...

Appendix B Engineering Study NaturEner Canada

by user

on
Category: Documents
41

views

Report

Comments

Transcript

Appendix B Engineering Study NaturEner Canada
Appendix B
Engineering Study
NaturEner Canada
Wild Rose 1 & 2 Wind Project
Project Numbers: 479,693
Date: October 25, 2010
Name
Signature
Date
Anuradha Dissanayaka
October 25, 2010
Andrew Isaacs P.Eng.
October 25, 2010
See "Responsibilities, Signature, and Seal" Chapter for Engineering Seal
APEGGA Permit to Practice P-10922
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
Table of Contents
1.0
Connection Description ................................................................................. 4
2.0
Criteria and Assumptions .............................................................................. 5
2.1
2.2
2.3
2.4
2.5
Reliability Criteria ............................................................................................................. 5
AESO Load Assumptions................................................................................................... 6
Generation and Dispatch Assumptions............................................................................ 6
Facility Ratings.................................................................................................................. 9
Transmission Assumptions ............................................................................................. 10
2.5.1
2.5.2
2.5.3
2.5.4
2.5.5
2.5.6
2.5.7
2.5.8
3.0
Monitored Elements ........................................................................................................... 14
Generation Balancing ......................................................................................................... 15
Wind Farm Model ............................................................................................................... 16
LVRT and Reactive Power Criteria ...................................................................................... 16
SATR Transmission Assumptions ........................................................................................ 17
Additional Transmission Assumptions ................................................................................ 17
Additional Stability Analysis Assumptions, Observations, and Recommendations ........... 17
Special Wind Farm Considerations for Short Circuit Analysis............................................. 19
Existing System Assessment - 2012 Cases ................................................... 20
3.1
Powerflow Analysis ........................................................................................................ 20
3.1.1
3.1.3
3.1.4
3.2
Stability Analysis ............................................................................................................. 27
3.2.1
3.2.2
3.2.3
3.2.4
3.3
4.0
Existing System Powerflow Analysis Summary ................................................................... 20
2012 Summer Light Cases – Existing System ...................................................................... 21
2012 Summer Peak Cases – Existing System ...................................................................... 23
Existing System Dynamic Analysis Summary ...................................................................... 27
Contingency Description Existing System Cases ................................................................. 28
2012 Summer Light Cases – Existing System ...................................................................... 29
2012 Summer Peak Cases – Existing System ...................................................................... 30
Short Circuit Analysis - Existing System.......................................................................... 31
Proposed Connection Scenarios .................................................................. 32
4.1
4.2
5.0
Alternative 1 - Concept # 1 Wild Rose wind farm connection ....................................... 33
Alternative 2 - Concept # 2 Wild Rose Wind Farm connection..................................... 35
Evaluation of Proposed Connection ............................................................ 37
5.1
Powerflow Analysis ........................................................................................................ 37
5.1.1
5.1.2
5.1.3
5.1.4
5.1.5
5.1.6
5.1.7
5.2
Powerflow Analysis Summary (2012 Pre-SATR) ................................................................. 37
2012 Summer Light Cases ................................................................................................... 38
2012 Summer Peak Cases ................................................................................................... 45
Powerflow Analysis Summary (2013 SATR) ........................................................................ 51
Special Notes and Assumptions for 2013 Cases ................................................................. 52
2013 Summer Cases............................................................................................................ 53
Reactor Design .................................................................................................................... 57
Stability Analysis ............................................................................................................. 60
Alberta Electric System Operator
479,693
2
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
5.2.1
5.2.2
5.2.3
5.2.4
5.3
Short Circuit Analysis - Wind added System .................................................................. 67
5.3.1
5.3.2
6.0
Stability Analysis Summary ................................................................................................. 60
Contingency description ..................................................................................................... 62
2012 (Pre-SATR) Cases ........................................................................................................ 63
2013 (SATR) Cases............................................................................................................... 65
Short Circuit Analysis Results – 2012 (Pre-SATR)................................................................ 67
Short Circuit Analysis Results – 2013 (SATR) ...................................................................... 68
Summary and Conclusions .......................................................................... 69
6.1
Summary - Powerflow Analysis ...................................................................................... 69
6.1.1
6.1.2
6.1.3
6.2
Summary - Stability Analysis .......................................................................................... 72
6.2.1
6.3
6.4
7.0
Local Violations ................................................................................................................... 69
Remote Violations............................................................................................................... 70
System-Wide Concerns ....................................................................................................... 70
Results and Observations ................................................................................................... 72
Summary - Short Circuit Analysis ................................................................................... 74
Conclusions..................................................................................................................... 74
Responsibilities, Signature and Seal ............................................................ 75
Appendices ........................................................................................................... 76
Appendix A:
Single Line Diagrams .................................................................... 77
Appendix B:
Category C Powerflow Contingency Analysis ............................. 164
Appendix C:
Acciona DYR model invocation................................................... 185
Appendix D:
Dynamic Analysis Traces ............................................................ 186
Alberta Electric System Operator
479,693
3
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
1.0 Connection Description
NaturEner Energy Canada Inc, through its project companies NaturEner Wild Rose 1 Energy Inc. and
NaturEner Wild Rose 2 Energy Inc. (jointly referred to as NEC) is proposing to develop two wind-powered
generation projects, Wild Rose 1 and Wild Rose 2, collectively the Wild Rose Wind Power Projects
(WRWPP). The Nominal capacity of each plant is 200 MW. This study assumes 204 MW of generation
using 136 – 1.5MW wind turbine generators for each project. Wild Rose 1 is located approximately 55 km
southeast of the City of Medicine Hat and Wild Rose 2 is located and is approximately 30 km south of
Medicine Hat.
NEC plans to connect WRWPP generators to a collector substation they will construct to transform the
voltage from 34.5 kV to 240 kV. Two conceptual connection alternatives were developed for study
(named Concept 1 and Concept 2, described in detail in Chapter 4.0). These alternatives differed
primarily in configuration of the lines connecting Wild Rose 1 and Wild Rose 2 together and to the
Elkwater and Bowmanton Substations. Concept 1 has been removed from consideration by NEC, and all
analysis in this report refers to Concept 2 only.
Figure 1-1 Wild Rose 1 and 2 interconnection with SATR (ref. Section 2.5.5)
Alberta Electric System Operator
479,693
4
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis ______________________________________________________________________ 2.0 Criteria and Assumptions The analysis for the connection of the Wild Rose Wind Power Project has been conducted based upon both 2012 and 2013 summer light and summer peak cases, using PSS/E’s contingency processor version 30.3.3. The following criteria and assumptions have been used for the analysis. 2.1 Reliability Criteria The voltage criteria are based on the AESO Transmission Reliability Criteria Part II (System Planning – dated March 11, 2005), as shown in Table 2‐1 and Table 2‐2 and was applied for N‐1 or Category B disturbances. Loading levels above 100 percent of Summer MVA rating (‘A’ Rating in PSS/E) were reported for all cases. Table 2‐1 illustrates the AESO planning criteria for steady state voltages. The “Extreme” values in this table were applied under contingency conditions, and the “Normal” values in the table were applied under normal conditions. Based on AESO screening suggestions during the preliminary studies, a more relaxed voltage magnitude criteria of 0.95 to 1.1 pu was applied to eliminate nuisance violations at the 240 kV level. Additionally, at the 138 kV level, the voltage magnitude criteria was tightened from the values in Table 2‐1 to 0.95 to 1.08 pu. The minimum contingency case voltage change for range violations to be reported is 0.01 pu. Table 2‐1 AESO Acceptable Range of Steady State Voltage Criteria Alberta Electric System Operator 479,693 5 25/10/2010 Wild Rose Wind Farm – Interconnection Proposal Technical Analysis ______________________________________________________________________ Table 2‐2 AESO Voltage Deviation Criteria 2.2 AESO Load Assumptions The study area loads modeled in the 2012 and 2013 summer light and summer peak load scenarios as provided by the AESO are listed in Table 2‐3. Table 2‐3 Study area load profile (2012 and 2013) 2012 2013 Base Case Summer Light (MW) Summer Peak (MW) Summer Light (MW) Study Area Total 768 1066 792 Summer Peak (MW) 1226 2.3 Generation and Dispatch Assumptions The generation facilities in the Hanna Area were dispatched as shown in Table 2‐4 and Table 2‐5 for the 2012 and 2013 cases. The wind interest in the south system was modeled as shown in Table 2‐6. The initial 2012 case analysis for the area was performed with existing area generation set at maximum levels. The addition of the wind generation projects in the south system with the maximum generation levels listed in Table 2‐5 Hanna Region generation and dispatch assumptions created significant overloads under system normal conditions. Due to these overloads, the dispatch levels for the existing generators in the 2012 cases were reduced to ease these overloads, primarily on the Red Deer to Nevis (912L) transmission line and allow the impact of full output of the Wild Rose Power Projects to be reviewed. This is an important assumption, since the Red Deer to Nevis line will overload if the generation in the south area of the system as represented in this study is at full power with the load levels and system ratings as modeled herein. These dispatch levels were adjusted to eliminate the Red Deer – Nevis overload during system intact (N‐0) conditions for selected worst overloading base cases. Until such time as transmission reinforcements are in place, it is understood that the AESO will develop operational rules to manage potential system constraints as required. The load and topology considered for the 2013 cases allowed full output of the existing area generation units to be reestablished, indicating the importance of load and topology issues. Alberta Electric System Operator 479,693 6 25/10/2010 Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
Table 2-4 2012 Hanna Region generation and dispatch assumptions. (Based on S2C2GGA)
Station Service
Name
Location
Dispatch (MW)
Load (MW)
Battle River 3
Battle River 757S
158
9.2 + 4.9 MVAR
Battle River 4
Battle River 757S
156.5
9.2 + 4.9 MVAR
Battle River 5
Battle River 757S
407
25.6 + 18 MVAR
Sheerness 1
Sheerness 807S
275
17 + 7.5 MVAR
Sheerness 2
Sheerness 807S
275
17 + 7.5 MVAR
Total Generation
1271.5
Wind Generation
IP-518
81
IP-634
88
Total - Wind
169
Table 2-5 2013 Hanna Region generation and dispatch assumptions. (Based on S8C2GGA)
Station Service
Name
Location
Dispatch (MW)
Load (MW)
Battle River 3
Battle River 757S
158
9.2 + 4.9 MVAR
Battle River 4
Battle River 757S
156.5
9.2 + 4.9 MVAR
Battle River 5
Battle River 757S
407
25.6 + 18 MVAR
Sheerness 1
Sheerness 807S
408
17 + 7.5 MVAR
Sheerness 2
Sheerness 807S
408
17 + 7.5 MVAR
Total Generation
1537.5
Wind Generation
IP-518
81
IP-634
88
Total - Wind
169
Alberta Electric System Operator
479,693
7
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
Table 2-6 Wind interest in the South system
SATR Wind
Interest
Region
2012 base
case Dispatch
(MW)
2013 base
case Dispatch
(MW)
Goose Lake
Peigan
MATL
Blackie
Vulcan
Sub A
Sub B
Sub C
Sub D (Whitla)
Med Hat
IP-513
Cypress
IP-617
Wild Rose 1
IP-479
356
356
137
137
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
200 (modeled
by Electranix)
200 (modeled
by Electranix)
Wild Rose 2
IP-693
200 (modeled
by Electranix)
200 (modeled
by Electranix)
Total Wind
Interest in
South
893
893
Alberta Electric System Operator
479,693
8
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
2.4 Facility Ratings
Table 2-7 provides the ratings of the transmission lines near the Wild Rose Wind Power Facility.
Table 2-7 Transmission Line Ratings
Burdet 368S
Voltage
(kV)
138
Rate A
(MVA)
85
Rate B
(MVA)
90
Rate C
(MVA)
99
Taber 83S
138
85
90
99
Langdon 102S
Milo Junction 356S
240
609
609
697
Lethbridge 370S
Milo Junction 356S
240
481
481
529
Ware Junction 132S
Jenner 275S
240
550
679
815
Line
From
To
612L
Finacastle 336S
610L
Finacastle 336S
923L/924L
923L/924L
944L/951L
931L
Ware Junction 132S
West Borok 28S
240
592
592
592
9L950/9L934
Ware Junction 132S
Anderson 801S
240
519
663
663
814L/827L
West Brrok 28S
Brooks 121S
138
167
191
191
795L
Hays 421S
Brooks 121S
138
119
119
119
1002L
Jenner 275S
Dome Empress 163S
240
550
679
815
945L
Jenner 275S
Cypress 562S
240
550
679
815
760L
Empress A7 394S
Dome Empress 163S
138
119
146
161
669L
Empress A7 394S
Cypress 562S
138
90
110
121
1011L
Cypress 562S
Dome Empress 163S
138
177
191
210
879L
100L
892L
Burdet 368S
Suffile 895S
Suffile 895S
East Medicine Hat 41S
Tilly 498S
East Medicine Hat 41S
138
138
138
85
69
67
90
115
96
99
127
106
763L
Taber 83S
Vauxhal 158S
138
121
107
118
172L
Taber 83S
Chinchute 315S
138
119
146
161
821L
Vauxhal 158S
Hays 421S
138
85
90
99
763L
Vauxhal 158S
Ench tap
138
121
92
101
100L
Tilly 498S
West Borok 28S
138
96
96
106
853L
West Brrok 28S
Bassano Tap
138
121
148
163
763L
West Brrok 28S
Ench tap
138
117
89
98
923L/924L
Milo Junction 356S
West Borok 28S
240
599
599
599
924L
Milo Junction 356S
MATLB
240
481
499
599
138
90
96
106
760L
East Medicine Hat 41S Chappice Lake 649S
760L
Glendridge
Chappice Lake 649S
138
90
110
121
853L
Queens Town 504S
Basano Tap
138
121
148
163
1034L/1035L
West Brrok 28S
Bowmanton 244S
240
1000
1200
1440
933L
West Brrok 28S
Anderson 801S
240
519
592
599
830L
Cypress 562S
MaCneil 840S
138
177
191
210
760L
Glendridge
Cypress 562S
138
90
110
121
978L
Elkwater 264S
Wild Rose 1 547S
240
492
606
606
1076L
Elkwater 264S
Eagle Butte 274S
240
492
606
606
1073L/1074L
Elkwater 264S
Bowmanton 244S
240
1000
1200
1440
1009L
964L/983L
Cypress 562S
Elkwater 264S
Bowmanton 244S
Witla 251S
240
240
638
1000
788
1200
788
1440
Alberta Electric System Operator
479,693
9
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
2.5 Transmission Assumptions
41 base cases were initially prepared according to the AESO requirements both in 2012 and 2013 summer
light and summer peak cases. These base cases were developed according to the conceptual
configurations set out jointly by AESO and NEC, showing both varying dispatch and load levels, and
alternate connection configurations proposed by NEC and AltaLink. Medicine Hat import/export levels
were fixed to 50MW export in summer light cases and 26MW import in summer peak. During the course
of the study, one of the two connection alternatives was dropped from the analysis and 21 base cases
were selected for further studies (identified as “concept 2”). Wild Rose 1 and Wild Rose 2 wind farms
were added to the models, and the final base case list is shown in Table 2-8 and Table 2-9.
Table 2-8 Cases for Powerflow and Dynamic Analysis 2012
Base Case Description 2012 Concept 2
Base Case
Import from
Saskatchewan
(Export is -ve)
Import from
BC(Export is
-ve)
Medicine
Hat Export
Wild Rose 1
Wind
Wild Rose 2
Wind
Case
Designation
Concept #2
Existing System Cases
2012SL
2012SP
0MW
-200MW
50MW
0MW
0MW
S1C2ES
150MW
-200MW
50MW
0MW
0MW
S2C2ES
-150MW
-200MW
50MW
0MW
0MW
S3C2ES
0MW
-100MW
-26MW
0MW
0MW
S4C2ES
150MW
-100MW
-26MW
0MW
0MW
S5C2ES
-150MW
-100MW
-26MW
0MW
0MW
S6C2ES
WR1
2012SL
2012SP
0MW
-200MW
50MW
200MW
0MW
S1C2GA
150MW
-200MW
50MW
200MW
0MW
S2C2GA
-150MW
-200MW
50MW
200MW
0MW
S3C2GA
0MW
-100MW
-26MW
200MW
0MW
S4C2GA
150MW
-100MW
-26MW
200MW
0MW
S5C2GA
-150MW
-100MW
-26MW
200MW
0MW
S6C2GA
WR1+WR2
2012SL
2012SP
0MW
-200MW
50MW
200MW
200MW
S1C2GGA
150MW
-200MW
50MW
200MW
200MW
S2C2GGA
-150MW
-200MW
50MW
200MW
200MW
S3C2GGA
0MW
-100MW
-26MW
200MW
200MW
S4C2GGA
150MW
-100MW
-26MW
200MW
200MW
S5C2GGA
-150MW
-100MW
-26MW
200MW
200MW
S6C2GGA
Alberta Electric System Operator
479,693
10
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
Table 2-9 Cases for Powerflow and Dynamic Analysis 2013
Base Case Description 2013
Base Case
Import from
Saskatchewan
(Export is -ve)
Import from
BC(Export is
-ve)
Medicine
Hat Export
Wild Rose 1
Wind
Wild Rose 2
Wind
Case
Designation
Concept #2
WR1 + WR2
2013SL
0MW
-200MW
50MW
200MW
200MW
S8C2GGA
2013SP
0MW
-100MW
-26MW
200MW
200MW
S9C2GGA
2013SP
150MW
-100MW
-26MW
200MW
200MW
S10C2GGA
The network configuration diagrams of the Wild Rose connection for 2012 and 2013 cases are shown in
Figure 2-2 and Figure 2-3.
Alberta Electric System Operator
479,693
11
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis ______________________________________________________________________ 138 kV existing in base case Amoco Empress 163S
1002L 240 kV existing in base case 240 kV Wind Facilities 1011L 945L Jenner 275S To Ware 944L/951L Junction 132S Cypress 562S 669L 830L McNeil 840S
760L 75 km Single Circuit 100L Bowmanton East (Medicine Hat) 244S (B0)
Chappice Lake 649S 47.2 km Medicine Hat 41S Double Circuit Elkwater 264S 1.0 km Single Circuit 172L 36.4km WR2
WR1
2012 (pre‐SATR): Concept 2
Figure 2‐2 2012 pre‐SATR Wild Rose connection Concept #2 Alberta Electric System Operator 479,693 12 25/10/2010 Wild Rose Wind Farm – Interconnection Proposal Technical Analysis ______________________________________________________________________ Amoco Empress 163S
138 kV existing in base case 1002L 240 kV existing in base case 240 kV Wind Facilities 1011L 945L Jenner 275S To Ware 944L/951L Junction 132S Cypress 562S
669L 830L McNeil 840S
1034L 760L 75 km 1035L Single Circuit 100L Bowmanton (East Medicine Hat) 244S (B0) Chappice Lake 649S 47.2 km Medicine Hat 41S Whitla 251S Double Circuit Elkwater 264S 1.0 km Double Circuit
Single Circuit 172L 36.4km WR2
WR1
2013 (SATR): Concept 2
Figure 2‐3 2013 SATR Wild Rose connection Concept #2 Alberta Electric System Operator 479,693 13 25/10/2010 Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
2.5.1 Monitored Elements
All elements (above 70 kV) within the following planning areas (Table 2-10) were analysed as a part of the
contingency analysis to satisfy the requirements of the AESO Reliability Criteria. This list was prepared by
Electranix and approved by the AESO, and includes all line and transformer thermal overloads and bus
voltage violations (steady state and voltage deviation). The violations identified in remote places such as
Keephills and Brazeau were neglected according to the AESO instructions as these areas are remote from
this project and the violations not necessary for inclusion in this project analysis.
Table 2-10 Monitored Areas for Powerflow Analysis
Powerflow Contingency Analysis Monitored Areas
Monitored
Area Number
Area Name
Lines
48
4
47
43
52
54
45
50
Empress
Medicine Hat
Brooks
Sheerness
Vauxhall
Lethbridge
Strathmore/Blackie
Backbone
All Branches
All Branches
All Branches
All Branches
All Branches
All Branches
All Branches
All Branches
All branch outages (above 70 kV) within the following planning areas (Table 2-11) were analyzed and
contingency screening was done to find the problematic contingencies. Only the contingencies (reported
in Sections 3.0 and 5.0) associated with overloading of branches or voltage violations are reported. N-2
(Category C) contingencies have been run (Table 2-12), and are reported in Appendix B. Table 2-13
shows the set of monitored elements used in the dynamic analysis.
Table 2-11 Outage Screening Areas for Powerflow Analysis (Category B)
Powerflow Contingency Screening Area List
Monitored
Area Number
Area Name
Outages
48
4
47
43
52
54
45
50
Empress
Medicine Hat
Brooks
Sheerness
Vauxhall
Lethbridge
Strathmore/Blackie
Backbone
All Branches
All Branches
All Branches
All Branches
All Branches
All Branches
All Branches
All Branches
Alberta Electric System Operator
479,693
14
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
Table 2-12 Selected N-2 (Category C) contingencies for Powerflow Analysis
Contingency
Reference #
Elements Outage
Fault Location (line end)
Fault
C17
945L/951L - from Cypress to Jenner
3LG
Cypress 240kV Substation - 562S
C18
944L - from Jenner to Ware Junction
3LG
Ware Jct 240kV Substation -132S
C19
9L950/9L934 - from Ware Junction to Anderson
3LG
Anderson 240kV Substation -801S
C20
9L950/9L934 - from Ware Junction to Anderson
3LG
Ware Junction 240kV Substation - 132S
C21
923L/924L - from W. Brook to N.Lethbridge (Milo for 2013 cases)
3LG
West Brooks 240kV Substation - 28S
C22
1034L/1035L -from Bowmanton to W.Brook
3LG
Bowmanton 240kV Substation -244S
C23
1073L/1074L - Both circuits lost between Bowmanton and Elkwater
3LG
Bowmanton 240kV Substation -244S
C24
964L/983L - Line West towards Witla/Lethbridge (both lines)
3LG
Elkwater 240kV Substation - 264S
Table 2-13 List of Monitored Items for Dynamic Analysis
Voltage & Frequency
PSS/E Bus
Number
Relative Machine Angles
P,Q
Bus Name
Bus #
Name
477
Elk Water (POI) 240kV
Cypress to Jenner 240kV
1482
Sheerness 1
531
Wild Rose 1 240 kV
Empress to McNeill 138kV
4111
Sand Hill
462
Wild Rose 2 240 kV
Bowmanton - Cypress 240kV
713
Medicine Hat #14
2531/3531
Wild Rose 1 34.5 kV
Wild Rose 1
4631
Wild Rose 1 Terminals
Wild Rose 2
430
West Brooks 138kV
W. Brook to Bowmanton 1034L
680
Medicine Hat 138kV
240 kV line West to Lethbridge
1484
Anderson 240kV
Anderson to Ware Junction 240 kV
167
North Lethbridge 240kV
159
Langdon 240kV
267
Dome Empress 138kV
1473
McNeill 138kV
677
Cypress 240kV
669
Bowmanton 240 kV
2.5.2 Generation Balancing
For all the base cases, coal generation in Wabamun area 40 was adjusted to maintain the import/export
levels from British Columbia and Saskatchewan at fixed levels as shown in Table 2-8 and Table 2-9. The
same Wabamun area coal generation was adjusted to balance 400 MW of new Wild Rose wind
generation.
Alberta Electric System Operator
479,693
15
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
2.5.3 Wind Farm Model
For ACCC analysis, the wind farm was modelled according to standards outlined in the AESO document
entitled “Transmission Modelling Data Requirements – Wind Power Facility Supplement”. Each of the
two 200 MW wind farms were modelled with 2 substation transformers, 10 equivalent feeder cables, 10
Generator step-up transformers, and 10 equivalent generators (shown in Figure 2-4). Additional details
were added for the dynamic analysis.
Since the nominal voltage is high at the Empress area buses, the 34.5 kV/240 kV transformers at Wild
Rose collector substations were operated using a fixed tap of 1.05 pu for 2012 cases and 1.06 pu for 2013
cases. The tap settings were adjusted to keep the voltage level at the Cypress 240 kV bus at pre-Wild Rose
voltage levels. The generator voltage controllers were set to hold the voltage at 1.0 pu at the 34.5kV side
of the 34.5kV/240kV transformer.
A 50 MVAR shunt reactor was installed at Bowmanton substation to mitigate the overvoltage violations
during line energization and loss of all the generation at Wild Rose wind power plant for 2012 cases. The
reactor was modeled out of service for most N-1 contingency cases, and may be of use in reducing
existing Medicine Hat and Empress area over-voltages under contingency conditions if it is in service.
Both wind farm collector models are lumped models and are modeled according to the connection
diagrams provided by NEC (Drawing Nos. H-331725-A-E-82-0253 and H-331725-A-E-82-0254), dated
August 12, 2008.
Wind Farm Models assume 9% collector substation transformer impedances, base rated at 69 MVA.
Overhead lines from collector substations to Elkwater were modeled with ACSR Curlew 1033.5 kcmil
conductor with a single circuit. The overhead line from Bowmanton to Cypress (75km) is modeled with a
single circuit ACSR Falcon 1590 kcmil conductor.
All “Existing System” cases were analyzed with no Wild Rose transmission facilities in service.
2.5.4 LVRT and Reactive Power Criteria
The proposed Wind Power Facility (WPF) meets AESO LVRT requirements, and meets requirements for
dynamic and continuous VAR capability of the plant, as laid out in AESO document entitled
“Wind_Power_Facility_Technical_Requirements_Revision0_signatures_JRF.pdf”.
Alberta Electric System Operator
479,693
16
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
Figure 2-4 PSS/E power flow model for 400 MW Wind Power Facility
2.5.5 SATR Transmission Assumptions
The South Area Transmission Reinforcement (SATR) facilities modeled in the 2013 base cases include:
- Double circuit 240 kV line between Bowmanton and West Brooks (1034L/1035L)
- Double circuit 240 kV line between Elkwater and Whitla Substation
- Expansion of Bowmanton Substation
- Reinforcement and expansion in Cypress/Empress area
Note: During the course of this study, the AESO determined that the ability to expand West Brooks to
accept the line from Bowmanton was not practical. A new substation, Cassils, was developed to the west
of West Brooks for terminating the Bowmanton line. This revised configuration is shown in Figure 1-1.
From an electrical modeling standpoint, this topology modification has no material impact on the results
presented in this study. (Figure 1-1 includes new facilities Southwest of Whitla which were not in the
analysis).
2.5.6 Additional Transmission Assumptions
For all the 2013 base cases a double circuit line was added between Janet and Peigan to represent 911L.
Parameters of each line were set equal to the model available in the 2012 base cases. Rate A of each line
was set to 1000 MVA. These modifications reflect the proposed upgrade of the Janet to Peigan Line in
the SATR.
2.5.7 Additional Stability Analysis Assumptions, Observations, and Recommendations
Dynamic analysis was performed using PSS/E version 30.3.3. The following assumptions were made in
order to allow the cases to run:
- For dynamic analysis, the wind farm was modelled according to standards outlined in the AESO
document entitled “Transmission Modelling Data Requirements – Wind Power Facility
Supplement”. Each of the two 200 MW wind farms were modelled with 2 substation
Alberta Electric System Operator
479,693
17
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
-
transformers, 2 equivalent feeder cables, 2 Generator step-up transformers, and 2 equivalent
generators (shown in Figure 2-5).
The 240kV/138kV transformers are operated at the same fixed tap settings as in the power flow
cases. The generator voltage controllers were set to hold the voltage of the Elkwater 240kV bus.
Category B and C three phase to ground fault contingencies were cleared in 6 cycles.
Category C SLG fault and common breaker-fail events were cleared in 18 cycles.
Several small generator units in the North with no validated models were netted with load to run
the dynamic simulations, per AESO instructions.
SVC models in service in loadflow but with disabled dynamic models were enabled in dynamics,
per AESO instructions.
The Whitla SVC dynamic model was copied from the similarly sized Langdon SVC as no dynamic
model was available in DYR file.
The Wind Turbine Generator Model version used in this study supplied directly by PTI in July,
2010 named AW1530X.obj. Documentation for the model was dated October 2009. The AVR
model used was supplied in July 2010 by PTI named AWTVRW.OBJ.
Figure 2-5 PSS/E dynamic model for 400 MW Wind Power Facility
Alberta Electric System Operator
479,693
18
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
2.5.8 Special Wind Farm Considerations for Short Circuit Analysis
Three‐phase and single-phase to ground short circuit studies were performed using PSS/E Version 30.3.3.
The fault locations considered for the short circuit study are shown in Table 2-14.
Table 2-14 Fault locations for Short Circuit Analysis
Fault Location
PSS/E Bus
Substation
Ware Junction 240kV
225
132S
Jenner 240kV
260
275S
Amoco Empress 240kV
262
163S
West Brooks 138kV
276
121S
Elkwater 240kV
477
264S
West Brooks 240kV
430
28S
Bowmanton 240kV
669
244S
Cypress 1 138kV
674
562S
Cypress 2 240kV
677
562S
Medicine Hat 138kV
680
41S
Sheerness 240kV
1481
807S
Anderson 240kV
1484
801S
Alberta Electric System Operator
479,693
19
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
3.0 Existing System Assessment - 2012 Cases
3.1 Powerflow Analysis
3.1.1 Existing System Powerflow Analysis Summary
For existing system powerflow simulations, several overloading conditions are evident:
-
Elerslie to Argyle 240 kV Circuit: This overload is primarily due to high VAR flows stemming from
the power factor on lines in the Wabamun generation area. VAR management in this region may
be adequate to mitigate this problem or it may be alleviated by proposed system expansions in
the area. This region is far away from the Wild Rose project area, and this overload is not
impacted by the addition of the new wind generation.
Empress to Cypress 138 kV Circuit: This line is rated at 90 MVA and is overloaded under several
load scenarios and contingencies. The overload is made worse by the addition of the Wild Rose
project. The thermal capacity of this line will be upgraded to mitigate these overloads as part of
the scope of the Wild Rose 1 project.
Nevis 240/138 kV Transformer: This transformer overloads under certain load conditions when
the 240 kV line between Nevis and Cordel is out of service. The overload is made worse by the
addition of the Wild Rose project. It is expected that this overload will be handled by future
mitigative solutions currently under assessment by the AESO.
-
-
Note: The generation dispatch assumptions summarized in Section 2.3 for the 2012 cases are critical in
ensuring the N-0 (System Intact) scenarios, with the 2012 system assumptions, are free of overloads.
Altering these dispatch assumptions can cause system intact loading violations, exacerbate contingency
overloading violations, and cause new overloading violations. Until such time as transmission
reinforcements are in place, it is understood that the AESO will develop operational rules to manage the
potential system constraints.
3.1.2 Special Mitigation Notes and Assumptions for 2012 Cases
1.
2.
3.
The Janet to Peigan (911L) line is overloaded in N-0 conditions and overloading becomes
worse during N-1 contingencies. Under N-0 conditions 911L is overloaded, and with 200 MW
Wild Rose wind generation added, overloading increases by a further 9%. With approximately
400 MW Wild Rose wind generation, overloading increases by further 17% (average values).
Since this violation occurs in every case and is known to the AESO, it is excluded from the
results tables.
Non-convergent contingency: Langdon 240kV/500kV Transformer outage in 2012 Summer
Light cases. This problem is appears in all the 2012 Summer light base cases irrespective of the
Wild Rose Wind power project.
A 50 MVAR shunt reactor will be installed at Bowmanton substation to mitigate the
overvoltage violations in Wild Rose area due to sudden loss(trip) of 400 MW Wild Rose wind
Alberta Electric System Operator
479,693
20
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
4.
5.
6.
7.
generation or line energization. (More detailed analysis is presented in 5.1.7 Reactor Design
Section.)
Blackie area 138kV over-voltages may be mitigated by adjusting local transformer tap settings.
Sheerness area 240kV over-voltages may be mitigated by adjusting local transformer tap
settings.
Nevis 240kV/138kV transformer overloading may be mitigated by backing down wind
generation at IP-518 and IP-634.
Capacitor bank operating voltage levels at Calgary area were adjusted to 1.05pu-1.10pu from
0.95pu-1.10pu for 240kV buses and to 1.03pu-1.05pu from 1.00pu-1.05pu for 138kV buses to
mitigate the overvoltage and overloading conditions of the Langdon SVC transformer.
However, overvoltage and overloading conditions are still present for some N-1 contingencies.
3.1.3 2012 Summer Light Cases – Existing System
3.1.3.1 Contingency description 2012 Summer Light cases
Table 3-4 shows a reduced list of contingencies which may be used for reference in the subsequent
tables. Although all Category B contingencies in the regions identified in Table 2-11 were tested, these
contingencies were of particular interest as they exhibited some manner of criteria violation.
Table 3-1 2012SL Contingency description Note 1
Contingency
Note 1
Outage element
D1
Ware Junction to West Brook 4 240kV (931L)
D2
Fincastle 7 to Taber CKT 10 138kV(610L)
D3
Bulls Head 7 to Medicine Hat 7 CKT 80 138kV
D4
Red Deer to Nevis 240kV (912L)
D5
Langdon 4 to West Brook 240kV (924L)
D7
Nevis 4 to Cordell 4 240kV (9L20)
D8
Battle River 79 to Cordell 4 CKT 79 240kV
D9
Anderson 4 240kV/138 1T Transformer
D10
Willesd 4 to W.Grn Tap CKT 95 240kV
D11
Red Deer to Benalto CKT 00 240kV (900L)
D12
Gleiche 7 to Namakwa 7 CKT 33 138kV
D13
Tilley 7 to West Brook 7 CKT 66 138kV
D14
Wint H17 to Bull Pond 7 CKT 85 138kV
D16
Gleiche 7 to Queens Town CKT 76 138kV
D17
Janet 4 to East Calgary CKT 17 240kV
D18
Dome EM 4 to Cypress 2 CKT 11 240kV (945L)
D19
Dome EM 7 to Cypress 1 CKT 69 138kV
Comprehensive analysis was performed, but this table reflects problematic contingencies only.
Alberta Electric System Operator
479,693
21
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
3.1.3.2 S1C2ES - ( 2012 Summer Light case, 0 MW Wild Rose, 0 MW Import from Sask.)
Table 3-2 S1C2ES overloaded branches and voltage violations
Figure
Contingency Overloaded element
%
Overload
Rating A
Other system performance
concerns (Maximum reported)
Blackie area (138kV) overvoltages ( 1.095pu)
S1ES_N0
N-0
None
-
S1ES_D7
D7
Nevis 240kV /138kV
transformer
115%
D8,D9,
D14
None
-
D12
None
-
Many (N-1)
None
-
100MVA
None
Sheerness area (240kV) overvoltages (1.105pu)
Blackie (138kV) over-voltages
(1.105pu)
Empress (240kV) over-voltages
1
(1.109pu)
Additional Notes:
1. Empress area overvoltage may be mitigated by adjusting transformer tap settings and
switching off capacitor banks at Dome Empress 138kV bus.
3.1.3.3 S2C2ES - ( 2012 Summer Light case, 0 MW Wild Rose, 150 MW Import from Sask.)
Table 3-3 S2C2ES overloaded branches and voltage violations
Figure
Contingency Overloaded element
S2ES_N0
N-0
S2ES_D7
D7
S2ES_D18
S2ES_D19
D18,
D19
D1,D8,
D9,D14
%
Overload
None
Rating A
Other system performance
concerns (Maximum reported)
Blackie area (138kV)
overvoltage (1.097pu)
-
Nevis 240kV /138kV
transformer
Empress A7 to
Cypress 1 138kV
128%
100MVA
None
110%,
129.1%
90MVA
None
None
-
Many (N-1)
None
-
Many (N-1)
None
-
D1
None
-
Many (N-1)
None
-
Sheerness area (240kV) overvoltages (1.11pu)
Backbone area (240kV)
overvoltage (1.109pu)
Blackie area (138kV) overvoltages (1.107pu)
Brooks area (240kV) overvoltages (1.102pu)
Empress area (240kV) 1 overvoltages (1.114pu)
Additional Notes:
1. Empress area overvoltage may be mitigated by adjusting transformer tap settings and
switching off capacitor banks at Dome Empress 138kV bus.
Alberta Electric System Operator
479,693
22
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
3.1.3.4 S3C2ES - ( 2012 Summer Light case, 0 MW Wild Rose, 150 MW export to Sask.)
Table 3-4 S3C2ES overloaded branches and voltage violations
Figure
Contingency Overloaded element
%
Overload
S3ES_N0
N-0
None
-
S3ES_D7
D7
Nevis 240kV /138kV
transformer
105%
D8,D14
None
-
Many (N-1)
None
-
Many (N-1)
None
-
Rating A
Other system performance
concerns (Maximum reported)
Blackie area (138kV)
overvoltage (1.099pu)
100MVA
None
Sheerness area (240kV) overvoltages (1.106pu)
Backbone area (240kV)
overvoltage (1.108pu)
Blackie area (138kV)
overvoltage (1.108pu)
3.1.4 2012 Summer Peak Cases – Existing System
3.1.4.1 Contingency description 2012 Summer peak cases
Table 3-5 shows a reduced list of contingencies which may be used for reference in the subsequent
tables. Although all contingencies in the regions identified in Table 2-11 were monitored, these
contingencies were of particular interest as they exhibited some manner of criteria violation.
Alberta Electric System Operator
479,693
23
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
Table 3-5 2012SP contingency description Note 2
Contingency
Note 2
Outage element
E1
Red Deer to Nevis 240kV (912L)
E2
Langdon 4 to West Brook 240kV (924L)
E4
Nevis 4 to Cordell 4 240kV (9L20)
E5
Ware Junction to West Brook 4 240kV (931L)
E6
Tilley 7 to West Brook 7 CKT 66 138kV
E7
Bellamy 4 to Argyll W CKT 04 240kV
E8
Langdon 4 240kV/500kV T1 Transformer
E9
Ellersli to Genesee 4 CKT 09 500kV (1209L)
E10
Battle River 79 to Cordell 4 CKT 79 240kV
E11
Anderson 4 240kV/138 1T Transformer
E12
Wint H17 to Bull Pond 7 CKT 85 138kV
E13
Gaetz 4 to Red Deer 4 CKT 14 240kV
E14
Dome EM 4 to Cypress 2 CKT 11 240kV (945L)
E15
Dome EM 7 to Cypress 1 CKT 69 138kV
E16
Chappice Lake 7 to Medicine Hat 7 CKT 60 138kV
E17
Chappice Lake to Glenridge CKT 58 138kV
E18
Cypress 1 to Glenridge CKT58 138kV
Comprehensive analysis was performed, but this table reflects problematic contingencies only.
Alberta Electric System Operator
479,693
24
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
3.1.4.2 S4C2ES - ( 2012 Summer peak case, 0 MW Wild Rose, 0 MW export to Sask.)
Table 3-6 S4C2ES overloaded branches and voltage violations
Figure
Contingency
Overloaded element
%
Overload
S4ES_N0
N-0
None
-
S4ES_E7
E7
Ellersli to Argylle
240kV
100%
E8,E9,
E13
None
-
E9,E13
None
-
E11
None
-
Many (N-1)
None
-
Rating A
419MVA
Other system performance
concerns (Maximum
reported)
Blackie area (138kV)
Overvoltage (1.094pu)
None
Backbone area (500
kV,240kV)
over-voltages
(1.135pu,1.166pu),
high voltage deviation
Backbone area (500
kV,240kV)
low voltage
(0.962pu,0.946pu)
Sheerness area (240kV)
over-voltages (1.103pu)
Blackie area (138kV)
over-voltages (1.102pu)
Alberta Electric System Operator
479,693
25
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
3.1.4.3 S5C2ES - ( 2012 Summer peak, 0 MW Wild Rose, 150 MW import from Sask.)
Table 3-7 S5C2ES overloaded branches and voltage violations
Figure
Contingency
Overloaded
element
%
Overload
S5ES_N0
N-0
None
-
S5ES_E7
E7
S5ES_E15
E15
Ellersli to
Argylle
240kV
Empress A7 to
Cypress 1138kV
Rating A
Other system performance
concerns (Maximum reported)
Blackie area (138kV)
overvoltage (1.094pu)
101%
419MVA
None
108%
90MVA
None
E8,E9,
E13
None
-
E9,E13
None
-
E10,E11
None
-
Many (N-1)
None
-
E5
None
-
Backbone area (500 kV,240kV)
over-voltages
(1.135pu,1.167pu),
high voltage deviation
Backbone area (500 kV,240kV)
low voltage (0.964pu,0.949pu)
Sheerness area (240kV)
over-voltages (1.103pu)
Blackie area (138kV)
over-voltages (1.103pu)
Empress area (240kV) 1
overvoltage (1.10pu)
Additional Notes:
1. Empress area overvoltage may be mitigated by adjusting transformer tap settings.
3.1.4.4 S6C2ES - ( 2012 Summer peak case, 0 MW Wild Rose, 150 MW export to Sask.)
Table 3-8 S6C2ES overloaded branches and voltage violations
Overloaded
%
Figure
Contingency
Rating A
element
Overload
S6ES_N0
N-0
None
-
E8, E9,
E13
None
-
E9,E13
None
-
E11
None
-
Many
(N-1)
None
-
Other system performance concerns
(Maximum reported)
Blackie area (138kV)
overvoltage (1.098pu)
Backbone area (500 kV,240kV)
over-voltages (1.133pu,1.165pu),
high voltage deviation
Backbone area (500 kV,240kV)
low voltage (0.953pu,0.945pu)
Sheerness area (240kV) over-voltages
(1.103pu)
Blackie area (138kV)over-voltages
(1.105pu)
Alberta Electric System Operator
479,693
26
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
3.2 Stability Analysis
3.2.1 Existing System Dynamic Analysis Summary
Dynamic analysis was performed using PSS/E version 30.3.3. For each of the base cases analyzed, a set of
36 contingencies was applied, including selected Category B and C disturbances. The primary goal of
these studies is to determine whether the system remains dynamically stable under fault and outage
conditions, but each run was examined for additional concerns, such as post-fault voltage, AVR operation,
machine tripping, poorly damped oscillations, and any other problematic behaviour. The assumptions
and additional observations discussed in section 2.5.7 apply for existing system analysis as well as “wind
added” analysis.
The 2012 cases studied here do not exhibit dynamic instability due to the loss of the lines south from
Anderson. The cases use the same dispatch assumptions as the steady state analysis, that being existing
units operating under reduced power to prevent overloading on the Red-Deer Nevis circuit. North-South
power flow through Anderson is reduced, and the loss of this circuit no longer causes instability under
these conditions. This issue is not significantly impacted by the addition of the Wild Rose plant.
Specific dynamic concerns identified with the existing system are:
1. Castle, MacBride, Kettles, and Summerview wind farms experience tripping in some
contingencies. This is due to undervoltage protection operation. This tripping may not be
realistic, and are represented using older unsupported PSS/E models. The existing system wind
farm tripping is not impacted significantly by the addition of the Wild Rose plant.
2. Loss of the double circuit line (N-2) between Cypress and Ware Junction leaves the Empress area
in a very weak condition, and depending on the status of the McNeil DC tie can result in
load/generation imbalance in the area. This imbalance may be sufficient to cause instability. This
condition is not eliminated by the addition of Wild Rose wind farm in 2012, but the
generation/load balance does change depending on wind levels. In 2013, it is expected that this
problem will be reduced due to the strengthened ties into the Empress area as planned in the
Hanna area upgrades.
3. It is noted that while the system is capable of sustaining SLG faults with long clearing times
(during fault-and-common-breaker-fail events), many breaker fail events cause instability if the
fault type is LLLG instead of SLG.
Alberta Electric System Operator
479,693
27
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
3.2.2 Contingency Description Existing System Cases
Table 3-9 shows a list of contingencies and events which were applied for all dynamic analysis cases.
Table 3-9 List of Outages and Events Applied for Dynamic Analysis
Contingency
Reference #
Elements Outage
Fault
Fault Location (line end)
CAT B (N-1)
C1
1009L - from Bowmanton to Cypress
3LG
Bowmanton Substation - 244S
C2
945L or 951L - from Cypress to Jenner
3LG
Cypress 240kV Substation - 562S
C3
944L - from Jenner to Ware Junction
3LG
Ware Jct 240kV Substation -132S
C4
931L - from Ware Junction to W.Brook
3LG
Ware Jct 240kV Substation -132S
C5
9L 933 - from Anderson to W.Brook
3LG
Anderson 240kV Substation -801S
C6
9L 933 - from Anderson to W.Brook
3LG
West Brooks 240kV Substation - 28S
C7
9L950 or 9L934 - from Ware Junction to Anderson
3LG
Ware Junction 240kV Substation - 132S
C8
9L950 or 9L934 - from Ware Junction to Anderson
3LG
Anderson 240kV Substation - 801S
C9
923L or 924L - from W. Brook to N.Lethbridge ( Milo for 2013 cases)
3LG
West Brooks 240kV Substation - 28S
C10
Amoco Empress 163S (240/138kV transformer)
3LG
Amoco Empress 240kV Substation -163S
C11
830L - from Cypress 562S to McNeill 840S
3LG
Cypress 138kV Substation -562S
C12
Elkwater to Wild Rose 1 (Loss of 200MW) 978L
3LG
Elkwater 240kV Substation - 264S
C13
Elkwater to Eagle Butte (Loss of 200 MW) 1076L
3LG
Elkwater 240kV Substation - 264S
C14
One circuits lost between Bowmanton and Elkwater - 1073L/1074L
3LG
Bowmanton 240kV Substation -244S
C15
Sudden loss of all 400 MW wind 978L and 1076L
N/A
N/A
C16
1034L or 1035L - from Bowmanton to W.Brook (2013 only)
3LG
Bowmanton 240kV Substation -244S
C16B
Rd Deer to Nevis - 912L
3LG
Red Deer240kV Substation - 63S
CAT C (N-2)
C17
945L/951L - from Cypress to Jenner
3LG
Cypress 240kV Substation - 562S
C18
944L - from Jenner to Ware Junction
3LG
Ware Jct 240kV Substation -132S
C19
9L950/9L934 - from Ware Junction to Anderson
3LG
Anderson 240kV Substation -801S
C20
9L950/9L934 - from Ware Junction to Anderson
3LG
Ware Junction 240kV Substation - 132S
C21
923L/924L - from W. Brook to N.Lethbridge (Milo for 2013 cases)
3LG
West Brooks 240kV Substation - 28S
C22
1034L/1035L -from Bowmanton to W.Brook
3LG
Bowmanton 240kV Substation -244S
C23
1073L/1074L - Both circuits lost between Bowmanton and Elkwater
3LG
Bowmanton 240kV Substation -244S
C24
964L/983L - Line West towards Witla/Lethbridge (both lines)
3LG
Elkwater 240kV Substation - 264S
Breaker Failure Contingencies ( Delayed clearing time 18cycles)
C25
Janet to Red Deer std time and Janet to Langdon delayed
1LG
Janet 240kV Substation - 74S
C26
Janet to Red Deer std time and trip Janet to Peigan delayed
1LG
Janet 240kV Substation - 74S
C27
Langdon to Milo std time and Langdon to Janet delayed
1LG
Langdon 240kV Substation - 102S
C28
1LG
Langdon 240kV Substation - 102S
C29
Langdon to Janet std time and Langdon SVC delayed time
West Brooks to Milo Junction std time and West Brooks to Ware
Junction delayed time
1LG
West Brooks 240kV Substation - 28S
C30
Red Deer to Gaetz std time and Red Deer to Nevis delayed time
1LG
Red Deer 240kV Substation - 63S
C31
Nevis to Cordel std time and Nevis to Red Deer delayed time
1LG
Nevis 240kV Substation - 766S
C32
Cordel to Nevis std time and BR Unit 5 delayed time
1LG
Cordel 240kV Substation
C33
1LG
Anderson 240kV Substation - 801S
C35
Anderson to West Brooks std time and SH Unit 1 delayed time
Ware Junction to Jenner std time and Ware Junction to West
Brooks delayed time
Jenner to Amoco Empress std time and Jenner to Ware Junction
delayed time
C36
Langdon to Milo std time and Nevis to Red Deer delayed time
C34
1LG
1LG
Ware Junction 240kV Substation - 132S
Jenner 240kV Substation - 275S
N-1-1 contingencies ( 2nd fault and outage after 1st outage reaches steady state)
3LG
Red Deer 240kV Substation - 63S
Alberta Electric System Operator
479,693
28
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
3.2.3 2012 Summer Light Cases – Existing System
Table 3-10 2012 Summer Light Case with no Saskatchewan Import and 0 MW Wild Rose wind
S1C2ES: Existing System - 2012 Light Load (Pre-SATR) with no McNeil activity
Contingency
Expected
Stable?
(Summary)
C1
C2
C3
C4
C5
C6
C7
C8
N-1
C9
C10
C11
C12
C13
C14
C15
C16
C16B
C17
C18
C19
C20
N-2
C21
C22
C23
C24
C25
C26
C27
C28
Breaker C29
fail (SLG - C30
18cycle) C31
C32
C33
C34
C35
N-1-1
C36
N/A
√
√
√
√
√
√
√
√
√
√
N/A
N/A
N/A
N/A
N/A
√
X
X
√
√
√
N/A
N/A
N/A
√
√
√
√
√
√
√
√
√
√
√
√
Comments
N/A
No tripping
100003,4,5 - MCBRIDE tripped (VTGTPTA - UV)
100003,4,5 - MCBRIDE tripped (VTGTPTA - UV)
100003,4,5 - MCBRIDE tripped (VTGTPTA - UV)
100001,2 - CASTLE, 3,4,5 - MACBRIDE, 6,7 - SUMMERG, 8,11 - KETTLES Tripped (VTGTPTA - UV)
100003,4,5 - MCBRIDE tripped (VTGTPTA - UV)
100003,4,5 - MCBRIDE tripped (VTGTPTA - UV)
100001,2 - CASTLE, 3,4,5 - MACBRIDE, 6,7 - SUMMERG, 8,11- KETTLES Tripped (VTGTPTA - UV)
No tripping
No tripping
N/A
N/A
N/A
N/A
N/A
100003,4,5 - MCBRIDE tripped (VTGTPTA - UV)
Unstable (loss of 240 ccts from Cypress to Jenner… no supply to Empress Area load)
Unstable (same comment as C17)
100003,4,5 - MCBRIDE tripped (VTGTPTA - UV)
100003,4,5 - MCBRIDE tripped (VTGTPTA - UV)
100001,2 - CASTLE, 3,4,5 - MACBRIDE, 6,7 - SUMMERG, 8,11- KETTLES Tripped (VTGTPTA - UV)
N/A
N/A
N/A
No tripping
No tripping
No tripping
No tripping
No tripping
No tripping
No tripping
No tripping
No tripping
No tripping
No tripping
100003,4,5 - MCBRIDE tripped (VTGTPTA - UV)
Alberta Electric System Operator
479,693
29
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
3.2.4 2012 Summer Peak Cases – Existing System
Table 3-11 2012 Summer Peak Case with 150 MW Saskatchewan Import and 0 MW Wild Rose wind
S5C2ES:
Expected
Contingency
Stable?
(Summary)
C1
N/A
C2
√
C3
√
C4
√
C5
√
C6
√
C7
√
C8
√
N-1
C9
√
C10
√
C11
√
C12
N/A
C13
N/A
C14
N/A
C15
N/A
C16
N/A
C16B
√
C17
√
C18
√
C19
√
C20
√
N-2
C21
√
C22
N/A
C23
N/A
C24
N/A
C25
√
C26
√
C27
√
C28
√
Breaker C29
√
fail (SLG - C30
√
18cycle) C31
√
C32
√
C33
√
C34
√
C35
√
N-1-1
C36
√
Existing System - 2012 Heavy Load (Pre-SATR) with 150 MW McNeil import
Comments
N/A
No tripping
100003,4,5 - MCBRIDE tripped (VTGTPTA - UV)
100003,4,5 - MCBRIDE tripped (VTGTPTA - UV)
100003,4,5 - MCBRIDE tripped (VTGTPTA - UV)
100001,2 - CASTLE, 3,4,5 - MACBRIDE, 6,7 - SUMMERG, 8 - KETTLES Tripped (VTGTPTA - UV)
100003,4,5 - MCBRIDE tripped (VTGTPTA - UV)
100003,4,5 - MCBRIDE tripped (VTGTPTA - UV)
100001,2 - CASTLE, 3,4,5 - MACBRIDE, 6,7 - SUMMERG, 8 - KETTLES Tripped (VTGTPTA - UV)
No tripping
No tripping
N/A
N/A
N/A
N/A
N/A
100003,4,5 - MCBRIDE tripped (VTGTPTA - UV)
No tripping (loss of 240 ccts from Cypress to Jenner, Empress area load supplied by McNeil)
100003,4,5 - MCBRIDE tripped (VTGTPTA - UV)
100003,4,5 - MCBRIDE tripped (VTGTPTA - UV)
100003,4,5 - MCBRIDE tripped (VTGTPTA - UV)
100001,2 - CASTLE, 3,4,5 - MACBRIDE, 6,7 - SUMMERG, 8 - KETTLES Tripped (VTGTPTA - UV)
N/A
N/A
N/A
No tripping
No tripping
No tripping
No tripping
No tripping
No tripping
No tripping
No tripping
No tripping
No tripping
No tripping
100003,4,5 - MCBRIDE tripped (VTGTPTA - UV)
Alberta Electric System Operator
479,693
30
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
3.3 Short Circuit Analysis - Existing System
A short circuit study was performed using the Summer Peak case with 150MW import from Saskatchewan
(Case designation S5C2ES) to simulate the worst case short circuit faults in existing system.
The results for the existing system analysis are shown in Table 3-12.
Table 3-12 2012 Summer Peak Case with 150MW Saskatchewan Import and 0MW Wild Rose wind
2012 Summer Peak Case with 150MW Saskatchewan Import and 100MW BC Export
(Existing System, S5C2ES)
Pre
Positive Seq Zthev
Zero Seq Zthev
Base
3LG
SLG
Fault
(pu)
(pu)
Fault Location
Voltage
Fault
Fault
Voltage
(kV)
(kA)
(kA)
R
jX
R
jX
(pu)
1.0742
10.402
0.00394 0.02453
7.910
0.00976 0.04617
Ware Junction
240
Jenner
240
1.0748
6.798
0.00580
0.03759
4.136
0.02617
0.10825
Amoco Empress
240
1.0710
5.691
0.00535
0.04496
3.167
0.03822
0.15016
West Brooks
138
1.0327
13.099
0.00719
0.03219
13.627
0.00217
0.02879
Elkwater
240
N/A
N/A
N/A
N/A
N/A
N/A
N/A
West Brooks
240
1.0550
10.772
0.00480
0.02306
11.281
0.00202
0.01969
Bowmanton
240
N/A
N/A
N/A
N/A
N/A
N/A
N/A
Cypress 1
138
1.0225
8.459
0.00519
0.05030
5.315
0.03566
0.13873
Cypress 2
240
1.0714
5.653
0.00547
0.04526
3.178
0.03794
0.14883
Medicine Hat
138
0.9965
5.381
0.02313
0.07394
5.413
0.00797
0.07720
Sheerness
240
1.0865
12.491
0.00238
0.02079
12.458
0.00186
0.01857
Anderson
240
1.0859
12.815
0.00235
0.02025
12.910
0.00171
0.01750
Alberta Electric System Operator
479,693
31
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
4.0 Proposed Connection Scenarios
Two connecting alternatives have been studied for the Wild Rose wind farm connection, referred to here
as concept numbers 1 and 2. These two alternatives represent various concepts under consideration by
NEC, and are illustrated in Figure 4-6 and Figure 4-7 (Concept 1) and Figure 4-8 and Figure 4-9 (Concept
2). Subsequent to the commencement of this analysis, concept 2 was selected, and all concept 1 analysis
was abandoned.
Both approaches utilize 240kV switching stations to connect to the AESO system. The switching stations
would be a breaker and a half arrangement. The difference between the two alternatives would be that
the wind farms in Concept 1 would be connected in to only one 240kV line for either wind farm by means
of two separate switching stations where in Concept 2 both farms would be connected in to both 240kV
lines using a common switching station. Either approach was considered acceptable for consideration by
the AESO. Subsequent to the commencement of this analysis, concept 2 was selected by NEC as the
preferred alternative. This selection was based primarily on considerations associated with the preferred
route selected by AltaLink for the SATR project.
The AESO accepted either connection for consideration and was indifferent if NEC determined to remove
one connection alternative from consideration.
Alberta Electric System Operator
479,693
32
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis ______________________________________________________________________ 4.1 Alternative 1 ‐ Concept # 1 Wild Rose wind farm connection Amoco Empress 163S
138 kV existing in base case 1002L 240 kV existing in base case 240 kV Wind Facilities 1011L 945L Jenner 275S To Ware 944L/951L Junction 132S Cypress 562S 669L 830L McNeil 840S
760L 75 km Single Circuit 100L East Medicine Hat 244S (B0) Chappice Lake 649S 75.6 km Medicine Hat 41S 54.2km Double Circuit Elkwater 264S Single Circuit 172L 15 km WR1 0.1‐1.0 km WR2
2012 (pre‐SATR): Concept 1
Figure 4‐6 2012 Pre ‐ SATR Wild Rose connection concept #1 (Not Studied) Alberta Electric System Operator 479,693 33 25/10/2010 Wild Rose Wind Farm – Interconnection Proposal Technical Analysis ______________________________________________________________________ Amoco Empress 163S
138 kV existing in base case 1002L 240 kV existing in base case 240 kV Wind Facilities 1011L 945L Jenner 275S To Ware 944L/951L Junction 132S Cypress 562S 669L 830L McNeil 840S
1034L 760L 75 km 1035L Single Circuit 100L East Medicine Hat 244S (B0) Chappice Lake 649S 75.6 km Medicine Hat 41S 54.2km
Double Circuit Whitla 251S Elkwater 264S Single Circuit 172L 15 km WR1 0.1‐1.0 km WR2
2013 (SATR): Concept 1
Figure 4‐7 2013 SATR Wild Rose connection concept #1 (Not Studied) Alberta Electric System Operator 479,693 34 25/10/2010 Wild Rose Wind Farm – Interconnection Proposal Technical Analysis ______________________________________________________________________ 4.2 Alternative 2 ‐ Concept # 2 Wild Rose Wind Farm connection 138 kV existing in base case Amoco Empress 163S
1002L 240 kV existing in base case 240 kV Wind Facilities 1011L 945L Jenner 275S To Ware 944L/951L Junction 132S Cypress 562S 669L 830L McNeil 840S
760L 75 km Single Circuit 100L East Medicine Hat 244S (B0) Chappice Lake 649S 47.2 km Medicine Hat 41S Double Circuit Elkwater 264S 0.1 ‐ 1.0 km Single Circuit 172L 36.4km WR2
WR1
2012 (pre‐SATR): Concept 2 Figure 4‐8 2012 Pre ‐ SATR Wild Rose connection concept #2 Alberta Electric System Operator 479,693 35 25/10/2010 Wild Rose Wind Farm – Interconnection Proposal Technical Analysis ______________________________________________________________________ Amoco Empress 163S
138 kV existing in base case 1002L 240 kV existing in base case 240 kV Wind Facilities 1011L 945L Jenner 275S To Ware 944L/951L Junction 132S Cypress 562S
669L 830L McNeil 840S
1034L 760L 75 km 1035L Single Circuit 100L East Medicine Hat 244S (B0) Chappice Lake 649S 47.2 km Medicine Hat 41S Double Circuit Whitla 251S Elkwater 264S 0.1 ‐ 1.0 km Double Circuit
Single Circuit 172L 36.4km WR2
WR1
2013 (SATR): Concept 2
Figure 4‐9 2013 SATR Wild Rose connection concept #2 Alberta Electric System Operator 479,693 36 25/10/2010 Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
5.0 Evaluation of Proposed Connection
5.1 Powerflow Analysis
5.1.1 Powerflow Analysis Summary (2012 Pre-SATR)
Of the 2012 cases studied, the worst overloading occurs with the 2012 summer light case with 150 MW
importing from Saskatchewan (S2C2GGA). For powerflow simulations with the Wild Rose Wind Farm
added, several overloading conditions are evident:
-
-
-
-
-
-
Elerslie to Argyle 240 kV Circuit: This overload is primarily due to high VAR flows stemming from
poor power factor on lines in the Wabamun generation area. VAR management in this region
may be adequate to mitigate this problem. This region is far away from the Wild Rose project
area, and this overload is not substantially impacted by the addition of the new wind generation.
Empress to Cypress 138 kV Circuit: This line is rated at 90 MVA and is overloaded under several
load scenarios and contingencies. The overload is made worse by the addition of the Wild Rose
project. The thermal capacity of this line must be upgraded to mitigate these overloads.
Nevis 240/138 kV Transformer: This transformer overloads under certain load conditions when
the 240 kV line between Nevis and Cordel is out of service. The overload is made worse by the
addition of the Wild Rose project. It is expected that this overload will be mitigated by future cutplane management currently being evaluated by the AESO.
West Brooks – Bassano Tap – Queenstown 138 kV Circuit: The addition of the Wild Rose Wind
Farm overloads this circuit under contingency conditions. A RAS scheme exists to manage this
overload, and should be extended to account for the Wild Rose project.
Medicine Hat – Suffield 138 kV Circuit, and Medicine Hat – Chappice Lake – Glenridge – Cypress
Circuit: The 138 kV network around Medicine Hat is stressed by the addition of any injection of
power in the Cypress/Empress area, including Wild Rose and the McNeil DC tie. Wind connecting
into the 138 kV system around Medicine Hat also stresses this network, causing overloads under
contingency conditions. It is expected that the SATR network upgrades will mitigate these
overloads.
Red Deer – Nevis 138 kV Circuit (912L): The dispatch levels for existing area generators in the 2012
“system intact” cases were set at low levels to ease the overloading of the Red Deer to Nevis
(912L) transmission line and allow the impact of full output of the Wild Rose Power Projects to be
studied. However, under contingency conditions, this circuit will overload unless generation is
further reduced.
Several additional marginal overloads are evident under contingency conditions, including Ware Junction
to West Brook 240kV, Blackie 7 to Vulcan 7 138kV and Empress A7 to Dome Empress 7 138kV. These
overloads indicate that the system is operating in a marginal state during these contingencies, and should
be carefully examined in future study efforts.
Note: The generation dispatch assumptions summarized in section 2.3 for the 2012 cases are critical in
ensuring the N-0 (System Intact) scenarios, considering the 2012 system assumptions, are free of
overloads. Altering these dispatch assumptions can cause system intact loading violations, exacerbate
Alberta Electric System Operator
479,693
37
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
contingency overloading violations, and cause new overloading violations. In particular, south system
wind interest and the existing generation levels are critical assumptions for all Pre-SATR 2012 cases.
5.1.2 2012 Summer Light Cases
5.1.2.1 Contingency Description 2012 Summer Light Cases
Table 5-1 shows a reduced list of contingencies which may be used for reference in the subsequent
tables. Although all contingencies in the regions identified in Table 2-11 were monitored, these
contingencies were of particular interest as they exhibited some manner of criteria violation.
Table 5-1 2012SL Contingency description Note 3
Contingency
Note 3
Outage element
D1
Ware Junction to West Brook 4 240kV (931L)
D2
Fincastle 7 to Taber CKT 10 138kV(610L)
D3
Bulls Head 7 to Medicine Hat 7 CKT 80 138kV
D4
Red Deer to Nevis 240kV (912L)
D5
Langdon 4 to West Brook 240kV (924L)
D7
Nevis 4 to Cordell 4 240kV (9L20)
D8
Battle River 79 to Cordell 4 CKT 79 240kV
D9
Anderson 4 240kV/138 1T Transformer
D10
Willesd 4 to W.Grn Tap CKT 95 240kV
D11
Red Deer to Benalto CKT 00 240kV (900L)
D12
Gleiche 7 to Namakwa 7 CKT 33 138kV
D13
Tilley 7 to West Brook 7 CKT 66 138kV
D14
Wint H17 to Bull Pond 7 CKT 85 138kV
D16
Gleiche 7 to Queens Town CKT 76 138kV
D17
Janet 4 to East Calgary CKT 17 240kV
D18
Dome EM 4 to Cypress 2 CKT 11 240kV (945L)
D19
Dome EM 7 to Cypress 1 CKT 69 138kV
Comprehensive analysis was performed, but this table reflects problematic contingencies only.
Alberta Electric System Operator
479,693
38
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
5.1.2.2 S1C2GA - (2012 Summer Light case, 200 MW Wild Rose, 0 MW export to Sask.)
Table 5-2 S1C2GA overloaded branches and voltage violations
Figure
Contingency
S1GA_N0
N-0
S1GA_D7
D7
S1GA_D18
D18
Overloaded
element
None
Nevis 240kV
/138kV
transformer
Empress A7
to Cypress 1
138kV
D1,D8,
D9,D14
None
D11
None
D1,D8
None
D16
(Many N-1)
None
Existing
system
1.095pu
%
Overload
Rating A
Other system
performance concerns
(Maximum reported)
Blackie area (138kV)
over-voltages
(1.096pu)
-
115%
130%
100MVA
None
None
100%1
90MVA
None
1.105pu
None
1.109pu
1.105pu
None
-
None
-
None
-
None
-
Sheerness area
(240kV) over-voltages
(1.106pu)
Backbone area
(240kV) over-voltages
(1.102pu)
Empress area (240kV)
over-voltages
(1.108pu)
Blackie area (138kV)
over-voltages (1.10pu)
1
Although this overload is new for this contingency, the overloaded element is overloaded in
other existing system cases (eg. S2C2ES)
Alberta Electric System Operator
479,693
39
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
5.1.2.3 S2C2GA - ( 2012 Summer Light case, 200 MW Wild Rose, 150 MW import from Sask.)
Table 5-3 S2C2GA overloaded branches and voltage violations
Existing
Figure
Contingency
Overloaded element
S2GA_N0
N-0
None
N-0
None
S2GA_D4
S2GA_D5
S2GA_D7
D4,
D5,
D7
West Brook 7 to
Bassano Tap 138kV
S2GA_D7
D7
S2GA_D4
D4
S2GA_D1
8
System
1.097pu
Nevis 240kV /138kV
transformer
Queens Town to
Bassano Tap 138kV
%
Overload
Rating A
-
Other system
performance
concerns
(Maximum
reported)
Blackie area
(138kV) overvoltages
(1.097pu)
Empress area
(240kV) overvoltages
(1.101pu)
None
-
None
None
None
128%
111.7%
103.0%
101.6%
121MVA
None
142%
100MVA
None
103%
121MVA
None
None
Many (N-1)
Empress A7 to
Cypress 1 138kV
129.1%
up to
145%
D1,D8,
D9,D14,
None
1.110pu
None
D11
None
1.109pu
None
D1
None
1.114pu
None
D16
None
1.107pu
None
90MVA
Reported
separately in this
table
Sheerness area
(240kV) overvoltages
(1.105pu)
Backbone area
(240kV) overvoltages
(1.105pu)
Empress area
(240kV) overvoltages
(1.107pu)
Blackie area
(138kV) overvoltages
(1.110pu)
Alberta Electric System Operator
479,693
40
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
5.1.2.4 S3C2GA - (2012 Summer Light case, 200 MW Wild Rose, 150 MW export to Sask.)
Table 5-4 S3C2GA overloaded branches and voltage violations
Figure
S3GA_N0
S3GA_D7
Contingency
Overloaded
element
Existing
System
%
Overload
N-0
None
1.099pu
-
D7
Nevis 240kV
/138kV
transformer
105%
119%
D1,D8,
D9,D14
None
D11
None
D1
None
1.106%
1.108pu
None
None
None
None
1.108pu
D16
None
None
Rating A
Other system
performance
concerns (Maximum
reported)
Blackie area (138kV)
over-voltages
(1.097pu)
100MVA
None
Sheerness area
(240kV) overvoltages (1.105pu)
Backbone area
(240kV) overvoltages (1.103pu)
Empress area
(240kV) overvoltages (1.101pu)
Blackie area (138kV)
overvoltage
(1.100pu)
Alberta Electric System Operator
479,693
41
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
5.1.2.5 S1C2GGA - (2012 Summer Light case, 400 MW Wild Rose, 0 MW export to Sask.)
Table 5-5 S1C2GGA overloaded branches and voltage violations
Overloaded
%
Overload
Figure
Contingency
element
Existing
System
S1GGA_N0
N-0
None
1.095pu
-
S1GGA_D4
S1GGA_D5
S1GGA_D7
D4,
D5,
D7
None
115%
108%
105%
121MVA
None
S1GGA_D4
D4
None
106%
121MVA
None
S1GGA_D7
D7
115%
144%
100MVA
None
S1GGA_D18
D18
West Brook 7 to
Bassano Tap
138kV
Queens Town to
Bassano Tap
138kV
Nevis 240kV/
138kV
transformer
Empress A7 to
Cypress 1 138kV
None
138%
90MVA
None
D8,
D9
None
1.105pu
-
D11
None
None
-
D12
None
1.105pu
-
Rating A
Other system
performance
concerns
(Maximum
reported)
Blackie area
(138kV) overvoltages
(1.094pu)
Sheerness area
(240kV) overvoltages
(1.104pu)
Backbone area
(240kV) overvoltages
(1.101pu)
Blackie area
(138kV) overvoltages
(1.106pu)
Alberta Electric System Operator
479,693
42
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
5.1.2.6 S2C2GGA - (2012 Summer Light, 400 MW Wild Rose, 150 MW import from Sask.)
Table 5-6 S2C2GGA overloaded branches and voltage violations
Figure
Contingency
Overloaded
element
Existing
System
S2GGA_N0
N-0
None
1.097pu
S2GGA_N0
N-0
S2GGA_D1
S2GGA_D5
S2GGA_D1
S2GGA_D2
S2GGA_D3
S2GGA_D4
S2GGA_D5
S2GGA_D7
D1,
D5
D1,
D2,
D3
D4,
D5,
D7
S2GGA_D1
D1
S2GGA_D4
S2GGA_D5
S2GGA_D7
D4,
D5,
D7
S2GGA_D1
D1
S2GGA_D7
D7
S2GGA_D18
Many (N-1)
Empress A7 to
Cypress 1 138kV
Red Deer to Nevis
240kV (912L)
Suffield 7 to
Medicine Hat 7
138kV (892L)
West Brook 7 to
Bassano Tap
138kV
Chappice Lake to
Glenridge 138kV
Queens Town to
Bassano Tap
138kV
Cypress 1 to
Glenridge 138kV
Nevis 240kV
/138kV
transformer
Empress A7 to
Cypress 1 138kV
%
Overload
Rating A
-
90MVA
None
488MVA
None
67MVA
None
121MVA
None
104%
90MVA
None
118%
111%
107%
121MVA
None
104%
90MVA
None
128%
155%
100MVA
None
129.1%
up to
184%
90MVA
None
None
None
None
None
None
None
None
105.6%
Other system
performance
concerns
(Maximum
reported)
Blackie area
(138kV) overvoltages
(1.092pu)
109.0%
102.2%
121%
117%
103%
127%
120%
116%
D8,
D9
None
1.11pu
-
D10,
D11
None
1.109pu
-
D12
None
1.107pu
-
Sheerness area
(240kV) overvoltages
(1.104pu)
Backbone area
(240kV)
overvoltage
(1.101pu)
Blackie area
(138kV)
overvoltage
(1.106pu)
Alberta Electric System Operator
479,693
43
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
5.1.2.7 S3C2GGA - (2012 Summer Light case, 400 MW Wild Rose, 150 MW export to Sask.)
Table 5-7 S3C2GGA overloaded branches and voltage violations
%
Overload
Other system
performance
concerns
(Maximum
reported)
Blackie area
(138kV) overvoltages (1.093pu)
Figure
Contingency
Overloaded
element
Existing
System
S3GGA_N0
N-0
None
1.099pu
-
S3GGA_D7
D7
105%
133%
100MVA
None
S3GGA_D4
D4
None
103%
121MVA
None
Nevis 240kV
/138kV
transformer
West Brook 7 to
Bassano Tap
138kV
D8,
D9
None
D11
(Many N-1)
None
1.106pu
1.108pu
-
-
Rating A
Sheerness area
(240kV) overvoltages (1.104pu)
Backbone area
(240kV) overvoltages (1.102pu)
Alberta Electric System Operator
479,693
44
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
5.1.3 2012 Summer Peak Cases
5.1.3.1 Contingency Description 2012 Summer Peak Cases
Table 5-8 shows a reduced list of contingencies which may be used for reference in the subsequent
tables. Although all contingencies in the regions identified in Table 2-11 were monitored, these
contingencies were of particular interest as they exhibited some manner of criteria violation.
Table 5-8 2012SP contingency description Note 4
Contingency
Note 4
Outage element
E1
Red Deer to Nevis 240kV (912L)
E2
Langdon 4 to West Brook 240kV (924L)
E4
Nevis 4 to Cordell 4 240kV (9L20)
E5
Ware Junction to West Brook 4 240kV (931L)
E6
Tilley 7 to West Brook 7 CKT 66 138kV
E7
Bellamy 4 to Argyll W CKT 04 240kV
E8
Langdon 4 240kV/500kV T1 Transformer
E9
Ellersli to Genesee 4 CKT 09 500kV (1209L)
E10
Battle River 79 to Cordell 4 CKT 79 240kV
E11
Anderson 4 240kV/138 1T Transformer
E12
Wint H17 to Bull Pond 7 CKT 85 138kV
E13
Gaetz 4 to Red Deer 4 CKT 14 240kV
E14
Dome EM 4 to Cypress 2 CKT 11 240kV (945L)
E15
Dome EM 7 to Cypress 1 CKT 69 138kV
E16
Chappice Lake 7 to Medicine Hat 7 CKT 60 138kV
E17
Chappice Lake to Glenridge CKT 58 138kV
E18
Cypress 1 to Glenridge CKT58 138kV
Comprehensive analysis was performed, but this table reflects problematic contingencies only.
Alberta Electric System Operator
479,693
45
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
5.1.3.2 S4C2GA - (2012 Summer peak case, 200 MW Wild Rose, 0 MW export to Sask.)
Table 5-9 S4C2GA overloaded branches and voltage violations
Existing
Overloaded
%
Figure
Contingency
System
element
Overload
S4GA_N
0
N-0
None
1.094pu
-
S4GA_E7
E7
Ellersli to
Argylle 240kV
100%
102%
E8,E13
None
(1.135pu,
1.166pu)
-
E9,E13
None
(0.962pu,
0.946pu)
-
None
1.103pu
-
None
1.102pu
-
E10,E11,
E12
Many
(N-1)
E5,E10
None
None
-
Rating A
419MVA
Other system
performance concerns
(Maximum reported)
Blackie area (138kV)
overvoltage (1.094pu)
None
Backbone area (500
kV,240kV)
over-voltages
(1.132pu,1.163pu),
high voltage deviation
Backbone area (500
kV,240kV)
low voltage
(0.964pu,0.9495pu)
Sheerness area (240kV)
over-voltages (1.103pu)
Blackie area (138kV)
over-voltages (1.103pu)
Empress area (240kV)
overvoltage (1.10pu)
Alberta Electric System Operator
479,693
46
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
5.1.3.3 S5C2GA - (2012 Summer peak case, 200 MW Wild Rose, 150 MW import from Sask.)
Table 5-10 S5C2GA overloaded branches and voltage violations
Figure
Conting
ency
Overloaded
element
S5GA_N0
N-0
None
S5GA_E5
E5
S5GA_E5
E5
S5GA_E5
E5
S5GA_E7
E7
S5GA_E14
S5GA_E15
S5GA_E16
S5GA_E17
S5GA_E18
E14,
E15
E16
E17
E18
E8,
E13
E9,
E13
E10
E11
E12
Many
(N-1)
E5,
E10
Chappice Lake 7
to
Medicine Hat 7
138kV
Chappice Lake 7
to
Glenridge 138kV
Cypress 1 to
Glenridge 138kV
Ellersli to Argylle
240kV
240.00
Empress A7
to Cypress 1
138kV
Existing
System
%
Overload
Rating A
Other system
performance concerns
(Maximum reported)
Blackie area (138kV)
overvoltage (1.097pu)
1.094pu
-
None
114%
90MVA
None
None
122%
90MVA
None
None
122%
90MVA
None
101%
101%
419MV
A
None
None
108%
None
None
None
129.4%
115.4%
100.1%
102.2%
102.3%
90MVA
None
None
(1.135pu,
1.167pu)
-
None
0.964pu
-
None
1.103pu
-
None
1.103pu
-
None
1.10pu
-
Backbone area
(500 kV,240kV) overvoltages
(1.132pu,1.163pu),
high voltage deviation
Backbone area (500 kV)
low voltage (0.97pu)
Sheerness area (240kV)
over-voltages (1.104pu)
Blackie area (138kV)
over-voltages (1.104pu)
Empress area (240kV)
overvoltage (1.10pu)
Alberta Electric System Operator
479,693
47
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
5.1.3.4 S6C2GA - (2012 Summer peak case, 200 MW Wild Rose, 150 MW export to Sask.)
Table 5-11 S6C2GA overloaded branches and voltage violations
Existing
Contingen Overloaded
%
Figure
System
cy
element
Overload
S6GGA_N0
N-0
None
S6GA_E7
E7
Ellersli to
Argylle
240kV
1.098pu
None
101%
(1.133pu,
1.165pu)
Rating A
419MVA
None
Backbone area (500
kV,240kV) over-voltages
(1.134pu,1.166pu),
high voltage deviation
Backbone area (500
kV,240kV) low voltage
(0.962pu,0.947pu)
E8,E13
None
E9,E13
None
(0.953pu,
0.945pu)
-
None
1.103pu
-
Sheerness area (240kV)
over-voltages (1.103pu)
-
Blackie area (138kV)
over-voltages (1.102pu)
E10,
E11,
E12
Many
(N-1)
None
1.105pu
-
Other system
performance concerns
(Maximum reported)
Blackie area (138kV)
overvoltage (1.094pu)
Alberta Electric System Operator
479,693
48
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
5.1.3.5 S4C2GGA - (2012 Summer peak case, 400 MW Wild Rose, 0 MW export to Sask.)
Table 5-12 S4C2GGA overloaded branches and voltage violations
Existing
Overloaded
%
Figure
Contingency
System
element
Overload
S4GGA_N0
N-0
S4GGA_E1
E1
S4GGA_E5
E5
S4GGA_E5
E5
S4GGA_E5
E5
S4GGA_E7
E7
S4GGA_E14
E14,
None
West Brook 7
to
Bassano Tap
138kV
Chappice
Lake 7 to
Medicine Hat
7 138kV
Chappice
Lake 7 to
Glenridge
138kV
Cypress 1 to
Glenridge
138kV
Ellersli to
Argylle 240kV
Empress A7 to
Cypress 1
138kV
Rating A
Other system
performance concerns
(Maximum reported)
Blackie area (138kV)
overvoltage (1.093pu)
1.094pu
-
None
103%
121MV
A
None
None
117%
90MVA
None
None
125%
90MVA
None
None
126%
90MVA
None
100%
102%
419MV
A
None
None
123%
90MVA
None
E8,
E13
None
(1.135pu,
1.166pu)
-
E9
None
0.962pu
-
E10,
E11,
E12
None
Many (N-1)
None
1.103pu
1.102pu
Backbone area
(500 kV,240kV)
over-voltages
(1.1365pu,1.168pu),
high voltage deviation
Backbone area (500 kV)
low voltage (0.962pu)
-
Sheerness area (240kV)
over-voltages (1.103pu)
-
Blackie area (138kV)
over-voltages (1.103pu)
Alberta Electric System Operator
479,693
49
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
5.1.3.6 S5C2GGA - (2012 Summer peak, 400 MW Wild Rose, 150 MW import from Sask.)
Table 5-13 S5C2GGA overloaded branches and voltage violations
Existing
Contin
Overloaded
%
Figure
System
gency
element
Overload
Rating A
Other system
performance concerns
(Maximum reported)
Blackie area (138kV)
overvoltage (1.095pu)
S5GGA_N0
N-0
None
1.094pu
-
S5GGA_E1
S5GGA_E2
S5GGA_E4
E1,
E2,
E4
E1,
E5,
E6
(More
N-1)
E1,
E5,
E6,
(More
N-1)
West Brook 7 to
Bassano Tap
138kV
None
116%
113%
108%
121MVA
None
Chappice Lake 7
to
Medicine Hat 7
138kV
None
107%
151%
110%
90MVA
None
Chappice Lake 7
to
Glenridge
138kV
None
115%
159%
118%
90MVA
None
None
106%
103%
121MVA
None
90MVA
None
S5GGA_E1
S5GGA_E5
S5GGA_E6
S5GGA_E1
S5GGA_E5
S5GGA_E6
S5GGA_E1
S5GGA_E2
E1,
E2
Queens Town to
Bassano Tap
138kV
S5GGA_E1
S5GGA_E5
S5GGA_E6
E1,
E5,
E6,
(More
N-1)
Cypress 1 to
Glenridge 138kV
S5GGA_E4
E4
S5GGA_E7
E7
S5GGA_E14
S5GGA_E15
S5GGA_E16
S5GGA_E17
S5GGA_E18
E14,
E15,
E16,
E17,
E18
None
116%
160%
118%
Nevis 240kV
/138kV
transformer
Ellersli to Argylle
240kV
Empress A7 to
Cypress 1 138kV
E8,
E13
None
E9
None
None
107%
100MVA
None
101%
102%
419MVA
None
None
108%
None
None
None
168.0%
125.6%
114.0%
116.2%
116.4%
90MVA
(1.135pu,
1.167pu)
0.964pu
-
-
None
Backbone area
(500 kV,240kV) overvoltages
(1.1360pu,1.167pu),
high voltage deviation
Backbone area (500
kV)
low voltage (0.968pu)
Alberta Electric System Operator
479,693
50
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
E10,
E11,
E12
None
Many
(N-1)
None
1.103pu
1.103pu
Sheerness area
(240kV)
over-voltages
(1.103pu)
Blackie area (138kV)
over-voltages
(1.104pu)
-
-
5.1.3.7 S6C2GGA - (2012 Summer peak, 400 MW Wild Rose, 150 MW export to Sask.)
Table 5-14 S6C2GGA overloaded branches and voltage violations
Figure
S6GGA_
N0
S6GGA_
E7
Overloaded
element
Existing
N-0
None
1.098pu
-
E7
Ellersli to
Argylle 240kV
None
102%
Contingency
E8,
E13
None
E9
None
E10,
E11,
E12
None
Many
(N-1)
None
System
(1.133pu,
1.165pu)
0.953pu
1.103pu
1.105pu
%
Overload
-
-
-
-
Rating A
Other system
performance concerns
(Maximum reported)
Blackie area (138kV)
overvoltage (1.094pu)
419MVA
None
Backbone area (500
kV,240kV)
over-voltages
(1.1360pu,1.167pu),
high voltage deviation
Backbone area (500
kV)
low voltage (0.963pu)
Sheerness area (240kV)
over-voltages
(1.104pu)
Blackie area (138kV)
over-voltages
(1.103pu)
5.1.4 Powerflow Analysis Summary (2013 SATR)
Of the 2013 cases, the worst overloading occurs with the 2013 summer light case with no importing from
Saskatchewan (S8C2GGA). For the 2013 summer light cases, the import case from Saskatchewan was not
studied. For powerflow simulations with the Wild Rose Wind Farm added, several overloading conditions
are evident in the 2013 cases with the SATR upgrades in service:
-
Empress to Cypress 138 kV Circuit: This line is rated at 90 MVA and is overloaded under several
load scenarios and contingencies. The overload is made worse by the addition of the Wild Rose
project. The thermal capacity of this line must be upgraded to mitigate these overloads.
Alberta Electric System Operator
479,693
51
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
-
-
-
-
-
Nevis 240/138 kV Transformer: This transformer overloads under certain load conditions when
the 240 kV line between Nevis and Cordel is out of service. The overload is made worse by the
addition of the Wild Rose project. It is expected that this overload will be mitigated by future cutplane management currently being evaluated by the AESO.
Red Deer – Nevis 138 kV Circuit (912L): The dispatch levels for existing area generators in the 2012
“system intact” cases were set at low levels to ease the overloading of the Red Deer to Nevis
(912L) transmission line and allow the impact of the full output of the Wild Rose Power Projects
to be studied. However, under contingency conditions, this circuit will overload unless
generation is further reduced. It is expected that this overload will be resolved by mitigative
solutions currently under assessment by the AESO.
Janet 240/138 kV Transformer: This is an existing overload condition made marginally worse by
the addition of the Wild Rose Wind Farm. (Existing overload 100%, wind added overload 104%).
This region is currently being evaluated in a separate study, and overloads will be mitigated as an
output of that work.
East Calgary 240/138 kV Transformer: This is an existing overload condition made marginally
worse by the addition of the Wild Rose Wind Farm. (Existing overload 101%, wind added
overload 105%). This region is currently being evaluated in a separate study, and overloads will be
mitigated as an output of that work.
Janet to East Calgary 240 kV Circuit: A marginal overload (101%) is observed on this line when a
circuit between Benalto and Sarcee is out of service under certain loading scenarios. Pre-Wild
Rose Generation loading during this contingency is 95%. This region is currently being evaluated
in a separate study, and overloads will be mitigated as an output of that work.
Note: The generation dispatch assumptions summarized in section 2.3 are critical in ensuring the N-0
(System Intact) scenarios are free of overloads. Altering these dispatch assumptions can cause system
intact loading violations, exacerbate contingency overloading violations, and cause new overloading
violations.
5.1.5 Special Notes and Assumptions for 2013 Cases
1. Accurate model for 911L Peigan to Janet line is not available for 2013 cases (see section
2.5.6).
2. Capacitor bank operating voltage levels at Calgary area were adjusted to 1.05pu-1.10pu from
0.95pu-1.10pu for 240kV buses and to 1.06pu-1.08pu from 1.00pu-1.05pu for 138kV buses to
mitigate the overvoltage and overloading conditions near the Langdon SVC. However, over
voltage and overloading conditions are still present for some N-1 contingencies.
3. The Bowmanton 240kV/138kV transformer tap setting was adjusted to match with parallel
transformer.
Alberta Electric System Operator
479,693
52
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
5.1.6 2013 Summer Cases
5.1.6.1 Contingency description for 2013 cases
Table 5-15 shows a reduced list of contingencies which may be used for reference in the subsequent
tables. Although all contingencies in the regions identified in Table 2-11 were monitored, these
contingencies were of particular interest as they exhibited some manner of criteria violation.
Table 5-15 2013 contingency description Note 5
Contingency
Note 5
Outage element
C1
Gaetz 4 to Red Deer 4 CKT 14 240kV
C2
Langdon 4 to Milo Junction 240kV (924L)
C3
Janet 4 to East Calgary CKT 17 240kV
C4
Sarcee 4 to East Calgary CKT 16 240kV
C5
Nevis 4 to Cordell 4 240kV (9L20)
C6
Ware Junction to West Brook 4 240kV (931L)
C7
Langdon 4 240kV/500kV T1 Transformer
C8
Stratham to Namakwa 7 CKT 33 138kV
C9
Suffield 7 to Tilley 7 CKT 00 138kV (100L)
C10
Tilley 7 to West Brook 7 CKT 66 138kV
C11
Cavalier 138kV/13.8kV T1 Transformer
C12
Cavalier to Namakwa 7CKT 01 138kV
C13
Dome EM7 to Oyen CKT 60 138kV (760L)
C15
Benalto 4 to Sarcee 4 CKT 28 240kV
C16
Dome EM 4 to Cypress 2 CKT 11 240kV (945L)
C17
Battle River 79 to Cordell 4 CKT 79 240kV
C18
Dome EM 7 to Cypress 1 CKT 69 138kV
C19
6Cypress 1 to Glenridge CKT58 138kV
Contingency Screening was done and only problematic contingencies are reported.
Alberta Electric System Operator
479,693
53
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
5.1.6.2 S8C2GGA - ( 2013 Summer Light, 400 MW Wild Rose, 0 MW Import from Sask.)
Table 5-16 S8C2GGA overloaded branches and voltage violations
Conting
ency
Overloaded element
%
Overload
N-0
None
-
S8GGA_N0
N-0
None
-
S8GGA_C1
C1
S8GGA_C2
S8GGA_C6
C2,
C6
S8GGA_C5
C5
Figure
Red Deer to Red Deer B
240kV/138kV T2
Transformer (See note 2)
Red Deer to Nevis 240kV
(912L)
Nevis 240kV /138kV
transformer
Rating A
Other system
performance concerns
(Maximum reported)
Backbone area (500kV)
Overvoltage (1.101pu)1
Blackie area (138kV)
over-voltages (1.086pu)
119%
200 MVA
None
105%,
104%
488MVA
None
155%
100MVA
None
C7
None
-
Backbone area (500
kV,240kV) over-voltages
(1.109pu,1.139pu), high
voltage deviation
C8
None
-
Blackie area (138kV) high
voltage deviation
Additional Notes:
1. Genesee generation step up transformer tap ratios may be adjusted to 1.00 from 1.06 to
mitigate overvoltage issues at Genesee buses (525).
2. Red Deer Transformer overload is due to a VAR looping condition in the power flow case.
This overload can be eliminated by adjusting transformer tap settings.
Alberta Electric System Operator
479,693
54
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
5.1.6.3 S9C2GGA - (2013 Summer peak, 400 MW Wild Rose, 0 MW import from Sask.)
Table 5-17 S9C2GGA overloaded branches
Figure
Contingency
Overloaded element
%
Overload
Rating A
Other system
performance
concerns (Maximum
reported)
Blackie area (138kV)
over-voltages
(1.092pu)
S9GGA_N0
N-0
None
-
S9GGA_C3
C3
Janet 4 to Janet 7
240kV/138kV T1 Transformer
104%
2X
400MVA
Calgary (240kV) high
voltage deviation
S9GGA_C4
C4
East Calgary Enmax2S7
240kV/138kV T1 Transformer
104%
336MVA
None
Backbone area (500
kV,240kV) overvoltages
(1.137pu,1.168pu),
high voltage deviation
Medicine Hat and
Brooks areas (138kV)
low voltages(
0.948pu,0.939pu),
high voltage deviation
C7
None
-
C9, C10
None
-
C11,12
None
-
Blackie area (138kV)
high voltage deviation
C13
None
-
Empress (138kV) high
voltage deviation
Alberta Electric System Operator
479,693
55
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
5.1.6.4 S10C2GGA - (2013 Summer peak, 400 MW Wild Rose, 150 MW import from Sask.)
Table 5-18 S10C2GGA overloaded branches
Figure
Contingency
Overloaded element
%
Overload
A10GGA_N0
N-0
None
-
S10GGA_C3
C3
S10GGA_C4
C4
S10GGA_C5
C5
S10GGA_C15
C15
S10GGA_C16
S10GGA_C17
S10GGA_C18
S10GGA_C19
C16,
C17,
C18,
C19
Janet 4 to Janet 7
240kV/138kV T1
Transformer
East Calgary Enmax2S7
240kV/138kV T1
Transformer
Rating A
Other system
performance
concerns (Area)
Blackie area (138kV)
over-voltages
(1.0923pu)
106%
2X
400MVA
Calgary (240kV) high
voltage deviation
105%
336MVA
None
Nevis 240kV /138kV
transformer
108%
100MVA
None
Janet 4 to East Calgary
17
101%
478MVA
None
121.5%,
101.7%,
129.8%,
106.8%
90MVA
None
Empress A7 to
Cypress 1 138kV
C7
None
-
Backbone area (500
kV,240kV) overvoltages
(1.137pu,1.169pu),
high voltage deviation
C9, C10
None
-
Medicine Hat, Brooks
areas (138kV) high
voltage deviation
C11,12
None
-
Blackie area (138kV)
high voltage deviation
C13
None
-
Empress area (138kV)
high voltage deviation
Alberta Electric System Operator
479,693
56
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
5.1.7 Reactor Design
5.1.7.1 Summary
Base cases for 2012 and 2013 were studied for compliance with operating voltage regulations in the Wild
Rose area and sizing of additional shunt reactance as needed.
A 50 MVAR shunt reactor is required to mitigate overvoltage violations on the 240 kV path from Cypress
to Wild Rose in the 2012 case. The 2013 case has significant topology differences, including an SVC at
Whitla, such that the overvoltage violations do not occur. No reactor is required after the 2013 upgrades
have been added.
5.1.7.2 2012 Configuration
The Wild Rose wind power plant is radially connected to the Cypress substation in the 2012 configuration.
See Figure 5-1 Study area in 2012 cases. Figure 5-1.
Figure 5-1 Study area in 2012 cases.
Overvoltage conditions occur during energization of the 240 kV path from Cypress to Wild Rose. Of the
2012 cases studied, the worst overvoltage violations occur with the 2012 summer light case with 150 MW
importing from Saskatchewan.
5.1.7.3 Line Energization Voltage Violations (2012)
In Table 5-19, overvoltage conditions are shown during sequential line energization from Cypress to Wild
Rose. The respective voltage levels with 45 MVAR and 50 MVAR shunt reactors added are shown in last
two columns. Overvoltage conditions occur at the Bowmanton 240 kV bus during initial energization of
the Cypress to Bowmanton line. Bowmanton was therefore selected as the site of the Switched Reactor.
Alberta Electric System Operator
479,693
57
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
A 50 MVAR shunt reactor connected at Bowmanton is sufficient to keep the voltage below 1.1 pu during
energization of the lines. Since the pre-fault voltage (1.1pu) must be the same as the post fault voltage,
the reactor must 100 % compensate the charging on the line, which is approximately 50 MVARs.
Table 5-19 Line Energization Voltage Levels
Bus Energization voltage (pu) during sequential
energization (No reactor added)
Voltage Measuring
Location
Voltage after Reactor
Addition (pu) (Entire path
energized*)
Pre
Energization
Line
energized to
Bowmanton
Line
energized
to
Elkwater**
Entire path
energized to
Wild Rose*
With 45
MVAR
Reactor at
Bowmanton
With 50
MVAR
Reactor at
Bowmanton
1.100
1.110
1.128
1.134
1.102
1.099
Bowmanton 240kV
N/A
1.115
1.153
1.163
1.099
1.092
Elkwater 240kV
N/A
N/A
1.155
1.167
1.102
1.096
Wild Rose 240kV
N/A
N/A
N/A
1.168
1.103
1.097
Anderson 240kV
1.087
1.089
1.092
1.093
1.088
1.087
Cypress 240kV
*No Wild Rose wind generation in service
**Both lines from Bowmanton to Elkwater connected
5.1.7.4 Voltage violations during no-wind conditions (2012)
No overvoltage conditions are observed when the entire path is energized and the wind farm is
connected but no wind is blowing. The voltage levels with no-wind blowing conditions are shown in
Table 5-20. For the no-wind condition, no reactor is required provided the wind turbines are in service.
Table 5-20 Voltage Levels with wind farm full power and wind farm connected to the grid
Voltage (pu)
Wind Farm at
Full Power No
Reactor
Wind Farm
Energized
(Zero wind)
No Reactor
Cypress 240kV
Bowmanton 240kV
Elkwater 240kV
1.062
1.046
1.048
1.095
1.084
1.078
Wild Rose 240kV
1.050
1.070
Anderson 240kV
1.073
1.086
Voltage Measuring Location
5.1.7.5 2013 Configuration
The 2013 cases present two significant topology changes from the 2012 cases: there is a new double
circuit 240 kV line connecting Bowmanton to West Brooks and there is a new 240 kV double circuit
connecting Elkwater to Whitla (SUBD1). Whitla is the site of a 125 MVAR SVC. See Figure 5-2.
Alberta Electric System Operator
479,693
58
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
Figure 5-2 Study area in 2013 cases.
With this network configuration, the wind farm is no longer radially connected from Cypress, and the
connections to West Brooks and Whitla contribute to maintaining the voltage profile during the
energization of the pertinent line segments. Therefore, reactor will be of minimal use after the 2013
upgrades have been added.
5.1.7.6 Additional Shunt Reactor Notes
1. During no wind blowing conditions, the line side convertor of the AW1500 wind generator has the
limited capability to consume 300 kVAr according to the "Electric Grid Data AW 1500+
(DG178022-M) " document. This capability is reflected in the results above.
2. The reactor capacities are specified at a rated voltage of 1.0 pu. However, reactors are operated
at a voltage closer to 1.1 pu. Therefore, actual inductive reactive power is higher than the rated
value.
3. The 2*24 MVAR capacitor bank at 267 Dome Empress (138 kV) and 2*24.8 MVAR capacitor bank
at McNeil are switched off during the reactor design to keep analysis consistent with wind farm in
service and out of service conditions.
4. The following loads were switched off to raise the Cypress voltage to 1.1 pu before line
energization.
Alberta Electric System Operator
479,693
59
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
Table 5-21 Table of loads switched out to keep Cypress voltage at 1.1 pu
Load Bus PSSE
2260
3260
4260
4986
2053
3053
4266
4111
JENNERA9
JENNERB9
JENNERC9
JENNERD9
SANDYPA9
SANDYPB9
EMPRESS9
SANDHIL9
Area
25.000
25.000
25.000
25.000
4.7000
4.7000
25.000
13.800
Total
48
48
48
48
48
48
48
48
EMPRESS
EMPRESS
EMPRESS
EMPRESS
EMPRESS
EMPRESS
EMPRESS
EMPRESS
Load
(MW)
11.8
11.8
11.8
11.8
3.4
3.4
6.3
33.2
93.5
(MVAR)
3.8
3.8
3.8
3.8
1.2
1.2
2.1
0
19.7
5.2 Stability Analysis
5.2.1 Stability Analysis Summary
Dynamic analysis was performed using PSS/E version 30.3.3. For each of the base cases analyzed, a set of
36 contingencies was applied, including selected Category B and C disturbances. The primary goal of
these studies is to determine whether the system remains dynamically stable under fault and outage
conditions, but each run was examined for additional concerns, such as post-fault voltage, AVR operation,
machine tripping, poorly damped oscillations, and any other problematic behaviour. The assumptions
and additional observations discussed in section 2.5.7 apply for “wind added” analysis.
Specific dynamic concerns identified with the “wind added” system are:
1. Existing Castle, MacBride, Kettles, and Summerview wind farms experience tripping in some
contingencies. This is due to under-voltage protection operation. This tripping may not be
realistic, as these wind farms are modeled in a fixed Q mode, and using obsolete models. The
tripping is evident in the existing system and is not impacted significantly by the addition of the
Wild Rose plant.
2. Loss of the double circuit line (N-2) between Cypress and Ware Junction leaves the Empress area
in a very weak condition, and depending on the status of the McNeil DC tie can result in
load/generation imbalance in the area. This imbalance may be sufficient to cause instability. This
condition is not eliminated by the addition of Wild Rose wind farm in 2012, but the
generation/load balance does change depending on wind levels. In 2013, it is expected that this
problem will be eliminated due to the strengthened ties into the Empress area, but until these
upgrades are implemented, a fast reduction in power from the wind farm or cross-trip may be
required when both circuits from Cypress to Ware Junction are lost.
Alberta Electric System Operator
479,693
60
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
3. While the system is capable of sustaining SLG faults with long clearing times (during fault-andcommon-breaker-fail events), many breaker fail events cause instability if the fault type is LLLG
instead of SLG. The addition of the Wild Rose plant does not affect this condition.
4. The 2012 cases studied here do not exhibit dynamic instability due to the loss of lines south from
Anderson. The cases use the same dispatch assumptions as the steady state analysis, that being
the existing area units operating under reduced power to prevent overloading on the Red-Deer
Nevis circuit. North-South powerflow through Anderson is reduced, and the loss of this circuit no
longer causes instability under these conditions. However, for the 2012 cases the Wild Rose wind
farm is more susceptible to tuning parameters and model limitations for these conditions and will
trip depending on control tuning. For the 2013 cases with existing area generation at full power,
the instability is still evident. The Wild Rose plant does not improve this condition.
5. A fault at West Brooks followed by the loss of both of the Milo – West Brooks line in the 2013
cases (Category C) exhibits poorly damped or unstable conditions. This is related to the same
instability indicated above with the loss of the line(s) through Anderson, interrupting the path
south from Sheerness and causing additional power to flow North from Sheerness and Battle
River. This has been identified by AESO studies as an existing problem.
6. An N-1-1 contingency where the line from Nevis to Red Deer is lost following the loss of the line
from Langdon to Milo Junction exhibits poor stability, sensitive to the specific control parameters
set in the Wild Rose wind farm. Control parameter selections used in this analysis indicate stable
operation.
Except for the above mentioned issues, all cases maintain stability and good voltage profiles within a few
seconds following the fault. It is noted that in 2012, the wind farm is radially connected into Cypress, and
the short circuit ratio (SCR, or ratio of plant MVA to network SCMVA) at the wind farm is relatively low.
The Wild Rose turbines are of a DFIG type, which may be vulnerable to performance issues in weak
systems such as this. Such issues fall outside the requirements of this analysis and will be examined
separately by NEC.
Alberta Electric System Operator
479,693
61
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
5.2.2 Contingency description
Table 5-22 shows a list of contingencies and events which were applied for all dynamic analysis cases.
Table 5-22 List of Outages and Events Applied for Dynamic Analysis
Contingency
Reference #
Elements Outage
Fault
Fault Location (line end)
CAT B (N-1)
C1
1009L - from Bowmanton to Cypress
3LG
East Medicine Hat Substation
C2
945L or 951L - from Cypress to Jenner
3LG
Cypress 240kV Substation - 562S
C3
944L - from Jenner to Ware Junction
3LG
Ware Jct 240kV Substation -132S
C4
931L - from Ware Junction to W.Brook
3LG
Ware Jct 240kV Substation -132S
C5
9L 933 - from Anderson to W.Brook
3LG
Anderson 240kV Substation -801S
C6
9L 933 - from Anderson to W.Brook
3LG
West Brooks 240kV Substation - 28S
C7
9L950 or 9L934 - from Ware Junction to Anderson
3LG
Ware Junction 240kV Substation - 132S
C8
9L950 or 9L934 - from Ware Junction to Anderson
3LG
Anderson 240kV Substation - 801S
C9
923L or 924L - from W. Brook to N.Lethbridge ( Milo for 2013 cases)
3LG
West Brooks 240kV Substation - 28S
C10
Amoco Empress 163S (240/138kV transformer)
3LG
Amoco Empress 240kV Substation -163S
C11
830L - from Cypress 562S to McNeill 840S
3LG
Cypress 138kV Substation -562S
C12
Elkwater to WR1 (Loss of 200MW)
3LG
Elkwater Substation
C13
Elkwater to WR2 (Loss of 200 MW)
3LG
Elkwater Substation
C14
One circuits lost between Bowmanton and Elkwater
3LG
Bowmanton
C15
Sudden loss of all 400 MW wind
N/A
N/A
C16
1034L or 1035L - from Bowmanton to W.Brook (2013 only)
3LG
Bowmanton
C16B
Rd Deer to Nevis
3LG
Red Deer240kV Substation
CAT C (N-2)
C17
945L/951L - from Cypress to Jenner
3LG
Cypress 240kV Substation - 562S
C18
944L - from Jenner to Ware Junction
3LG
Ware Jct 240kV Substation -132S
C19
9L950/9L934 - from Ware Junction to Anderson
3LG
Anderson 240kV Substation -801S
C20
9L950/9L934 - from Ware Junction to Anderson
3LG
Ware Junction 240kV Substation - 132S
C21
923L/924L - from W. Brook to N.Lethbridge (Milo for 2013 cases)
3LG
West Brooks 240kV Substation - 28S
C22
1034L/1035L -from Bowmanton to W.Brook
3LG
Bowmanton
C23
Both circuits lost between Bowmanton and Elkwater
3LG
Bowmanton
C24
Line West towards Withla/Lethbridge (both lines)
3LG
Elkwater Substation
Breaker Failure Contingencies ( Delayed clearing time 18cycles)
C25
Janet to Red Deer std time and Janet to Langdon delayed
1LG
Janet 240kV Substation
C26
Janet to Red Deer std time and trip Janet to Peigan delayed
1LG
Janet 240kV Substation
C27
Langdon to Milo std time and Langdon to Janet delayed
1LG
Langdon 240kV Substation
C28
1LG
Langdon 240kV Substation
C29
Langdon to Janet std time and Langdon SVC delayed time
West Brooks to Milo Junction std time and West Brooks to Ware
Junction delayed time
1LG
West Brooks 240kV Substation - 28S
C30
Red Deer to Gaetz std time and Red Deer to Nevis delayed time
1LG
Red Deer 240kV Substation
C31
Nevis to Cordel std time and Nevis to Red Deer delayed time
1LG
Nevis 240kV Substation
C32
Cordel to Nevis std time and BR Unit 5 delayed time
1LG
Cordel 240kV Substation
C33
1LG
Anderson 240kV Substation
C35
Anderson to West Brooks std time and SH Unit 1 delayed time
Ware Junction to Jenner std time and Ware Junction to West
Brooks delayed time
Jenner to Amoco Empress std time and Jenner to Ware Junction
delayed time
C36
Langdon to Milo std time and Nevis to Red Deer delayed time
C34
1LG
1LG
Ware Junction 240kV Substation - 132S
Jenner 240kV Substation
N-1-1 contingencies ( 2nd fault and outage after 1st outage reaches steady state)
3LG
Red Deer 240kV Substation
Alberta Electric System Operator
479,693
62
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
5.2.3 2012 (Pre-SATR) Cases
5.2.3.1 S1C2GGA - ( 2012 Summer Light case, 400 MW Wild Rose, 0 MW export to Sask.)
Table 5-23 2012 Summer Light Case with no Saskatchewan Import and 400 MW Wild Rose wind
C1
C2
C3
C4
C5
C6
C7
C8
C9
C10
C11
Existing
System
Stable?
N/A
√
√
√
√
√
√
√
√
√
√
S1C2GGA:
WR Case
Expected
Stable?
√
√
√
√
√
√
√
√
√
√
√
C12
N/A
√
C13
N/A
√
C14
C15
C16
C16B
C17
N/A
N/A
N/A
√
X
√
√
N/A
√
X
X
X
√
√
√
N/A
N/A
N/A
√
√
√
√
√
√
√
√
√
√
√
√
√
√
√
N/A
√
N/A
√
√
√
√
√
√
√
√
√
√
√
√
Contingency
N-1
N-2
Breaker
fail (SLG 18cycle)
N-1-1
C18
C19
C20
C21
C22
C23
C24
C25
C26
C27
C28
C29
C30
C31
C32
C33
C34
C35
C36
400 MW Wind Added - 2012 Light Load (Pre-SATR) with no McNeil activity
Comments
No tripping
No tripping
100003,4,5 - MCBRIDE tripped (VTGTPTA - UV)
100003,4,5 - MCBRIDE tripped (VTGTPTA - UV) (With 2 Mode Changes)
100003,4,5 - MCBRIDE tripped (VTGTPTA - UV)
100001,2 - CASTLE, 3,4,5 - MACBRIDE, 6,7 - SUMMERG, 8,11 - KETTLES Tripped (VTGTPTA - UV)
100003,4,5 - MCBRIDE tripped (VTGTPTA - UV)
100003,4,5 - MCBRIDE tripped (VTGTPTA - UV)
100001,2 - CASTLE, 3,4,5 - MACBRIDE, 6,7 - SUMMERG, 8,11 - KETTLES Tripped (VTGTPTA - UV)
No tripping
No tripping
OV, with slow recovery to 1.1pu, May be fixed by wind farm tuning, but Bowmanton reactor may
need to be switched in until wind farm AVR can respond.
OV, with slow recovery to 1.1pu, May be fixed by wind farm tuning, but Bowmanton reactor may
need to be switched in until wind farm AVR can respond.
No tripping
Overvoltage occurs unless Bowmanton reactor is switched in (See reactor sizing study)
N/A
100003,4,5 - MCBRIDE tripped (VTGTPTA - UV)
Unstable - Loss of 2 ccts from Empress to WJ result in too much generation at Empress (use x-trip)
Weak System: See comment C17, but system stays together with wind farm control oscillations. Xtrip probably required for backup.
100003,4,5 - MCBRIDE tripped (VTGTPTA - UV)
100003,4,5 - MCBRIDE tripped (VTGTPTA - UV)
100001,2 - CASTLE, 3,4,5 - MACBRIDE, 6,7 - SUMMERG, 8,11 - KETTLES Tripped (VTGTPTA - UV)
N/A
No tripping
N/A
No tripping
No tripping
No tripping
No tripping
No tripping
No tripping
No tripping
No tripping
No tripping
No tripping
No tripping
100003,4,5 - MCBRIDE tripped (VTGTPTA - UV)
Alberta Electric System Operator
479,693
63
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
5.2.3.2 S5C2GGA - (2012 Summer peak, 400 MW Wild Rose, 150 MW import from Sask.)
Table 5-24 2012 Summer Peak Case with 150 MW Saskatchewan Import and 400 MW Wild Rose wind
Contingency
C1
C2
C3
C4
C5
C6
C7
C8
N-1
C9
C10
C11
C12
C13
C14
C15
C16
C16B
C17
C18
C19
C20
N-2
Breaker
fail (SLG 18cycle)
N-1-1
C21
C22
C23
C24
C25
C26
C27
C28
C29
C30
C31
C32
C33
C34
C35
C36
S5C2GGA: 400 MW Wind Added - 2012 Heavy Load (Pre-SATR) with 150 MW McNeil import
Existing WR Case
System Expected
Comments
Stable?
Stable?
N/A
√
No tripping
√
√
No tripping
√
√
100003,4,5 - MCBRIDE tripped (VTGTPTA - UV)
√
√
100003,4,5 - MCBRIDE tripped (VTGTPTA - UV)
√
√
100003,4,5 - MCBRIDE tripped (VTGTPTA - UV)
100001,2 - CASTLE, 3,4,5 - MACBRIDE, 6,7 - SUMMERG, 8,11 - KETTLES Tripped (VTGTPTA - UV), WR
√
√
tripped due to model problem in weak system (Can be solved by adjusting DYR parameters, but this
is a known weak system condition due to loss of Anderson line) Use Bowmanton Reactor
√
√
100003,4,5 - MCBRIDE tripped (VTGTPTA - UV)
√
√
100003,4,5 - MCBRIDE tripped (VTGTPTA - UV)
100001,2 - CASTLE, 3,4,5 - MACBRIDE, 6,7 - SUMMERG, 8,11 - KETTLES Tripped (VTGTPTA - UV), WR
tripped due to model problem (Can be solved by adjusting DYR parameters, but this is a weak system
√
√
condition due to loss of line from West Brooks to Lethbridge) Use Bowmanton Reactor
√
√
No tripping
√
√
No tripping
OV, with slow recovery to 1.1pu, May be fixed by wind farm tuning, but Bowmanton reactor may
N/A
√
need to be switched in until wind farm AVR can respond.
OV, with slow recovery to 1.1pu, May be fixed by wind farm tuning, but Bowmanton reactor may
N/A
√
need to be switched in until wind farm AVR can respond.
N/A
√
No tripping
N/A
√
Overvoltage occurs unless Bowmanton reactor is switched in (See reactor sizing study)
N/A
N/A
N/A
√
√
100003,4,5 - MCBRIDE tripped (VTGTPTA - UV)
√
X
Unstable - Loss of 2 ccts from Empress to WJ result in too much generation at Empress (use x-trip)
√
X
Unstable - Loss of 2 ccts from Empress to WJ result in too much generation at Empress (use x-trip)
√
√
100003,4,5 - MCBRIDE tripped (VTGTPTA - UV)
√
√
100003,4,5 - MCBRIDE tripped (VTGTPTA - UV), WR trip Same comment as C6
100001,2 - CASTLE, 3,4,5 - MACBRIDE, 6,7 - SUMMERG, 8- KETTLES Tripped (VTGTPTA - UV), WR tripped
√
√
(same comment as C6)
N/A
N/A
N/A
N/A
√
No tripping
N/A
N/A
N/A
√
√
No tripping
√
√
No tripping
√
√
No tripping
√
√
No tripping
√
√
No tripping
√
√
No tripping
√
√
No tripping
√
√
No tripping
√
√
No tripping
√
√
No tripping
√
√
No tripping
√
√
100003,4,5 - MCBRIDE tripped (VTGTPTA - UV)
Alberta Electric System Operator
479,693
64
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
5.2.4 2013 (SATR) Cases
5.2.4.1 S8C2GGA - ( 2013 Summer Light, 400 MW Wild Rose, 0 MW Import from Sask.)
Table 5-25 2013 Summer Light Case with no Saskatchewan Import and 400 MW Wild Rose wind
S8C2GGA: 400 MW Wind Added - 2013 (SATR) Light Load with no Mcneil activity
Contingency
N-1
N-2
Breaker
fail (SLG 18cycle)
N-1-1
WR Case
Expected
Stable?
C1
C2
C3
C4
C5
C6
C7
C8
C9
C10
C11
C12
C13
C14
C15
C16
C16B
C17
C18
C19
C20
√
√
√
√
X
√
√
X
√
√
√
√
√
√
√
√
√
√
√
X
X
C21
√
C22
C23
C24
C25
C26
C27
C28
C29
C30
C31
C32
C33
C34
C35
C36
√
√
√
√
√
√
√
√
√
√
√
√
√
√
√
Comments
100003,4,5 - MCBRIDE tripped (VTGTPTA - UV)
100003,4,5 - MCBRIDE tripped (VTGTPTA - UV)
100003,4,5 - MCBRIDE tripped (VTGTPTA - UV)
100003,4,5 - MCBRIDE tripped (VTGTPTA - UV)
Unstable (Loss of Anderson to WB line)
100001,2 - CASTLE, 3,4,5 - MACBRIDE, 6,7 - SUMMERG, 8,9,11,12 - KETTLES Tripped (VTGTPTA - UV)
100003,4,5 - MCBRIDE tripped (VTGTPTA - UV)
Unstable (Loss of Anderson to WJ line)
100001,2 - CASTLE, 3,4,5 - MACBRIDE, 6,7 - SUMMERG, 8,9,11,12 - KETTLES Tripped (VTGTPTA - UV)
No Tripping
No Tripping
No Tripping
No Tripping
100003,4,5 - MCBRIDE tripped (VTGTPTA - UV)
No Tripping
100003,4,5 - MCBRIDE tripped (VTGTPTA - UV)
100001,2 - CASTLE, 3,4,5 - MACBRIDE, 6,7 - SUMMERG, 8,9, - KETTLES Tripped (VTGTPTA - UV)
100003,4,5 - MCBRIDE tripped (VTGTPTA - UV)
100003,4,5 - MCBRIDE tripped (VTGTPTA - UV)
Unstable (2 cct outage from WJ to Anderson)
Unstable (2 cct outage from WJ to Anderson)
Poor damping - Oscillations last 15 seconds, 100001,2-CASTLE, 3,4,5-MACBRIDE, 6,7-SUMMERG,
8,9,11,12-KETTLES Tripped
100003,4,5 - MCBRIDE tripped (VTGTPTA - UV)
100003,4,5 - MCBRIDE tripped (VTGTPTA - UV)
No Tripping
No Tripping
No Tripping
No Tripping
No Tripping
No Tripping
No Tripping
No Tripping
No Tripping
No Tripping
No Tripping
No Tripping
100001,2 - CASTLE, 6 - SUMMERG Tripped (VTGTPTA - UV)
Alberta Electric System Operator
479,693
65
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
5.2.4.2 S10C2GGA - (2013 Summer peak, 400 MW Wild Rose, 150 MW import from Sask.)
Table 5-26 2013 Summer Peak Case with 150 MW Saskatchewan Import and 400 MW Wild Rose wind
S10C2GGA: 400 MW Wind Added - 2013 (SATR) Heavy Load with 150 MW Mcneil import
WR Case
Contingency
Expected
Comments
Stable?
C1
√
100003,4,5 - Wind generators at MCBRIDE tripped
C2
√
100003,4,5 - Wind generators at MCBRIDE tripped
C3
√
100003,4,5 - Wind generators at MCBRIDE tripped
C4
√
100003,4,5 - Wind generators at MCBRIDE tripped
C5
X
Unstable (Loss of Anderson to WB line)
C6
√
100001,2,3-CASTLE, 3,4,5-MACBRIDE, 6,7-SUMMERG, 8,9-KETTLES Tripped
C7
√
100003,4,5 - Wind generators at MCBRIDE tripped
C8
X
Unstable (Loss of Anderson to WJ line)
N-1
C9
√
100001,2-CASTLE, 3,4,5-MACBRIDE, 6,7-SUMMERG, 8,9-KETTLES Tripped
C10
√
100003,4,5 - Wind generators at MCBRIDE tripped
C11
√
No tripping
C12
√
No tripping
C13
√
No tripping
C14
√
100003,4,5 - Wind generators at MCBRIDE tripped
C15
√
No tripping
C16
√
100003,4,5 - Wind generators at MCBRIDE tripped
C16B
√
100003,4,5 - Wind generators at MCBRIDE tripped
C17
√
100003,4,5 - Wind generators at MCBRIDE tripped
C18
√
100003,4,5 - Wind generators at MCBRIDE tripped
C19
X
Unstable (2 cct outage from WJ to Anderson)
C20
√
100003,4,5-MACBRIDE, 97559,60 - IP - 634 Tripped
N-2
Under damped - Oscillations last 15 seconds, 100001,2-CASTLE, 3,4,5-MACBRIDE, 6,7-SUMMERG,
√
C21
8,9-KETTLES Tripped
C22
√
100003,4,5 - Wind generators at MCBRIDE tripped
C23
√
100003,4,5 - Wind generators at MCBRIDE tripped
C24
√
No tripping
C25
√
No tripping
C26
√
No tripping
C27
√
No tripping
C28
√
No tripping
Breaker
C29
√
No tripping
fail (1LG - C30
√
No tripping
18cycle) C31
√
No tripping
C32
√
No tripping
C33
√
No tripping
C34
√
No tripping
C35
√
No tripping
N-1-1
C36
√
No tripping
Alberta Electric System Operator
479,693
66
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
5.3 Short Circuit Analysis - Wind added System
A short circuit study was performed using the Summer Peak cases with 150MW import from
Saskatchewan (Case designation S5C2GA,S5C2GGA and S10C2GGA) to simulate the worst case short
circuit faults in wind added systems.
5.3.1 Short Circuit Analysis Results – 2012 (Pre-SATR)
The results for the wind added system analysis are shown in Table 5-27 and Table 5-28.
Table 5-27 2012 Summer Peak Case with 150MW Saskatchewan Import and 200 MW Wild Rose Wind
2012 Summer Peak Case with 150MW Saskatchewan Import and 100MW BC Export
(With Wild Rose 1, 200 MW, S5C2GA)
Positive Seq Zthev
Zero Seq Zthev
Pre
Base
3LG
SLG
(pu)
(pu)
Fault
Fault Location
Voltage
Fault
Fault
Voltage
(kV)
(kA)
(kA)
R
jX
R
jX
(pu)
1.0735
10.534
0.00388 0.02421
8.164
0.00928 0.04396
Ware Junction
240
240
1.0740
6.990
0.00561
0.03654
4.599
0.02203
0.09243
Amoco Empress
240
1.0698
5.981
0.00496
0.04274
3.976
0.02674
0.10728
West Brooks
138
1.0325
13.131
0.00718
0.03210
13.671
0.00218
0.02872
Elkwater
240
1.0542
2.431
0.00935
0.10392
2.534
0.02271
0.09945
West Brooks
240
1.0540
10.814
0.00479
0.02295
11.339
0.00203
0.01959
Bowmanton
240
1.0574
2.687
0.00852
0.09428
2.654
0.02345
0.10411
Cypress 1
138
1.0231
8.748
0.00488
0.04868
6.408
0.02508
0.10296
Cypress 2
240
1.0701
5.959
0.00504
0.04290
4.048
0.02592
0.10371
Medicine Hat
138
0.9959
5.394
0.02310
0.07371
5.457
0.00817
0.07568
Sheerness
240
1.0859
12.562
0.00237
0.02066
12.546
0.00187
0.01846
Anderson
240
1.0853
12.892
0.00234
0.02012
13.009
0.00171
0.01737
Jenner
Alberta Electric System Operator
479,693
67
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
Table 5-28 2012 Summer Peak Case with 150MW Saskatchewan Import and 400 MW Wild Rose Wind
2012 Summer Peak Case with 150MW Saskatchewan Import and 100MW BC Export
(With Wild Rose 1 and Wild Rose 2, 400 MW, S5C2GGA)
Positive Seq Zthev
Zero Seq Zthev
Pre
Base
3LG
SLG
(pu)
(pu)
Fault
Fault Location
Voltage
Fault
Fault
Voltage
(kV)
(kA)
(kA)
R
jX
R
jX
(pu)
1.0715
10.603
0.00386 0.02400
8.222
0.00922 0.04363
Ware Junction
240
Jenner
240
1.0745
7.122
0.00551
0.03587
4.714
0.02148
0.09004
Amoco Empress
240
1.0749
6.214
0.00478
0.04134
4.206
0.02530
0.10091
West Brooks
138
1.0297
13.117
0.00717
0.03205
13.658
0.00218
0.02869
Elkwater
240
1.0577
2.851
0.00737
0.08894
3.634
0.00461
0.04453
West Brooks
240
1.0502
10.813
0.00478
0.02287
11.338
0.00203
0.01957
Bowmanton
240
1.0560
3.063
0.00703
0.08263
3.661
0.00594
0.05252
Cypress 1
138
1.0385
8.956
0.00486
0.04827
6.679
0.02391
0.09903
Cypress 2
240
1.0749
6.208
0.00483
0.04138
4.307
0.02423
0.09678
Medicine Hat
138
1.0081
5.397
0.02363
0.07448
5.466
0.00839
0.07640
Sheerness
240
1.0845
12.593
0.00237
0.02058
12.574
0.00187
0.01845
Anderson
240
1.0839
12.925
0.00233
0.02004
13.042
0.00171
0.01735
5.3.2 Short Circuit Analysis Results – 2013 (SATR)
The results for the wind added system analysis are shown in Table 5-29.
Table 5-29 2013 Summer Peak Case with 150MW Saskatchewan Import and 400 MW Wild Rose Wind
2013 Summer Peak Case with 150MW Saskatchewan Import and 100MW BC Export
(With Wild Rose 1 and Wild Rose 2, 400 MW, S10C2GGA)
Positive Seq Zthev
Zero Seq Zthev
Pre
Base
3LG
SLG
(pu)
(pu)
Fault
Fault Location
Voltage
Fault
Fault
Voltage
(kV)
(kA)
(kA)
R
jX
R
jX
(pu)
1.0761
10.576
0.00403 0.02414
8.179
0.00933 0.04426
Ware Junction
240
Jenner
240
1.0750
7.318
0.00581
0.03486
4.744
0.02156
0.09050
Amoco Empress
240
1.0711
6.997
0.00467
0.03653
4.438
0.02498
0.09883
West Brooks
138
1.0364
12.688
0.00712
0.03343
13.642
0.00186
0.02709
Elkwater
240
1.0678
5.470
0.00621
0.04655
6.749
0.00317
0.02375
West Brooks
240
1.0574
11.439
0.00451
0.02178
12.478
0.00176
0.01654
Bowmanton
240
1.0696
7.038
0.00546
0.03615
7.944
0.00336
0.02581
Cypress 1
138
1.0428
9.403
0.00503
0.04612
6.714
0.02491
0.10185
Cypress 2
240
1.0715
7.078
0.00466
0.03611
4.579
0.02399
0.09448
Medicine Hat
138
1.0112
7.029
0.00814
0.05963
6.708
0.00834
0.06967
Sheerness
240
1.0906
12.535
0.00247
0.02078
12.233
0.00206
0.02019
Anderson
240
1.0898
12.864
0.00244
0.02023
12.631
0.00196
0.01930
Alberta Electric System Operator
479,693
68
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
6.0 Summary and Conclusions
6.1 Summary - Powerflow Analysis
Powerflow analysis performed herein evaluated 21 base case scenarios encompassing existing system
cases, 2012 (pre-SATR) wind added cases, and 2013 (post-SATR) wind added cases with a complete set of
Category A and B contingencies. The violations observed in all these cases may be categorized as one of
three types:
-
-
Local violations requiring RAS or network upgrades. Many of these concerns are addressed by
the addition of the 2013 SATR network upgrades.
External violations which are remote from the wind farm connection, and are currently under
examination in other studies. Those studies are expected to propose resolutions for the specific
violations identified.
System wide concerns involving load/generation/interchange sensitivities, which may be
mitigated using operational practices or cut-plane management. In addition, a planned NorthSouth HVDC line is expected to assist in mitigating these system constraints.
A selected set of Category C contingencies has been studied, and these results are reported in Appendix B
(not reflected in this summary). A summary of the worst power flow violations are presented in Table
6.1.
6.1.1 Local Violations
Local violations requiring RAS or network upgrades include the following overloads:
-
-
-
Empress to Cypress 138 kV Circuit: This line is rated at 90 MVA and is overloaded under several
load scenarios and contingencies. The overload is made worse by the addition of the Wild Rose
project. The thermal capacity of this line will be up-rated as the part of the scope of this project.
West Brooks – Bassano Tap – Queenstown 138 kV Circuit: The addition of the Wild Rose Wind
Farm overloads this circuit under contingency conditions. A RAS scheme exists to manage this
overload, and should be extended to account for the Wild Rose project. It is expected that the
SATR upgrades and projects proposed for the Blackie area will mitigate this overload.
Medicine Hat – Suffield 138 kV Circuit, and Medicine Hat – Chappice Lake – Glenridge – Cypress
138 kV Circuit: The 138 kV network around Medicine hat is stressed by the addition of any
injection of power in the Cypress/Empress area, including Wild Rose and the McNeil DC tie. Wind
connecting into the 138 kV system around Medicine Hat also stresses this network, causing
overloads under contingency conditions. It is expected that the SATR network upgrades (2013)
will mitigate these overloads with the reconnection of the 138 kV system at Medicine Hat. In the
interim period RAS must be implemented to reduce imports through McNeil or other generator
power in the case of the specific contingencies causing the overloads.
Alberta Electric System Operator
479,693
69
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
6.1.2 Remote Violations
The following violations are relatively remote from the Wild Rose wind farm:
Calgary area violations: The Calgary region encompassing these overloads are currently being evaluated
in a separate study, and overloads will be mitigated as an output of that work:
- Janet 240/138 kV Transformer: This is an existing overload condition made marginally worse by
the addition of the Wild Rose Wind Farm.
- Janet to Peigan (911L) line: This circuit is overloaded under N-0 conditions in the existing system,
and overloading becomes worse during N-1 contingencies. This overload is made worse by the
addition of the Wild Rose Wind Farm, and is expected to be mitigated by the planned upgrades to
911L.
- East Calgary 240/138 kV Transformer: This is an existing overload condition made marginally
worse by the addition of the Wild Rose Wind Farm.
- Janet to East Calgary 240 kV Circuit: A marginal overload (101%) is observed on this line when a
circuit between Benalto and Sarcee is out of service under certain loading scenarios.
The improvements planned for the Calgary Area associated with the Foothills development and other
projects are expected to remove the above violations.
Elerslie to Argyle 240 kV Circuit: This overload is primarily due to high VAR flows stemming from poor
power factor on lines in the Wabamun generation area. VAR management in this region may be
adequate to mitigate this problem. This region is far away from the Wild Rose project area, and this
overload is not substantially impacted by the addition of the new wind generation.
6.1.3 System-Wide Concerns
The following concerns are dependent on system wide generation and load dispatch conditions. An AESO
overall system management study is ongoing which will discuss mitigation and prevention of these
overload conditions.
-
Nevis 240/138 kV Transformer: This transformer overloads under certain load conditions when
the 240 kV line between Nevis and Cordel is out of service. The overload is made worse by the
addition of the Wild Rose project. The study shows as much as a 155% overload under certain
conditions.
-
Red Deer – Nevis 138 kV Circuit (912L): The dispatch levels for existing generators in the 2012
“system intact” cases were adjusted to ease the overloading of the Red Deer to Nevis (912L)
transmission line and allow the impact of full output of the Wild Rose Power Project to be
studied. However, under contingency conditions, this circuit will overload unless generation is
further reduced.
Langdon to Janet 240 kV Path: Under certain generation dispatch levels and contingencies this
path may experience overloading.
-
Alberta Electric System Operator
479,693
70
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
Table 6-1 Summary of Worst Powerflow Violations (see table footnote)
Base Case &
Figure
Contingency
Overloaded
element
Existing
System
%
Overload
Rating A
Other system
performance
concerns
(Maximum
reported)
S2GGA_D18
D18
Empress A7 to
Cypress 1 138kV
129%
184%
90MVA
None
S2GGA_D4
D4
None
127%
121MVA
None
S2GGA_D4
D4
None
118%
121MVA
None
S2GGA_D1
D1
None
121%
67MVA
None
S5GGA_E5
E5
None
151%
90MVA
None
S5GGA_E5
E5
Chappice Lake 7 to
Glenridge 138kV
None
159%
90MVA
None
S5GGA_E5
E5
Cypress 1 to
Glenridge 138kV
None
160%
90MVA
None
S10GGA_C3
C3
Janet 4 to Janet 7
240kV/138kV T1
Transformer
None
106%
2X
400MVA
Calgary (240kV)
high voltage
deviation
S10GGA_C4
C4
East Calgary
Enmax2S7
240kV/138kV T1
Transformer
None
105%
336MVA
None
S10GGA_C15
C15
Janet 4 to East
Calgary 17
None
101%
478MVA
None
S8GGA_C5
C5
Nevis 240kV
/138kV
transformer
None
155%
100MVA
None
S2GGA_C1
D1
Red Deer to Nevis
240kV (912L)
None
109%
488MVA
None
West Brook 7 to
Bassano Tap
138kV
Queens Town to
Bassano Tap
138kV
Suffield 7 to
Medicine Hat 7
138kV (892L)
Chappice Lake 7 to
Medicine Hat 7
138kV
Note: The violations indicated in this table represent the conditions producing the worst overload on a
given element. Other conditions or contingencies can produce lesser overloads on these elements. See
tables in the Chapters 3 and 5 for complete list of contingencies capable of causing element overloading.
Alberta Electric System Operator
479,693
71
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
Table 6-2 Contingency description for worst powerflow violations
Contingency
Outage element
D1 & E5
D4
D18
C3
C4
C5
C15
Ware Junction to West Brook 4 240kV (931L)
Red Deer to Nevis 240kV (912L)
Dome EM 4 to Cypress 2 CKT 11 240kV (945L)
Janet 4 to East Calgary CKT 17 240kV
Sarcee 4 to East Calgary CKT 16 240kV
Nevis 4 to Cordell 4 240kV (9L20)
Benalto 4 to Sarcee 4 CKT 28 240kV
6.2 Summary - Stability Analysis
Dynamic analysis has been performed to evaluate the stability of the system before and after the addition
of the Wild Rose plant. 36 contingencies were performed, including Category B and C events, for 2
existing system base cases and 4 wind added base cases. The wind-added base cases include heavy and
light conditions, both before the addition of the SATR network upgrades (2012) and after (2013). A
summary of the worst unstable contingencies is presented in Table 6-3.
6.2.1 Results and Observations
Loss of the double circuit line (N-2) between Cypress and Ware Junction leaves the Empress area in a very
weak condition, and depending on the status of the McNeil DC tie can result in load/generation
imbalance in the area. This imbalance may be sufficient to cause instability. This condition is not
eliminated by the addition of Wild Rose wind farm in 2012, but the generation/load balance does change
depending on wind levels. It is expected that this problem will be reduced due to the strengthened ties
into the Empress area planned with the Hanna Area upgrades. Until these upgrades are implemented,
system operations will limit generation levels in the area to alleviate the potential for this condition.
For the 2013 cases with existing generating units at full power, dynamic instability is still evident when
ahigh level of existing generation is in service and either or both of the lines south through Anderson are
interrupted. Additionally, poor damping is evident when the double-circuit line is lost between West
Brook and Milo Junction . The Wild Rose plant does not improve this existing condition, and may be
required to participate in existing OPPs dealing with this concern.
6.2.1.1 2012 (Pre-SATR) Discussion and Recommendations
In 2012 the wind farm is connected radially into Cypress via a relatively long line, and low short circuit
levels are evident at the Elkwater bus. Aside from the issues mentioned above and in Chapter 5.2,
stability is maintained after several seconds, and post fault voltages are acceptable.
Alberta Electric System Operator
479,693
72
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
Table 6-3 Summary of unstable contingencies
Base Case
S1C2ES
S1C2GGA
S5C2GGA
Contingenc
y
N-2
Expected
Stable?
(Summary)
C17
X
Unstable (loss of 240 ccts from Cypress to Jenner… no supply
to Empress Area load)
C18
X
Unstable (same comment as C17)
C17
X
C18
X
C17
X
C18
X
C5
X
Unstable (Loss of Anderson to WB line)
C8
X
Unstable (Loss of Anderson to WJ line)
C19
X
Unstable (2 cct outage from WJ to Anderson)
C20
X
Unstable (2 cct outage from WJ to Anderson)
C21
√
Poor damping - Oscillations last 15 seconds, 100001,2-CASTLE,
3,4,5-MACBRIDE, 6,7-SUMMERG, 8,9,11,12-KETTLES Tripped
C5
X
Unstable (Loss of Anderson to WB line)
C8
X
Unstable (Loss of Anderson to WJ line)
C19
X
Unstable (2 cct outage from WJ to Anderson)
C21
√
Under damped - Oscillations last 15 seconds, 100001,2-CASTLE,
3,4,5-MACBRIDE, 6,7-SUMMERG, 8,9-KETTLES Tripped
N-2
N-2
N-1
S8C2GGA
N-2
N-1
S10C2GGA
N-2
Comments
Unstable - Loss of 2 ccts from Empress to WJ result in too much
generation at Empress (use x-trip)
Weak System: See comment C17, but system stays together
with wind farm control oscillations. X-trip probably required
for backup.
Unstable - Loss of 2 ccts from Empress to WJ result in too much
generation at Empress (use x-trip)
Unstable - Loss of 2 ccts from Empress to WJ result in too much
generation at Empress (use x-trip)
Alberta Electric System Operator
479,693
73
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
Table 6-4 Contingency description for unstable contingencies
Contingency
Reference #
Elements Outage
Fault
Fault Location (line end)
CAT B (N-1)
C5
9L 933 - from Anderson to W.Brook
3LG
Anderson 240kV Substation -801S
C8
9L950 or 9L934 - from Ware Junction to Anderson
3LG
Anderson 240kV Substation - 801S
CAT C (N-2)
C17
945L/951L - from Cypress to Jenner
3LG
Cypress 240kV Substation - 562S
C18
944L - from Jenner to Ware Junction
3LG
Ware Jct 240kV Substation -132S
C19
9L950/9L934 - from Ware Junction to Anderson
3LG
Anderson 240kV Substation -801S
C20
9L950/9L934 - from Ware Junction to Anderson
3LG
Ware Junction 240kV Substation - 132S
C21
923L/924L - from W. Brook to N.Lethbridge (Milo
for 2013 cases)
3LG
West Brooks 240kV Substation - 28S
6.3 Summary - Short Circuit Analysis
Short Circuit Analysis has been performed for selected fault locations near the Wild Rose Wind Farm. All
substation equipment should be checked during the project design to ensure that fault levels do not
exceed equipment specifications.
6.4 Conclusions
The study results showed that the connection of the 400 MW Wild Rose wind projects increase system
overloads under both normal and Category B and Category C contingency conditions. In addition, current
system stability issues associated with existing generation continue with the addition of the Project. The
Category B overloads identified as being made worse or fully attributed to the Project will require
incorporation of the Project in to existing Remedial Action Schemes (RAS) or the development of new
RAS. The RAS should resolve the overloads in the interim, while future system developments planned for
the area, including those approved as part of the SATR and Hanna Area, are expected to permanently
address these issues.
Certain Category B and C contingencies result in thermal and stability violations that will require that the
system be managed via existing OPPs or new ones that will be required. System operating studies will be
developed closer to the in-service date of the Project and any new OPPs required will be developed at
that time.
Alberta Electric System Operator
479,693
74
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
7.0 Responsibilities, Signature and Seal
This Report was prepared by Electranix Corporation on behalf of NEC for the sole purpose of assisting the
AESO with the preparation of the Need Information Filing associated with the interconnection
requirements of the Wild Rose 1 and 2 wind projects. To prepare this report, Electranix required
information that was provided by the AESO (particularly powerflow cases and assumptions) and Acciona
(particularly custom dynamic models and powerflow assumptions). In addition, information pertaining to
the proposed mitigation of constraints or criteria violations identified by Electranix was provided by the
AESO. Electranix was responsible for conducting the system impact studies and preparing this report in
reliance upon this information, and according to their professional judgement. While Electranix has no
reason to believe that the information provided by the AESO, and on which this report is based, is
inaccurate in any material respect, Electranix has not independently verified such information and cannot
guarantee its accuracy or completeness. To the extent that actual future conditions or assumptions differ
from the information provided to Electranix, the results will vary from those reported here.
I hereby certify, as a Professional Engineer in the province of Alberta, that the information in this
document was assembled under my direct personal charge. This report is not intended or represented to
be suitable for re-use by the AESO or others without specific verification or adaptation by the Engineer.
Signed and sealed,
__________________________
Andrew Isaacs P.Eng. (Alberta)
Date:
October 25, 2010
_
Alberta Electric System Operator
479,693
75
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
Appendices
Appendix A:
Appendix B:
Appendix C:
Appendix D:
Single Line Diagrams
Category C Powerflow Contingency Analysis
PSSE Dynamic Invocations (DYRE records)
Dynamic Traces
Alberta Electric System Operator
479,693
76
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
Appendix A: Single Line Diagrams
Alberta Electric System Operator
479,693
77
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S1ES_N0 - 2012 Summer Light Existing System 0MW import from Saskatchewan N-0 conditions.
Alberta Electric System Operator
479,693
78
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S1ES_D7 - Nevis 240kV/138kV transformer overloading, Nevis 4 to Cordell 4 240kV (9L20) outage
Overloaded branch
Branch outage
Alberta Electric System Operator
479,693
79
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S2ES_N0 - 2012 Summer Light Existing System 150MW import from Saskatchewan N-0 conditions.
Alberta Electric System Operator
479,693
80
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S2ES_D7 - Nevis 240kV/138kV transformer overloading, Nevis 4 to Cordell 4 240kV (9L20) outage
Alberta Electric System Operator
479,693
81
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S2ES_D18 - EmpressA7 to Cypress 1 138kV line overloading, Dome EM 4 to Cypress 2 CKT 11 240kV (945L) outage
Alberta Electric System Operator
479,693
82
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S2ES_D19 - EmpressA7 to Cypress 1 138kV line overloading, Dome EM 7 to Cypress 1 CKT 69 138kV outage
Alberta Electric System Operator
479,693
83
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S3ES_N0 - 2012 Summer Light Existing System 150MW export to Saskatchewan N-0 conditions.
Alberta Electric System Operator
479,693
84
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S3ES_D7 - Nevis 240kV/138kV transformer overloading, Nevis 4 to Cordell 4 240kV (9L20) outage.
Alberta Electric System Operator
479,693
85
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S4ES_N0 - 2012 Summer Peak Existing System 0MW import from Saskatchewan N-0 conditions.
Alberta Electric System Operator
479,693
86
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S4ES_E7 - Ellersli to Argylle 240kV line overloading, Bellamy 4 to Argyll W CKT 04 240kV outage.
Alberta Electric System Operator
479,693
87
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S5ES_N0 - 2012 Summer Peak Existing System 0MW import from Saskatchewan N-0 conditions.
Alberta Electric System Operator
479,693
88
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S5ES_E7- Ellersli to Argylle 240kV line overloading, Bellamy 4 to Argyll W CKT 04 240kV outage.
Alberta Electric System Operator
479,693
89
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S5ES_E15 - Empress A7 to Cypress 1 138kV line overloading, Dome EM 7 to Cypress 1 CKT 69 138kV outage.
Alberta Electric System Operator
479,693
90
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S1GA_N0 - 2012 Summer Light Wild Rose 200 MW and 0MW import from Saskatchewan N-0 conditions.
Alberta Electric System Operator
479,693
91
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S1GA_D7 - Nevis 240kV/138kV transformer overloading, Nevis 4 to Cordell 4 240kV (9L20) outage.
Alberta Electric System Operator
479,693
92
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S1GA_D18 - Empress A7 to Cypress 1 138kV line overloading, Dome EM 4 to Cypress 2 CKT 11 240kV (945L) outage.
Alberta Electric System Operator
479,693
93
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S2GA_N0 - 2012 Summer Light Wild Rose 200 MW and 150MW import from Saskatchewan N-0 conditions.
Alberta Electric System Operator
479,693
94
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S2GA_D4 - West Brook 7 to Bassano Tap 138kV, Queens Town to Bassano Tap 138kV line overloading, Red Deer to Nevis 240kV (912L) outage.
Alberta Electric System Operator
479,693
95
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S2GA_D5 - West Brook 7 to Bassano Tap 138kV line overloading, Langdon 4 to West Brook 240kV (924L) outage.
Alberta Electric System Operator
479,693
96
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S2GA_D7 - Nevis 240kV/138kV transformer overloading, Nevis 4 to Cordell 4 240kV (9L20) outage.
Alberta Electric System Operator
479,693
97
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S2GA_D18 - Empress A7 to Cypress 1 138kV line overloading, Dome EM 4 to Cypress 2 CKT 11 240kV (945L) outage.
Alberta Electric System Operator
479,693
98
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S3GA_N0 - 2012 Summer Light Wild Rose 200MW and 150MW export to Saskatchewan N-0 conditions.
Alberta Electric System Operator
479,693
99
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S3GA_D7 - Nevis 240kV/138kV transformer overloading, Nevis 4 to Cordell 4 240kV (9L20) outage.
Alberta Electric System Operator
479,693
100
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S1GGA_N0 - 2012 Summer Light Wild Rose 400MW and OMW import from Saskatchewan N-0 conditions.
Alberta Electric System Operator
479,693
101
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S1GGA_D4 - West Brook 7 to Bassano Tap 138kV, Queens Town to Bassano Tap 138kV lines overloading, Red Deer to Nevis 240kV (912L) outage.
Alberta Electric System Operator
479,693
102
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S1GGA_D5 - West Brook 7 to Bassano Tap 138kV line overloading, Langdon 4 to West Brook 240kV (924L) outage.
Alberta Electric System Operator
479,693
103
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S1GGA_D7 - Nevis 240kV/138kV transformer overloading, Nevis 4 to Cordell 4 240kV (9L20) outage.
Alberta Electric System Operator
479,693
104
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S1GGA_D18 - Empress A7 to Cypress 1 138kV line overloading, Dome EM 4 to Cypress 2 CKT 11 240kV (945L) outage.
Alberta Electric System Operator
479,693
105
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S2GGA_N0 - 2012 Summer Light Wild Rose 400MW and 15OMW import from Saskatchewan N-0 conditions. Empress A7 to Cypress 1 138kV line overloading.
Alberta Electric System Operator
479,693
106
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S2GGA_D1 - Red Deer to Nevis (912L), Suffield to MH (892L), Chappice Lake to Glenridge 138kV, Cypress to Glenridge overloading, Ware Junction to West
Brook 4 240kV (931L) line outage.
Alberta Electric System Operator
479,693
107
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S2GGA_D2 - Suffield 7 to Medicine Hat 7 (892L), Empress A7 to Cypress1 138kV lines overloading, Fincastle 7 to Taber CKT 10 138kV(610L) outage
Alberta Electric System Operator
479,693
108
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S2GGA_D3 - Suffield 7 to Medicine Hat 7 (892L), Empress A7 to Cypress1 138kV lines overloading, Bulls Head 7 to Medicine Hat 7 CKT 80 138kV outage
Alberta Electric System Operator
479,693
109
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S2GGA_D4 - West Brook 7 to Bassano Tap 138kV, Queens Town to Bassano Tap 138kV lines overloading, Red Deer to Nevis 240kV (912L) outage
.
Alberta Electric System Operator
479,693
110
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S2GGA_D5 - West Brook 7 to Bassano Tap 138kV, Queens Town to Bassano Tap 138kV, Red Deer to Nevis (912L) lines overloading, Langdon 4 to West Brook
240kV (924L) outage. (Note: Vulcan 7 to Steveley to Fort MA7 overloading is not within the Monitored area)
Alberta Electric System Operator
479,693
111
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S2GGA_D7 - West Brook 7 to Bassano Tap 138kV, Queens Town to Bassano Tap 138kV, Nevis 240kV/138kV transformer overloading, Nevis 4 to Cordell 4
240kV (9L20) outage.
Alberta Electric System Operator
479,693
112
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S2GGA_D18 - Empress A7 to Cypress 1 138kV line overloading, Dome EM 4 to Cypress 2 CKT 11 240kV (945L) outage.
Alberta Electric System Operator
479,693
113
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S3GGA_N0 - 2012 Summer Light Wild Rose 400MW and 15OMW export to Saskatchewan N-0 conditions.
Alberta Electric System Operator
479,693
114
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S3GGA_D7 - Nevis 240kV/138kV transformer overloading, Nevis 4 to Cordell 4 240kV (9L20) outage.
Alberta Electric System Operator
479,693
115
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S3GGA_D4 - West Brook 7 to Bassano Tap 138kV line overloading, Red Deer to Nevis 240kV (912L) outage.
Alberta Electric System Operator
479,693
116
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S4GA_N0 - 2012 Summer Peak Wild Rose 200MW and OMW import from Saskatchewan N-0 conditions.
Alberta Electric System Operator
479,693
117
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S4GA_E7 - Ellersli to Argylle 240kV line overloading, Bellamy 4 to Argyll W CKT 04 240kV outage.
Alberta Electric System Operator
479,693
118
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S5GA_N0 - 2012 Summer Peak Wild Rose 200MW and 15OMW import from Saskatchewan N-0 conditions.
Alberta Electric System Operator
479,693
119
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S5GA_E5 - Chappice Lake to Glenridge 138kV, Cypress to Glenridge, Chappice Lake to Glenridge lines overloading, Ware Junction to West Brook 4 240kV (931L)
line outage.
Alberta Electric System Operator
479,693
120
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S5GA_E7 - Ellersli to Argylle 240kV line overloading, Bellamy 4 to Argyll W CKT 04 240kV outage.
Alberta Electric System Operator
479,693
121
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S5GA_E14 - Empress A7 to Cypress 1 138kV line overloading, Dome EM 4 to Cypress 2 CKT 11 240kV (945L) line outage.
Alberta Electric System Operator
479,693
122
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S5GA_E15 - Empress A7 to Cypress 1 138kV line overloading, Dome EM 7 to Cypress 1 CKT 69 138kV line outage.
Alberta Electric System Operator
479,693
123
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S5GA_E16 - Empress A7 to Cypress 1 138kV line overloading, Chappice Lake 7 to Medicine Hat 7 CKT 60 138kV line outage.
Alberta Electric System Operator
479,693
124
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S5GA_E17 - Empress A7 to Cypress 1 138kV line overloading, Chappice Lake to Glenridge CKT 58 138kV line outage.
Alberta Electric System Operator
479,693
125
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S5GA_E18 - Empress A7 to Cypress 1 138kV line overloading, Cypress 1 to Glenridge CKT58 138kV line outage.
Alberta Electric System Operator
479,693
126
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S6GA_N0 - 2012 Summer Peak Wild Rose 200MW and 15OMW export to Saskatchewan N-0 conditions.
Alberta Electric System Operator
479,693
127
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S6GA_E7 - Ellersli to Argylle 240kV line overloading, Bellamy 4 to Argyll W CKT 04 240kV outage.
Alberta Electric System Operator
479,693
128
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S4GGA_N0 - 2012 Summer Peak Wild Rose 400MW and OMW import from Saskatchewan N-0 conditions.
Alberta Electric System Operator
479,693
129
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S4GGA_E1 - West Brook 7 to Bassano Tap 138kV line overloading, Red Deer to Nevis 240kV (912L) line outage.
Alberta Electric System Operator
479,693
130
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S4GGA_E5 - Chappice Lake to Glenridge 138kV, Cypress to Glenridge, Chappice Lake to Medicine Hat 7 138kV lines overloading, Ware Junction to West Brook 4
240kV (931L) line outage.
Alberta Electric System Operator
479,693
131
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S4GGA_E7 - Ellersli to Argylle 240kV line overloading, Bellamy 4 to Argyll W CKT 04 240kV outage.
Alberta Electric System Operator
479,693
132
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S4GGA_E14 - Empress A7 to Cypress 1 138kV line overloading, Dome EM 4 to Cypress 2 CKT 11 240kV (945L) line outage.
Alberta Electric System Operator
479,693
133
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S5GGA_N0 - 2012 Summer Peak Wild Rose 400MW and 15OMW import from Saskatchewan N-0 conditions.
Alberta Electric System Operator
479,693
134
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S5GGA_E1 - Chappice Lake to Glenridge 138kV, Cypress to Glenridge, Chappice Lake to Glenridge, West Brook 7 to Bassano Tap, Queens Town to Bassano Tap
lines overloading, Red Deer to Nevis 240kV (912L) line outage.
Alberta Electric System Operator
479,693
135
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S5GGA_E2 - West Brook 7 to Bassano Tap, Queens Town to Bassano Tap lines overloading, Langdon 4 to West Brook 240kV (924L) line outage.
Alberta Electric System Operator
479,693
136
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S5GGA_E4 - West Brook 7 to Bassano Tap, Nevis240kV/138kV transformer overloading, Nevis 4 to Cordell 4 240kV (9L20) line outage.
Alberta Electric System Operator
479,693
137
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S5GGA_E5 - Chappice Lake to Glenridge 138kV, Cypress to Glenridge, Chappice Lake to Medicine Hat 7 138kV lines overloading, Ware Junction to West Brook
4 240kV (931L) line outage.
Alberta Electric System Operator
479,693
138
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S5GGA_E6 - Chappice Lake to Glenridge 138kV, Cypress to Glenridge, Chappice Lake to Medicine Hat 7 138kV lines overloading, Tilley 7 to West Brook 7 CKT 66
138kV line outage.
Alberta Electric System Operator
479,693
139
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S5GGA_E14 - Empress A7 to Cypress 1 138kV line overloading, Dome EM 4 to Cypress 2 CKT 11 240kV (945L) line outage.
Alberta Electric System Operator
479,693
140
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S5GGA_E15 - Empress A7 to Cypress 1 138kV line overloading, Dome EM 7 to Cypress 1 CKT 69 138kV line outage.
Alberta Electric System Operator
479,693
141
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S5GGA_E16 - Empress A7 to Cypress 1 138kV line overloading, Chappice Lake 7 to Medicine Hat 7 CKT 60 138kV line outage.
Alberta Electric System Operator
479,693
142
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S5GGA_E17 - Empress A7 to Cypress 1 138kV line overloading, Chappice Lake to Glenridge CKT 58 138kV line outage.
Alberta Electric System Operator
479,693
143
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S5GGA_E18 - Empress A7 to Cypress 1 138kV line overloading, Cypress 1 to Glenridge CKT58 138kV line outage.
Alberta Electric System Operator
479,693
144
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S6GGA_N0 - 2012 Summer Peak Wild Rose 400MW and 15OMW export to Saskatchewan N-0 conditions.
Alberta Electric System Operator
479,693
145
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S6GGA_E7 - Ellersli to Argylle 240kV line overloading, Bellamy 4 to Argyll W CKT 04 240kV outage.
Alberta Electric System Operator
479,693
146
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S8GGA_N0 - 2013 Summer Light Wild Rose 400MW and OMW import from to Saskatchewan N-0 conditions.
Alberta Electric System Operator
479,693
147
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S8GGA_C1 - Red Deer to Red Deer B 240kV/138kV transformer overloading, Gaetz 4 to Red Deer 4 CKT 14 240kV line outage.
Alberta Electric System Operator
479,693
148
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S8GGA_C2 - Red Deer to Nevis 240kV (912L) line overloading, Langdon 4 to Milo Junction 240kV (924L) line outage.
Alberta Electric System Operator
479,693
149
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S8GGA_C6 - Red Deer to Nevis 240kV (912L) line overloading, Ware Junction to West Brook 4 240kV (931L) line outage.
Alberta Electric System Operator
479,693
150
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S8GGA_C5 - Nevis 240kV/138kV transformer, Nevis 4 to Cordell 4 240kV (9L20) line outage.
Alberta Electric System Operator
479,693
151
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S9GGA_N0 - 2013 Summer Peak Wild Rose 400MW and OMW import from to Saskatchewan N-0 conditions.
Alberta Electric System Operator
479,693
152
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S9GGA_C3 - Janet 4 to Janet 7 240kV/138kV transformers overloading, Janet 4 to East Calgary CKT 17 240kV line outage.
Alberta Electric System Operator
479,693
153
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S9GGA_C4 - East Calgary Enmax2S7 240kV/138kV T1 transformer overloading, Sarcee 4 to East Calgary CKT 16 240kV line outage.
Alberta Electric System Operator
479,693
154
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S10GGA_N0 - 2013 Summer Peak Wild Rose 400MW and 15OMW import from to Saskatchewan N-0 conditions.
Alberta Electric System Operator
479,693
155
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S10GGA_C3- Janet 4 to Janet 7 240kV/138kV transformers overloading, Janet 4 to East Calgary CKT 17 240kV line outage.
Alberta Electric System Operator
479,693
156
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S10GGA_C4 - East Calgary Enmax2S7 240kV/138kV T1 transformer overloading, Sarcee 4 to East Calgary CKT 16 240kV line outage.
Alberta Electric System Operator
479,693
157
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S10GGA_C5 - Nevis 240kV/138kV transformer overloading, Nevis 4 to Cordell 4 240kV (9L20)
Alberta Electric System Operator
479,693
158
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S10GGA_C15 - Janet 4 to East Calgary 17 line outage, Benalto 4 to Sarcee 4 CKT 28 240kV line outage.
Alberta Electric System Operator
479,693
159
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S10GGA_C16 - Empress A7 to Cypress 1 138kV line overloading, Dome EM 4 to Cypress 2 CKT 11 240kV (945L) line outage.
Alberta Electric System Operator
479,693
160
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S10GGA_C17 - Empress A7 to Cypress 1 138kV line overloading, Battle River 79 to Cordell 4 CKT 79 240kV line outage.
Alberta Electric System Operator
479,693
161
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S10GGA_C18 - Empress A7 to Cypress 1 138kV line overloading, Dome EM 7 to Cypress 1 CKT 69 138kV line outage.
Alberta Electric System Operator
479,693
162
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S10GGA_C19 - Empress A7 to Cypress 1 138kV line overloading, Cypress 1 to Glenridge CKT58 138kV line outage.
Alberta Electric System Operator
479,693
163
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
Appendix B: Category C Powerflow Contingency Analysis
Note: Overloading on Janet to Peigan (911L) and Landon SVC reported in most of Category C
contingencies and not reported in these tables.
S1C2ES - ( 2012 Summer Light case, 0 MW Wild Rose, 0 MW Import from Sask.)
944L - Jenner to Ware Junction
9L950/9L934 - Ware Junction
to Anderson
923L/924L - W. Brook to
N.Lethbridge
1034L/1035L - Bowmanton to
W.Brook
Both circuits lost between
Bowmanton and Elkwater
Line West towards
Whitla/Lethbridge
-
117%
-
N/A
N/A
N/A
Fincastle 7 to Taber CKT 10 138kV(610L)
Red Deer to Nevis 240kV (912L)
Carsela 7 to Janet 7 CKT50 138kV
Carsela 7 to Blackie 7 CKT51 138kV
Blackie 7 Vulcan 7 CKT 61 138kV
Gleiche 7 to Queenstown CKT 76 138kV
Empress 7 to Dome Empress 7 CKT 97 138kV
Empress 7 to Cypress 1 CKT 68 138kV
Dome EM 7 to EMPLIQTP CKT 60 138kV
Suffield 7 to Tilley 7 CKT 00 138kV
Suffield 7 to Medicine Hat 7 CKT 92 138kV
West Brook 7 to Bassano Tap CKT 53 138kV
Chappice Lake to Medicine Hat 7 CKT 60 138kV
Chappice Lake to Glenridge CKT 58 138kV
Queenstown to Bassano Tap CKT 53 138kV
Cypress 1 to Glenridge CKT 58 138kV
EMPLIQ Tap to KSP Tap CKT 60 138kV
Nevis 4 to Cordell 4 CKT 20 240kV
Nevis 240kV/138kV transformer
Not Converged
Overloaded Line
Not Converged
945L/951L - Cypress to Jenner
Contingency
Alberta Electric System Operator
479,693
164
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S2C2ES - ( 2012 Summer Light case, 0 MW Wild Rose, 150 MW Import from Sask.)
944L - Jenner to Ware Junction
9L950/9L934 - Ware Junction
to Anderson
923L/924L - W. Brook
to N.Lethbridge
1034L/1035L - Bowmanton
to W.Brook
Both circuits lost between
Bowmanton and Elkwater
Line West towards
Whitla/Lethbridge
-
121%
123%
113%
-
N/A
N/A
N/A
Fincastle 7 to Taber CKT 10 138kV(610L)
Red Deer to Nevis 240kV (912L)
Carsela 7 to Janet 7 CKT50 138kV
Carsela 7 to Blacki 7 CKT51 138kV
Blackie 7 Vulcan 7 CKT 61 138kV
Gleiche 7 to Queenstown CKT 76 138kV
Empress 7 to Dome Empress 7 CKT 97 138kV
Empress 7 to Cypress 1 CKT 68 138kV
Dome EM 7 to EMPLIQTP CKT 60 138kV
Suffield 7 to Tilley 7 CKT 00 138kV
Suffield 7 to Medicine Hat 7 CKT 92 138kV
West Brook 7 to Bassano Tap CKT 53 138kV
Chappice Lake to Medicine Hat 7 CKT 60 138kV
Chappice Lake to Glenridge CKT 58 138kV
Queenstown to Bassano Tap CKT 53 138kV
Cypress 1 to Glenridge CKT 58 138kV
EMPLIQ Tap to KSP Tap CKT 60 138kV
Nevis 4 to Cordell 4 CKT 20 240kV
Nevis 240kV/138kV transformer
Not Converged
Overloaded Line
Not Converged
945L/951L - Cypress to Jenner
Contingency
Alberta Electric System Operator
479,693
165
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S3C2ES - ( 2012 Summer Light case, 0 MW Wild Rose, 150 MW export to Sask.)
944L - Jenner to Ware Junction
9L950/9L934 - Ware Junction
to Anderson
923L/924L - W. Brook
to N.Lethbridge
1034L/1035L - Bowmanton
to W.Brook
Both circuits lost between
Bowmanton and Elkwater
Line West towards
Whitla/Lethbridge
-
112%
-
N/A
N/A
N/A
Fincastle 7 to Taber CKT 10 138kV(610L)
Red Deer to Nevis 240kV (912L)
Carsela 7 to Janet 7 CKT50 138kV
Carsela 7 to Blacki 7 CKT51 138kV
Blackie 7 Vulcan 7 CKT 61 138kV
Gleiche 7 to Queenstown CKT 76 138kV
Empress 7 to Dome Empress 7 CKT 97 138kV
Empress 7 to Cypress 1 CKT 68 138kV
Dome EM 7 to EMPLIQTP CKT 60 138kV
Suffield 7 to Tilley 7 CKT 00 138kV
Suffield 7 to Medicine Hat 7 CKT 92 138kV
West Brook 7 to Bassano Tap CKT 53 138kV
Chappice Lake to Medicine Hat 7 CKT 60 138kV
Chappice Lake to Glenridge CKT 58 138kV
Queenstown to Bassano Tap CKT 53 138kV
Cypress 1 to Glenridge CKT 58 138kV
EMPLIQ Tap to KSP Tap CKT 60 138kV
Nevis 4 to Cordell 4 CKT 20 240kV
Nevis 240kV/138kV transformer
Not Converged
Overloaded Line
Not Converged
945L/951L - Cypress to Jenner
Contingency
Alberta Electric System Operator
479,693
166
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S4C2ES - ( 2012 Summer peak case, 0 MW Wild Rose, 0 MW export to Sask.)
944L - Jenner to Ware Junction
9L950/9L934 - Ware Junction
to Anderson
923L/924L - W. Brook
to N.Lethbridge
1034L/1035L - Bowmanton
to W.Brook
Both circuits lost between
Bowmanton and Elkwater
Line West towards
Whitla/Lethbridge
-
-
N/A
N/A
N/A
Blackie 7 Vulcan 7 CKT 61 138kV
Gleiche 7 to Queenstown CKT 76 138kV
Empress 7 to Dome Empress 7 CKT 97 138kV
Empress 7 to Cypress 1 CKT 68 138kV
Suffield 7 to Medicine Hat 7 CKT 92 138kV
Taber 7 to Chin chute CKT 72 138kV
West Brook 7 to Bassano Tap CKT 53 138kV
Chappice Lake to Medicine Hat 7 CKT 60 138kV
Chappice Lake to Glenridge CK 58 138kV
Queenstown to Bassano Tap CKT 53 138kV
Cypress 1 to Glenridge CKT 58 138kV
Nevis 240kV/138kV transformer
Not Converged
Overloaded Line
Not Converged
945L/951L - Cypress to Jenner
Contingency
Alberta Electric System Operator
479,693
167
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S5C2ES - ( 2012 Summer peak, 0 MW Wild Rose, 150 MW import from Sask.)
944L - Jenner to Ware Junction
9L950/9L934 - Ware Junction
to Anderson
923L/924L - W. Brook
to N.Lethbridge
1034L/1035L - Bowmanton
to W.Brook
Both circuits lost between
Bowmanton and Elkwater
Line West towards
Whitla/Lethbridge
-
109%
-
N/A
N/A
N/A
Blackie 7 Vulcan 7 CKT 61 138kV
Gleiche 7 to Queenstown CKT 76 138kV
Empress 7 to Dome Empress 7 CKT 97 138kV
Empress 7 to Cypress 1 CKT 68 138kV
Suffield 7 to Medicine Hat 7 CKT 92 138kV
Taber 7 to Chin chute CKT 72 138kV
West Brook 7 to Bassano Tap CKT 53 138kV
Chappice Lake to Medicine Hat 7 CKT 60 138kV
Chappice Lake to Glenridge CKT 58 138kV
Queenstown to Bassano Tap CKT 53 138kV
Cypress 1 to Glenridge CKT 58 138kV
Nevis 240kV/138kV transformer
Not Converged
Overloaded Line
Not Converged
945L/951L - Cypress to Jenner
Contingency
Alberta Electric System Operator
479,693
168
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S6C2ES - ( 2012 Summer peak case, 0 MW Wild Rose, 150 MW export to Sask.)
923L/924L - W. Brook
to N.Lethbridge
1034L/1035L - Bowmanton
to W.Brook
Both circuits lost between
Bowmanton and Elkwater
Line West towards
Whitla/Lethbridge
-
109%
-
N/A
N/A
N/A
944L - Jenner to Ware Junction
9L950/9L934 - Ware
Junction to Anderson
Blackie 7 Vulcan 7 CKT 61 138kV
Gleiche 7 to Queenstown CKT 76 138kV
Empress 7 to Dome Empress 7 CKT 97 138kV
Empress 7 to Cypress 1 CKT 68 138kV
Shuffle 7 to Medicine Hat 7 CKT 92 138kV
Taber 7 to Chin chute CKT 72 138kV
West Brook 7 to Bassano Tap CKT 53 138kV
Chappice Lake to Medicine Hat 7 CKT 60 138kV
Chappice Lake to Glenridge CKT 58 138kV
Queenstown to Bassano Tap CKT 53 138kV
Cypress 1 to Glenridge CKT 58 138kV
Nevis 240kV/138kV transformer
Not Converged
Overloaded Line
Not Converged
945L/951L - Cypress to Jenner
Contingency
-
Alberta Electric System Operator
479,693
169
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S1C2GA - ( 2012 Summer Light case, 200 MW Wild Rose, 0 MW export to Sask.)
122%
131%
121%
-
Line West towards
Whitla/Lethbridge
-
-
N/A
923L/924L - W. Brook
to N.Lethbridge
-
Both circuits lost between
Bowmanton and Elkwater
9L950/9L934 - Ware
Junction to Anderson
-
1034L/1035L - Bowmanton
to W.Brook
944L - Jenner to Ware Junction
Fincastle 7 to Taber CKT 10 138kV(610L)
Red Deer to Nevis 240kV (912L)
Carsela 7 to Janet 7 CKT50 138kV
Carsela 7 to Blacki 7 CKT51 138kV
Blackie 7 Vulcan 7 CKT 61 138kV
Gleiche 7 to Queenstown CKT 76 138kV
Empress 7 to Dome Empress 7 CKT 97 138kV
Empress 7 to Cypress 1 CKT 68 138kV
Dome EM 7 to EMPLIQTP CKT 60 138kV
Suffield 7 to Tilley 7 CKT 00 138kV
Suffield 7 to Medicine Hat 7 CKT 92 138kV
West Brook 7 to Bassano Tap CKT 53 138kV
Chappice Lake to Medicine Hat 7 CKT 60 138kV
Chappice Lake to Glenridge CKT 58 138kV
Queenstown to Bassano Tap CKT 53 138kV
Cypress 1 to Glenridge CKT 58 138kV
EMPLIQ Tap to KSP Tap CKT 60 138kV
Nevis 4 to Cordell 4 CKT 20 240kV
Nevis 240kV/138kV transformer
N/A
Overloaded Line
945L/951L - Cypress to Jenner
Contingency
Alberta Electric System Operator
479,693
170
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S2C2GA - ( 2012 Summer Light case, 200 MW Wild Rose, 150 MW import from Sask.)
113%
127%
114%
155%
146%
-
Line West towards
Whitla/Lethbridge
-
-
N/A
923L/924L - W. Brook
to N.Lethbridge
-
Both circuits lost between
Bowmanton and Elkwater
9L950/9L934 - Ware Junction
to Anderson
107%
106%
110%
-
1034L/1035L - Bowmanton
to W.Brook
944L - Jenner to Ware Junction
Fincastle 7 to Taber CKT 10 138kV(610L)
Red Deer to Nevis 240kV (912L)
Carsela 7 to Janet 7 CKT50 138kV
Carsela 7 to Blacki 7 CKT51 138kV
Blackie 7 Vulcan 7 CKT 61 138kV
Gleiche 7 to Queenstown CKT 76 138kV
Empress 7 to Dome Empress 7 CKT 97 138kV
Empress 7 to Cypress 1 CKT 68 138kV
Dome EM 7 to EMPLIQTP CKT 60 138kV
Suffield 7 to Tilley 7 CKT 00 138kV
Suffield 7 to Medicine Hat 7 CKT 92 138kV
West Brook 7 to Bassano Tap CKT 53 138kV
Chappice Lake to Medicine Hat 7 CKT 60 138kV
Chappice Lake to Glenridge CKT 58 138kV
Queenstown to Bassano Tap CKT 53 138kV
Cypress 1 to Glenridge CKT 58 138kV
EMPLIQ Tap to KSP Tap CKT 60 138kV
Nevis 4 to Cordell 4 CKT 20 240kV
Nevis 240kV/138kV transformer
N/A
Overloaded Line
945L/951L - Cypress to Jenner
Contingency
Alberta Electric System Operator
479,693
171
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S3C2GA - ( 2012 Summer Light case, 200 MW Wild Rose, 150 MW export to Sask.)
119%
112%
111%
-
160%
153%
152%
-
-
-
-
Line West towards
Whitla/Lethbridge
118%
-
N/A
-
Both circuits lost between
Bowmanton and Elkwater
108%
-
1034L/1035L - Bowmanton
to W.Brook
923L/924L - W. Brook
to N.Lethbridge
-
N/A
9L950/9L934 - Ware Junction
to Anderson
Fincastle 7 to Taber CKT 10 138kV(610L)
Red Deer to Nevis 240kV (912L)
Carsela 7 to Janet 7 CKT50 138kV
Carsela 7 to Blacki 7 CKT51 138kV
Blackie 7 Vulcan 7 CKT 61 138kV
Gleiche 7 to Queenstown CKT 76 138kV
Empress 7 to Dome Empress 7 CKT 97 138kV
Empress 7 to Cypress 1 CKT 68 138kV
Dome EM 7 to EMPLIQTP CKT 60 138kV
Suffield 7 to Tilley 7 CKT 00 138kV
Suffield 7 to Medicine Hat 7 CKT 92 138kV
West Brook 7 to Bassano Tap CKT 53 138kV
Chappice Lake to Medicine Hat 7 CKT 60
138kV
Chappice Lake to Glenridge CKT 58 138kV
Queenstown to Bassano Tap CKT 53 138kV
Cypress 1 to Glenridge CKT 58 138kV
EMPLIQ Tap to KSP Tap CKT 60 138kV
Nevis 4 to Cordell 4 CKT 20 240kV
Nevis 240kV/138kV transformer
944L - Jenner to Ware Junction
Overloaded Line
945L/951L - Cypress to Jenner
Contingency
-
Alberta Electric System Operator
479,693
172
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S1C2GGA - ( 2012 Summer Light case, 400 MW Wild Rose, 0 MW export to Sask.)
114%
121%
121%
-
-
-
153%
105%
-
Line West towards
Whitla/Lethbridge
117%
105%
113%
128%
119%
163%
N/A
-
Both circuits lost between
Bowmanton and Elkwater
106%
-
1034L/1035L - Bowmanton
to W.Brook
923L/924L - W. Brook
to N.Lethbridge
122%
117%
128%
-
N/A
9L950/9L934 - Ware Junction
to Anderson
Fincastle 7 to Taber CKT 10 138kV(610L)
Red Deer to Nevis 240kV (912L)
Carsela 7 to Janet 7 CKT50 138kV
Carsela 7 to Blacki 7 CKT51 138kV
Blackie 7 Vulcan 7 CKT 61 138kV
Gleiche 7 to Queenstown CKT 76 138kV
Empress 7 to Dome Empress 7 CKT 97 138kV
Empress 7 to Cypress 1 CKT 68 138kV
Dome EM 7 to EMPLIQTP CKT 60 138kV
Suffield 7 to Tilley 7 CKT 00 138kV
Suffield 7 to Medicine Hat 7 CKT 92 138kV
West Brook 7 to Bassano Tap CKT 53 138kV
Chappice Lake to Medicine Hat 7 CKT 60
138kV
Chappice Lake to Glenridge CKT 58 138kV
Queenstown to Bassano Tap CKT 53 138kV
Cypress 1 to Glenridge CKT 58 138kV
EMPLIQ Tap to KSP Tap CKT 60 138kV
Nevis 4 to Cordell 4 CKT 20 240kV
Nevis 240kV/138kV transformer
944L - Jenner to Ware Junction
Overloaded Line
945L/951L - Cypress to Jenner
Contingency
-
Alberta Electric System Operator
479,693
173
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S2C2GGA - ( 2012 Summer Light, 400 MW Wild Rose, 150 MW import from Sask.)
-
130%
113%
120%
134%
130%
-
157%
143%
139% 121%
156% 136%
187% 168%
-
-
-
-
-
-
188%
-
221%
228%
229%
141%
-
172%
179%
179%
122%
-
-
178%
108%
113%
-
Line West towards
Whitla/Lethbridge
N/A
Both circuits lost between
Bowmanton and Elkwater
1034L/1035L - Bowmanton
to W.Brook
126% 114%
-
N/A
Fincastle 7 to Taber CKT 10 138kV(610L)
Red Deer to Nevis 240kV (912L)
Carsela 7 to Janet 7 CKT50 138kV
Carsela 7 to Blacki 7 CKT51 138kV
Blackie 7 Vulcan 7 CKT 61 138kV
Gleiche 7 to Queenstown CKT 76 138kV
Empress 7 to Dome Empress 7 CKT 97
138kV
Empress 7 to Cypress 1 CKT 68 138kV
Dome EM 7 to EMPLIQTP CKT 60 138kV
Suffield 7 to Tilley 7 CKT 00 138kV
Suffield 7 to Medicine Hat 7 CKT 92 138kV
West Brook 7 to Bassano Tap CKT 53
138kV
Chappice Lake to Medicine Hat 7 CKT 60
138kV
Chappice Lake to Glenridge CKT 58 138kV
Queenstown to Bassano Tap CKT 53 138kV
Cypress 1 to Glenridge CKT 58 138kV
EMPLIQ Tap to KSP Tap CKT 60 138kV
Nevis 4 to Cordell 4 CKT 20 240kV
Nevis 240kV/138kV transformer
923L/924L - W. Brook to
N.Lethbridge
Overloaded Line
944L - Jenner to Ware
Junction
9L950/9L934 - Ware
Junction
to Anderson
945L/951L - Cypress to
Jenner
Contingency
Alberta Electric System Operator
479,693
174
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
3C2GGA - ( 2012 Summer Light case, 400 MW Wild Rose, 150 MW export to Sask.)
-
104%
123%
103%
-
-
-
-
-
-
-
-
-
139%
-
-
-
-
129%
-
-
N/A
N/A
Line West towards
Whitla/Lethbridge
-
Both circuits lost between
Bowmanton and Elkwater
923L/924L - W. Brook
to N.Lethbridge
-
1034L/1035L - Bowmanton
to W.Brook
9L950/9L934 - Ware Junction
to Anderson
Fincastle 7 to Taber CKT 10 138kV(610L)
Red Deer to Nevis 240kV (912L)
Carsela 7 to Janet 7 CKT50 138kV
Carsela 7 to Blacki 7 CKT51 138kV
Blackie 7 Vulcan 7 CKT 61 138kV
Gleiche 7 to Queenstown CKT 76 138kV
Empress 7 to Dome Empress 7 CKT 97
138kV
Empress 7 to Cypress 1 CKT 68 138kV
Dome EM 7 to EMPLIQTP CKT 60 138kV
Suffield 7 to Tilley 7 CKT 00 138kV
Suffield 7 to Medicine Hat 7 CKT 92 138kV
West Brook 7 to Bassano Tap CKT 53
138kV
Chappice Lake to Medicine Hat 7 CKT 60
138kV
Chappice Lake to Glenridge CKT 58 138kV
Queenstown to Bassano Tap CKT 53 138kV
Cypress 1 to Glenridge CKT 58 138kV
EMPLIQ Tap to KSP Tap CKT 60 138kV
Nevis 4 to Cordell 4 CKT 20 240kV
Nevis 240kV/138kV transformer
944L - Jenner to Ware Junction
Overloaded Line
945L/951L - Cypress to Jenner
Contingency
Alberta Electric System Operator
479,693
175
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S4C2GA - ( 2012 Summer peak case, 200 MW Wild Rose, 0 MW export to Sask.)
117%
107%
-
Line West towards
Whitla/Lethbridge
-
-
N/A
923L/924L - W. Brook
to N.Lethbridge
-
Both circuits lost between
Bowmanton and Elkwater
9L950/9L934 - Ware Junction
to Anderson
-
1034L/1035L - Bowmanton
to W.Brook
944L - Jenner to Ware Junction
Blackie 7 Vulcan 7 CKT 61 138kV
Gleiche 7 to Queenstown CKT 76 138kV
Empress 7 to Dome Empress 7 CKT 97 138kV
Empress 7 to Cypress 1 CKT 68 138kV
Suffield 7 to Medicine Hat 7 CKT 92 138kV
Taber 7 to Chin chute CKT 72 138kV
West Brook 7 to Bassano Tap CKT 53 138kV
Chappice Lake to Medicine Hat 7 CKT 60 138kV
Chappice Lake to Glenridge CKT 58 138kV
Queenstown to Bassano Tap CKT 53 138kV
Cypress 1 to Glenridge CKT 58 138kV
Nevis 240kV/138kV transformer
N/A
Overloaded Line
945L/951L - Cypress to Jenner
Contingency
Alberta Electric System Operator
479,693
176
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S5C2GA - (2012 Summer peak case, 200 MW Wild Rose, 150 MW import from Sask.)
141%
131%
-
Line West towards
Whitla/Lethbridge
-
-
N/A
923L/924L - W. Brook
to N.Lethbridge
-
Both circuits lost between
Bowmanton and Elkwater
9L950/9L934 - Ware Junction
to Anderson
-
1034L/1035L - Bowmanton
to W.Brook
944L - Jenner to Ware Junction
Blackie 7 Vulcan 7 CKT 61 138kV
Gleiche 7 to Queenstown CKT 76 138kV
Empress 7 to Dome Empress 7 CKT 97 138kV
Empress 7 to Cypress 1 CKT 68 138kV
Suffield 7 to Medicine Hat 7 CKT 92 138kV
Taber 7 to Chin chute CKT 72 138kV
West Brook 7 to Bassano Tap CKT 53 138kV
Chappice Lake to Medicine Hat 7 CKT 60 138kV
Chappice Lake to Glenridge CKT 58 138kV
Queenstown to Bassano Tap CKT 53 138kV
Cypress 1 to Glenridge CKT 58 138kV
Nevis 240kV/138kV transformer
N/A
Overloaded Line
945L/951L - Cypress to Jenner
Contingency
Alberta Electric System Operator
479,693
177
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S6C2GA - (2012 Summer peak case, 200 MW Wild Rose, 150 MW export to Sask.)
Both circuits lost between
Bowmanton and Elkwater
Line West towards
Whitla/Lethbridge
-
N/A
923L/924L - W. Brook
to N.Lethbridge
-
1034L/1035L - Bowmanton
to W.Brook
9L950/9L934 - Ware Junction
to Anderson
-
N/A
944L - Jenner to Ware Junction
Blackie 7 Vulcan 7 CKT 61 138kV
Gleiche 7 to Queenstown CKT 76 138kV
Empress 7 to Dome Empress 7 CKT 97 138kV
Empress 7 to Cypress 1 CKT 68 138kV
Suffield 7 to Medicine Hat 7 CKT 92 138kV
Taber 7 to Chin chute CKT 72 138kV
West Brook 7 to Bassano Tap CKT 53 138kV
Chappice Lake to Medicine Hat 7 CKT 60 138kV
Chappice Lake to Glenridge CKT 58 138kV
Queenstown to Bassano Tap CKT 53 138kV
Cypress 1 to Glenridge CKT 58 138kV
Nevis 240kV/138kV transformer
Not Converged
Overloaded Line
Not Converged
945L/951L - Cypress to Jenner
Contingency
Alberta Electric System Operator
479,693
178
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S4C2GGA - (2012 Summer peak case, 400 MW Wild Rose, 0 MW export to Sask.)
136%
144%
145%
-
108%
108%
-
-
138%
-
-
Line West towards
Whitla/Lethbridge
147%
N/A
-
Both circuits lost between
Bowmanton and Elkwater
-
1034L/1035L - Bowmanton
to W.Brook
923L/924L - W. Brook
to N.Lethbridge
105%
105%
-
N/A
9L950/9L934 - Ware Junction
to Anderson
Blackie 7 Vulcan 7 CKT 61 138kV
Gleiche 7 to Queenstown CKT 76 138kV
Empress 7 to Dome Empress 7 CKT 97 138kV
Empress 7 to Cypress 1 CKT 68 138kV
Suffield 7 to Medicine Hat 7 CKT 92 138kV
Taber 7 to Chin chute CKT 72 138kV
West Brook 7 to Bassano Tap CKT 53 138kV
Chappice Lake to Medicine Hat 7 CKT 60
138kV
Chappice Lake to Glenridge CKT 58 138kV
Queenstown to Bassano Tap CKT 53 138kV
Cypress 1 to Glenridge CKT 58 138kV
Nevis 240kV/138kV transformer
944L - Jenner to Ware Junction
Overloaded Line
945L/951L - Cypress to Jenner
Contingency
-
Alberta Electric System Operator
479,693
179
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S5C2GGA - (2012 Summer peak, 400 MW Wild Rose, 150 MW import from Sask.)
Line West towards
Whitla/Lethbridge
-
N/A
104%
111%
171%
161%
-
Both circuits lost between
Bowmanton and Elkwater
923L/924L - W. Brook
to N.Lethbridge
-
1034L/1035L - Bowmanton
to W.Brook
9L950/9L934 - Ware Junction
to Anderson
109%
199%
207%
207%
-
N/A
944L - Jenner to Ware
Junction
Blackie 7 Vulcan 7 CKT 61 138kV
Gleiche 7 to Queenstown CKT 76 138kV
Empress 7 to Dome Empress 7 CKT 97 138kV
Empress 7 to Cypress 1 CKT 68 138kV
Suffield 7 to Medicine Hat 7 CKT 92 138kV
Taber 7 to Chin chute CKT 72 138kV
West Brook 7 to Bassano Tap CKT 53 138kV
Chappice Lake to Medicine Hat 7 CKT 60 138kV
Chappice Lake to Glenridge CKT 58 138kV
Queenstown to Bassano Tap CKT 53 138kV
Cypress 1 to Glenridge CKT 58 138kV
Nevis 240kV/138kV transformer
945L/951L - Cypress to Jenner
Overloaded Line
Not Converged
Contingency
Alberta Electric System Operator
479,693
180
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S6C2GGA - (2012 Summer peak, 400 MW Wild Rose, 150 MW export to Sask.)
-
Line West towards
Whitla/Lethbridge
124%
114%
-
-
N/A
923L/924L - W. Brook
to N.Lethbridge
-
Both circuits lost between
Bowmanton and Elkwater
9L950/9L934 - Ware Junction
to Anderson
-
1034L/1035L - Bowmanton
to W.Brook
944L - Jenner to Ware Junction
Blackie 7 Vulcan 7 CKT 61 138kV
Gleiche 7 to Queenstown CKT 76 138kV
Empress 7 to Dome Empress 7 CKT 97 138kV
Empress 7 to Cypress 1 CKT 68 138kV
Suffield 7 to Medicine Hat 7 CKT 92 138kV
Taber 7 to Chin chute CKT 72 138kV
West Brook 7 to Bassano Tap CKT 53 138kV
Chappice Lake to Medicine Hat 7 CKT 60 138kV
Chappice Lake to Glenridge CKT 58 138kV
Queenstown to Bassano Tap CKT 53 138kV
Cypress 1 to Glenridge CKT 58 138kV
Nevis 240kV/138kV transformer
N/A
Overloaded Line
945L/951L - Cypress to Jenner
Contingency
Alberta Electric System Operator
479,693
181
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S8C2GGA - ( 2013 Summer Light, 400 MW Wild Rose, 0 MW Import from Sask.)
Overloaded Line
945L/951L - Cypress to Jenner
944L - Jenner to Ware Junction
9L950/9L934 - Ware Junction to
Anderson
923L/924L - W. Brook to
N.Lethbridge
1034L/1035L - Bowmanton to
W.Brook
Both circuits lost between
Bowmanton and Elkwater
Line West towards
Whitla/Lethbridge
Contingency
Red Deer to Red Deer B 240kV/138kV Transformer
Red Deer to Nevis
Janet 4 to Janet 7 240kV/138kV transformer
East Calgary to Enmax Transformer 240kV/138kV
Taber 7 to Vauxhal 7 CKT 63 138kV
Taber 7 to Chin chute CKT 72 138kV
West Brook 7 to Ench Tap CKT 63 138kV
Cordell 7 to Chin chute CKT 72 138kV
Nevis 4 to Cordell 4 CKT 20 240kV
Nevis 240kV/138kV transformer
-
-
113%
-
142%
107%
128%
143%
119%
116%
-
-
-
Alberta Electric System Operator
479,693
182
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S9C2GGA - (2013 Summer peak, 400 MW Wild Rose, 0 MW import from Sask.)
Overloaded Line
945L/951L - Cypress to Jenner
944L - Jenner to Ware Junction
9L950/9L934 - Ware Junction to
Anderson
923L/924L - W. Brook to
N.Lethbridge
1034L/1035L - Bowmanton to
W.Brook
Both circuits lost between
Bowmanton and Elkwater
Line West towards
Whitla/Lethbridge
Contingency
Red Deer to Red Deer B 240kV/138kV Transformer
Red Deer to Nevis
Janet 4 to Janet 7 240kV/138kV transformer
East Calgary to Enmax Transformer 240kV/138kV
Taber 7 to Vauxhall 7 CKT 63 138kV
Taber 7 to Chin chute CKT 72 138kV
West Brook 7 to Ench Tap CKT 63 138kV
Cordell 7 to Chin chute CKT 72 138kV
Nevis 4 to Cordell 4 CKT 20 240kV
Nevis 240kV/138kV transformer
-
-
-
-
-
-
-
Alberta Electric System Operator
479,693
183
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
S10C2GGA - (2013 Summer peak, 400 MW Wild Rose, 150 MW import from Sask.)
Overloaded Line
945L/951L - Cypress to Jenner
944L - Jenner to Ware Junction
9L950/9L934 - Ware Junction to
Anderson
923L/924L - W. Brook to
N.Lethbridge
1034L/1035L - Bowmanton to
W.Brook
Both circuits lost between
Bowmanton and Elkwater
Line West towards
Whitla/Lethbridge
Contingency
Red Deer to Red Deer B 240kV/138kV Transformer
Red Deer to Nevis
Janet 4 to Janet 7 240kV/138kV transformer
East Calgary to Enmax Transformer 240kV/138kV
Taber 7 to Vauxhall 7 CKT 63 138kV
Taber 7 to Chin chute CKT 72 138kV
West Brook 7 to Ench Tap CKT 63 138kV
Cordell 7 to Chin chute CKT 72 138kV
Nevis 4 to Cordell 4 CKT 20 240kV
Nevis 240kV/138kV transformer
-
-
-
115%
115%
108%
111%
124%
-
-
-
-
Alberta Electric System Operator
479,693
184
25/10/2010
Wild Rose Wind Farm – Interconnection Proposal Technical Analysis
______________________________________________________________________
Appendix C:
Acciona DYR model invocation
The dynamic model invocation for the Acciona wind farm used in the dynamic analysis is as follows. Note
that these values differ from the recommended values in the Acciona documentation. Please refer to
Acciona documentation for a full description of each dynamic record:
1601 'USRMDL' 1
'A1530X '
0 1500
15.00
63.00
57.00
1.15
1.20
5.00
0.80
0.85
0.50
15.00
210.00
0.50
0.90
0.20
0.90
1.00
0.50
3.00
3000.00
500.00/
2101 'USRMDL' 1
'A1530X '
0 1500
15.00
63.00
57.00
1.15
1.20
5.00
0.80
0.85
0.50
15.00
210.00
0.50
0.90
0.20
0.90
1.00
0.50
3.00
3000.00
500.00/
1602 'USRMDL' 1
'A1530X '
0 1500
15.00
63.00
57.00
1.15
1.20
5.00
0.80
0.85
0.50
15.00
210.00
0.50
0.90
0.20
0.90
1.00
0.50
3.00
3000.00
500.00/
2102 'USRMDL' 1
'A1530X '
0 1500
15.00
63.00
57.00
1.15
1.20
5.00
0.80
0.85
0.50
15.00
210.00
0.50
0.90
0.20
0.90
1.00
0.50
3.00
3000.00
500.00/
0 'USRMDL' 0 'AWTVRW' 8 0 19
335
0
4
1
1
5.00
0.10
1.00
0.90
0.90
25.00
1
5.00
0.10
1.00
0.90
0.90
25.00
1
1
2
2
32
0
2
2
32
0
2
0
2
5.00
0.10
2.75
0.40
1.00
500.00
1
5.00
0.10
1.00
0.90
0.90
25.00
2
0
5.00
0.10
2.75
0.40
1.00
500.00
5.00
0.10
1.00
0.90
0.90
25.00
6
32
5.00
0.10
2.75
0.40
1.00
500.00
1
1
2
2
32
5.00
0.10
2.75
0.40
1.00
500.00
3
1601 '1 '
2101 '1 '
1602 '1 '
2102 '1 '
0 '1 '
0 '1 '
0 '1 '
0 '1 '
0.5000
0.4000
0.0100
0.1000
0.3973
-0.3973/
Alberta Electric System Operator
479,693
185
25/10/2010
Fly UP