...

Fort McMurray Area Transmission Bulk System Reinforcement

by user

on
Category: Documents
14

views

Report

Comments

Transcript

Fort McMurray Area Transmission Bulk System Reinforcement
Fort McMurray Area
Transmission Bulk
System Reinforcement
Functional Specification
File No. RP-05-838
March 2011
APEGGA Permit to Practice P-8200
Fort McMurray Area Transmission Bulk System Reinforecement Stage 1A - Rev. 1
TABLE OF CONTENTS
1.
INTRODUCTION ................................................................................ 3
2.
DATA DISCLAIMER ........................................................................... 3
3.
PROPOSAL AND ESTIMATE............................................................. 3
4.
PROJECT OVERVIEW ....................................................................... 3
5.
6.
7.
4.1
Proposed Facility Additions........................................................................ 3
4.2
System Development Prior to the Project .................................................. 4
4.3
Ultimate System Development ................................................................... 5
SCOPE OF WORK ............................................................................. 5
5.1
General ...................................................................................................... 5
5.2
Standards .................................................................................................. 5
5.3
Transmission Equipment Specifications .................................................... 6
5.3.1
General Environmental and Electrical Ratings ...................................................... 6
5.3.2
Circuit Breaker ....................................................................................................... 7
5.4
Proponent Scope of Work .......................................................................... 7
5.4.1
500 kV Transmission Line 9L44 ............................................................................ 7
5.4.2
500kV Substation Thickwood Hills 951S ............................................................... 8
TRANSMISSION SYSTEM OPERATING CHARACTERISTICS
ERROR! BOOKMARK NOT DEFINED.
6.1
Short Circuit Current Levels ........................Error! Bookmark not defined.
6.2
Voltage Levels ............................................Error! Bookmark not defined.
6.3
Insulation Levels .........................................Error! Bookmark not defined.
APPENDICES ................................................................................... 22
7.1
System Configuration - Existing ............................................................... 22
7.2
System Configuration –Development Prior to the Project ........................ 23
7.3
System Configuration – Proposed Development - Stage 1A ................... 24
7.4
System Configuration – Proposed Development – Stage 1B................... 25
7.5
System Configuration – Proposed Development – Stage 2 ..................... 26
7.6
System Configuration – Ultimate Development ....................................... 27
File No. RP-05-838
AESO Functional Specification
Page i
Fort McMurray Area Transmission Bulk System Reinforecement Stage 1A - Rev. 1
LIST OF TABLES
Table 1: Minimum & Maximum Continuous Equipment Operating Voltages ( kV) ........... 6
Table 2: Minimum Continuous Equipment Current Ratings (A) ....................................... 6
Table 3: Maximum Fault Levels (kA) ............................................................................... 7
Table 4: Area 2015-2017 Anticipated Short Circuit Levels with Proposed Development
...................................................................................................................................... 19
Table 5: Area 2021-2023 Anticipated Short Circuit Levels with Ultimate Development 20
Table 6: Acceptable Range of Steady State Voltage ( kV) ............................................ 20
Table 7: BIL Levels ( kV) ............................................................................................... 21
LIST OF FIGURES
Figure 1: System Configuration – Existing .................................................................... 22
Figure 2: System Configuration –Development Prior to the Project .............................. 23
Figure 3: System Configuration – Proposed Development - Stage 1A .......................... 24
Figure 4: System Configuration – Proposed Development – Stage 1B ......................... 25
Figure 5: System Configuration – Proposed Development – Stage 2 ........................... 26
Figure 6: System Configuration – Ultimate Development .............................................. 27
File No. RP-05-838
AESO Functional Specification
Page ii
Fort McMurray Area Transmission Bulk System Reinforecement Stage 1A - Rev. 1
1. INTRODUCTION
This Alberta Electric System Operator (“AESO”) Functional Specification (“the Specification”) is
intended to provide an overview of the specifications that will be utilized in the RFQ/RFP as part
of the competitive process for the development of new transmission facilities for interconnection
with the Alberta Transmission System (“ATS”). The Specification also serves to delineate the
work to be completed by various parties involved in the development of such facilities, provides
reference to applicable standards and guidelines to be applied in the design of such facilities,
outlines the electrical environment in which such facilities will operate, and provides reference to
the applicable rules and templates for the format required for proposals and estimates to be
submitted by the proponents.
2. DATA DISCLAIMER
The AESO has taken reasonable steps to verify this data where possible and believes it to be
accurate.
3. PROPOSAL AND ESTIMATE
THIS DOCUMENT IS FOR ILLUSTRATIVE PURPOSES ONLY. THE FINAL FUNCTIONAL
SPECIFICATION WILL BE INCLUDED IN THE RFP UPON APPROVAL AND
IMPLEMENTATION OF THE COMPETITIVE PROCESS.
4. PROJECT OVERVIEW
4.1 PROPOSED FACILITY ADDITIONS
The objective of Fort McMurray area transmission bulk system reinforcement project (the
"project") is to increase transfer capability into the Fort McMurray area to supply load growth in
the Fort McMurray area.
The project consists of three stages of development. Projects identified in italics are NOT
considered components of the CTI Fort McMurray project. They are provided to identify
additional facilities that will influence the development of the Fort McMurray CTI project. The
AESO believes this information is required as bidders consider this project. Facilities identified
in italics will be direct assigned to incumbent TFOs.
The proposed facility additions and modifications of the project include the following:
Stage 1A (refer to Figure 3):
ƒ
Construct 500kV substation Thickwood Hills 951S with one (1) 500 kV circuit breaker,
one 500 kV 200 MVAr line-end reactor (size to be determined).
ƒ
Construct approximately 100 km of 500 kV transmission line 9L44 from Thickwood Hills
951S to Livock 939S using single circuit structures. The transmission line will be
operated at 240 kV.
ƒ
Add one (1) 240 kV circuit breaker at 240 kV Livock 939S substation.
ƒ
The target In Service Date (ISD) of stage 1A is approximately 2017.
Stage 1B (refer to Figure 4):
File No. RP-05-838
AESO Functional Specification
Page 3
Fort McMurray Area Transmission Bulk System Reinforecement Stage 1A - Rev. 1
ƒ
Add one (1) 500/240 kV 1200 MVA transformer, one 500 kV circuit breaker to Thickwood
Hills 951S.
ƒ
Construct approximately 390 km of 500 kV transmission line from Genesee 330P to
Livock 939S and connect the line to the 500 kV transmission line between Livock 939S
and Thickwood Hills 951S.
ƒ
Add two 500 kV circuit breakers and one 500 kV 200 MVAr line-end reactor at Genesee
330P.
ƒ
The target In Service Date (ISD) of stage 1B is approximately 2019.
Stage 2 (refer to Figure 5):
ƒ
Expand the Thickwood Hills 951S with the 2nd 500/240 kV 1200 MVA transformer, two
(2) 500 kV circuit breakers, one 500 kV 200 MVAr line-end reactor.
ƒ
Construct approximately 410 km of 500 kV transmission line from Thickwood Hills 951S
to Heartland 12S.
ƒ
Add two 500 kV circuit breakers and one (1) 500 kV 200 MVAr line-end reactor at
Heartland 12S.
ƒ
The target In Service Date (ISD) of stage 2 is approximately 2021.
4.2 SYSTEM DEVELOPMENT PRIOR TO THE PROJECT
The major system development prior to the project is expected to include the following additions
and modifications (refer to Figure 2):
Edmonton Region 240 kV Line Upgrades Project:
ƒ
Add one 600 MVA 240 kV phase shifting transformer on the existing 240 kV
transmission line 9L57 at Livock 939S.
Northeast Voltage Support Project:
ƒ
Add one 240 kV 100 MVAr capacitor bank at Dover 888S.
ƒ
Add one 240 kV 100 MVAr capacitor bank at Whitefish Lake 825S.
ƒ
Add two 138 kV 30 MVAr capacitor bank at Leismer 72S.
ET Energy Poplar Island Project:
ƒ
Construct 240 kV sub station Poplar Island 965S.
Livock 240/144kV Reinforcement Project:
ƒ
Construct 240 kV substation Livock 939S and re-terminate the Wesley-Brintnell line from
Brintnell 876S to Livock 939S.
Heartland Project:
ƒ
Construct 500 kV substation Heartland 12S with one (1) 500/240 kV 1200 MVA
transformers and four (4) 500 kV circuit breakers.
ƒ
Construct two 500 kV transmission lines from Ellerslie 89S to Heartland 12S.
Fort McMurray 240kV Transmission Development Project:
ƒ
Construct 240kV portion of the Thickwood Hills 951S substation, including 240kV switch
yard, one 240kV SVC (size to be determined) and two 240kV capacitor banks (size to be
determined).
File No. RP-05-838
AESO Functional Specification
Page 4
Fort McMurray Area Transmission Bulk System Reinforecement Stage 1A - Rev. 1
ƒ
Add one 240kV transmission line from Thickwood Hills 951S to Poplar Island 965S.
ƒ
Cut the existing 240 kV transmission line 9L07 open near Thickwood Hills 951S and
terminate both ends into Thickwood Hills 951S.
ƒ
Cut the existing 240 kV transmission line 9L58 between Ruth Lake 848S and Dover
888S. Construct approximately 32 km of 240 kV transmission line using single circuit
structures to terminate both ends of 9L58 line into Thickwood Hills 951S.
4.3 ULTIMATE SYSTEM DEVELOPMENT
The ultimate system development of the Fort McMurray area bulk system could include the
following additions and modifications (refer to Figure 6):
5.
ƒ
Add 500 kV series capacitor banks to the 500 kV transmission lines from Thickwood
Hills 951S to Genesee 330P and from Thickwood Hills 951S to Heartland 12S.
ƒ
Increase the capacity of each capacitor bank at Thickwood Hills 951S. Add dedicated
circuit breakers to the 500 kV line-end reactors.
ƒ
Relocate the phase shifting transformer at Livock 939S from 9L57 to 9L15.
THE ULTIMATE DEVELOPMENT REPRESENTS THE POTENTIAL LONG TERM
SYSTEM DEVELOPMENT, AND IS INCLUDED FOR SUBSTATION DEVELOPMENT
PLANNING PURPOSES ONLY. SCOPE OF WORK
5.1 GENERAL
The proponent is accountable for all engineering, design, land or land-use acquisition, siting,
applicable regulatory approvals and permits, material procurement, construction,
commissioning, and associated permitting requirements for their facilities. The proponent shall
coordinate as required on all design details (e.g., protection & control, grounding, insulation,
point of interconnection, site layout, power quality, etc.) and develop Joint Operating Procedures
and/or Interconnection Agreements as required to ensure that interconnected facilities are
operated safely and reliably.
All final design and as-built facility information shall be supplied in the format and content as
required by the AESO for purposes of updating and maintaining the AESO’s technical records
and system models. This information shall be submitted under signature of a registered
Professional Engineer in Alberta who is representing the facility owner and is assuming
responsibility for the preparation and accuracy of the submission. The AESO accepts no
responsibility for facilities designed by or for any third party, or installed on a third parties behalf,
to accomplish the interconnection. The facility owners shall ensure that their facilities have been
inspected and declared safe for operation prior to energization. No facilities are to be energized
until an Energization Certificate has been issued by the AESO.
5.2 STANDARDS
All work undertaken by the proponent must be designed, constructed, and operated to meet the
functional requirements of the Specification and all applicable standards, guidelines, codes and
regulations governing such installations including, but not limited those listed below. All AESO
documentation can be found on the AESO website (www.aeso.ca).
ƒ
AESO Operating Policies and Procedures
ƒ
AESO Measurement System Standard Rev 1 (dated September 18, 2007)
File No. RP-05-838
AESO Functional Specification
Page 5
Fort McMurray Area Transmission Bulk System Reinforecement Stage 1A - Rev. 1
ƒ
AESO Generation and Load Interconnection Standard (dated September 19, 2006)
ƒ
Technical Requirements (Part 3) for Connecting Transmission Facilities (dated
December 2, 1999)
ƒ
AESO Alberta Interconnected Electric System (AIES) Protection Standard (dated
December 1, 2004)
ƒ
AESO Operational Voice Communication Standard (dated September 7, 2005)
ƒ
AESO SCADA Standard (dated September 6, 2005)
ƒ
AESO Transmission Modeling Data Requirements (dated April 29, 2003)
ƒ
AESO PMU Requirements Version 2.0 (dated July 6, 2005)
ƒ
AESO Transmission Line Standard DRAFT (dated April 24, 2007)
ƒ
AESO Alberta Reliability Standards (in effect: January 22, 2010)
In case there is a discrepancy between this functional specification and the aforementioned
standards, this functional specification shall be the overriding requirement.
5.3 TRANSMISSION EQUIPMENT SPECIFICATIONS
5.3.1 General Environmental and Electrical Ratings
All transmission equipment must meet the following minimum specifications:
ƒ
Temperature rating of -50C for all outdoor equipment
ƒ
Minimum and maximum operating voltage ratings as indicated in Table 1
ƒ
Minimum continuous current ratings as indicated in Table 2
ƒ
Maximum fault levels as indicated in Table 3
Table 1: Minimum & Maximum Continuous Equipment Operating Voltages ( kV)
Area
500 kV
240 kV
Minimum
500
220
Maximum
550
285
Table 2: Minimum Continuous Equipment Current Ratings (A)
Component
500 kV
240 kV
Main Bus1
4000
4600
3000
3000
3000
3000
N/A
600
Cross Bus
2
Transmission Termination
3
Capacitor Bank Termination
4
1. Main bus includes all sections of ring bus scheme and single bus of simple bus scheme.
2. Cross bus includes diameter sections of breaker and a half or breaker and a third schemes.
3. Transmission termination includes all equipment from the connection to the cross bus up to the
transmission line connection point, usually the transmission line disconnect switch.
File No. RP-05-838
AESO Functional Specification
Page 6
Fort McMurray Area Transmission Bulk System Reinforecement Stage 1A - Rev. 1
4. Capacitor bank termination includes circuit breaker, isolating switches, CT's, pipe bus, risers, jumpers
and connectors.
Table 3: Maximum Fault Levels (kA)
Nominal Voltage
500 kV
240 kV
Maximum Fault
Levels
31.5
40
5.3.2 Circuit Breaker
A 500 kV circuit breaker shall satisfy the following specifications:
ƒ
The rated voltage shall be no less than the maximum continuous equipment operating
voltages listed in Table 1
ƒ
The rated continuous operating current shall be no less than the minimum continuous
equipment current ratings listed in Table 2
ƒ
The minimum symmetrical short-circuit breaking current rating shall be no less than the
maximum fault levels listed in Table 3
ƒ
The nominal interrupting time shall be no more than 2 cycles. The nominal interrupting
time is defined as the time interval between when a trip signal is received by the trip coil
of the circuit breaker and when the arc is extinguished in all poles. The nominal
interrupting time is applicable to interrupting currents with a magnitude ranges from zero
to the rated interrupting current.
ƒ
Be capable of single-pole operation
5.4 SCOPE OF WORK – STAGE 1A
5.4.1 500 kV Transmission Line 9L44
The scope of work for 500 kV transmission line 9L44 between Thickwood Hills 951S and Livock
939S includes the following (refer to Figure 3):
ƒ
Construct approximately 100 km of 500 kV transmission line 9L44 from Thickwood Hills
951S to Livock 939S (the "line 9L44") using single circuit structures. The circuit will be
energized at 240 kV at stage 1A and the circuit will be numbered as 12L44 after it is
energized to 500 kV in the future.
ƒ
The minimum continuous capacity of the line 9L44 shall be no less than 2400 MVA
(2771 A at 500 kV). The actual line ratings shall be submitted to AESO in the form of a
Summer rating at 30 degrees Celsius and a Winter rating at 0 degrees Celsius. The
ratings shall be for an assumed wind speed of 0.6 m/s.
ƒ
The design and routing of the line 9L44 shall allow live line maintenance and shall
consider that the line could be series compensated in the future. For example, open
right-of-way on one side may be considered for line routing to accommodate live line
maintenance requirement.
ƒ
The line 9L44 shall have optical fiber composite overhead ground wire (OPGW).
File No. RP-05-838
AESO Functional Specification
Page 7
Fort McMurray Area Transmission Bulk System Reinforecement Stage 1A - Rev. 1
ƒ
The detail design of the structures and line optimization will be undertaken by the
proponent.
ƒ
From a system reliability perspective, the minimum separation distance between
structures of parallel transmission lines is to be selected so that a 240 kV structure
failure will not affect a 500 kV structure, however a 500 kV structure failure can affect a
240 kV structure. The reason for this is to avoid having a 'lower' reliability transmission
line affect a 'higher' reliability line.
ƒ
In circumstances where a 500 kV transmission line crosses over one or more 240 kV
transmission lines, a 500 kV conductor failure should not affect more than one 240 kV
transmission circuit. In locations where this criterion is impractical to achieve, TFO is to
advise the AESO of the specific details.
ƒ
The demarcation points of line 9L44 are the first transmission line structures outside the
fence of Thickwood Hills 951S and Livock 939S. Line 9L44 between the two
demarcation points will be owned by the proponent. Line 9L44 outside the demarcation
point will be deemed as part of substation Thickwood Hills 951S or Livock 939S and will
be owned by ATCO.
5.4.2 500kV Substation Thickwood Hills 951S
The scope of work at Thickwood Hills 951S includes the following (refer to Figure 3):
Transmission Equipment:
ƒ
Add one (1) 500 kV circuit breaker meeting the specification outlined in section 5.3.2
ƒ
Add 500 kV bus into simple bus configuration that can be developed into folded breaker
and a half configuration in the future. Each diameter of the folded breaker and a half
shall have space for two line bays at either side of the bus.
ƒ
Add one 500 kV 200 MVAr line-end reactor with the provision of space to add a
dedicated reactor switching breaker in the future. The size and type of the line-end
reactor, as well as the neutral reactor for the line-end reactor need to be determined
through future studies.
ƒ
The design of the substation shall consider the future and ultimate development of the
project, as outlined in sections 4.3 and 4.4.
Protection and Control:
ƒ
The fault clearing system needs to cover all fault types and meet the associated
maximum fault clearing times.
ƒ
The fault clearing system is generally defined to include:
o
Current and voltage instrument transformers
o
Protection relays
o
Teleprotection communication equipment
o
Circuit breakers
o
All functionally associated equipment
File No. RP-05-838
AESO Functional Specification
Page 8
Fort McMurray Area Transmission Bulk System Reinforecement Stage 1A - Rev. 1
ƒ
Anticipated fault clearing times are to be calculated by adding the maximum operating
time of all applicable equipment comprising the fault clearing system, without additional
undefined time margin.
ƒ
The maximum operating time for each type of equipment, where applicable, is to include
the variation of operating time associated with all possible fault inception times within the
60 Hz waveform.
ƒ
The actual maximum operating time for the equipment is to be confirmed through test
measurement of the equipment, with the applicable specific configuration and settings
applied. Results of the test measurement shall be provided to the AESO.
ƒ
The source impedance ratio (SIR) is to be included when determining equipment
operating speeds to meet the required maximum fault clearing times.
ƒ
A single point of failure within the fault clearing system shall not cause a loss or
diminishment of the functionality, with the exception of the primary winding of instrument
transformers.
ƒ
The fault clearing system also needs to meet the functional requirement specified by the
AESO AIES Protection Standard (“the Standard”), with the following exceptions:
o
The maximum fault clearing times described within this Functional Specification
are to be used
o
The types of fault detection equipment or methods is not restricted to those
described within the Standard
ƒ
The existing fault clearing, control systems and settings are to be reviewed and modified
to accommodate the proposed equipment additions.
ƒ
If the fault clearing system includes teleprotection communication equipment, the
associated teleprotection communication equipment is to meet the requirements in the
AESO standards and the following WECC guidelines:
ƒ
o
WECC Guidelines for the Design of Critical Communications Circuits (revised
October 2002)
o
WECC Communications Systems Performance Guide for Protective Relaying
Application (dated November 2001)
In case there is a discrepancy between AESO standards and the WECC guidelines
regarding communication requirements, the discrepancy shall be brought to the AESO
for review.
SCADA:
ƒ
Provide SCADA information for the proposed equipment additions and modifications as
required by the AESO SCADA Standard.
ƒ
Control Center data mapping and verification of SCADA information for the proposed
equipment additions and modifications.
5.4.3 240 kV Substation Livock 939S – THIS IS NOT PART OF THE BID
PACKAGE. IT HAS BEEN PROVIDED FOR INFORMATIONAL PURPOSES
ONLY.
The scope of work at Livock 939S includes the following (refer to Figure 3):
File No. RP-05-838
AESO Functional Specification
Page 9
Fort McMurray Area Transmission Bulk System Reinforecement Stage 1A - Rev. 1
Transmission Equipment:
ƒ
Add one (1) 240 kV circuit breaker meeting the specification outlined in section 5.3.2 to
terminate line 9L44
Protection and Control:
ƒ
The fault clearing system needs to cover all fault types and meet the associated
maximum fault clearing times listed in the tables above.
ƒ
The fault clearing system is generally defined to include:
o
Current and voltage instrument transformers
o
Protection relays
o
Teleprotection communication equipment
o
Circuit breakers
o
All functionally associated equipment
ƒ
Anticipated fault clearing times are to be calculated by adding the maximum operating
time of all applicable equipment comprising the fault clearing system, without additional
undefined time margin.
ƒ
The maximum operating time for each type of equipment, where applicable, is to include
the variation of operating time associated with all possible fault inception times within the
60 Hz waveform.
ƒ
The actual maximum operating time for the equipment is to be confirmed through test
measurement of the equipment, with the applicable specific configuration and settings
applied. Results of the test measurement shall be provided to the AESO.
ƒ
The source impedance ratio (SIR) is to be included when determining equipment
operating speeds to meet the required maximum fault clearing times.
ƒ
A single point of failure within the fault clearing system shall not cause a loss or
diminishment of the functionality, with the exception of the primary winding of instrument
transformers.
ƒ
The fault clearing system also needs to meet the functional requirement specified by the
AESO AIES Protection Standard (“the Standard”), with the following exceptions:
o
The maximum fault clearing times described within this Functional Specification
are to be used
o
The types of fault detection equipment or methods is not restricted to those
described within the Standard
ƒ
The existing fault clearing, control systems and settings are to be reviewed and modified
to accommodate the proposed equipment additions.
ƒ
If the fault clearing system includes teleprotection communication equipment, the
associated teleprotection communication equipment is to meet the requirements in the
AESO standards and the following WECC guidelines:
o
WECC Guidelines for the Design of Critical Communications Circuits (revised
October 2002)
o
WECC Communications Systems Performance Guide for Protective Relaying
Application (dated November 2001)
File No. RP-05-838
AESO Functional Specification
Page 10
Fort McMurray Area Transmission Bulk System Reinforecement Stage 1A - Rev. 1
ƒ
In case there is a discrepancy between AESO standards and the WECC guidelines
regarding communication requirements, the discrepancy shall be brought to the AESO
for review.
SCADA:
ƒ
Provide SCADA information for the proposed equipment additions and modifications as
required by the AESO SCADA Standard.
ƒ
Control Center data mapping and verification of SCADA information for the proposed
equipment additions and modifications.
5.5 SCOPE OF WORK – STAGE 1B
5.5.1 500 kV Transmission Line 12L44
The scope of work for 500 kV transmission line 12L44 between Thickwood Hills 951S and
Genesee 330P includes the following (refer to Figure 4):
ƒ
Construct approximately 390 km of 500 kV transmission line from Genesee 330P to
Livock 939S using single circuit structures.
ƒ
Disconnect 9L44 from Livock 939S and connect 9L44 to the new 500kV line from
Genesee 330P to develop a 500kV line between Thickwood Hills 951S and Genesee
330P. Number the line as 12L44.
ƒ
The minimum continuous capacity of the line 12L44 shall be no less than 2400 MVA
(2771 A at 500 kV). The actual line ratings shall be submitted to AESO in the form of a
Summer rating at 30 degrees Celsius and a Winter rating at 0 degrees Celsius. The
ratings shall be for an assumed wind speed of 0.6 m/s.
ƒ
The design and routing of the line 12L44 shall allow live line maintenance and shall
consider that the line could be series compensated in the future. For example, open
right-of-way on one side may be considered for line routing to accommodate live line
maintenance requirement.
ƒ
The line 12L44 shall have optical fiber composite overhead ground wire (OPGW).
ƒ
The detail design of the structures and line optimization will be undertaken by the TFO.
For PPS cost estimate purpose, the conductor can be assumed to be ACSR 3x1590.
ƒ
From a system reliability perspective, the minimum separation distance between
structures of parallel transmission lines is to be selected so that a 240 kV structure
failure will not affect a 500 kV structure, however a 500 kV structure failure can affect a
240 kV structure. The reason for this is to avoid having a 'lower' reliability transmission
line affect a 'higher' reliability line.
ƒ
In circumstances where a 500 kV transmission line crosses over one or more 240 kV
transmission lines, a 500 kV conductor failure should not affect more than one 240 kV
transmission circuit. In locations where this criterion is impractical to achieve, TFO is to
advise the AESO of the specific details.
ƒ
The demarcation points of line 12L44 are the first transmission line structures outside
the fence of Thickwood Hills 951S and Genesee 330P. Line 12L44 between the two
File No. RP-05-838
AESO Functional Specification
Page 11
Fort McMurray Area Transmission Bulk System Reinforecement Stage 1A - Rev. 1
demarcation points will be owned by one TFO. Line 12L44 outside the demarcation point
will be deemed as part of the substation Thichwood Hills 951S or Genesee 330P and will
be owned by ATCO and EPCOR respectively.
5.5.2 500kV Substation Thickwood Hills 951S
The scope of work at Thickwood Hills 951S includes the following (refer to Figure 4):
Transmission Equipment:
ƒ
Add one (1) 500/240 kV autotransformer bank at Thickwood Hills 951S meeting the
following specifications:
o
The maximum continuous capacity rating is 1200 MVA for the autotransformer
bank and 400 MVA for each single-phase unit. The minimum continuous rating,
without forced cooling, is 600 MVA for the autotransformer bank and 200 MVA for
each single-phase unit.
o
The rated voltage shall be no less than the maximum continuous equipment
operating voltages listed in Table 1.
o
Tertiary windings are not required.
o
The autotransformer bank shall be solidly grounded.
o
The impedance of the autotransformer bank shall be lower than….
o
The autotransformer bank shall have a De-Energized Tap Changer (“DETC”) on
the 500 kV side with a tap range of ±2×2.5% (500-550kV) for voltage variation on
the 500 kV side.
o
The emergency overload rating of the transformer shall be xx% for xx minutes,
followed by xx% for xx hours with a pre-overload of xx%. The overload capability
shall be achieved with normal loss of life.
o
Transformer loss evaluation shall be based on the cost of losses as $xx/kW for
both load losses and no load losses.
o
The autotransformer bank shall be able to be energized from a cold state at an
ambient temperature of -50°C.
ƒ
Add one (1) 500 kV circuit breaker meeting the specification outlined in section 5.3.2
ƒ
Add 500 kV bus into double bus double breaker configuration that can be developed into
folded breaker and a half configuration in the future. Each diameter of the folded breaker
and a half shall have space for two line bays at either side of the bus.
ƒ
The design of the substation shall consider the ultimate development of the project, as
outlined in sections 4.3.
Protection and Control:
ƒ
The fault clearing system needs to cover all fault types and meet the associated
maximum fault clearing times listed in the tables above.
ƒ
The fault clearing system is generally defined to include:
o
Current and voltage instrument transformers
o
Protection relays
File No. RP-05-838
AESO Functional Specification
Page 12
Fort McMurray Area Transmission Bulk System Reinforecement Stage 1A - Rev. 1
o
Teleprotection communication equipment
o
Circuit breakers
o
All functionally associated equipment
ƒ
Anticipated fault clearing times are to be calculated by adding the maximum operating
time of all applicable equipment comprising the fault clearing system, without additional
undefined time margin.
ƒ
The maximum operating time for each type of equipment, where applicable, is to include
the variation of operating time associated with all possible fault inception times within the
60 Hz waveform.
ƒ
The actual maximum operating time for the equipment is to be confirmed through test
measurement of the equipment, with the applicable specific configuration and settings
applied. Results of the test measurement shall be provided to the AESO.
ƒ
The source impedance ratio (SIR) is to be included when determining equipment
operating speeds to meet the required maximum fault clearing times.
ƒ
A single point of failure within the fault clearing system shall not cause a loss or
diminishment of the functionality, with the exception of the primary winding of instrument
transformers.
ƒ
The fault clearing system also needs to meet the functional requirement specified by the
AESO AIES Protection Standard (“the Standard”), with the following exceptions:
o
The maximum fault clearing times described within this Functional Specification
are to be used
o
The types of fault detection equipment or methods is not restricted to those
described within the Standard
ƒ
The existing fault clearing, control systems and settings are to be reviewed and modified
to accommodate the proposed equipment additions.
ƒ
If the fault clearing system includes teleprotection communication equipment, the
associated teleprotection communication equipment is to meet the requirements in the
AESO standards and the following WECC guidelines:
ƒ
o
WECC Guidelines for the Design of Critical Communications Circuits (revised
October 2002)
o
WECC Communications Systems Performance Guide for Protective Relaying
Application (dated November 2001)
In case there is a discrepancy between AESO standards and the WECC guidelines
regarding communication requirements, the discrepancy shall be brought to the AESO
for review.
SCADA:
ƒ
Provide SCADA information for the proposed equipment additions and modifications as
required by the AESO SCADA Standard.
ƒ
Control Center data mapping and verification of SCADA information for the proposed
equipment additions and modifications.
File No. RP-05-838
AESO Functional Specification
Page 13
Fort McMurray Area Transmission Bulk System Reinforecement Stage 1A - Rev. 1
5.5.3 500kV Substation Genesee 330P - THIS IS NOT PART OF THE BID
PACKAGE. IT HAS BEEN PROVIDED FOR INFORMATIONAL PURPOSES
ONLY.
The scope of work at Genesee 330P includes the following (refer to Figure 4):
Transmission Equipment:
ƒ
Add two (2) 500 kV circuit breakers meeting the specification outlined in section 5.3.2
ƒ
Add one 500 kV 200 MVAr line-end reactor with the provision of space to add a
dedicated reactor switching breaker in the future. The size and type of the line-end
reactor, as well as the neutral reactor for the line-end reactor need to be determined
through future studies.
Protection and Control:
ƒ
The fault clearing system needs to cover all fault types and meet the associated
maximum fault clearing times listed in the tables above.
ƒ
The fault clearing system is generally defined to include:
o
Current and voltage instrument transformers
o
Protection relays
o
Teleprotection communication equipment
o
Circuit breakers
o
All functionally associated equipment
ƒ
Anticipated fault clearing times are to be calculated by adding the maximum operating
time of all applicable equipment comprising the fault clearing system, without additional
undefined time margin.
ƒ
The maximum operating time for each type of equipment, where applicable, is to include
the variation of operating time associated with all possible fault inception times within the
60 Hz waveform.
ƒ
The actual maximum operating time for the equipment is to be confirmed through test
measurement of the equipment, with the applicable specific configuration and settings
applied. Results of the test measurement shall be provided to the AESO.
ƒ
The source impedance ratio (SIR) is to be included when determining equipment
operating speeds to meet the required maximum fault clearing times.
ƒ
A single point of failure within the fault clearing system shall not cause a loss or
diminishment of the functionality, with the exception of the primary winding of instrument
transformers.
ƒ
The fault clearing system also needs to meet the functional requirement specified by the
AESO AIES Protection Standard (“the Standard”), with the following exceptions:
o
The maximum fault clearing times described within this Functional Specification
are to be used
o
The types of fault detection equipment or methods is not restricted to those
described within the Standard
File No. RP-05-838
AESO Functional Specification
Page 14
Fort McMurray Area Transmission Bulk System Reinforecement Stage 1A - Rev. 1
ƒ
The existing fault clearing, control systems and settings are to be reviewed and modified
to accommodate the proposed equipment additions.
ƒ
If the fault clearing system includes teleprotection communication equipment, the
associated teleprotection communication equipment is to meet the requirements in the
AESO standards and the following WECC guidelines:
ƒ
o
WECC Guidelines for the Design of Critical Communications Circuits (revised
October 2002)
o
WECC Communications Systems Performance Guide for Protective Relaying
Application (dated November 2001)
In case there is a discrepancy between AESO standards and the WECC guidelines
regarding communication requirements, the discrepancy shall be brought to the AESO
for review.
SCADA:
ƒ
Provide SCADA information for the proposed equipment additions and modifications as
required by the AESO SCADA Standard.
ƒ
Control Center data mapping and verification of SCADA information for the proposed
equipment additions and modifications.
5.6 SCOPE OF WORK – STAGE 2
5.6.1 500 kV Transmission Line Thickwood Hills to Heartland
The scope of work for 500 kV transmission line between Thickwood Hills 951S and Heartland
12S (Thickwood – Heartland line) includes the following (refer to Figure 5):
ƒ
Construct approximately 410 km of 500 kV transmission line from Thickwood Hills 951S
to Heartland 12S using single circuit structures.
ƒ
The minimum continuous capacity of the Thickwood-Heartland line shall be no less than
2400 MVA (2771 A at 500 kV). The actual line ratings shall be submitted to AESO in the
form of a Summer rating at 30 degrees Celsius and a Winter rating at 0 degrees Celsius.
The ratings shall be for an assumed wind speed of 0.6 m/s.
ƒ
The design and routing of the Thickwood-Heartland line shall allow live line maintenance
and shall consider that the line could be series compensated in the future. For example,
open right-of-way on one side may be considered for line routing to accommodate live
line maintenance requirement.
ƒ
The Thickwood-Heartland line shall have optical fiber composite overhead ground wire
(OPGW).
ƒ
From a system reliability perspective, the minimum separation distance between
structures of parallel transmission lines is to be selected so that a 240 kV structure
failure will not affect a 500 kV structure, however a 500 kV structure failure can affect a
240 kV structure. The reason for this is to avoid having a 'lower' reliability transmission
line affect a 'higher' reliability line.
ƒ
In circumstances where a 500 kV transmission line crosses over one or more 240 kV
transmission lines, a 500 kV conductor failure should not affect more than one 240 kV
File No. RP-05-838
AESO Functional Specification
Page 15
Fort McMurray Area Transmission Bulk System Reinforecement Stage 1A - Rev. 1
transmission circuit. In locations where this criterion is impractical to achieve, TFO is to
advise the AESO of the specific details.
ƒ
The demarcation points of the Thickwood-Heartland line are the first transmission line
structures outside the fence of Thickwood Hills 951S and Heartland 12S. The
Thickwood-Heartland line between the two demarcation points will be owned by one
TFO. Thickwood-Heartland line outside the demarcation point will be deemed as part of
the substation Thichwood Hills 951S or Heartland 12S and will be owned by ATCO and
AltaLink respectively.
5.6.2 500kV Substation Thickwood Hills 951S
The scope of work at Thickwood Hills 951S includes the following (refer to Figure 5):
Transmission Equipment:
ƒ
Add one (1) 500/240 kV autotransformer bank at Thickwood Hills 951S meeting the
following specifications:
o
The maximum continuous capacity rating is 1200 MVA for the autotransformer
bank and 400 MVA for each single-phase unit. The minimum continuous rating,
without forced cooling, is 600 MVA for the autotransformer bank and 200 MVA for
each single-phase unit.
o
The rated voltage shall be no less than the maximum continuous equipment
operating voltages listed in Table 1.
o
Tertiary windings are not required.
o
The autotransformer bank shall be solidly grounded.
o
The impedance of the autotransformer bank shall be lower than….
o
The autotransformer bank shall have a De-Energized Tap Changer (“DETC”) on
the 500 kV side with a tap range of ±2×2.5% (500-550kV) for voltage variation on
the 500 kV side.
o
The emergency overload rating of the transformer shall be xx% for xx minutes,
followed by xx% for xx hours with a pre-overload of xx%. The overload capability
shall be achieved with normal loss of life.
o
Transformer loss evaluation shall be based on the cost of losses as $xx/kW for
both load losses and no load losses.
o
The autotransformer bank shall be able to be energized from a cold state at an
ambient temperature of -50°C.
ƒ
Add two (2) 500 kV circuit breakers meeting the specification outlined in section 5.3.2
ƒ
Add one 500 kV 200 MVAr line-end reactor with the provision of space to add a
dedicated reactor switching breaker in the future. The size and type of the line-end
reactor, as well as the neutral reactor for the line-end reactor need to be determined
through future studies.
ƒ
The design of the substation shall consider the ultimate development of the project, as
outlined in sections 4.3.
Protection and Control:
File No. RP-05-838
AESO Functional Specification
Page 16
Fort McMurray Area Transmission Bulk System Reinforecement Stage 1A - Rev. 1
ƒ
The fault clearing system needs to cover all fault types and meet the associated
maximum fault clearing times listed in the tables above.
ƒ
The fault clearing system is generally defined to include:
o
Current and voltage instrument transformers
o
Protection relays
o
Teleprotection communication equipment
o
Circuit breakers
o
All functionally associated equipment
ƒ
Anticipated fault clearing times are to be calculated by adding the maximum operating
time of all applicable equipment comprising the fault clearing system, without additional
undefined time margin.
ƒ
The maximum operating time for each type of equipment, where applicable, is to include
the variation of operating time associated with all possible fault inception times within the
60 Hz waveform.
ƒ
The actual maximum operating time for the equipment is to be confirmed through test
measurement of the equipment, with the applicable specific configuration and settings
applied. Results of the test measurement shall be provided to the AESO.
ƒ
The source impedance ratio (SIR) is to be included when determining equipment
operating speeds to meet the required maximum fault clearing times.
ƒ
A single point of failure within the fault clearing system shall not cause a loss or
diminishment of the functionality, with the exception of the primary winding of instrument
transformers.
ƒ
The fault clearing system also needs to meet the functional requirement specified by the
AESO AIES Protection Standard (“the Standard”), with the following exceptions:
o
The maximum fault clearing times described within this Functional Specification
are to be used
o
The types of fault detection equipment or methods is not restricted to those
described within the Standard
ƒ
The existing fault clearing, control systems and settings are to be reviewed and modified
to accommodate the proposed equipment additions.
ƒ
If the fault clearing system includes teleprotection communication equipment, the
associated teleprotection communication equipment is to meet the requirements in the
AESO standards and the following WECC guidelines:
ƒ
o
WECC Guidelines for the Design of Critical Communications Circuits (revised
October 2002)
o
WECC Communications Systems Performance Guide for Protective Relaying
Application (dated November 2001)
In case there is a discrepancy between AESO standards and the WECC guidelines
regarding communication requirements, the discrepancy shall be brought to the AESO
for review.
SCADA:
File No. RP-05-838
AESO Functional Specification
Page 17
Fort McMurray Area Transmission Bulk System Reinforecement Stage 1A - Rev. 1
ƒ
Provide SCADA information for the proposed equipment additions and modifications as
required by the AESO SCADA Standard.
ƒ
Control Center data mapping and verification of SCADA information for the proposed
equipment additions and modifications.
5.6.3 500kV Substation Heartland 12S - THIS IS NOT PART OF THE BID
PACKAGE. IT HAS BEEN PROVIDED FOR INFORMATIONAL PURPOSES
ONLY.
The scope of work at Heartland 12S includes the following (refer to Figure 5):
Transmission Equipment:
ƒ
Add two (2) 500 kV circuit breakers meeting the specification outlined in section 5.3.2
ƒ
Add one 500 kV 200 MVAr line-end reactor with the provision of space to add a
dedicated reactor switching breaker in the future. The size and type of the line-end
reactor, as well as the neutral reactor for the line-end reactor need to be determined
through future studies.
Protection and Control:
ƒ
The fault clearing system needs to cover all fault types and meet the associated
maximum fault clearing times listed in the tables above.
ƒ
The fault clearing system is generally defined to include:
o
Current and voltage instrument transformers
o
Protection relays
o
Teleprotection communication equipment
o
Circuit breakers
o
All functionally associated equipment
ƒ
Anticipated fault clearing times are to be calculated by adding the maximum operating
time of all applicable equipment comprising the fault clearing system, without additional
undefined time margin.
ƒ
The maximum operating time for each type of equipment, where applicable, is to include
the variation of operating time associated with all possible fault inception times within the
60 Hz waveform.
ƒ
The actual maximum operating time for the equipment is to be confirmed through test
measurement of the equipment, with the applicable specific configuration and settings
applied. Results of the test measurement shall be provided to the AESO.
ƒ
The source impedance ratio (SIR) is to be included when determining equipment
operating speeds to meet the required maximum fault clearing times.
ƒ
A single point of failure within the fault clearing system shall not cause a loss or
diminishment of the functionality, with the exception of the primary winding of instrument
transformers.
ƒ
The fault clearing system also needs to meet the functional requirement specified by the
AESO AIES Protection Standard (“the Standard”), with the following exceptions:
File No. RP-05-838
AESO Functional Specification
Page 18
Fort McMurray Area Transmission Bulk System Reinforecement Stage 1A - Rev. 1
o
The maximum fault clearing times described within this Functional Specification
are to be used
o
The types of fault detection equipment or methods is not restricted to those
described within the Standard
ƒ
The existing fault clearing, control systems and settings are to be reviewed and modified
to accommodate the proposed equipment additions.
ƒ
If the fault clearing system includes teleprotection communication equipment, the
associated teleprotection communication equipment is to meet the requirements in the
AESO standards and the following WECC guidelines:
ƒ
o
WECC Guidelines for the Design of Critical Communications Circuits (revised
October 2002)
o
WECC Communications Systems Performance Guide for Protective Relaying
Application (dated November 2001)
In case there is a discrepancy between AESO standards and the WECC guidelines
regarding communication requirements, the discrepancy shall be brought to the AESO
for review.
SCADA:
ƒ
Provide SCADA information for the proposed equipment additions and modifications as
required by the AESO SCADA Standard.
ƒ
Control Center data mapping and verification of SCADA information for the proposed
equipment additions and modifications.
TRANSMISSION SYSTEM OPERATING CHARACTERISTICS
The following sections provide data to outline the electrical environment in which the facilities
outlined in the Specification will operate. Proponents shall incorporate these characteristics into
their facility designs and operating procedures as deemed appropriate.
5.7 SHORT CIRCUIT CURRENT LEVELS
The following short circuit current levels in Table 4 and Table 7 have been developed by the
AESO based on information provided by Transmission Facility Owners (“TFO’s”), Generation
Facility Owners ("GFO’s") and adjacent operating areas. Available fault current levels will
continue to increase as generation, transmission, and system inter-ties are added to the ATS.
Affected TFO's, GFO's and customers providing their own transmission facilities should
consider this eventuality and exercise good engineering judgment in the specification of power
interrupting equipment and the design and installation of safety grounding systems in and
around high voltage power transmission lines and stations. The AESO cannot guarantee and
accepts no responsibility for short circuit current growth that may exceed the capabilities of TFO
or customer electric power delivery systems and equipment.
Table 4: Area 2015-2017 Anticipated Short Circuit Levels with Proposed Development
Substation Name
and Number
File No. RP-05-838
Base
Voltage
( kV)
Pre-Fault
Voltage
(p.u.)
3-Φ
Fault
(kA)
Positive Sequence
Impedance
(R1 + j X1)
AESO Functional Specification
Page 19
Fort McMurray Area Transmission Bulk System Reinforecement Stage 1A - Rev. 1
(p.u.)
Thickwood Hills 951S
240
Livock 939S
240
Poplar Island 965S
240
Dover 888S
240
Ruth Lake 848S
240
McMillan 885S
240
NOTES: Vbase= Vbus ; MVAbase= 100.
Table 5: Area 2021-2023 Anticipated Short Circuit Levels with Ultimate Development
Substation Name
and Number
Base
Voltage
( kV)
Thickwood Hills 951S
500
Thickwood Hills 951S
240
Livock 939S
240
Poplar Island 965S
240
Dover 888S
240
Ruth Lake 848S
240
McMillan 885S
240
Pre-Fault
Voltage
(p.u.)
3-Φ
Fault
(kA)
Positive Sequence
Impedance
(R1 + j X1)
(p.u.)
NOTES: Vbase= Vbus ; MVAbase= 100.
5.8 VOLTAGE LEVELS
Table 6 provides the acceptable ranges of steady state voltage in the area of the proposed
system modifications and additions. Please refer to AESO Transmission Reliability Criteria,
Part II System Planning, Section 5.1, voltage standards for detail information. The document
can be found through the following link:
http://www.aeso.ca/downloads/TransmissionReliabilityCriteriaVersion0cleancopup
art2systemplanning.pdf
Table 6: Acceptable Range of Steady State Voltage ( kV)
Nominal
500
240
Extreme Minimum
500
220
Normal Minimum
510
260
Normal Maximum
540
269
Extreme Maximum
550
285
File No. RP-05-838
AESO Functional Specification
Page 20
Fort McMurray Area Transmission Bulk System Reinforecement Stage 1A - Rev. 1
5.9 INSULATION LEVELS
Table 7 provides the required Basic Impulse Levels (“BIL”) levels for the ATS. Station
equipment with lower BIL levels can be used provided protection and coordination can be
maintained with judicious insulation design and use of appropriate surge arresting equipment.
Table 7: BIL Levels ( kV)
Nominal Voltage
Classification ( kV rms)
500
240
Transformer Windings
1425
950
Station Post Insulators and
Airbreaks
1550
1050
Circuit Breakers
1800
1050
Current and Potential
Transformers
1800
1050
File No. RP-05-838
AESO Functional Specification
Page 21
Fort McMurray Area Transmission Bulk System Reinforecement Stage 1A - Rev. 1
6. APPENDICES
6.1 SYSTEM CONFIGURATION - EXISTING
Figure 1: System Configuration – Existing
File No. RP-05-838
AESO Functional Specification
Page 22
Fort McMurray Area Transmission Bulk System Reinforecement Stage 1A - Rev. 1
6.2 SYSTEM CONFIGURATION –DEVELOPMENT PRIOR TO THE PROJECT
New Station
CNRL
IOL Kearl
9L900
Aurora
Joslyn
Creek
849S
Thickwood Hills substation
951S – 240kV portion
9L08
9L09
Shell
Jackpine
9L43
MacKay
River
874S
Muskeg
River
847S
Black Fly
9L01
Dover 888S
Millennium
Syncrude
D05
9L58
9L07
Cap Bank
9L57
+90 /-75 MVAR
SVC
9L01
Wesley
Creek
834S
Ruth Lake
848S
9L58
9L68
9L30
9L990
Ivanhoe
9L57
9L91
9L15
Livock
911S
Paplor Island
965S
Q3/2012
ATCO Scope
of Work
9L07
Wabasca
720S
Kinosis
856S
Brintnel
876S
9L56
Mitsue
732S
9L990
McMillan
885S
Little
Smoky
813S
Conklin
762S
ATCO Service
Area
9L55
To be
determined
9L40
Lousie
Creek
809S
9L05
937L
971L
Christina
Lake 841S
Heartlake
898S
9L930
9L22
Heartland
AltaLink Service 12S
Area
North
Barrhead
69S
938L
957L
Leismer
72S
9L02
Alberta
Newsprint
122S
Salt Creek
977S
Thickwood Hills
951S
9L11
Whitefish
825S
9L37
HVDC
9L36
907L
913L
Sagitawah
77S
919L
9L36
9L960
Marguerite
Lake 826S
Deerland
13S
989L
Wabamun
19S
947L
905L
Castle
Downs
557S
North
Calder
37S
Josephburg
410S
Lamoureux
71S
Jasper
805S
902L
973L
Victoria
Bickerdile
39S
902L
909L
Petrolia
816S
913L
1055L
Bellamy
814S
1056L
1045L
922L
Sundance
310P
190L
1203L
1057L
909L
908L
946L
High
Z%
947L
Legend
TFO service area boundary
PST
Ellerslie 89S
KH1
KH2
Keephills
320P
1209L
Low
Z%
910L
914L
500kV overhead lines
240kV overhead lines
138kV or lower overhead lines
240kV underground cables
KH3
structure
To be
determined
EDTI Service
Area
HVDC
Fort McMurray 240kV
development project
Heartland project
G1 G2 G3
Genesee 330P
To Benalto
17S
To
Southern
Alberta
908L
1202L
903L
ATCO Service
Area
Summerside
675S
Dome
665S
1043L
Clover Bar
E987S
East
Edmonton
38S
To Benalto
17S
To
Southern
Alberta
East & West HVDC project
Other 240kV projects
To Red
Deer 63S
Salvage facilities
Figure 2: System Configuration –Development Prior to the Project
File No. RP-05-838
AESO Functional Specification
Page 23
Fort McMurray Area Transmission Bulk System Reinforecement Stage 1A - Rev. 1
6.3 SYSTEM CONFIGURATION – PROPOSED DEVELOPMENT - STAGE 1A
New Station
CNRL
IOL Kearl
9L900
Aurora
Joslyn
Creek
849S
Thickwood Hills substation
951S – 500kV portion stage 1A
9L08
9L09
Shell
Jackpine
9L43
MacKay
River
874S
Muskeg
River
847S
Black Fly
9L01
Dover 888S
Millennium
Syncrude
D05
9L58
9L07
9L57
Cap Bank
9L01
SVC
Wesley
Creek
834S
Ruth Lake
848S
9L58
9L68
9L30
9L990
Ivanhoe
9L91
9L57
9L15
Livock
911S
Paplor Island
965S
9L44
9L11
ATCO Scope
of Work
9L07
Wabasca
720S
9L56
Mitsue
732S
9L990
McMillan
885S
ATCO Service
Area
9L55
To be
determined
9L40
Lousie
Creek
809S
937L
957L
971L
Christina
Lake 841S
Heartlake
898S
9L930
9L22
Heartland
AltaLink Service 12S
Area
North
Barrhead
69S
938L
Conklin
762S
Leismer
72S
9L02
Alberta
Newsprint
122S
Kinosis
856S
Brintnel
876S
Little
Smoky
813S
9L05
Salt Creek
977S
Thickwood Hills
951S
Dec 2013
Whitefish
825S
9L37
HVDC
9L36
907L
913L
Sagitawah
77S
919L
9L36
9L960
Marguerite
Lake 826S
Deerland
13S
989L
Wabamun
19S
947L
905L
Castle
Downs
557S
North
Calder
37S
Josephburg
410S
Lamoureux
71S
Jasper
805S
902L
973L
Victoria
Bickerdile
39S
902L
909L
Petrolia
816S
913L
1055L
Bellamy
814S
1056L
1045L
922L
Sundance
310P
190L
1203L
1057L
909L
908L
946L
High
Z%
947L
Legend
TFO service area boundary
PST
Ellerslie 89S
KH1
KH2
Keephills
320P
1209L
Low
Z%
910L
914L
500kV overhead lines
240kV overhead lines
138kV or lower overhead lines
240kV underground cables
KH3
structure
To be
determined
EDTI Service
Area
HVDC
Fort McMurray CTI stage 1A
Heartland project
G1 G2 G3
Genesee 330P
To Benalto
17S
To
Southern
Alberta
908L
1202L
903L
ATCO Service
Area
Summerside
675S
Dome
665S
1043L
Clover Bar
E987S
East
Edmonton
38S
To Benalto
17S
To
Southern
Alberta
East & West HVDC project
Other 240kV projects
To Red
Deer 63S
Figure 3: System Configuration – Proposed Development - Stage 1A
File No. RP-05-838
AESO Functional Specification
Page 24
Fort McMurray Area Transmission Bulk System Reinforecement Stage 1A - Rev. 1
6.4 SYSTEM CONFIGURATION – PROPOSED DEVELOPMENT – STAGE 1B
New Station
CNRL
IOL Kearl
9L900
Aurora
Joslyn
Creek
849S
Thickwood Hills Substation
951S – 500kV portion stage 1B
MacKay
River
874S
1x1200MVA
9L08
9L09
9L43
Shell
Jackpine
Muskeg
River
847S
Black Fly
9L01
Dover 888S
Millennium
Syncrude
D05
9L58
9L07
Cap Bank
9L57
SVC
Ruth Lake
848S
9L01
Wesley
Creek
834S
9L01
9L30
9L68
9L58
9L990
Ivanhoe
9L57
9L91
Livock
911S
Paplor Island
965S
Brintnel
876S
Salt Creek
977S
Thickwood Hills
951S
9L11
9L07
Kinosis
856S
Wabasca
720S
12L44
Mitsue
732S
9L56
9L990
McMillan
885S
Little
Smoky
813S
ATCO Service
Area
9L55
To be
determined
9L02
937L
Alberta
Newsprint
122S
9L40
Lousie
Creek
809S
9L05
957L
971L
Christina
Lake 841S
Heartlake
898S
9L930
9L22
Heartland
AltaLink Service 12S
Area
North
Barrhead
69S
938L
Conklin
762S
Leismer
72S
Whitefish
825S
9L37
HVDC
9L36
907L
913L
Sagitawah
77S
919L
Marguerite
Lake 826S
9L36
9L960
Deerland
13S
989L
Wabamun
19S
947L
905L
Castle
Downs
557S
North
Calder
37S
Josephburg
410S
Lamoureux
71S
Jasper
805S
902L
973L
Clover Bar
E987S
Victoria
Bickerdile
39S
902L
909L
Petrolia
816S
913L
1055L
Bellamy
814S
1056L
1045L
922L
Sundance
310P
190L
1203L
1057L
909L
908L
946L
High
Z%
947L
Legend
TFO service area boundary
PST
Ellerslie 89S
KH1
KH2
Keephills
320P
To
Southern
Alberta
908L
1202L
903L
ATCO Service
Area
Summerside
675S
Dome
665S
1043L
East
Edmonton
38S
1209L
Low
Z%
910L
914L
500kV overhead lines
240kV overhead lines
138kV or lower overhead lines
240kV underground cables
KH3
structure
To be
determined
EDTI Service
Area
HVDC
Fort McMurray CTI Stage 1B
Heartland project
G1 G2 G3
N-S project
Genesee 330P
To Benalto
17S
To Benalto
17S
To
Southern
Alberta
Other 240kV projects
To Red
Deer 63S
Figure 4: System Configuration – Proposed Development – Stage 1B
File No. RP-05-838
AESO Functional Specification
Page 25
Fort McMurray Area Transmission Bulk System Reinforecement Stage 1A - Rev. 1
6.5 SYSTEM CONFIGURATION – PROPOSED DEVELOPMENT – STAGE 2
New Station
Q4/2012
CNRL
9L900
IOL Kearl
Q2/2010
Aurora
Joslyn
Creek
849S
Thickwood Hills Substation
951S – 500kV portion Stage 2
2x1200MVA
9L08
9L09
Shell
Jackpine
9L43
MacKay
River
874S
Muskeg
River
847S
Black Fly
Q1/2012
9L01
9L01
Dover 888S
Cap Bank
Millennium
Syncrude
D05
9L58
9L07
9L57
SVC
Ruth Lake
848S
2x200 MVAR
Line-end
reactors
9L01
Wesley
Creek
834S
9L68 9L30
9L58
9L990
Ivanhoe
Q1/2013
9L57
Livock
911S
9L91Island
Paplor
965S
Q3/2012
Thickwood Hills
951S
Brintnel
876S
9L11
Salt Creek
977S
Q4/2011
9L07
Kinosis
856S
Wabasca
720S
12L44
Mitsue
732S
9L990
9L56
Little
Smoky
813S
McMillan
885S
ATCO Service
Area
9L55
To be
determined
9L02
9L05
937L
Alberta
Newsprint
122S
9L40
Lousie
Creek
809S
971L
9L930
9L22
AltaLink Service
Area
957L
Christina
Lake 841S
Heartlake
898S
Heartland
12S
North
Barrhead
69S
938L
Conklin
762S
Leismer
72S
Whitefish
825S
9L37
HVDC
9L36
907L
913L
Sagitawah
77S
919L
9L960
Marguerite
Lake 826S
9L36
Deerland
13S
989L
Wabamun
19S
947L
905L
Castle
Downs
557S
North
Calder
37S
Josephburg
410S
Lamoureux
71S
Jasper
805S
902L
973L
Victoria
Bickerdile
39S
902L
909L
Petrolia
816S
913L
1055L
Bellamy
814S
1056L
1045L
922L
Sundance
310P
1202L
909L
908L
946L
High
Z%
947L
Low
Z%
KH2
Keephills
320P KH3
Legend
Ellerslie 89S
1203L
1209L
910L
914L
Future
line
500kV overhead lines
240kV overhead lines
138kV or lower overhead lines
240kV underground cables
structure
To be
determined
EDTI Service
Area
HVDC
Fort McMurray CTI Stage 2
Heartland project
G1 G2 G3
N-S project
Genesee 330P
To Benalto
17S
To
Southern
Alberta
TFO service area boundary
PST
KH1
1057L
908L
190L
903L
ATCO Service
Area
Summerside
675S
Dome
665S
1043L
Clover Bar
E987S
East
Edmonton
38S
To Benalto
17S
To
Southern
Alberta
Other 240kV projects
To Red
Deer 63S
Figure 5: System Configuration – Proposed Development – Stage 2
File No. RP-05-838
AESO Functional Specification
Page 26
Fort McMurray Area Transmission Bulk System Reinforecement Stage 1A - Rev. 1
6.6 SYSTEM CONFIGURATION – ULTIMATE DEVELOPMENT
Figure 6: System Configuration – Ultimate Development
File No. RP-05-838
AESO Functional Specification
Page 27
Fly UP