2
1.1
267.7
468
LEISMER7
9L40
56.8
7L15
-36.8
1241
LONGLK1
-125.9
9L85
1402
SALTCR1
1.1
262.2
56.3
1.0
144.8
1.1
256.0
1.0
25.2
9L929
9L56
1409
QUIGL1
-0.0
1.1
145.3
1
799
CHARD_TP
page B-4
16.4
-61.6
6.8
12.2
920
ROUND01
1228
MITS E.4
1260
LOU CR.4
-15.7
15241
LONGLK15
179
MARIANA7 1623
ENGSTRM1
SW
8.6
7LA114
1226
WABASCA4
138
N BARRH4
15.0
1.1
146.1
1411
WADDELL7
1.1
265.3
9L15
1010
CHARD_01
20.8
-63.4
-0.4
34.4
1.1
146.9
1.1
146.1
0.0
-0.0
-12.9
-14.9
2.8
1.1
265.9
-14.3
-14.9
-15.7H
SW
-39.6
5.6
1.0
141.5
20.2
16.4
19242
KINOSIS3
G2
23.5R
12249
LNGLKCG2
1.1
14.9
6.0
1227
CROWLK7
1.0
141.7
1280
BRINT02
15.0
-15.7
80.0
-17.2
1277
BLK_FLY1
-0.0
1.1
262.2
-79.8
1246
LNGLKC02
-2.7
9L84
SW
1.1
14.6
-13.8
10204
885ST1
-79.8
-14.9
-12.3
7L121
-31.9
1249
LNGLKC01
-17.1
M2
1.0
143.5
-8.0
7L02
1.0
144.3
-79.8
1276
S-SHINE1
26.5
-25.0
-3.7
8.0
1.1
147.5
1.1
147.3
12.6
-15.7H
17241
LONGLK17
1.1
147.7
-31.9
-22.6
-5.5
13.9
-13.8
-38.5
27.4
144
ALGAR 7
1.1
264.3
52.0
1.1
258.6
1405
SALTCR2
1.0
144.3
-14.9
7L38
1290
HORSERV7
-79.8
40.2H
13249
LNGLKCG1
1.1
14.9
M1
-5.0
5.6
1286
S-SHINE4
9L39
-25.0
1008
SALE01
-51.9
-7.3
1.1
264.3
1.7
11402
977S901T
-52.0
1.0
144.3
-13.0
-0.0
-23.1
1.1
266.0
1.1
149.0
80.0
5.9
-42.1
-11.9
22.6 9L77
7L135
G1
7L36
1256
SWEETHE7
1.1
264.4
10200
848S901T
1201
RUTH LK8
1.1
148.6
1.1
148.6
1282
WILL01
-8.5
1006
GERMAIN1
9L10
19.4
3.6
13.3
1.0
142.3
1.1
147.5
-12.3
-42.5
3.5
1.1
265.2
204
MCMILLA4
1.1
267.8
-20.2
21.0
-7.9
42.1
1.0000
18288
LIVOCK03
28.8
1602
LIVOCKPS
1.1
264.8
16.6
PST
-9.7
10288
LIVOCK02
1288
LIVOCK01
-43.9
12.3
-30.1
1.1
148.6
4.4
9L89
20.1
1224
HANGSTO7
1.1
148.0
43.9
-12.4
1.1
260.0
6.4
7L194
17288
LIVOCK05
-20.1
5.8
1.1
257.4
-43.9
1673
HALF_01
19.4
-7.5
31.2
1.0
14.4
-12.8
-54.9
7.3
-12.2
-12.9
SW
-42.1
54.9
11201
848S703T
23.3 -31.1
2.8 -6.1
1.0
142.7
11.1
7L170
-0.1
1.1
-0.1
264.9
9L57
9L144
10655
DAWE701T
0.0
-43.4
11200
848S902T
-35.7
1.1
148.0
-7.3
1.0
24.7
0.0
1462
1.0000
8.6
1.0375
1.0
247.0
-1.7
1.1
148.8
12.2
1622
TWR_RD1
1627
7LA97_TP
-54.9
7L47
4.2
1.1
147.5
7
-3.5
7L155
-19.3
1.1
147.6
1.1
257.0
54.9
1202
RUTH LA7
-23.3
43.4
-12.2
8.8
7L165
-3.1
-8.2
-1.5
-14.5
50.8
73.9
-45.9
-62.3
6.5
-13.1
13.2
1.0
20.8
-1.1
1.1
264.9
1670
BWC01
1.1
147.7
-43.4
32.6
5.8 -9.2
1.0
143.1
4.5 -4.5
1.1
148.4
7L97
9L19
1222
PARS CR7
10201
848S704T
24.8 -32.6
1200
RUTH LK4
1.1
262.5
1.1
257.4
44.0
-34.2R
88.5
88.5
SW
1.1
266.0
1.1
267.5
-11.7
1.1
264.9
1203
RUTH LK7
24.8 -24.8
7L71
-34.2
9L43
70107
GENCOG7
1655
DAWES240
9L74
1686
DOGRIB01
1.0
20.8
1.1
148.0
-36.8
-164.6
-32.2
35.7
1.0
71.3
666
DOVER
9L07
3.0
70159
GENCOG59
1.1
261.7
9L58
59
9L09
9L28
-11.7
1.1
264.9
1626
AMRBUS04
-22.3
52.7
53.6
159.2
1669
AMRBUS01
-22.3
-19.9
9L08
1
66.7R
66.7
14.9
181.0
18274
MACKAY2
1.1
266.2
2.2
-26.7
-23.1
-6.8
-26.8
1.1
266.2
1208
MILLENN4
9L01
181.0
-122.8
-17.0
89.8
-26.7
-23.1
9L76
1800
ER_01
1.1
266.1
1.1
257.2
183.6
1.0
18.7
-180.1
1.1
264.9
1295
1206
AURORA 4
1212
MIL_G5 4
1205
SYNC_D04
43.4
1274
MACKAY
-45.0
1263
JOSLYN4
1.1
262.8
-29.5
-83.2
1236
MUSKEG1
13.2
6.0
1251
HORMIN1
1.1
262.8
1610
MCCLE_01
-6.0
9L66
1213
MIL_G6 4
-0.2
1603
KEARL240
-51.7
-6.0L
-16.4
22.7
1612
SECORD01
1.1
261.5
9L32
6.0
1.1
262.8
-28.1
-80.0
-16.4
1214
EDD34
117.6
1.1
263.0
-70.7
12.1
1.1
265.7
21.9
12.1
-70.7
111.0
1.1
265.0
1.1
265.1
1.1
265.0
111.0
1680
BITUMONT
1.0
142.0
1483
KIRBY1
Bus - Voltage (kV/pu)
Branch - MW/Mvar
Equipment - MW/Mvar
100.0%Rate B
kV: <=72.000 <=144.000 <=240.000 <=500.000 >500.000
10.9
3405
CONKLIN4
2
37
1.1
267.6
9L69
1239
GREGOIRE
1.1
149.1
-5.1
1625
DAWES138
42.1
-13.2
-14.1
-9.6
11.0
10204
885ST1
309
MCMILLA7
9L56
799
CHARD_TP
-62.5
25.0
-27.8
7L167
1046
-34.8
9L22
-94.2
42.7
-64.6
-15.7
-15.7
-64.6
23.1
117.6
23.2
-4.4
181.3
-4.4
181.3
-11.0
9.3
-9.2
10282
898ST1
9L81
-97.4
43.7
SW
1292
MEAD_144
-69.4
8.0
26.7
-62.9
-38.0
13.8
21.8
10245
KINOSIS5
-21.8
22.7
99
5.9
19687
BOHN_02
1.1
260.5
-12.0
12.0
-5.9
6.6
-61.6
957L
-64.1
-10.3
11.0
-11.0
-65.8
-10.3
10.3
10.3
-7.1
7.1
3.4
18687
BOHN9
-3.4
1687 3.7
-27.8
1.1
902
263.3
BCKSP_01
1.1
262.0
1090L
-112.1
-0.0
SW
1348
WHITFISH
971L 38.8
38.8
25.0
24.4
1099L
-22.2
-39.0
-28.6
29.9
-13.9
43.4
457L
1.1
261.1
2949
ILAKE_02
CATEGORY B, LOSS OF 9L990
2016WP POST-CONNECTION
MON, JAN 25 2016 14:48
306
WINEFRE7
-1.5
3.0
-28.7
1.1
262.3
1.5
2405
CONKLIN2
1.0
14.0
-49.6
49.8
-29.9
33.5
974
PIKE_01
1.1
262.4
1.1
263.1
1.0
143.2
-25.1
-13.6
2974
PIKE_02
71.6
21.8
405
CONKLIN1
1118L
36
44.4H
879
539S_240
51.1
SW
-45.5
1
-3.0
1.6
435
1134L_TP
1.0
143.6
428L
1.0
14.0
-20.5
1116
39.1
1291
KR01
3.1
-23.7
1.1
263.2
1949
ILAKE_01
1245
KINOSIS1
10295
KR05
282
HEARTLAK
1.1
264.4
19.5
-69.5
-9.6
1.1
263.4
878
JFISH01
434
189_240
1.0
143.5
9L45
27.8
27.8
18291
KR03
BOHN_01
9L930
-4.1
-9.6
1.1
260.5
9.6
7.1
369
CHRISLK1
348
LEISMER4
1.0
26.0
10291
KR02
-5.0
36.6
1.1
266.5
SW
-19.2
9L990
35.8
27.2
-0.0
9.6
4.3
1242
KINOSIS2
19291
KR04
0.0
-27.8
1.1
148.5
1.1
261.9
-6.7
46.2
1.1
149.9
P1570
- Bohn Transformer Addition
1.0
17282
HEARTLAK
-111.4
39.7
-26.1
-50.1
321
HEARTLAK
4.3
-39.7
-46.2
12.0
60.7
SW
-145.6
9L85
39.7
11245
KINOSIS6
1.0
4.4
1.1
148.0
1.0
24.5
115.7
1117L
22.3
-62.9
22.3
7L183
7L104
19.2
11.0
9L23
21.2
1.1
146.9
1.1
264.3
9L913
27.9
-21.2
24.8
51.1
1.0
143.5
-103.7
P1570 - Bohn 931S Transformer Addition
-27.9
21.0
1.1
259.1
SW
1.1
261.3
7L15
-59.0
1241
LONGLK1
56.8
1.1
262.6
1.0
25.8
1.1
267.9
56.3
1.1
148.0
-20.9
76.0
9L47
15.9
-139.4
21.6
-69.5
1.1
264.8
9L40
16.4
1.1
263.4
1.1
264.8
1228
MITS E.4
page B-5
15.0
-15.7
5.8
9L55
468
LEISMER7
16.3
-110.2
8.0
1.0
142.8
-0.0
1402
SALTCR1
20.9
7L114
2.3
1.1
266.2
0.0
-0.0
1.1
148.5
1
12.2
920
ROUND01
SW
-21.8
-14.9
-59.1
6.9
12249
LNGLKCG2
9L929
9L56
9L15
1409
QUIGL1
19242
KINOSIS3
G2
7.5R
-39.7
1.0
143.0
1411
WADDELL7
1.1
265.5
1260
LOU CR.4
-14.9
-15.7H
179
MARIANA7 1623
ENGSTRM1
SW
8.6
7LA114
23.6
-68.8
-4.4
42.5
1.0
143.9
1.0
143.0
1010
CHARD_01
1226
WABASCA4
138
N BARRH4
16.3
80.0
-1.6
1277
BLK_FLY1
-0.0
1.1
267.8
-79.8
1246
LNGLKC02
2.6
9L84
SW
1.1
14.6
1.1
15.1
2.8
1.1
266.1
-15.5
15.0
-15.7
5.6
1.0
141.8
22.8
-14.9
8.6
1227
CROWLK7
-79.8
1276
S-SHINE1
14.9
-13.8
8.5
-27.8
1249
LNGLKC01
-13.8
7L121
1.1
146.5
-79.8
-22.6
-5.5
23.9
-25.0
-50.6
-27.8
15241
LONGLK15
-10.6
7L02
-79.8
35.7R
-1.6
M2
1.1
146.7
8.5
1.1
147.2
14.1
-15.7H
17241
LONGLK17
1.1
148.0
1.1
147.6
1.0
142.0
1280
BRINT02
1290
HORSERV7
1.1
266.7
48.2
1.1
261.2
1405
SALTCR2
1.1
146.5
-14.9
7L38
144
ALGAR 7
1.1
147.2
-14.1
-48.2
80.0
13249
LNGLKCG1
1.1
15.1
M1
-6.5
8.3
1286
S-SHINE4
9L39
11402
977S901T
-13.8
1008
SALE01
-23.0
-0.0
-23.1
1.1
265.9
1.1
150.6
1.1
146.5
-48.1
-10.9
1.1
266.7
1.6
-25.0
-21.5
22.6 9L77
7L135
G1
7L36
1256
SWEETHE7
1.1
266.8
10200
848S901T
1201
RUTH LK8
1.1
150.0
1.1
150.0
1282
WILL01
-11.0
1006
GERMAIN1
9L10
29.9
3.6
1.0
142.6
1.1
147.9
-11.0
-47.9
3.5
1.1
265.6
13.3
28.8
-42.1
1.0000
18288
LIVOCK03
204
MCMILLA4
1.1
267.3
-20.1
21.0
0.1
42.1
1.1
265.3
16.6
PST
1602
LIVOCKPS
-13.8
10288
LIVOCK02
1288
LIVOCK01
-44.3
11.0
-18.3
1.1
150.0
5.9
9L89
20.1
1224
HANGSTO7
1.1
148.4
44.3
-11.1
1.1
263.7
8.7
7L194
17288
LIVOCK05
-20.1
4.6
1.1
258.9
-44.3
1673
HALF_01
27.4
-3.5
31.6
1.1
14.5
-15.9
-56.8
3.3
-10.9
-22.9
SW
-42.1
56.8
11201
848S703T
23.7 -31.5
1.5 -4.9
1.0
143.4
18.9
7L170
-0.1
1.1
-0.1
265.7
9L57
9L144
10655
DAWE701T
-0.0
-43.7
11200
848S902T
-39.0
1.1
148.4
-3.3
1.0
24.8
0.0
1462
1.0000
4.7
1.0375
1.0
247.5
-0.5
1.1
150.0
10.9
1622
TWR_RD1
1627
7LA97_TP
-56.8
7L47
4.2
1.1
148.4
7
-5.8
7L155
-18.5
1.1
148.6
1.1
257.7
56.8
1202
RUTH LA7
-23.7
43.7
-11.0
7.6
7L165
-5.4
-7.4
-0.3
-14.9
46.6
68.1
-41.1
-55.8
6.5
-13.1
13.2
1.0
20.9
-1.1
1.1
265.7
1670
BWC01
1.1
148.9
-43.7
33.0
4.6 -7.9
1.0
143.9
3.3 -3.3
1.1
149.6
7L97
9L19
1222
PARS CR7
10201
848S704T
25.2 -33.0
1200
RUTH LK4
1.1
263.6
1.1
259.0
44.4
-40.3R
88.5
88.5
SW
1.1
266.8
1.1
267.8
-11.7
1.1
265.7
1203
RUTH LK7
25.1 -25.1
7L71
-40.3
9L43
70107
GENCOG7
1655
DAWES240
9L74
1686
DOGRIB01
1.0
20.8
1.1
149.2
-32.0
-164.6
-26.8
27.0
1.0
71.8
666
DOVER
9L07
6.8
70159
GENCOG59
1.1
262.7
9L58
59
9L09
9L28
-11.7
1.1
265.7
1626
AMRBUS04
-22.3
44.6
55.0
163.2
1669
AMRBUS01
-22.3
-22.5
9L08
1
61.5R
61.5
13.6
181.0
18274
MACKAY2
1.1
267.0
-5.0
-27.4
-22.1
-5.6
-27.4
1.1
267.3
1208
MILLENN4
9L01
181.0
-123.6
-27.3
95.2
-27.4
-22.0
9L76
1800
ER_01
1.1
267.2
1.1
258.3
194.4
1.0
18.7
-180.1
1.1
266.1
1295
1206
AURORA 4
1212
MIL_G5 4
1205
SYNC_D04
43.8
1274
MACKAY
-40.1
1263
JOSLYN4
1.1
263.8
-39.2
-85.6
1236
MUSKEG1
13.2
6.7
1251
HORMIN1
1.1
263.9
1610
MCCLE_01
-6.0
9L66
1213
MIL_G6 4
-2.1
1603
KEARL240
-51.7
-6.0L
-16.4
33.3
1612
SECORD01
1.1
262.6
9L32
6.7
1.1
263.9
-28.1
-72.3
-16.4
1214
EDD34
117.6
1.1
264.0
-76.0
8.6
1.1
267.6
32.3
8.6
-76.1
111.0
1.1
266.2
1.1
266.6
1.1
266.4
111.0
1680
BITUMONT
1.0
142.0
1483
KIRBY1
Bus - Voltage (kV/pu)
Branch - MW/Mvar
Equipment - MW/Mvar
100.0%Rate B
kV: <=72.000 <=144.000 <=240.000 <=500.000 >500.000
10.9
3405
CONKLIN4
2
37
1.1
268.4
9L69
1.1
150.0
1.0000
1625
DAWES138
-20.1
42.1
1008
SALE01
43.1
-13.2
8.7
1.2
1.2
-13.6
6.7
309
MCMILLA7
8.0
9L56
56.8
-62.5
25.0
-27.9
1046
-26.0
SW
9L22
9L913
9L81
7.6
-7.6
9.6
-9.5
10282
898ST1
-64.4
-15.7
-15.7
-64.4
21.8
117.6
21.8
-8.0
181.3
-8.0
207.5
42.1
-13.6
-112.8
1292
MEAD_144
-66.9
99
-0.0
SW
8.0
-0.0
-63.5
-38.6
12.8
42.2
12.6
41.6
5.9
60.7
9.7
19687
BOHN_02
9L23
1.1
257.7
-118.4
957L
-0.0
-12.0
12.0
-5.9
6.6
-7.1
7.1
3.4
18687
BOHN9
-3.4
1687 3.7
-62.8
-10.3
-27.1
-39.0
-28.0
29.3
1.1
902
261.7
BCKSP_01
1.1
260.3
1090L
-168.8
42.7
457L
2949
ILAKE_02
306
WINEFRE7
1291
KR01
971L 38.8
38.8
24.9
24.4
1099L
-79.1
1.0
13.9
1
3.1
-3.0
1.6
-1.5
3.0
-49.6
49.8
-29.8
33.5
21.8
405
CONKLIN1
1118L
974
PIKE_01
1.1
260.8
1.1
261.4
1.0
142.2
-25.1
-13.6
2974
PIKE_02
71.6
44.4H
435
1134L_TP
879
539S_240
51.1
-19.4
1.1
260.7
36
1.5
2405
CONKLIN2
1.0
13.9
-11.0
SW
-44.9
1245
KINOSIS1
-9.6
-22.7
1.1
261.2
-13.9
-47.6
10295
KR05
1.0
142.6
428L
-125.9
27.1
18291
KR03
1116
39.1
9L45
27.1
1.1
261.8
878
JFISH01
1949
ILAKE_01
-9.6
1.1
257.7
10291
KR02
BOHN_01
29.8
1.0
142.5
1.0
25.8
SW
-19.2
-3.8
348
LEISMER4
1.1
261.2
9.6
7.1
369
CHRISLK1
-155.6
17.5
-27.1
9L990
38.0
19291
KR04
0.0
9.6
-21.9
434
189_240
2.3
CATEGORY B, LOSS OF 9L85
2016WP POST-CONNECTION
MON, JAN 25 2016 14:49
46.2
1.1
148.3
4.3
1242
KINOSIS2
-20.9
321
HEARTLAK
1.1
259.8
14.7
1.1
146.9
1.1
260.2
17282
HEARTLAK
-168.4
-13.8
P1570
- Bohn Transformer Addition
1.0
SW
-7.6
39.6
13.8
10245
KINOSIS5
-16.5
-49.2
7.6
-39.6
-46.2
12.0
9L930
1117L
22.3
-63.5
22.3
SW
1.0
24.3
-9.7
9L85
39.6
11245
KINOSIS6
1.0
4.3
1.1
145.2
282
HEARTLAK
1.1
265.0
1348
WHITFISH
page B-6
-109.1
43.0
P1570 - Bohn 931S Transformer Addition
11.6
1.0
144.0
1.1
262.5
1.1
261.9
27.9
-11.6
7L183
7L104
19.0
-102.3
138
N BARRH4
-27.9
24.8
50.2
1.1
256.9
1402
SALTCR1
146.6
1.0
142.5
-0.0
1.0
25.3
7L15
-39.3
1241
LONGLK1
21.0
1.1
257.3
0.0
-0.0
1.1
263.0
56.3
1.1
145.2
-20.9
-18.1
9L47
11.9
-123.2
1.1
265.7
12249
LNGLKCG2
SW
1.1
145.7
1.1
261.4
1.1
263.0
1228
MITS E.4
181.3
16.4
1277
BLK_FLY1
-0.0
19242
KINOSIS3
G2
21.2R
9L929
1.0
141.7
468
LEISMER7
20.4
-15.7
7L167
9L55
1409
QUIGL1
80.0
-13.9
15.0
20.9
7L114
2.3
1.1
264.7
799
CHARD_TP
-49.7
-14.9
-15.7H
15.5
-39.6
-14.9
1276
S-SHINE1
-33.5
9L84
SW
-15.0
-22.6
-5.5
18.9
1.1
262.9
-79.8
1246
LNGLKC02
1
12.2
920
ROUND01
9L40
16.4
-58.2
6.9
1.1
267.6
85.8
1.1
14.6
1.1
14.9
179
MARIANA7 1623
ENGSTRM1
SW
8.6
7.1
-74.2
1.0
142.8
1.0
142.0
7LA114
13.7
-32.9
9L56
9L15
15.0
-15.7
5.6
1010
CHARD_01
1226
WABASCA4
1260
LOU CR.4
-79.8
-14.9
4.1
1227
CROWLK7
-31.9
-15.0
1.4
7L121
1.0
144.6
-79.8
1249
LNGLKC01
1.0
142.0
1411
WADDELL7
1.1
266.4
-15.2
-31.9
2.8
1.1
267.0
5.0
-79.8
40.2H
15241
LONGLK15
-6.1
7L02
80.0
13249
LNGLKCG1
M2
1.0
143.9
-6.7
1.1
146.3
-1.2
17241
LONGLK17
1.1
147.5
1.1
147.0
1.0
142.1
6.5
-11.2
1290
HORSERV7
144
ALGAR 7
1.1
146.3
-15.7H
7L38
3.7
1286
S-SHINE4
9L39
1.1
263.1
1405
SALTCR2
1.0
144.6
-14.9
M1
-5.6
1.0
142.2
1280
BRINT02
-85.6
1.1
14.9
SW
-23.1
1.1
264.2
10204
885ST1
-2.2
G1
7L36
1.1
267.7
1.5
11402
977S901T
-85.8
1.0
144.6
1.1
151.0
1282
WILL01
1256
SWEETHE7
10200
848S901T
1.1
151.6
7L135
5.9
-42.1
-14.8
22.6 9L77
1.1
151.0
-15.8
-6.7
1006
GERMAIN1
9L10
-48.5
3.6
13.3
1.0
142.8
1.1
147.6
1.1
267.8
-11.7
3.5
1.1
266.4
204
MCMILLA4
1.1
266.2
-20.1
21.0
-53.5
42.1
1.0000
18288
LIVOCK03
28.8
1602
LIVOCKPS
1.1
265.7
16.6
PST
-2.3
10288
LIVOCK02
1288
LIVOCK01
-10.4
-18.8
1.1
151.0
-9.3
9L89
20.1
1224
HANGSTO7
1.1
148.1
-42.1
10.4
1.1
265.0
9.6
7L194
17288
LIVOCK05
-42.1
42.1
-10.5
1201
RUTH LK8
1.0
14.4
31.1
-4.9
3.9
1.1
259.8
-42.1
1673
HALF_01
19.3
-38.3
4.8
-10.3
-16.2
17.2
38.3
29.3
0.8 -4.2
1.0
143.9
11.1
7L170
-0.1
1.1
-0.1
266.0
9L57
9L144
10655
DAWE701T
0.0
11201
848S703T
21.5 -29.3
-5.8
1.1
148.1
-4.8
1.0
24.8
0.0
1462
1.0375
5.4
-41.5
11200
848S902T
1622
TWR_RD1
1627
7LA97_TP
1.0
247.9
0.0
1.1
150.6
4.2
1.1
149.0
7
-38.3
7L47
10.3
-13.8
1239
GREGOIRE
-5.1
-6.6
7L155
-22.9
1.1
149.1
1.1
257.1
38.3
1202
RUTH LA7
-21.5
41.5
-10.3
6.9
7L165
-6.2
-11.8
0.2
-12.7
73.7
-101.0
50.2
-73.9
6.5
-13.1
13.2
1.0
20.9
-1.1
1.1
266.0
1670
BWC01
1.1
149.7
-41.5
30.8
3.8 -7.2
1.0
144.3
2.8 -2.8
1.1
150.3
7L97
9L19
1222
PARS CR7
10201
848S704T
23.0 -30.8
1200
RUTH LK4
1.1
264.1
1.1
259.8
-25.0
-42.8R
88.5
88.5
SW
1.1
267.2
1.1
267.4
-11.7
1.1
266.0
1203
RUTH LK7
22.9 -22.9
7L71
-42.8
9L43
-164.6
70107
GENCOG7
1655
DAWES240
9L74
1686
DOGRIB01
1.0
20.8
1.1
149.9
-30.0
-28.5
87.6
1.0
72.0
666
DOVER
9L07
-2.4
70159
GENCOG59
1.1
263.2
9L58
59
9L09
9L28
-11.7
1.1
266.0
1626
AMRBUS04
-22.3
98.7
45.8
135.9
1669
AMRBUS01
-22.3
-23.1
9L08
1
59.4R
59.4
-13.8
181.0
18274
MACKAY2
1.1
267.4
-6.7
-22.8
-22.1
-5.5
-22.8
1.1
267.8
1208
MILLENN4
9L01
181.0
-123.9
-28.0
58.8
-22.8
-22.1
9L76
1800
ER_01
1.1
267.7
1.1
258.8
120.4
1.0
18.7
-180.1
1.1
266.6
1295
1206
AURORA 4
1212
MIL_G5 4
1205
SYNC_D04
-25.0
1274
MACKAY
-38.2
1263
JOSLYN4
1.1
264.3
-30.8
-86.8
1236
MUSKEG1
13.2
7.0
1251
HORMIN1
1.1
264.3
1610
MCCLE_01
-6.0
9L66
1213
MIL_G6 4
-3.0
1603
KEARL240
-51.7
-6.0L
-16.4
32.7
1612
SECORD01
1.1
263.1
9L32
7.0
1.1
264.3
-28.1
-129.2
-16.4
1214
EDD34
117.6
1.1
264.4
-39.8
7.1
1.1
268.4
32.3
7.1
-39.8
111.0
1.1
266.7
1.1
267.3
1.1
267.1
111.0
1680
BITUMONT
1.0
141.1
1483
KIRBY1
Bus - Voltage (kV/pu)
Branch - MW/Mvar
Equipment - MW/Mvar
100.0%Rate B
kV: <=72.000 <=144.000 <=240.000 <=500.000 >500.000
10.9
3405
CONKLIN4
2
37
1.1
267.7
9L69
1.1
149.4
42.1
-13.2
1.1
147.4
-2.6
-2.6
-14.8
5.8
1008
SALE01
24.9
-12.3
10204
885ST1
309
MCMILLA7
8.0
9L56
15.6
-138.4
21.6
-62.5
25.0
-27.8
1046
SW
9L22
-64.5
-15.7
-15.7
-64.5
22.9
117.6
23.0
9L81
10.7
-10.7
8.8
-8.7
10282
898ST1
-95.0
163.9
40.0
-24.3
-98.2
40.8
-5.0
181.3
-5.0
181.3
SW
-69.1
99
5.9
60.7
19687
BOHN_02
10.8
-91.8
957L
-0.0
SW
22.3
-63.0
-31.6
13.3
43.7
9L23
-12.0
12.0
-5.9
6.6
-7.1
7.1
3.4
18687
BOHN9
-3.4
1687 3.7
39.1
-39.0
-28.5
29.8
-27.4
43.2
457L
2949
ILAKE_02
306
WINEFRE7
-45.4
-40.3
1090L
-142.3
1245
KINOSIS1
-9.6
10295
KR05
1291
KR01
971L 38.8
38.8
25.0
24.4
1099L
1
-3.0
1.6
-1.5
3.0
-49.6
49.8
-29.9
33.5
21.8
405
CONKLIN1
1118L
974
PIKE_01
1.1
262.6
1.1
263.0
1.0
143.0
-25.1
-13.6
2974
PIKE_02
71.6
44.4H
435
1134L_TP
879
539S_240
51.1
-29.9
1.1
262.5
36
1.5
2405
CONKLIN2
1.0
14.0
-10.7
-52.4
1.0
14.0
3.1
-9.0
SW
-57.8
27.4
18291
KR03
1.1
902
263.5
BCKSP_01
1.1
262.3
1.1
263.2
-13.9
9L45
27.4
10291
KR02
1.0
143.4
428L
-9.6
1.1
258.6
1.1
263.6
878
JFISH01
1949
ILAKE_01
CATEGORY B, LOSS OF 9L47
2016WP POST-CONNECTION
MON, JAN 25 2016 14:49
-63.2
-10.3
1116
1.0
143.3
1.0
25.9
SW
-19.2
BOHN_01
33.5
348
LEISMER4
1.1
264.7
9.6
7.1
369
CHRISLK1
-113.1
25.5
-0.0
8.1
49.5
19291
KR04
0.0
-27.4
9L990
434
189_240
6.4
1.1
260.5
1.1
258.6
9.6
-35.9
5.7
321
HEARTLAK
46.2
1.1
148.8
1.1
147.5
1.1
262.3
17282
HEARTLAK
-141.7
21.3
4.3
1242
KINOSIS2
SW
-10.7
-20.4
-24.4
-50.4
10.7
39.7
20.4
10245
KINOSIS5
P1570
- Bohn Transformer Addition
1.0
1.0
24.4
-10.8
-21.8
-39.7
-46.2
12.0
282
HEARTLAK
1.1
264.4
1348
WHITFISH
-63.0
22.3
1.0
4.3
1.1
147.6
1292
MEAD_144
-68.2
9L85
39.7
11245
KINOSIS6
9L930
1117L
13.2
43.1
19.5
77.5
1.1
264.0
9L913
27.9
-19.5
1.1
146.5
19.1
-103.0
P1570 - Bohn 931S Transformer Addition
-27.9
24.8
51.4
1.1
261.8
1402
SALTCR1
7L183
7L104
21.0
1.0
143.0
-0.0
1.0
25.7
7L15
-55.6
1241
LONGLK1
56.8
-20.9
9L47
0.0
-0.0
1.1
267.2
1.1
264.0
1.1
258.3
SW
1.1
148.1
56.3
1.1
147.6
20.9
7L114
1.0
143.1
15.8
-107.9
1409
QUIGL1
1.1
263.9
1.1
261.3
12249
LNGLKCG2
1
2.3
1.1
268.2
1.1
264.9
-68.2
16.4
7L167
9L55
6.8
468
LEISMER7
9L40
-15.7
-59.4
799
CHARD_TP
page B-7
15.0
1277
BLK_FLY1
-0.0
19242
KINOSIS3
G2
9.1R
9L929
9L56
179
MARIANA7 1623
ENGSTRM1
SW
12.2
920
ROUND01
1228
MITS E.4
1260
LOU CR.4
-14.9
-15.7H
80.0
-20.4
-14.9
-15.5
9L84
SW
-3.2
1276
S-SHINE1
18.2
1.1
267.2
-79.8
1246
LNGLKC02
-22.6
-5.5
16.1
-39.7
1.0
143.4
1411
WADDELL7
1.1
265.6
9L15
1.0
144.2
8.6
7LA114
23.1
-66.5
-3.9
39.0
1010
CHARD_01
1226
WABASCA4
138
N BARRH4
16.3
5.6
1.0
143.4
1.1
266.7
71.6
1.1
14.6
1.1
15.1
2.8
1.1
266.2
-15.6
15.0
-15.7
3.2
1227
CROWLK7
-79.8
-14.9
-2.4
7L121
-29.3
1249
LNGLKC01
15241
LONGLK15
-5.2
7L02
1.1
146.3
-79.8
-3.2
M2
1.1
146.3
-2.9
1.1
147.4
2.6
1.0
141.9
21.7
8.0
1.1
147.8
1.0
142.0
1280
BRINT02
-0.0
-23.1
1.1
266.2
144
ALGAR 7
-29.3
5.8
-42.1
-6.0
-15.7H
17241
LONGLK17
1.1
148.2
-79.8
37.3R
-14.9
7L38
1290
HORSERV7
80.0
13249
LNGLKCG1
1.1
15.1
M1
4.9
2.8
1286
S-SHINE4
9L39
1.1
261.9
1405
SALTCR2
1.1
146.3
1.1
146.3
-71.4
-5.7
1.1
266.7
1.6
11402
977S901T
-71.5
7L135
G1
7L36
1256
SWEETHE7
10200
848S901T
1.1
150.9
1.1
150.4
1282
WILL01
-5.8
1006
GERMAIN1
9L10
-34.1
3.6
13.3
1.0
142.7
1.1
148.0
22.6 9L77
1.1
150.4
3.5
1.1
265.7
204
MCMILLA4
1.1
268.4
-20.1
21.0
-3.4
42.1
1.0000
18288
LIVOCK03
28.8
1602
LIVOCKPS
1.1
265.4
16.6
PST
-13.2
10288
LIVOCK02
1288
LIVOCK01
1.1
266.8
-29.7
-14.1
1.1
148.6
-10.7
-21.7
1.1
150.4
-5.5
9L89
20.1
1224
HANGSTO7
28.0
1.0000
1625
DAWES138
-20.1
-43.6
10.7
1.1
263.5
9.2
7L194
17288
LIVOCK05
43.6
-10.8
1201
RUTH LK8
1.1
14.5
6.1
-6.4
4.2
1.1
259.2
-43.6
1673
HALF_01
18.0
-45.6
6.3
-10.6
-14.2
SW
-42.1
45.6
30.9
1.2 -4.5
1.0
143.5
9.8
7L170
-0.1
1.1
-0.1
265.8
9L57
9L144
10655
DAWE701T
0.0
11201
848S703T
23.0 -30.8
-16.9
1.1
148.6
-6.3
1.0
24.8
0.0
1462
1.0375
7.2
-43.0
11200
848S902T
1622
TWR_RD1
1627
7LA97_TP
1.0
247.6
-0.2
1.1
150.2
4.2
1.1
148.8
7
-45.6
7L47
10.6
-13.8
1239
GREGOIRE
-5.1
-6.3
7L155
-19.9
1.1
148.9
1.1
257.9
45.6
1202
RUTH LA7
-23.0
43.0
-10.7
7.2
7L165
-6.0
-8.8
-0.0
-14.2
49.9
72.9
-57.3
-78.0
6.5
-13.1
13.2
1.0
20.9
-1.1
1.1
265.8
1670
BWC01
1.1
149.2
-43.0
32.3
4.2 -7.5
1.0
144.0
3.0 -3.0
1.1
149.9
7L97
9L19
1222
PARS CR7
10201
848S704T
24.5 -32.3
1200
RUTH LK4
1.1
263.7
1.1
259.2
-25.0
-41.1R
88.5
88.5
SW
1.1
266.9
1.1
268.3
-11.7
1.1
265.8
1203
RUTH LK7
24.5 -24.5
7L71
-41.1
9L43
70107
GENCOG7
1655
DAWES240
9L74
1686
DOGRIB01
1.0
20.8
1.1
149.5
-31.4
-164.6
-36.9
80.3
1.0
71.8
666
DOVER
9L07
6.2
70159
GENCOG59
1.1
262.8
9L58
59
9L09
9L28
-11.7
1.1
265.8
1626
AMRBUS04
-22.3
48.1
50.4
149.5
1669
AMRBUS01
-22.3
-22.1
9L08
1
60.9R
60.9
-13.8
181.0
18274
MACKAY2
1.1
267.1
-3.9
-25.1
-22.4
-5.9
-25.1
1.1
267.4
1208
MILLENN4
9L01
181.0
-123.7
-25.0
76.9
-25.1
-22.4
9L76
1800
ER_01
1.1
267.3
1.1
258.4
157.1
1.0
18.7
-180.1
1.1
266.2
1295
1206
AURORA 4
1212
MIL_G5 4
1205
SYNC_D04
-25.0
1274
MACKAY
-39.5
1263
JOSLYN4
1.1
263.9
-28.0
-85.9
1236
MUSKEG1
13.2
6.8
1251
HORMIN1
1.1
263.9
1610
MCCLE_01
-6.0
9L66
1213
MIL_G6 4
-2.2
1603
KEARL240
-51.7
-6.0L
-16.4
30.2
1612
SECORD01
1.1
262.7
9L32
6.8
1.1
263.9
-28.1
-102.5
-16.4
1214
EDD34
117.6
1.1
264.0
-57.8
8.4
1.1
267.7
29.6
8.4
-57.9
111.0
1.1
266.3
1.1
266.7
1.1
266.5
111.0
1680
BITUMONT
1.0
142.0
1483
KIRBY1
Bus - Voltage (kV/pu)
Branch - MW/Mvar
Equipment - MW/Mvar
100.0%Rate B
kV: <=72.000 <=144.000 <=240.000 <=500.000 >500.000
10.9
3405
CONKLIN4
2
37
1.1
263.9
9L69
17288
LIVOCK05
1625
DAWES138
-9.8
25.6
PST
1008
SALE01
-22.6
0.9
1.1
271.7
-5.7
-10.4
-10.4
-14.4
7.1
10204
885ST1
309
MCMILLA7
-14.3
-15.7H
16.3
23.4
179
MARIANA7 1623
ENGSTRM1
1409
QUIGL1
468
LEISMER7
2.2
9L56
-28.3
28.8
-10.6
-16.5
16.7
SW
2.0
9L22
-67.6
9L81
-69.9
26.6
10282
898ST1
-16.7
P1570 - Bohn 931S Transformer Addition
99
57.2
19687
BOHN_02
37.7
-37.7
17.0
-16.1
-0.0
-45.0
-28.7
-28.7
-45.0
25.9
101.7
26.0
-3.5
159.3
-3.5
-8.1
-48.1
-14.4
-48.1
19.4
37.0
6.6
3.4
18687
BOHN9
-7.0
7.0
-3.4
3.7
-28.4
-0.0
457L
2949
ILAKE_02
1.1
262.6
1090L
1.1
263.6
902
BCKSP_01
971L
-154.4
1099L
88.9
49.6
15.4
28.6
-39.3
-15.3
-52.1
1.1
262.6
13.8
1291
KR01
1.0
14.0
1
-3.0
1.6
-1.5
3.0
405
CONKLIN1
1118L
1.1
262.8
733
193S_240
1.1
263.8
1.0
143.0
1483
KIRBY1
Bus - Voltage (kV/pu)
Branch - MW/Mvar
Equipment - MW/Mvar
100.0%Rate A
kV: <=72.000 <=144.000 <=240.000 <=500.000 >500.000
36
1.5
2405
CONKLIN2
1.0
14.1
-59.5
59.6
-33.7
38.8
70.0
43.9R
435
1134L_TP
1.0
143.2
2974
PIKE_02
1245
KINOSIS1
3.1
2.0
879
539S_240
50.4
-12.5
-60.0
-9.6
1.1
263.7
-28.8
-24.4
-48.9
10295
KR05
1.1
263.3
-3.8
9L45
28.4
28.4
18291
KR03
1.0
143.4
306
WINEFRE7
-9.6
1.1
261.2
10291
KR02
1687
BOHN_01
1.1
265.5
1949
ILAKE_01
CATEGORY A, N-0
2017SP POST-CONNECTION
MON, JAN 25 2016 14:50
-65.3
-10.3
9.6
7.0
974
PIKE_01
1.0
26.1
SW
-19.1
1.0
4.3
878
JFISH01
SW
1.1
264.6
9.6
20.8
-13.3
35.9
19291
KR04
0.0
-28.4
1116
1.0
143.4
1.1
261.2
-0.0
12.0
369
CHRISLK1
434
189_240
-42.1
1.1
265.2
40.4
1.1
150.3
-5.9
9L930
-78.6
30.1
P1570 - Bohn Transformer Addition
-107.9
957L
348
LEISMER4
4.0
1117L
-29.0
-12.0
-15.9
321
HEARTLAK
100.2
34.8
29.0
10245
KINOSIS5
9L990
-75.9
-21.2
-34.8
1.1
148.9
-18.5
59.6
428L
SW
36.5
5.9
1242
KINOSIS2
-19.7
16.7
282
HEARTLAK
1.1
263.9
1348
WHITFISH
-67.9
SW
-68.8
9L85
34.8
-34.8
12.0
1.1
262.7
17282
HEARTLAK
1.1
260.5
-40.4
-28.3
1.1
264.7
9L913
9L40
26.0
1.1
259.3
1292
MEAD_144
1.0
24.9
10.6
10.6
-106.0
page B-8
SW
68.4
19.3
1.0
143.3
-10.6
-0.0
11245
KINOSIS6
1.0
4.3
1.1
146.3
1.1
145.2
-0.0
47.0
9L47
-43.4
30.7
24.8
-19.2
1.1
259.0
8.4
-136.1
15.4
-39.0
1.1
262.7
23.5
-30.7
7L183
1.1
264.5
1.1
267.7
1228
MITS E.4
-23.5
9L929
4.6
11.3
799
CHARD_TP
0.0
-0.0
1.0
25.5
7L15
7L104
19.2
1.1
SW
1402
SALTCR1
1
1411
WADDELL7
19242
KINOSIS3
G2
34.4R
12249
LNGLKCG2
-75.2
-57.1
1046
7LA183TP
-29.9
7L114
1.1
268.8
78.0
-27.7
1.1
264.8
1241
LONGLK1
-26.1
-0.0
1.1
146.8
57.0
1.1
146.3
51.7
SW
7.9
0.2
1.0
144.2
138
N BARRH4
-8.1
-15.7
1.0
144.4
920
ROUND01
159.3
14.4
7L167
1.0
144.8
1.0
144.4
-77.8
1246
LNGLKC02
-29.1
-14.3
-16.3
SW
1.1
264.7
-34.8
5.4
1226
WABASCA4
-49.3
16.3
9L84
1276
S-SHINE1
-0.7
1.1
14.6
1.1
15.0
4.5
1227
CROWLK7
7LA114
20.7
-17.9
1.1
264.8
9L56
14.4
-15.7
-10.2
7L121
1010
CHARD_01
9L55
-10.1
-13.6
-14.3
15241
LONGLK15
-3.8
7L02
-77.8
-27.7
M2
1.1
145.2
4.7
1.1
150.5
10.4
15.4
1249
LNGLKC01
-19.4
-11.0
13.2
1277
BLK_FLY1
1.0
144.0
-77.8
2.7
1.1
263.8
9L15
-0.1
1.1
150.6
1.1
146.2
1260
LOU CR.4
8.0
144
ALGAR 7
1.1
150.4
-15.7H
17241
LONGLK17
1.1
150.6
15.3
-14.3
7L38
1290
HORSERV7
-77.8
-8.9R
13249
LNGLKCG1
1.1
15.0
M1
-2.9
-15.2
1.1
146.2
1280
BRINT02
-12.4
78.0
2.1
-9.8
-16.1
-50.0
3.4
1256
SWEETHE7
1.1
263.1
50.1
1.1
261.7
1405
SALTCR2
1.0
144.0
1.0
144.0
G1
7L36
-7.1
1006
GERMAIN1
9L10
10.8
1.5
9.4
1.1
146.6
1.1
149.3
1286
S-SHINE4
9L39
11402
977S901T
-50.1
7L135
-1.0
1.1
265.1
8.3
16.3
1602
LIVOCKPS
-25.6
1.0000
18288
LIVOCK03
-10.9
204
MCMILLA4
1.1
269.7
1.1
150.5
1.1
150.1
1.1
150.1
1282
WILL01
1.1
149.6
-16.4
1.1
265.1
10.1
-39.4
25.6
-8.2
10288
LIVOCK02
1288
LIVOCK01
1224
HANGSTO7
1.1
263.2
-22.4
1.1
150.1
0.0
9L89
9.8
7L194
29.5
8.9
9L77
7.2
1.1
262.2
12.6
-33.1
19.4
1.1
14.5
SW
-25.6
33.1
-9.0
1.1
263.4
10200
848S901T
-12.2
-10.7
10655
DAWE701T
-17.3
-14.0
8.6
7L170
9L57
9L144
-0.1
1.1
-0.1
265.6
0.0
-0.0
11.1
-37.0
17.3
1201
RUTH LK8
-22.1
1.1
149.6
9.0
1.0
25.4
1.1
265.1
1462
1.0000
-8.5
1.0425
1.1
254.4
-33.1
7.9 -11.4
1.1
147.3
37.0
-17.4
1673
HALF_01
1627
7LA97_TP
33.1
25.4
1.1
265.2
-37.0
1622
TWR_RD1
4.1
1.1
149.4
7
1.1
259.8
-17.1
-6.3
1.1
149.7
-36.5
11200
848S902T
7L165
1239
GREGOIRE
-2.7
2.9
7L155
17.1
13.2
11201
848S703T
18.2 -25.3
-7.2
1.1
151.1
7L47
36.5
-17.1
9L23
3.5
-12.0
-6.2
-9.4
58.9
-52.1
40.0
-38.3
1.1
149.5
-21.4
11.0
1.0
20.9
-1.8
1.1
265.6
1670
BWC01
1202
RUTH LA7
-18.2
1.1
149.7
7L97
9L19
1222
PARS CR7
-36.5
26.6
10.0 -13.4
1.1
147.6
9.1 -9.1
1.1
150.6
6.4
-11.0
70107
GENCOG7
1.1
266.2
10201
848S704T
19.4 -26.6
-12.8
-60.0L
77.2
77.2
-60.0
65.0
-76.7
SW
666
DOVER
1.1
269.9
-7.3
1.1
265.6
1203
RUTH LK7
19.4 -19.4
7L71
1.1
150.1
1655
DAWES240
9L74
1686
DOGRIB01
1.1
21.1
1200
RUTH LK4
1.1
263.4
1.1
265.3
19.1
1.1
73.5
-123.1
9L43
-137.5
-27.9
-45.9
-6.7
9L28
-7.3
1.1
265.6
1626
AMRBUS04
-14.2
22.5
9L07
9L08
1669
AMRBUS01
-14.2
68.1
54.3
-20.1
-8.6
9L82
1.1
262.7
9L58
59
9L09
-7.7
125.4
1.1
265.4
1
50.8R
50.8
-6.3
153.0
70159
GENCOG59
1208
MILLENN4
9L01
153.0
18274
MACKAY2
1.1
266.4
19.2
-3.9
-7.7
-20.3
21.3
11.5
-7.7
765
STONE_01
-38.7
-20.3
9L76
1800
ER_01
1.1
265.4
1.1
259.5
136.4
1.0
18.7
-152.3
1.1
264.5
1295
1206
AURORA 4
1212
MIL_G5 4
1205
SYNC_D04
-12.8
1274
MACKAY
-35.6
1263
JOSLYN4
1.1
263.6
-32.0
-69.1
1236
MUSKEG1
11.0
9.4
1251
HORMIN1
1.1
263.7
1610
MCCLE_01
-6.0
9L66
1213
MIL_G6 4
-29.9
1603
KEARL240
-62.9
-6.0L
-20.1
8.7
1612
SECORD01
1.1
261.6
9L32
9.4
1.1
263.7
-38.8
-40.9
-20.1
1214
EDD34
101.7
1.1
263.9
-61.2
21.1
1.1
263.9
81.6
8.3
-17.3
21.1
1.1
264.6
1.1
263.8
1.1
263.9
81.6
1680
BITUMONT
10.4
5.1
3405
CONKLIN4
2
37
1.1
261.6
9L69
17288
LIVOCK05
1625
DAWES138
-9.9
25.6
1008
SALE01
-54.4
1.7
1.1
271.0
-5.7
-15.8
-15.8
-13.4
7.9
10204
885ST1
309
MCMILLA7
16.4
23.6
179
MARIANA7 1623
ENGSTRM1
1409
QUIGL1
1.2
9L56
9.5
-141.9
15.1
-45.6
-26.8
28.4
7.7
9L22
9L913
9L81
-10.0
-3.3
3.4
10282
898ST1
-62.7
69.3
24.3
-2.9
-64.9
24.8
-22.4
99
57.2
19687
BOHN_02
37.7
-37.7
17.1
-16.2
-43.3
-28.7
-28.7
-43.3
30.1
101.7
30.2
7.1
159.2
7.1
-8.1
-43.2
15.0
-43.2
21.0
37.6
20.8
6.6
3.4
18687
BOHN9
-7.0
7.0
-3.4
3.6
-30.8
-10.3
-11.1
1090L
457L
2949
ILAKE_02
1.1
264.4
902
BCKSP_01
971L
-135.7
-0.0
1099L
88.9
49.6
11.5
26.1
-39.3
3.4
15.1
405
CONKLIN1
1118L
1.1
263.7
733
193S_240
1.1
264.5
1.0
141.8
-12.6
1
-3.0
1.6
-1.5
2974
PIKE_02
3.0
1.0
141.4
1483
KIRBY1
Bus - Voltage (kV/pu)
Branch - MW/Mvar
Equipment - MW/Mvar
100.0%Rate A
kV: <=72.000 <=144.000 <=240.000 <=500.000 >500.000
36
1.5
2405
CONKLIN2
1.0
14.1
-59.5
59.6
-31.1
36.0
70.0
41.1R
435
1134L_TP
879
539S_240
50.4
-52.1
1.1
263.5
1.0
14.0
3.1
9.1
-25.2
-24.4
1291
KR01
1.1
264.5
1.1
263.6
1245
KINOSIS1
-9.6
10295
KR05
1.1
264.1
-3.8
9L45
11.1
11.1
18291
KR03
1.0
142.0
306
WINEFRE7
-9.6
1.1
253.3
10291
KR02
1687
BOHN_01
1.1
266.4
1949
ILAKE_01
1.0
25.3
9.6
7.0
974
PIKE_01
23.5
SW
-19.1
1.0
4.3
878
JFISH01
SW
1.1
266.7
9.6
27.8
-13.3
19291
KR04
0.0
-11.1
1116
1.0
142.0
1.1
253.3
-0.0
12.0
369
CHRISLK1
434
189_240
-38.3
CATEGORY B, LOSS OF 9L45
2017SP POST-CONNECTION
MON, JAN 25 2016 14:50
40.3
1.1
145.9
P1570 - Bohn Transformer Addition
-89.2
957L
348
LEISMER4
321
HEARTLAK
1.1
265.4
19.7
-5.9
-11.2
-59.9
-18.8
-12.0
9L930
1117L
34.7
18.8
10245
KINOSIS5
9L990
-45.4
-58.5
-34.7
1.0
144.5
-30.9
66.9
428L
-0.0
37.1
5.9
1242
KINOSIS2
-1.0
22.4
282
HEARTLAK
1.1
263.6
SW
9L40
page B-9
-64.7
SW
-117.4
9L85
34.7
-22.6
12.0
1.1
263.7
17282
HEARTLAK
1.1
253.4
-40.3
-27.9
1.1
265.2
P1570 - Bohn 931S Transformer Addition
1292
MEAD_144
1.0
24.2
1.0
141.4
-10.0
-0.0
11245
KINOSIS6
1.0
4.3
SW
19.2
19.3
10.0
10.0
-106.1
1348
WHITFISH
18.5
1.0
141.7
18.7
79.1
SW
1.1
259.0
23.4
-18.5
25.0
-19.2
1.1
267.8
9L47
-42.3
-23.4
1.0
142.9
1.1
265.9
1.1
255.5
0.0
-0.0
1402
SALTCR1
9L929
5.7
468
LEISMER7
799
CHARD_TP
SW
1.0
24.9
7L15
7L104
19.2
1411
WADDELL7
2.2
1.1
262.2
12249
LNGLKCG2
7L183
-26.2
-0.0
19242
KINOSIS3
G2
39.7H
1
11.3
1228
MITS E.4
78.0
-32.5
-50.2
-57.1
1046
7LA183TP
-29.6
7L114
1.1
268.4
-77.8
1246
LNGLKC02
1.1
258.6
1241
LONGLK1
-5.8
9L84
SW
1.1
258.6
1.0
143.3
57.0
1.0
142.9
51.7
SW
7.9
0.2
1.0
143.2
138
N BARRH4
-8.1
-15.7
1.0
143.5
920
ROUND01
159.2
14.4
1276
S-SHINE1
9.7
-18.9
-14.3
7L167
1.0
143.9
1.0
143.5
1226
WABASCA4
-61.8
-14.3
-15.7H
8.6
-34.6
5.4
7LA114
22.0
-30.4
1.1
264.0
9L56
16.3
-19.4
-11.1
37.6
1.0
14.4
1.1
14.8
5.5
1227
CROWLK7
1010
CHARD_01
9L55
-10.6
4.5
14.4
-15.7
-15.6
7L121
-77.8
-14.3
15241
LONGLK15
-4.8
7L02
-1.9
1249
LNGLKC01
-32.5
M2
1.0
141.7
10.1
1.1
150.0
15.8
1.1
260.4
1277
BLK_FLY1
1.0
141.7
-77.8
2.7
1.1
263.0
9L15
-2.7
1.1
150.0
1.1
145.6
1260
LOU CR.4
8.0
144
ALGAR 7
1.1
150.0
-15.7H
17241
LONGLK17
1.1
149.9
-1.9
-14.3
7L38
1290
HORSERV7
-77.8
8.4R
13249
LNGLKCG1
1.1
14.8
M1
-8.2
-14.0
1.1
145.7
1280
BRINT02
-8.3
78.0
2.1
-9.9
-16.1
-37.6
4.3
1.1
260.4
1286
S-SHINE4
9L39
1.1
258.0
1405
SALTCR2
1.0
141.7
1.0
141.7
G1
7L36
1256
SWEETHE7
9L77
7.3
11402
977S901T
-37.6
7L135
1.1
148.1
1282
WILL01
1.1
148.8
-7.9
1006
GERMAIN1
9L10
37.2
1.5
9.4
1.1
146.0
1.1
148.6
1.1
148.4
1.1
148.1
-1.0
1.1
264.2
8.3
16.3
1602
LIVOCKPS
-25.6
1.0000
18288
LIVOCK03
-10.9
204
MCMILLA4
1.1
268.8
PST
1224
HANGSTO7
-16.3
1.1
264.1
10.2
-21.2
25.6
-8.7
10288
LIVOCK02
1288
LIVOCK01
19.4
10200
848S901T
-32.9
1.1
148.1
5.4
9L89
9.9
7L194
28.5
7.5
1.1
260.6
1.1
258.1
10.9
-39.4
-18.8
1201
RUTH LK8
1.1
14.5
-22.1
39.4
-7.6
-37.5
18.8
-8.0
SW
-25.6
1.0000
10655
DAWE701T
12.6
37.5
-18.9
-24.6
6.8
7L170
9L57
9L144
-0.1
1.1
-0.1
264.4
0.0
-0.0
9.4 -12.9
1.1
146.2
-33.5
1.1
148.8
7.6
1.0
25.4
1.1
263.5
1462
1.0425
-6.9
25.9
1.1
263.1
-37.5
1673
HALF_01
1627
7LA97_TP
1.1
253.5
-18.6
1622
TWR_RD1
4.1
1.1
147.9
-37.0
-6.3
1.1
147.9
18.6
11200
848S902T
11201
848S703T
18.7 -25.9
-8.6
1.1
149.5
37.0
-18.6
14.7
7L165
1239
GREGOIRE
-2.7
7
-39.4
1202
RUTH LA7
-18.7
7L47
5.5
7L155
1.1
258.5
39.4
11.5 -15.0
1.1
146.5
-37.0
27.1
9L23
6.1
-10.9
-7.6
-9.9
58.6
-36.0
39.9
1.1
148.0
-1.8
1.1
264.4
1670
BWC01
10.5 -10.5
1.1
149.0
7L97
9L19
10201
848S704T
19.9 -27.1
1.1
147.9
1.0
20.8
1.1
268.7
-7.3
1.1
264.4
1222
PARS CR7
-20.3
11.0
1.1
264.9
5.4
-11.0
70107
GENCOG7
-26.7
666
DOVER
1203
RUTH LK7
19.9 -19.9
1200
RUTH LK4
1.1
261.9
1.1
263.1
-12.8
-60.0L
77.2
77.2
-60.0
7L71
1.1
148.5
1655
DAWES240
9L74
1686
DOGRIB01
1.0
20.9
65.1
-76.7
SW
-43.7
2.4
1.1
72.9
-121.8
9L43
-35.7
-137.4
9L28
-7.3
1.1
264.4
1626
AMRBUS04
-14.2
-6.7
9L07
9L08
1669
AMRBUS01
-14.2
49.9
57.0
-20.1
-7.0
9L82
1.1
261.3
9L58
59
9L09
-9.1
133.4
1.1
263.9
1
59.2R
59.2
-6.3
153.0
70159
GENCOG59
1208
MILLENN4
9L01
153.0
18274
MACKAY2
1.1
265.1
23.2
-4.4
-9.1
-20.6
26.7
22.1
-9.1
765
STONE_01
-38.7
-20.6
9L76
1800
ER_01
1.1
263.8
1.1
258.1
163.0
1.0
18.7
-152.3
1.1
262.9
1295
1206
AURORA 4
1212
MIL_G5 4
1205
SYNC_D04
-12.8
1274
MACKAY
-43.4
1263
JOSLYN4
1.1
262.2
-28.3
-65.8
1236
MUSKEG1
11.0
8.5
1251
HORMIN1
1.1
262.3
1610
MCCLE_01
-5.1
9L66
1213
MIL_G6 4
-27.0
1603
KEARL240
-62.9
-5.1R
-20.1
0.0
1612
SECORD01
1.1
260.1
9L32
8.5
1.1
262.3
-38.8
-22.2
-20.1
1214
EDD34
101.7
1.1
262.5
-71.8
25.8
1.1
261.6
81.6
-2.3
-22.6
25.8
1.1
263.0
1.1
262.0
1.1
262.1
81.6
1680
BITUMONT
10.4
5.1
3405
CONKLIN4
2
37
1.1
263.5
9L69
17288
LIVOCK05
1625
DAWES138
-9.8
25.6
PST
-9.9
-21.2
1008
SALE01
-66.7
8.4
1.1
271.8
-5.7
-17.6
-17.6
-11.9
9.6
10204
885ST1
309
MCMILLA7
-14.3
-15.7H
23.5
1409
QUIGL1
468
LEISMER7
2.2
9L56
799
CHARD_TP
28.7
-32.1
10.7
-144.5
16.4
-48.5
SW
10.0
9L22
-12.1
-17.2
17.5
10282
898ST1
9L913
9L81
57.7
23.6
13.2
-63.3
24.1
-0.0
-44.7
-28.7
-44.7
-28.7
101.7
26.8
26.7
-1.6
159.2
-1.6
-8.1
-47.2
-15.7
-47.2
19.8
37.9
28.9
12.0
6.6
37.7
-37.7
17.0
-16.1
-65.0
-10.3
3.4
18687
BOHN9
-7.0
7.0
-3.4
3.7
-28.3
457L
1.1
265.2
2949
ILAKE_02
CATEGORY B, LOSS OF 9L990
2017SP POST-CONNECTION
MON, JAN 25 2016 14:50
1.1
263.2
902
BCKSP_01
971L
-128.1
-3.8
-0.0
1099L
88.9
49.6
16.4
29.1
-39.3
11.0
13.2
405
CONKLIN1
1118L
1.1
262.4
733
193S_240
1.1
263.5
1.0
143.0
-12.5
1
-3.0
1.6
-1.5
2974
PIKE_02
3.0
1.0
142.8
1483
KIRBY1
Bus - Voltage (kV/pu)
Branch - MW/Mvar
Equipment - MW/Mvar
100.0%Rate A
kV: <=72.000 <=144.000 <=240.000 <=500.000 >500.000
36
1.5
2405
CONKLIN2
1.0
14.1
-59.5
59.6
-34.1
39.3
70.0
44.4H
435
1134L_TP
879
539S_240
50.4
-50.9
1.1
262.2
1.0
14.0
3.1
-4.9
-33.2
-24.4
1291
KR01
1.1
263.3
1.1
262.2
1245
KINOSIS1
-9.6
10295
KR05
1.1
263.0
306
WINEFRE7
-70.0
28.3
18291
KR03
1687
BOHN_01
1090L
974
PIKE_01
19.4
9L45
28.3
10291
KR02
1.0
143.2
1949
ILAKE_01
-9.6
1.1
260.4
9.6
7.0
1.1
265.1
SW
1.0
26.0
SW
-19.1
1.0
4.3
878
JFISH01
-13.3
1.1
263.9
9.6
1116
1.0
143.3
34.6
19291
KR04
0.0
-28.3
13.8
434
189_240
-46.4
1.1
260.4
-0.0
-5.9
369
CHRISLK1
348
LEISMER4
321
HEARTLAK
40.4
-12.0
-27.4
-52.3
-27.9
P1570 - Bohn Transformer Addition
-81.6
957L
-33.8
428L
SW
37.4
19687
BOHN_02
9L930
1117L
27.9
10245
KINOSIS5
9L990
52.6
17.5
282
HEARTLAK
1.1
263.6
P1570 - Bohn 931S Transformer Addition
page B-10
-61.2
-17.5
34.8
1.1
148.5
1.1
262.2
1.1
264.5
1348
WHITFISH
5.9
1242
KINOSIS2
6.6
-8.8
-34.8
1.1
149.9
12.0
99
57.2
SW
-137.0
9L85
34.8
-33.5
-28.2
12.1
12.1
SW
1.1
258.9
-67.6
1.0
24.9
-0.0
-105.9
138
N BARRH4
1292
MEAD_144
7L104
17282
HEARTLAK
1.1
259.9
-40.4
19.3
1.0
143.3
-12.1
-0.0
11245
KINOSIS6
1.0
4.3
1.1
146.0
1.0
144.9
-19.2
1.1
259.0
91.6
9L47
-43.7
29.3
7L183
1.1
264.0
1.1
267.6
1.1
262.3
23.5
-29.4
9L929
8.7
11.3
1228
MITS E.4
-23.5
19.2
1.2
0.0
-0.0
1.0
25.4
7L15
1
1411
WADDELL7
SW
1402
SALTCR1
24.8
-29.8
7L114
1.1
268.5
19242
KINOSIS3
G2
35.6R
12249
LNGLKCG2
-72.5
-57.1
1046
7LA183TP
7L167
179
MARIANA7 1623
ENGSTRM1
78.0
-28.9
1.1
264.3
1241
LONGLK1
-26.1
-0.0
1.1
146.5
57.0
1.1
146.0
51.7
SW
7.9
0.2
1.0
143.9
9L40
-8.1
16.3
1.0
144.1
920
ROUND01
159.2
14.4
-15.7
2.1
1.0
144.5
1.0
144.1
-77.8
1246
LNGLKC02
-28.0
-14.3
-1.0
9L84
SW
1.1
264.2
-34.8
5.4
1226
WABASCA4
-67.1
16.3
1276
S-SHINE1
-1.3
1.1
14.6
1.1
15.0
7.2
7LA114
25.1
-35.6
1.1
264.4
9L56
14.4
-15.7
15241
LONGLK15
-6.5
1227
CROWLK7
-77.8
-14.3
-17.3
7L121
14.1
1249
LNGLKC01
-19.4
-11.0
16.9
1277
BLK_FLY1
1.0
143.8
-77.8
-28.9
M2
1.0
144.9
11.8
7L02
1010
CHARD_01
9L55
-15.0
12.2
-0.7
1.1
150.5
1.1
150.5
17.6
14.1
2.7
1.1
263.4
9L15
8.0
144
ALGAR 7
1.1
150.5
-15.7H
17241
LONGLK17
1.1
150.6
-77.8
-7.6R
-14.3
7L38
1290
HORSERV7
78.0
13249
LNGLKCG1
1.1
15.0
1.1
146.0
1260
LOU CR.4
-16.7
M1
-10.0
-12.5
1.1
146.1
1280
BRINT02
-33.6
0.9
1256
SWEETHE7
1.1
262.7
33.6
1.1
260.7
1405
SALTCR2
1.0
143.8
1.0
143.8
G1
7L36
-9.6
1006
GERMAIN1
9L10
47.7
1.5
9.4
1.1
146.4
1.1
149.2
1286
S-SHINE4
9L39
11402
977S901T
-33.6
7L135
-1.0
1.1
264.7
8.3
16.3
-25.6
1.0000
18288
LIVOCK03
1602
LIVOCKPS
-10.9
204
MCMILLA4
1.1
269.4
1.1
150.0
1.1
149.6
1.1
149.6
1282
WILL01
1.1
149.5
-16.4
1.1
264.8
10.1
-13.6
25.6
-13.1
10288
LIVOCK02
1288
LIVOCK01
1224
HANGSTO7
1.1
262.7
-37.7
1.1
149.6
7.1
9L89
9.8
7L194
27.9
10.3
9L77
7.3
1.1
261.7
17.4
-41.3
19.4
1.1
14.5
SW
-25.6
41.3
-10.4
1.1
262.9
10200
848S901T
-16.4
-25.5
10655
DAWE701T
-17.7
-13.5
13.1
7L170
9L57
9L144
-0.1
1.1
-0.1
265.4
0.0
-0.0
11.5
-37.8
17.7
1201
RUTH LK8
-37.0
1.1
149.5
10.4
1.0
25.4
1.1
264.8
1462
1.0000
-9.6
1.0425
1.1
254.2
-41.3
8.3 -11.8
1.1
147.1
37.8
-17.8
1673
HALF_01
1627
7LA97_TP
41.3
26.2
1.1
264.8
-37.8
1622
TWR_RD1
4.1
1.1
149.0
7
1.1
259.7
-17.5
-6.3
1.1
149.3
-37.3
11200
848S902T
7L165
1239
GREGOIRE
-2.7
3.5
7L155
17.5
13.6
11201
848S703T
19.0 -26.2
-7.5
1.1
150.7
7L47
37.3
-17.5
9L23
4.1
-10.3
-6.5
-10.2
54.8
-29.4
37.2
-21.8
1.1
149.1
-19.8
11.0
1.0
20.8
-1.8
1.1
265.4
1670
BWC01
1202
RUTH LA7
-19.0
1.1
149.3
7L97
9L19
1222
PARS CR7
-37.3
27.4
10.4 -13.9
1.1
147.4
9.4 -9.4
1.1
150.3
6.4
-11.0
70107
GENCOG7
1.1
266.0
10201
848S704T
20.2 -27.4
-12.8
-60.0L
77.2
77.2
-60.0
65.0
-76.7
SW
666
DOVER
1.1
269.6
-7.3
1.1
265.4
1203
RUTH LK7
20.2 -20.2
7L71
1.1
149.8
1655
DAWES240
9L74
1686
DOGRIB01
1.1
21.0
1200
RUTH LK4
1.1
263.2
1.1
264.8
19.6
1.1
73.4
-122.8
9L43
-137.5
-29.4
-41.4
-2.8
9L28
-7.3
1.1
265.4
1626
AMRBUS04
-14.2
-6.2
9L07
9L08
1669
AMRBUS01
-14.2
42.2
58.2
-20.1
-8.6
9L82
1.1
262.5
9L58
59
9L09
-9.7
137.0
1.1
265.1
1
52.4R
52.4
-6.3
153.0
70159
GENCOG59
1208
MILLENN4
9L01
153.0
18274
MACKAY2
1.1
266.2
18.9
-3.7
-9.7
-20.1
20.3
26.9
-9.7
765
STONE_01
-38.7
-20.1
9L76
1800
ER_01
1.1
265.1
1.1
259.3
174.0
1.0
18.7
-152.3
1.1
264.2
1295
1206
AURORA 4
1212
MIL_G5 4
1205
SYNC_D04
-12.8
1274
MACKAY
-37.1
1263
JOSLYN4
1.1
263.4
-36.4
-68.4
1236
MUSKEG1
11.0
9.3
1251
HORMIN1
1.1
263.5
1610
MCCLE_01
-6.0
9L66
1213
MIL_G6 4
-29.4
1603
KEARL240
-62.9
-6.0L
-20.1
9.4
1612
SECORD01
1.1
261.3
9L32
9.3
1.1
263.5
-38.8
-14.5
-20.1
1214
EDD34
101.7
1.1
263.6
-76.6
21.9
1.1
263.5
81.6
-7.1
-16.3
21.9
1.1
264.3
1.1
263.5
1.1
263.6
81.6
1680
BITUMONT
10.4
5.1
3405
CONKLIN4
2
37
1.1
264.6
9L69
17288
LIVOCK05
1625
DAWES138
-9.8
25.6
1008
SALE01
21.5
1.1
270.7
-5.7
-3.0
-3.0
5.6
309
MCMILLA7
23.5
179
MARIANA7 1623
ENGSTRM1
1409
QUIGL1
1.2
468
LEISMER7
2.2
799
CHARD_TP
9L56
-26.7
28.1
-8.8
-16.6
16.8
SW
-5.8
9L22
-74.6
9L81
-45.5
-28.7
-28.7
-45.5
24.6
101.7
24.6
-7.2
159.3
-7.2
10282
898ST1
19687
BOHN_02
-0.0
-49.7
-22.4
18.6
36.3
22.4
40.3
1.1
148.2
12.0
6.6
P1570 - Bohn Transformer Addition
37.7
-37.7
17.1
-16.2
SW
-19.1
-63.5
-10.3
3.4
18687
BOHN9
-7.0
7.0
-3.4
3.6
-27.5
971L
1099L
49.6
18.8
29.0
10.8
-28.2
-0.0
879
539S_240
50.4
405
CONKLIN1
1118L
1.1
260.8
733
193S_240
1.1
261.9
1.0
142.2
-24.4
-12.6
2974
PIKE_02
1.0
13.9
1
-3.0
1.6
-1.5
3.0
1.0
141.9
1483
KIRBY1
Bus - Voltage (kV/pu)
Branch - MW/Mvar
Equipment - MW/Mvar
100.0%Rate A
kV: <=72.000 <=144.000 <=240.000 <=500.000 >500.000
36
1.5
2405
CONKLIN2
1.0
14.0
-59.5
59.6
-34.1
39.3
70.0
44.4H
435
1134L_TP
1.1
261.5
457L
2949
ILAKE_02
88.9
-39.3
-42.0
1.0
142.4
-3.8
1291
KR01
3.1
-11.2
-41.2
1.1
260.7
1245
KINOSIS1
10295
KR05
1.1
261.7
902
BCKSP_01
-181.0
1.1
263.0
306
WINEFRE7
-117.5
-64.5
-9.6
1.1
261.8
1.1
260.4
1090L
974
PIKE_01
9L45
27.5
27.5
18291
KR03
1687
BOHN_01
878
JFISH01
1949
ILAKE_01
-9.6
1.1
257.5
10291
KR02
7.8
SW
1.0
25.8
9.6
7.0
369
CHRISLK1
-13.3
1.1
261.0
9.6
1116
1.0
142.4
26.8
19291
KR04
0.0
-27.5
1.0
4.3
-134.5
957L
434
189_240
-42.3
1.1
257.5
-0.0
-5.9
9L930
CATEGORY B, LOSS OF 9L85
2017SP POST-CONNECTION
MON, JAN 25 2016 14:50
-21.5
9L990
348
LEISMER4
9.5
1.1
264.1
34.7
21.5
10245
KINOSIS5
-12.0
-16.4
-105.3
-34.7
1.1
146.8
-6.1
-118.9
428L
SW
35.8
5.9
1242
KINOSIS2
47.1
321
HEARTLAK
143.9
1117L
-8.1
-49.7
-8.1
99
57.2
-46.3
16.8
282
HEARTLAK
1.1
264.1
P1570 - Bohn 931S Transformer Addition
page B-11
-77.1
23.4
1348
WHITFISH
-65.7
SW
-16.8
9L85
34.7
-25.8
12.0
1.1
260.4
17282
HEARTLAK
1.1
255.6
-40.3
-27.7
1.1
262.9
9L913
9L40
23.0
1.1
259.5
1292
MEAD_144
1.0
24.8
8.8
8.8
-104.8
138
N BARRH4
SW
137.9
19.3
1.0
142.5
-8.8
-0.0
11245
KINOSIS6
1.0
4.3
1.0
143.9
1.0
142.8
-0.0
2.8
9L47
-42.9
21.7
24.9
-19.2
1.1
257.5
6.2
-127.9
14.3
-29.8
1.1
263.1
23.4
-21.7
7L183
1.1
261.7
1.1
266.1
1228
MITS E.4
-23.4
9L929
0.7
11.3
1.0
142.6
0.0
-0.0
1.0
25.1
7L15
7L104
19.2
1411
WADDELL7
SW
1402
SALTCR1
1
7L114
1.1
267.6
19242
KINOSIS3
G2
39.7H
12249
LNGLKCG2
-56.9
-57.1
1046
7LA183TP
-29.3
0.2
78.0
-32.6
1.1
260.6
1241
LONGLK1
-26.2
-0.0
1.0
144.4
57.0
1.0
144.0
1.0
142.9
920
ROUND01
159.3
16.3
51.7
SW
1226
WABASCA4
-32.1
-15.7
7L167
1.0
143.3
7.9
7LA114
16.8
-0.7
9L56
-14.3
-15.7H
14.4
5.4
1.0
142.9
-77.8
1246
LNGLKC02
-21.6
-14.3
-31.4
SW
1.1
260.5
-34.7
2.9
1227
CROWLK7
1010
CHARD_01
9L55
1.1
265.1
-5.6
-38.6
16.3
9L84
1276
S-SHINE1
-3.9
1.1
14.5
1.1
14.8
2.7
1.1
264.1
9L15
14.4
-15.7
-2.9
7L121
-77.8
-14.3
15241
LONGLK15
-2.3
7L02
3.9
1249
LNGLKC01
-19.4
-11.0
13.1
1277
BLK_FLY1
1.0
142.5
-77.8
-32.6
M2
1.0
142.8
-2.6
1.1
150.0
3.0
17241
LONGLK17
1.1
150.4
1.1
150.3
1.1
146.3
1260
LOU CR.4
8.0
144
ALGAR 7
1.1
149.9
-15.7H
7L38
1290
HORSERV7
3.9
-14.3
M1
4.5
-16.7
-77.8
2.5R
13249
LNGLKCG1
1.1
14.8
5.1
1.1
146.3
1280
BRINT02
1.0
-11.4
1256
SWEETHE7
-15.7
10204
885ST1
-1.1
-67.0
78.0
2.1
-9.8
-15.5
G1
7L36
-5.6
1006
GERMAIN1
9L10
-25.9
1.5
9.4
1.1
146.7
1.1
149.3
1.1
264.1
67.1
1.1
263.2
1405
SALTCR2
1.0
142.5
1.0
142.5
1.1
150.9
1282
WILL01
1.1
149.5
1.1
264.2
1286
S-SHINE4
9L39
11402
977S901T
-67.1
7L135
-1.0
1.1
265.5
8.3
16.3
1602
LIVOCKPS
-25.6
1.0000
18288
LIVOCK03
-10.9
204
MCMILLA4
1.1
268.9
PST
1224
HANGSTO7
-16.4
1.1
265.3
10.1
-64.4
25.6
-4.1
10288
LIVOCK02
1288
LIVOCK01
1.1
151.4
1.1
150.9
1.1
150.9
-7.3
9L89
9.8
7L194
31.1
9.2
9L77
7.2
-7.3
1.1
14.5
4.7
-24.9
19.4
10200
848S901T
-11.5
SW
-25.6
24.9
-9.2
1.1
264.4
1.1
263.8
10.7
10655
DAWE701T
0.0
-16.6
-10.8
6.8
7L170
9L57
9L144
-0.1
1.1
-0.1
265.9
0.0
10.5
-36.2
16.6
1201
RUTH LK8
-6.6
1.1
149.5
9.2
1.0
25.5
1.1
265.5
1462
1.0000
-8.9
1.0425
1.1
254.6
-24.9
7.2 -10.7
1.1
147.7
36.2
-16.7
1673
HALF_01
1627
7LA97_TP
24.9
24.6
1.1
266.0
-36.2
1622
TWR_RD1
4.1
1.1
149.9
7
1.1
259.7
-16.4
-6.3
1.1
150.4
-35.7
11200
848S902T
7L165
1239
GREGOIRE
-2.7
1.8
7L155
16.4
12.5
11201
848S703T
17.4 -24.6
-6.6
1.1
151.7
7L47
35.7
-16.5
9L23
2.4
-13.5
-5.7
-8.6
60.6
-74.5
41.0
-54.6
1.1
150.0
-22.9
11.0
1.0
20.9
-1.8
1.1
265.9
1670
BWC01
1202
RUTH LA7
-17.4
1.1
150.3
7L97
9L19
1222
PARS CR7
-35.7
25.8
9.3 -12.8
1.1
148.0
8.5 -8.5
1.1
151.2
6.4
-11.0
70107
GENCOG7
1.1
266.6
10201
848S704T
18.6 -25.8
-12.8
-60.0L
77.2
77.2
-60.0
65.0
-76.7
SW
666
DOVER
1.1
269.7
-7.3
1.1
265.9
1203
RUTH LK7
18.6 -18.6
7L71
1.1
150.8
1655
DAWES240
9L74
1686
DOGRIB01
1.1
21.1
1200
RUTH LK4
1.1
264.0
1.1
266.0
18.4
1.1
73.7
-123.4
9L43
-137.5
-25.7
-45.7
-9.3
9L28
-7.3
1.1
265.9
1626
AMRBUS04
-14.2
51.1
9L07
9L08
1669
AMRBUS01
-14.2
93.5
50.4
-20.1
-9.2
9L82
1.1
263.2
9L58
59
9L09
-5.8
114.0
1.1
265.9
1
48.5R
48.5
-6.3
153.0
70159
GENCOG59
1208
MILLENN4
9L01
153.0
18274
MACKAY2
1.1
266.8
17.6
-3.7
-5.8
-20.2
19.6
-3.7
-5.8
765
STONE_01
-38.7
-20.2
9L76
1800
ER_01
1.1
265.9
1.1
260.0
99.1
1.0
18.7
-152.3
1.1
265.0
1295
1206
AURORA 4
1212
MIL_G5 4
1205
SYNC_D04
-12.8
1274
MACKAY
-33.4
1263
JOSLYN4
1.1
264.1
-31.7
-70.1
1236
MUSKEG1
11.0
9.7
1251
HORMIN1
1.1
264.2
1610
MCCLE_01
-6.0
9L66
1213
MIL_G6 4
-30.9
1603
KEARL240
-62.9
-6.0L
-20.1
11.3
1612
SECORD01
1.1
262.1
9L32
9.7
1.1
264.2
-38.8
-67.6
-20.1
1214
EDD34
101.7
1.1
264.3
-46.1
19.5
1.1
264.6
81.6
23.5
-15.7
19.5
1.1
265.1
1.1
264.4
1.1
264.5
81.6
1680
BITUMONT
10.4
5.1
3405
CONKLIN4
2
37
1.1
263.8
9L69
17288
LIVOCK05
1625
DAWES138
-9.8
25.6
PST
-9.8
-29.0
-7.5
1008
SALE01
24.2
-10.7
1.1
271.6
-5.7
144
ALGAR 7
1.1
150.4
-3.3
-3.3
-17.3
4.1
10204
885ST1
309
MCMILLA7
23.4
1409
QUIGL1
1.2
468
LEISMER7
2.2
9L56
SW
28.6
-11.3
-17.6
17.9
SW
6.8
9L22
-63.6
20.6
9L913
9L81
10282
898ST1
-17.9
19687
BOHN_02
-0.0
-45.0
-28.7
-28.7
-45.0
26.0
101.7
26.1
-3.4
159.3
-3.4
-8.1
-48.0
-11.2
-48.0
19.1
37.3
12.0
6.6
P1570 - Bohn Transformer Addition
37.7
-37.7
17.1
-16.1
3.4
18687
BOHN9
-7.0
7.0
-3.4
3.7
1.1
261.8
-28.3
457L
2949
ILAKE_02
1.1
262.9
971L
1099L
88.9
49.6
17.0
29.1
-39.3
-27.6
12.6
405
CONKLIN1
1118L
1.1
262.0
733
193S_240
1.1
262.9
1.0
142.6
-12.5
1291
KR01
2974
PIKE_02
1.0
13.9
1
3.1
-3.0
1.6
-1.5
3.0
1.0
142.5
1483
KIRBY1
Bus - Voltage (kV/pu)
Branch - MW/Mvar
Equipment - MW/Mvar
100.0%Rate A
kV: <=72.000 <=144.000 <=240.000 <=500.000 >500.000
36
1.5
2405
CONKLIN2
1.0
14.0
-59.5
59.6
-34.1
39.3
70.0
44.4H
435
1134L_TP
879
539S_240
50.4
-48.7
1.1
261.9
1245
KINOSIS1
-9.6
2.3
-23.8
-24.4
-49.1
10295
KR05
1.1
262.6
-0.0
-80.0
28.3
18291
KR03
1.0
142.8
-3.8
9L45
28.3
10291
KR02
902
BCKSP_01
-166.6
1.1
264.5
306
WINEFRE7
-9.6
1.1
260.5
1.1
263.0
878
JFISH01
1949
ILAKE_01
CATEGORY B, LOSS OF 9L47
2017SP POST-CONNECTION
MON, JAN 25 2016 14:50
-65.0
-10.3
1687
BOHN_01
1090L
974
PIKE_01
1.0
26.1
SW
-19.1
21.2
SW
1.1
264.0
9.6
9.6
7.0
369
CHRISLK1
-13.3
35.2
19291
KR04
0.0
-28.3
1116
1.0
142.8
1.1
260.5
1.0
4.3
-120.1
957L
434
189_240
-37.3
1.1
264.4
40.4
1.1
149.9
-5.9
9L930
-90.8
29.4
9L990
348
LEISMER4
-2.0
1117L
-28.4
-12.0
-7.9
321
HEARTLAK
119.7
34.8
28.4
10245
KINOSIS5
-0.0
-27.3
-95.2
428L
SW
36.8
5.9
1242
KINOSIS2
60.2
17.8
282
HEARTLAK
1.1
263.7
P1570 - Bohn 931S Transformer Addition
page B-12
-65.8
21.0
1348
WHITFISH
99
57.2
-31.9
-30.8
-34.8
1.1
148.6
1.1
261.9
1.1
263.7
1.1
259.1
-67.7
SW
-37.7
9L85
34.8
-34.1
-28.1
11.3
11.3
-105.0
138
N BARRH4
1292
MEAD_144
1.0
24.8
17282
HEARTLAK
1.1
260.2
-40.4
12.0
99.8
19.3
1.0
142.8
-11.3
-0.0
11245
KINOSIS6
1.0
4.3
1.1
146.2
1.1
145.0
-0.0
9L47
-43.7
30.0
24.8
-19.2
1.1
258.0
9.9
-141.1
16.1
-44.6
1.1
262.5
23.5
-30.0
7L183
1.1
263.7
1.1
266.4
1228
MITS E.4
-23.5
9L929
7.3
11.3
799
CHARD_TP
0.0
-0.0
1.0
25.4
7L15
7L104
19.2
1411
WADDELL7
SW
1402
SALTCR1
1
7L114
1.1
269.6
19242
KINOSIS3
G2
35.0R
12249
LNGLKCG2
-73.7
-57.1
1046
7LA183TP
7L167
179
MARIANA7 1623
ENGSTRM1
78.0
-28.3
1.1
264.5
1241
LONGLK1
-26.1
-0.0
1.1
146.6
57.0
1.1
146.2
-29.8
0.2
1.0
143.7
9L40
-8.1
16.3
1.0
144.0
920
ROUND01
159.3
-15.7
51.7
SW
7.9
1226
WABASCA4
-59.9
-14.3
-15.7H
14.4
2.1
1.0
144.4
1.0
144.0
-77.8
1246
LNGLKC02
-28.5
-14.3
-22.0
SW
1.1
264.4
-34.8
5.4
7LA114
23.6
-28.5
1.1
264.6
9L56
16.3
9L84
1276
S-SHINE1
0.3
1.1
14.6
1.1
15.0
1.4
1010
CHARD_01
9L55
-13.5
1.8
14.4
-15.7
15241
LONGLK15
-0.8
1227
CROWLK7
-77.8
-14.3
-3.2
7L121
14.7
1249
LNGLKC01
-19.4
-11.0
9.5
1277
BLK_FLY1
1.0
143.9
-77.8
2.7
1.1
263.6
9L15
14.7
-28.3
M2
1.1
145.0
-2.3
7L02
1.1
146.2
1260
LOU CR.4
17241
LONGLK17
1.1
150.6
1.1
150.6
1.1
150.4
3.3
-15.7H
7L38
1290
HORSERV7
-77.8
-8.2R
-14.3
M1
4.2
-18.3
78.0
13249
LNGLKCG1
1.1
15.0
6.4
1256
SWEETHE7
1.1
146.2
1280
BRINT02
8.0
-8.1
-4.1
1006
GERMAIN1
9L10
1.1
149.3
1.5
9.4
1.1
146.6
-61.6
-1.0
1.1
265.0
8.3
16.3
1602
LIVOCKPS
-25.6
1.0000
18288
LIVOCK03
-10.9
204
MCMILLA4
1.1
270.0
1.1
263.1
61.7
1.1
262.0
1405
SALTCR2
1.0
143.9
1.0
143.9
G1
7L36
1.1
263.1
1286
S-SHINE4
9L39
11402
977S901T
-61.7
7L135
1.1
150.3
1282
WILL01
1.1
149.6
-16.4
1.1
265.0
10.1
-24.0
25.6
-11.5
10288
LIVOCK02
1288
LIVOCK01
1224
HANGSTO7
-7.0
9L89
9.8
7L194
SW
-25.6
1.1
150.6
1.1
150.2
1.1
150.2
0.4
7.7
9L77
7.2
-16.7
1.1
14.5
29.1
-28.0
19.4
1.1
262.1
7.8
28.0
-7.7
1.1
263.3
10200
848S901T
-8.1
1.3
10655
DAWE701T
-17.0
-15.0
4.0
7L170
9L57
9L144
-0.1
1.1
-0.1
265.6
0.0
-0.0
10.8
-37.2
17.0
1201
RUTH LK8
-10.1
1.1
149.6
7.7
1.0
25.4
1.1
265.1
1462
1.0000
-7.3
1.0425
1.1
254.4
-28.0
7.6 -11.1
1.1
147.3
37.2
-17.1
1673
HALF_01
1627
7LA97_TP
28.0
25.6
1.1
265.3
-37.2
1622
TWR_RD1
4.1
1.1
149.5
7
1.1
259.8
-16.8
-6.3
1.1
149.8
-36.7
11200
848S902T
7L165
1239
GREGOIRE
-2.7
2.4
7L155
16.8
12.9
11201
848S703T
18.4 -25.5
-6.9
1.1
151.2
7L47
36.7
-16.9
9L23
3.0
-11.5
-6.0
-9.6
60.5
-60.0
41.0
-44.1
1.1
149.6
-21.0
11.0
1.0
20.9
-1.8
1.1
265.6
1670
BWC01
1202
RUTH LA7
-18.4
1.1
149.8
7L97
9L19
1222
PARS CR7
-36.7
26.8
9.7 -13.1
1.1
147.7
8.8 -8.8
1.1
150.7
6.4
-11.0
70107
GENCOG7
1.1
266.2
10201
848S704T
19.6 -26.8
-12.8
-60.0L
77.2
77.2
-60.0
65.0
-76.7
SW
666
DOVER
1.1
270.0
-7.3
1.1
265.6
1203
RUTH LK7
19.6 -19.6
7L71
1.1
150.3
1655
DAWES240
9L74
1686
DOGRIB01
1.1
21.0
1200
RUTH LK4
1.1
263.4
1.1
265.3
18.8
1.1
73.5
-123.1
9L43
-137.5
-27.9
-51.6
-4.1
9L28
-7.3
1.1
265.6
1626
AMRBUS04
-14.2
57.4
9L07
9L08
1669
AMRBUS01
-14.2
52.6
52.8
-20.1
-8.5
9L82
1.1
262.7
9L58
59
9L09
-7.0
121.1
1.1
265.4
1
50.9R
50.9
-6.3
153.0
70159
GENCOG59
1208
MILLENN4
9L01
153.0
18274
MACKAY2
1.1
266.4
19.6
-4.0
-7.0
-20.4
22.1
5.8
-7.0
765
STONE_01
-38.7
-20.4
9L76
1800
ER_01
1.1
265.4
1.1
259.5
122.3
1.0
18.7
-152.3
1.1
264.5
1295
1206
AURORA 4
1212
MIL_G5 4
1205
SYNC_D04
-12.8
1274
MACKAY
-35.7
1263
JOSLYN4
1.1
263.6
-27.0
-69.0
1236
MUSKEG1
11.0
9.4
1251
HORMIN1
1.1
263.7
1610
MCCLE_01
-6.0
9L66
1213
MIL_G6 4
-29.9
1603
KEARL240
-62.9
-6.0L
-20.1
7.8
1612
SECORD01
1.1
261.6
9L32
9.4
1.1
263.7
-38.8
-53.1
-20.1
1214
EDD34
101.7
1.1
263.8
-55.5
21.1
1.1
263.8
81.6
14.0
-18.1
21.1
1.1
264.6
1.1
263.8
1.1
263.9
81.6
1680
BITUMONT
10.4
5.1
3405
CONKLIN4
2
37
ATTACHMENT C
Post-Connection System Voltage Stability
Analysis Results
ATCO Electric
C-1
R1
C-1 Post-Connection System Voltage Stability Analysis Results
Scenario 2: 2016WP Post-Project
Figure C-1 shows the PV curves for the 240 kV transmission line 9L10, the MacKay generator’s
transformer, the 240 kV transmission line 9L43, the 240 kV transmission line 9L57, and the 240
kV transmission line 9L930 contingencies in the Study Area in the 2016WP post-connection
scenario.
Figure C-1: PV Curves for Scenario 2 – 2016WP Post-Project
Minimum Margin 5% =130.75MW
(a) 9L10 Contingency
Minimum Margin 5% =130.75MW
Minimum Margin 5% =130.75MW
(b) MacKay Generator’s Transformer Contingency
ATCO Electric
C-2
R1
Minimum Margin 5% =130.75MW
(c) 9L43 Contingency
Minimum Margin 5% =130.75MW
(d) 9L57 Contingency
ATCO Electric
C-3
R1
Minimum Margin 5% =130.75MW
(e) 9L930 Contingency
ATCO Electric
C-4
R1
Fly UP