...

Run II Status and Prospects Jeff Spalding Fermilab June 14, 2004

by user

on
Category: Documents
8

views

Report

Comments

Transcript

Run II Status and Prospects Jeff Spalding Fermilab June 14, 2004
Run II Status and Prospects
Jeff Spalding
Fermilab
June 14, 2004
Run II Status and Prospects - Spalding
1
Contents
ƒ
ƒ
ƒ
ƒ
ƒ
ƒ
Introduction
Major elements of the Run II “campaign”
Present performance
Status of the upgrade projects
Luminosity projection
Summary
Run II Status and Prospects - Spalding
2
Run II goal: maximize integrated luminosity delivered to CDF & D0 …
Run II Status and Prospects - Spalding
3
… with a program of upgrades throughout the complex
Recycler Ring
Run II Status and Prospects - Spalding
4
Basis for the Plan: What drives the luminosity
ƒ Peak Luminosity
L=
(, , , )
L
*

β
θ
ε
σ
F

N
3γ f0
x, y
p, p
p, p
p

BN

p
β*
 εp 
1+ εp εp
( )
(
)
εp, εpbar, form factor F, β* provide some gains
But major improvements from bunch intensities
¾ especially total number of pbars BNpbar, (B=36 bunches for Run II)
¾ proton brightness (Np/εp) is constrained by beam-beam tune shift
ƒ Luminosity lifetime (tunes, beam-beam interactions)
ƒ Reliable Operation
Run II Status and Prospects - Spalding
5
Major Elements of the Run II Campaign
Run II Status and Prospects - Spalding
6
Operational improvements and upgrade projects
Near Term (and ongoing)
ƒ Improved reliability and operating efficiency
¾ Failure modes, abort system improvements…
¾ Tevatron alignment
¾ Improved instrumentation throughout the complex
ƒ Optimization of transfers, improved optics and helices in
Tevatron
Upgrade Projects
ƒ Increase pbar production
¾ Slip stacking
¾ Pbar acceptance upgrade
¾ Stacking rate and stack size (stacktail, Recycler, e-cooling)
ƒ Upgrade Tevatron for higher bunch intensities
¾ Helix
¾ TEL: active beam-beam compensation
Run II Status and Prospects - Spalding
7
Reliability
ƒ The number of store hours per week is up 27% from FY03 the TEV is a more reliable machine.
ƒ Typical store length 15 hrs last year Æ >24 hrs now
ƒ Due to:
¾ Alignment of the TEV
• Dipole un-rolls, Low Beta alignment, Smart bolt retrofit
¾ Reliability strategy
• Aggressively pursue equipment failures
– Individual components and Systems (e.g. TEV abort system)
¾ Operations strategy
• With improved reliability Æ run long stores
– More time to ensure large stack size
– Minimize the effects of store turnaround time
– Minimize impact of parasitic studies
• Short focused dedicated studies
– Configuration control
Run II Status and Prospects - Spalding
8
Upgrade Projects
Dynamic plan – adjust the strategy when new information from
operations and project R&D
Major Elements
ƒ Increase number of protons on the pbar production target
¾ Slip stacking (5E12 Æ >8E12 protons on pbar target)
¾ Upgrade the target itself to handle higher intensity
ƒ Increase antiproton collection
¾ Increase the gradient of the antiproton collection lens
¾ Increase the aperture of the antiproton collection transfer line
(AP2) and the Debuncher ring.
ƒ Increase the antiproton stacking and storing capabilities
¾ Increase the flux capability of the Accumulator stacktail
stochastic cooling system.
¾ Use the Recycler as a second antiproton storage ring, with both
stochastic and electron cooling
ƒ Upgrade Tevatron to handle higher intensity bunches.
¾ Improvements to helix separation and smoothness
¾ Active compensation for beam-beam tune shift using the TEL
Run II Status and Prospects - Spalding
9
Status of Operations
Run I
Run II Status and Prospects - Spalding
10
Status: Integrated Luminosity
Compare the last 12 months to the year before
-1
Integrated Luminosity (pb )
300
250
Up 55% with 14% fewer
scheduled running weeks
200
Average integrated luminosity
per week is up 80%
6/03 - 6/04
6/02 - 6/03
FY04 Design
FY04 Base
150
100
50
0
0
30
60
90
120
150
180
210
240
270
300
330
360
390
Days Since June 1
Run II Status and Prospects - Spalding
11
Status: Peak Luminosity
Current best = 7.6E31 cm-2s-1
80
*
70
-1
Peak Luminosity ( b /sec)
60
50
6/03 - 6/04
6/02 - 6/03
FY04 Design
FY04 Base
40
30
20
10
0
0
30
60
90
120
150
180
210
240
270
300
330
360
390
Days Since June 1
Run II Status and Prospects - Spalding
12
Summary of Current Operations
ƒ Booster running at record intensities
ƒ Major improvements in transfer efficiencies and emittances,
TEV tunes, optics and helix
ƒ Improved reliability and operations allows longer stores Æ
larger stacks Æ higher luminosity
ƒ However, stacking rate is ~75% of current goal – present focus
of investigation and improvement for the stacktail and core
cooling systems
ƒ Near term: introduce mixed-source operation (pbars loaded
from both Accumulator and Recycler) – first [pilot] store
6/9/04 successful (6.7E31)
ƒ And slip-stacking by end of 04 ( already tested at 75% of design
intensity) – awaits completion of RF upgrade
Run II Status and Prospects - Spalding
13
Status of the Upgrade Projects
Run II Status and Prospects - Spalding
14
Main Injector
ƒ Slip Stacking (goal x1.8ppp on pbar tgt)
¾ Excellent progress
¾ Tested @ 6 x 1012 and 1.5 nsec bunch
length on pbar target
¾ Reliable operation >8 x 1012 requires RF
upgrade (beam-loading compensation)
¾ On track for end of this year.
Run II Status and Prospects - Spalding
15
Pbar Source
Pbar Acceptance (goal: x2)
ƒ
Lithium Lens (goal x 1.1)
¾ Prototype of new design (higher field gradient) bench test successful
ƒ
AP2 and Debuncher aperture increase (goal x1.8)
¾ Developed procedures for beam-based identification of limiting apertures,
identified components to modify
Stacktail cooling upgrade
ƒ
Cooling system upgrade (extends the bandwith 2-4 Æ2-6 GHz)
¾ Requires the large stack to be in Recycler (with e-cool), and “rapid
transfers”
¾ Not [easily] reversible
Æemphasize a phased approach
¾ Interim upgrade (05) [NEW]
• Reconfigure existing cooling tanks -quick and reversible
• Simulated performance ~30E10 per hr
¾ Full upgrade, with new cooling tanks (06)
• Simulated performance ~40E10 per hr
Run II Status and Prospects - Spalding
16
Recycler
ƒ
The Recycler has made excellent progress over the past year
¾ Transverse emittance growth is no longer an issue (vacuum problems solved)
¾ Met the performance specs needed for commissioning electron cooling
¾ Ready to be integrated into operations (with stochastic cooling)
Æ Provides possibility for interim operating phase [NEW]
ƒ
Extract pbars from both Accumulator and Recycler: “mixed-source”
ƒ
Reasons
¾ e.g. 24 bunches from the Accumulator + 12 bunches from the Recycler
¾ A few (2-4) interim transfers from Accumulator to Recycler
¾ Improves average stacking rate in the Accumulator
¾ Push Recycler commissioning progress by plunging it into operations
¾ Potential luminosity enhancement – more pbars for smaller emittances
• Break-even right now, potential for up to 20% gain in the next year
¾ Flexibility in the Run II Upgrade schedule
• Merge more naturally into commissioning electron cooling
Run II Status and Prospects - Spalding
17
Electron Cooling
ƒ
R&D program on e-beam is complete, now moving
the setup to the Recycler
¾ R&D scheduled stretched by ~2 months Å NOT
BAD!
ƒ
Operational test of the full system successful
¾ All major components, diagnostics and controls
developed and tested
¾ Beam properties achieved close to spec (analysis
ongoing)
ƒ
Will add additional Pelletron section at Recycler
Æ reliable operation at 4.3 MeV
ƒ
Commission e-beam and then pbar cooling in
Recycler, parasitic to HEP, then intro e-cooled
stacks to HEP (05)
ƒ
Still R&D (until pbar cooling demonstrated next
year), but excellent progress
Run II Status and Prospects - Spalding
18
Tevatron
Major improvements so far
ƒ Lifetime at 150 GeV
¾ Larger aperture, alignment and dipole un-rolls
ƒ Emittance dilution reduced
¾ De-coupling at TEV injection, optimization of injection optics
ƒ Helix improvements
ƒ CDF IP
¾ Centered beam in low beta quads (4mm move at CDF), and realigned the quadrupoles
ƒ New Low Beta Optics
¾ 20% increase in luminosity
Upgrades
ƒ Further alignment improvements in shutdown 04 (and 05)
ƒ Add separators and polarity switches in shutdown 04 and 05
Æ improved helices
Run II Status and Prospects - Spalding
19
Luminosity Projections
Run II Status and Prospects - Spalding
20
Luminosity Projection
ƒ Luminosity model incorporates
¾ Performance parameters from simulation, parametric model and data
¾ Long term operating experience
• Sustained average store length was 15 hrs (now >24)
• Sustained average 85 store hrs/week (operating weeks often >>100)
¾ Scheduled shutdowns + turn on & recovery + learning slopes
¾ Expect to do better on some parameters, worse on others
ƒ What’s new
¾ The following plots are from Feb04 DOE review
• Illustrate strategy
• Updated projection will be similar in scale
¾ We are in the process of updating the projections for:
• e-cooling and stacktail schedules and strategy
• Improved reliability (longer stores and stacking)
• Mixed-source op - assume break even (conservative)
Run II Status and Prospects - Spalding
21
Design and Base Projections (Feb04 DOE Review)
Integrated Luminosity
10
9
Design Projection
- No schedule contingency, maintains
eng. design margin per subproject
-1
Integrated Luminosity (fb )
8
7
6
Design Projection
Base Projection
- Assumes schedule slip for all
5
subprojects and that all subprojects
under perform
Base Projection
4
3
2
1
0
9/29/03
9/29/04
9/30/05
10/1/06
10/2/07
10/2/08
10/3/09
Start of Fiscal Year
Run II Status and Prospects - Spalding
22
Design and Base Projections (Feb04 DOE Review)
Integrated Luminosity per Week
-1
Integrated Luminosity per Week (pb)
60
50
40
30
20
Phase 6
(No upgrade-related studies)
Phase 5
Phase 4
(Tevatron upgrades
(Stacktail upgrade)
complete)
Design Projection
Phase 3
(Recycler &
Electron Cooling)
Phase 2
(Slip Stacking)
Base Projection
Phase 1
(FY04)
10
We are
here
0
9/29/03
9/29/04
9/30/05
10/1/06
10/2/07
10/2/08
10/3/09
Start of Fiscal Year
Run II Status and Prospects - Spalding
23
Risk Analysis / Strategy (Feb04 DOE Review)
Our plan is to deliver the Design Projection
but develop strategy for fallback scenarios:
ƒ Base Projection models schedule slip and under-performance
for all upgrades
ƒ Can also ask: where would we be
¾ without Recycler & e-cooling?
¾ with e-cooling, but without stacktail upgrade?
Run II Status and Prospects - Spalding
24
Risk Analysis / Strategy (Feb04 DOE Review)
ƒ Design Projection
ƒ Black Projection
¾ Electron Cooling
¾ Stacktail Upgrade
¾ NO Electron Cooling
¾ NO Stacktail Upgrade
¾ Parameters in FY09
¾ Parameters in FY09
•
•
•
•
•
Debuncher & AP2 at 32π-mm-mrad
Slip Stacking at 8x1012 ppp
Av. Stk Rate = 39x1010/hr
Stk in Accum = 20x1010
Stk in Rec’r = 570x1010
ƒ Base Projection
•
•
•
•
•
Debuncher & AP2 at 21π
Slip Stacking at 7x1012
Av. Stk Rate = 14x1010/hr
Stk in Accum = 205x1010
Stk in Rec’r = 0x1010
ƒ Purple Projection
¾ As above with sched & param slip
¾ Electron Cooling
¾ NO Stacktail Upgrade
¾ Parameters in FY09
¾ Parameters in FY09
•
•
•
•
•
Debuncher & AP2 at 25π
Slip Stacking at 7x1012 ppp
Av. Stk Rate = 24x1010/hr
Stk in Accum = 24x1010
Stk in Rec’r = 360x1010
•
•
•
•
•
Debuncher & AP2 at 20π
Slip Stacking at 8x1012
Av. Stk Rate = 23x1010/hr
Stk in Acum = 58x1010
Stk in Rec’r = 337x1010
Run II Status and Prospects - Spalding
25
Risk Analysis / Strategy (Feb04 DOE Review)
50
Integrated Luminosity per Week (pb-1
Branch points from Design Projection
40
30
20
Design
Stacktail Upgd ready to install
Rapid transfers
Acc Upgd on track
8/8/05
Purple
e-cooling antiprotons
for HEP
6/1/05
without e-cooling
& stacktail upgd
Black
10
0
9/29/03
with e-cooling, but
w/o stacktail upgd
Assumes average store
length 15 hrs
9/29/04
9/30/05
10/1/06
10/2/07
10/2/08
10/3/09
Start of Fiscal Year
Run II Status and Prospects - Spalding
26
Strategy Changes
Integrated Luminosity per Week (pb-1)
50
40
30
WARNING: curves not yet updated
changes in green to be implemented
Design
e-cooling and interim stacktail
upgrade will be delayed
to fall 2005, full
interim Stacktail
upgrade in 06
upgrade
20
Black
10
mixed-source
operation
0
9/29/03
Purple
9/29/04
9/30/05
longer stores
10/1/06
10/2/07
10/2/08
10/3/09
Start of Fiscal Year
Run II Status and Prospects - Spalding
27
Risk Analysis / Strategy (Feb04 DOE Review)
10
9
8.5 fb-1
Integrated Luminosity (fb-1)
8
7
Design
6.5
6
Purple
5
4.4
Black
4
3
Base
2
1
0
9/29/03
9/29/04
9/30/05
10/1/06
10/2/07
10/2/08
10/3/09
Start of Fiscal Year
Run II Status and Prospects - Spalding
28
Summary
ƒ Current performance is above the design projection
ƒ 80% higher weekly luminosity than a year ago
ƒ Major achievements in the last year (Tevatron perf, Recycler…)
ƒ There is a complex-wide plan for the Run II campaign
ƒ Plan is dynamic: schedule/scope adjustments, mixed-source,
capitalize on improved reliability
ƒ The upgrade projects are making good technical progress
ƒ The plan and progress are formally reviewed by DOE
ƒ With the updated plan, expect the design projection to be close
to the previous 8.5 fb-1 2009, with fall-back scenarios >4.5 fb-1
Run II Status and Prospects - Spalding
29
Fly UP