POSITION PAPER BANGLADESH 4 Meeting of the Working Group on the
by user
Comments
Transcript
POSITION PAPER BANGLADESH 4 Meeting of the Working Group on the
4th Meeting of the Working Group on the Trans-Asian Railway Network 23-24 November 2015 POSITION PAPER BANGLADESH Presented by: Najnin Ara Keya Additional Chief Engineer Bangladesh Railway Brief about Bangladesh Railway 1862: Started its journey as Eastern Bengal Railway with 53.11 km Jagoti-Darsana BG Rail link. 1961: Renamed as Pakistan Eastern Railway. 1972: Started providing services as Bangladesh Railway. 1998: East-West Railway connectivity over river Jamuna was established from the day of opening Bangabandhu Bridge. 2003: Direct BG train communication between East and West zone was established over Bangabandhu Bridge. 2007: Bangladesh signed TAR agreement. 2008: Direct passenger train “Maitree Express” between Dhaka and Kolkata established. 2011: Ministry of Railways formed under SRO-361. Covers and connects 44 Districts of the country out of 64 Districts. 456 stations encircling core business activities around the country. In 2014: 65 million Passengers and 2.52 million tonnes freight carried by BR. 3 Operational Information of Bangladesh Railway Two Zones: East and West Zone • East Zone: 1308.27 km • MG: 1273.38 km • BG: 0.00 km • DG: 34.89 km • West Zone: 1568.83 km • MG: 534.67 km • BD: 659.33 km • DG: 374.83 km Operational Division: 4 divisions • Dhaka • Chittagong • Paksey • Lalmonirhat Total Route Kilometer: • 2877.10 km • MG: 1808.05 km • BG: 659.33 km • DG: 409.72 km Existing Railway Network Government’s Strategic Position on establishing TAR Bangladesh singed the “Intergovernmental Agreement on the Trans-Asian Railway Network” on 09 November 2007 as 20th signatory. Cabinet Committee approved in-principle to ratify the agreement on 09 March 2009. The Hona’ble Minister of Foreign Affairs issued ratification of the said agreement on 11 August 2010. ESCAP recorded the date of 25 August 2010 as date of ratification. Status of Missing Links of TAR Network in Bangladesh Radhikapur (West Bengal, India) and Birol (Bangladesh): Train operation has been closed since 01 April, 2005 due to conversion of meter gauge line into broad gauge line in Indian side upto Radhikapur. To re-establish the connectivity, the government of Bangladesh undertook a project on 15-042009 to convert the existing BirolParbatipur meter gauge section into dual gauge under Japan Debt Cancellation Fund (JDCF). The physical progress of the project is about 95%. The project is targeted to be completed by June 2016. Status of Missing Links of TAR Network in Bangladesh (Contd.) Shahbazpur (Bangladesh) to Karimganj-Mohishasan (India): Train operation has been closed since 07 July, 2002 due to deplorable condition of railway track & bridges in KulauraShahbazpur section. GOB has taken a project to reestablish this inter-country railway linkage under Indian Line of Credit fund. Design and supervision consultancy contract was signed on 13.08.2015. The project is targeted to be completed by June 2019. Status of Missing Links of TAR Network in Bangladesh (Contd.) Dohazari-Gundum (Bangladesh): feasibility study, detailed design and preparation of Bid document for construction of dual gauge rail line is being carried out under ADB funded TA project. Total 128 km dual gauge single line Railway track with the provision of future double track will be constructed from Dohazari to Cox’s Bazar via Ramu and Ramu to Gundum near Myanmar Border. ADB has been agreed in-principle to finance more than US$ 1.00 Billion for the investment project. The project is planned to be completed by June 2020. The land acquisition process for the project is going on. Status of Missing Links of TAR Network in Bangladesh (Contd.) Railway Bridge parallel to existing Bangabandhu Bridge: •There is load restriction of 43.7 KN/m and speed restriction of 20 kmph on existing Bangabandhu Bridge. • As such it is essential to construct a separate bridge for railway to allow TAR traffic. •Feasibility study has been carried out under ADB funded TA project. • A dedicated railway bridge with the provision of DG double line is going to be constructed under JICA funding. • Detailed design under JICA fund is targeted to be completed by 2017. •The investment project would cost more than 1 billion USD. Improvement of Line Capacity of TAR Network in Bangladesh Dhaka - Chittagong railway corridor: Out of total 320.79 km DhakaChittagong railway corridor, only 78.34 km double track is to be constructed to establish double line train operation in the total corridor. Moreover, Government of Bangladesh has decided to convert the entire DhakaChittagong railway corridor into DG for capacity enhancement of the corridor and unification of gauge. Improvement of Line Capacity of TAR Network in Bangladesh (Contd.) Dhaka-Chittagong corridor (Contd.): railway •61km double track in LaksamChinki Astana section constructed under JICA & GOB fund was inaugurated on 19.04.2015. •64km double track in TongiBhairab Bazar section constructed under ADB & GOB fund is targeted to be inaugurated in December 2015. •2nd Bhairab and 2nd Titas along with railway approaches construction is targeted to be completed by 2018. •Only remaining single line section Akhaura-Laksam (72 km) will be double tracked under ADB, EIB and GOB fund which is expected to be completed by 2020. Improvement of Line Capacity of TAR Network in Bangladesh (Contd.) Chittagong-Dohazari section: railway •Government of Bangladesh has planned to construct a second rail-cum-road bridge over river Karnaphuli at Kalurghat point. •The project is likely to be financed by EDCF, Korea. • Feasibility study is on progress by the Korean consultants engaged by EDCF. Loan Agreement is yet to be signed. •Government of Bangladesh has planned to convert existing single meter gauge line of Chittagong-Dohazari section into dual gauge double line to cater increasing railway traffic. • Feasibility study, detailed design and tendering services is going to be carried out under ADB funded TA project. Investment project is also likely to be financed by ADB. Improvement of Line Capacity of TAR Network in Bangladesh (Contd.) Isurdi-Joydevpur section: •GOB has planned to construct 164 km new DG railway track to allow all type of containers commonly used in maritime shipping, double staking of containers and cross border traffic. •Feasibility study has been carried out under ADB funded TA project. •The investment project would cost around USD 1060 million. •A non-binding MOU was signed with China Civil Engineering Construction Corporation on 26 October 2014. The project assistance yet to be finalized. Improvement of Line Capacity of TAR Network in Bangladesh (Contd.) Parbatipur- Ishurdi Section: GOB has planned to construct a second dual gauge railway track in ParbatipurAbdulpur section (157 km) for double line operation of train services in the section. Feasibility study is yet to be done and project assistance yet to be arranged. Improvement of Line Capacity of TAR Network in Bangladesh (Contd.) Akhaura-KulauraSylhet : GOB has planned under Master Plan of Bangladesh Railway to convert meter gauge track of Akhaura-KulauraSylhet section (176.72 km) into dual gauge. The new dual gauge line will be designed with axle load of 25 ton and design speed of 120 kmph. Feasibility study is yet to be carried out. A non-binding MOU was signed with China Railway Construction Bridge Engineering Bureau Group Co. Ltd. on 15 September 2015. The project assistance is yet to be finalized. Establishment of an Inland Container Depot Proposed ICD at Dhirasram with the capacity of 3,54,000 TEUs will be ideally suited for containerization of IndoBangla trade in the near future and may serve as land hub in Trans-Asian Railway (TAR), SAARC and BIMSTEC corridors. A feasibility study for construction of ICD at Dhirasram was conducted in 2004. A TA project under ADB fund is taken in hand for upgradation of the feasibility study along with detailed design preparation and tendering services for construction of the ICD. The investment project is likely to be financed by ADB Proposed Padma Bridge Rail link in Bangladesh 180 km (approx.) BG railway line is going to be constructed connecting Dhaka-Mawa-Padma Bridge-BhangaNarail-Rupdia/Singia. The project is going to be implemented under China G2G funding. The line will shorten the distance between Dhaka-Benapole by 185 km. Feasibility study of phase-I & II and detailed design for phase-I is about to complete. Negotiation for commercial contract with China Railway Group Limited is going on. Railway connection with Sea Ports in Bangladesh • At present railway connection with only Chittagong sea port exists in Bangladesh. •A project is going on to connect Mongla Sea Port under Indian Line of Credit and targeted to be completed by 2018. •GOB has planned to construct another sea port at Payra and railway line from Bhanga to connect the port. Railway connection with Sea Ports in Bangladesh •Government of Bangladesh has decide to establish a power generation hub based on coal-fired power plants in Matarbari 3000 MW and Moheshkhali 6000 MW and also 3000 MW LNG based power plant in the same area in future. The power hub facility will include Deep Sea Port with Coal and Heavy jetty, coal yard, container handling facilities etc. • Feasibility study, detailed design and tendering services for construction of railway link with the power hub and deep sea port is going to be carried out under an ADB funded TA project. Proposed amendment in TAR network in Bangladesh In conformity with article 8(4) of the Agreement, Bangladesh has proposed an amendment as described hereafter: On the Darsana – Gundum line Replace Tongi (junction) Dhaka With Tongi (junction) Dhaka – Narayanganj – [Mawa – Bhanga – Narail – Jessore] – Benapol (border station) – (India) Policies and issues relating to the development of TAR Physical and institutional improvement of BR is undertaken in line with NLTP and Railway Master Plan. Major issues are to restructure Bangladesh Railway into commercially oriented organization in combination with substantial investment in infrastructure, rolling stocks, signalling systems, maintenance and technical modernization for sustainable development. Implementation of Tariff structure reform: A proposal for implementation of a fixed 'Tariff Structure' with an yearly adjustment formula based on various factors is now under active consideration of the government of Bangladesh for approval. Establishment of Container Company in Bangladesh Railway: Action has been taken to establish a company named "Container Company of Bangladesh Limited" dedicated for only container transportation. The proposal of establishment of the Container Company is now under consideration of the government of Bangladesh for approval.