Topic No. 700-000-000 Construction Project Administration Manual Effective: July 23, 2002 Preconstruction Activities
by user
Comments
Transcript
Topic No. 700-000-000 Construction Project Administration Manual Effective: July 23, 2002 Preconstruction Activities
Topic No. 700-000-000 Construction Project Administration Manual Preconstruction Activities Effective: July 23, 2002 Revision Date: November 21, 2008 Section 3.3 CONTRACTOR’S QUALITY CONTROL PLAN 3.3.1 Purpose This procedure describes the review and approval of the Contractor’s Quality Control Plan (QCP) when required per Contract Documents. This procedure also describes the process of acceptance of a Contractor’s Quality Control Manual (QCM) on a statewide basis. When accepted by the Department, the QCM can be referenced in a project specific QCP, thereby reducing the amount of information submitted for review and approval on a contract-by-contract basis. 3.3.2 Authority Section 334.048, Florida Statutes (F.S.) Section 105 of the Florida Department of Transportation Standard Specifications for Road and Bridge. 3.3.3 General In compliance with FHWA 23 CFR 637, the Department chose to implement the “Contractor option”. This option allows the Contractor to be responsible for Quality Control (QC) on Department projects. Section 105 of the Florida Department of Transportation Standard Specifications for Road and Bridge Construction details the requirements of a Contractor’s QCP. 3.3.4 Quality Control Manual 3.3.4.1. Review and Approval The Contractor may elect to submit a Quality Control Manual (QCM) to have it approved for statewide use. In the event that the Contractor has an approved QCM, the Contractor is still required to submit a contract specific QC plan but can include information from the Contractor’s QCM by reference. The QCM is not required, but is provided as an option to the Contractor as a vehicle to allow the majority of the Quality Control information to be pre-approved once prior to any contracts beginning. The QCM can be submitted to the Director, Office of Construction at Contractor's Quality Control Plan 3-3-1 Topic No. 700-000-000 Construction Project Administration Manual Preconstruction Activities Effective: July 23, 2002 Revision Date: November 21, 2008 any time. The Contractor does not need to have a contract with the Department to submit a QCM. The Contractor would not be allowed to submit a QCM for approval concurrently with a contract specific QC plan for a particular project, but is encouraged to submit a QCM as early as possible. The Contractor’s QCM shall be reviewed by all the following responsible parties using the checklist provided as a guide in Attachment 3-3-1, Quality Control Manual Review Checklist. (A) Central Office Level Responsibilities The Contractor submits a QCM in accordance with Section 105 of the Specifications for approval to the Director, Office of Construction or designee. The Director, Office of Construction or designee shall send a notification of receipt of the QCM within five (5) working days after receiving such plan. A sample letter is provided in the Guidance Document 3-3-A, Receipt of Quality Control Manual. The Director, Office of Construction or designee, within five (5) working days, will forward the QCM to all the District Construction Engineers (DCEs), and the Director, Office of Materials. The Director, Office of Materials or designee shall review the QCM and provide written findings and recommendations to the Director, Office of Construction or designee within 20 continuous working days from date of receipt from Director, Office of Construction or designee. Upon receipt of the findings and recommendations, the Director, Office of Construction or designee will review and resolve all findings with the DCEs and the State Materials Office (SMO). Response to the Contractor with acceptance or request for additional information shall be within 50 calendar days of receipt of the QCM. Any additional information submitted by the Contractor shall be reviewed and responded to within 10 calendar days of the receipt of such information. A sample letter for QCM approval is provided in the Guidance Document 3-3-B, Approval of Quality Control Manual. Upon approval, the QCM shall be posted on the State Construction Office (SCO) Infonet site. (B) District Level Responsibilities The DCEs or their designees shall review the QCM and provide written findings and recommendations to the Director, Office of Construction or designee within 20 working days. Contractor's Quality Control Plan 3-3-2 Topic No. 700-000-000 Construction Project Administration Manual Preconstruction Activities 3.3.4.2. Effective: July 23, 2002 Revision Date: November 21, 2008 Disapproval The following conditions may result in the disapproval of the QCM: 1. Failure to comply with the requirements of Specifications Section 105 and Material Manual (MM) Section 5.6. 2. Repeated failure to meet Specification requirements. 3. Failure to take immediate corrective action relative to deficiencies in the performance of the QC program. 4. Notification from the SMO and/or District Materials Office (DMO) in accordance with MM Section 5.6. 5. Numerous disapprovals of QCPs on multiple contracts. If in the opinion of the Director, Office of Construction, based on input from the DCEs, DMEs and/or the Director, Office of Materials, the above stated condition(s) are the result of a company-wide problem, the QCM shall be disapproved. A sample letter for QCM disapproval is provided in the Guidance Document 3-3-C, Disapproval of Quality Control Manual. 3.3.5 Quality Control Plan 3.3.5.1 Review and Approval The Contractor has 21 calendar days after the award of the contract to submit a Quality Control Plan (QCP) in accordance with Specifications Section 105 for approval to the Project Administrator (PA). All the following responsible parties shall review the QCP using the checklist provided as a guide in Attachment 3-3-2, Quality Control Plan Review Checklist. No phase of work covered under the QC program, as specified in Specifications Section 105, can begin until the Resident Engineer (RE) or designee has approved the QCP for that phase of work. If a portion of the QCP is in compliance, the Contractor may begin work for that phase, but not for phases that are non-compliant. This 21 day review process includes all participants within that timeframe and does not allow for each to be allocated more than the total 21 days. Contractor's Quality Control Plan 3-3-3 Topic No. 700-000-000 Construction Project Administration Manual Preconstruction Activities Effective: July 23, 2002 Revision Date: November 21, 2008 As an example: Contractor submits QC Plan to the PA on August 1st, the DCE reviews the plan until August 10th and submits to the PA on August 11th. The PA has until August the 22nd to respond to the Contractor. If the DME reviews the QC Plan until August 19th, the PA still has to respond to the Contractor by August 22nd. (A) Resident Level Responsibilities The PA will review the QCP for requirements of construction operations and compliance with the specifications. Upon completion of review, the Contractor’s QCP and comments will be forwarded to the DME for review and concurrence. This review period should take into consideration that the total review period is 21 calendar days and should allow sufficient time for others to review the QCP within that constraint. The QCP can be approved in part or all-inclusive. The RE or designee will review the DME’s findings and recommendations and resolve any conflicts presented by the DME and respond to the Contractor. The RE or designee has a total 21 calendar days from the date of receipt of the QCP by the PA to respond to the Contractor. A sample letter for QCP approval is provided in the Guidance Document 3-3D, Approval of a Quality Control Plan. The PA shall furnish a fee schedule that will be used to establish a credit on the monthly estimate in the event that resolution tests performed by a Department compare favorably with the Verification test results. The PA can obtain the fee schedule from the SMO website. In the event the QCP is disapproved, such disapproval must clearly state area(s) of concern and non-compliance with the Specifications and requirements of the Department. A sample letter for QCP disapproval is provided in the Guidance Document 3-3-E, Disapproval of Quality Control Plan. (B) District Level Responsibilities The DME will review the QCP in accordance with Specifications Section 105 and MM Section 5.6 and will make appropriate recommendations, if any, to the PA within the 21 calendar days after receipt from the Engineer. The DMRE shall also review the PA’s findings, and comment on possible conflicts with the requirements. The PA will forward a copy of the Contractor's QC Plan to the DCE office. The DCE will review the QCP in accordance with Specifications Section 105 and will make appropriate Contractor's Quality Control Plan 3-3-4 Topic No. 700-000-000 Construction Project Administration Manual Preconstruction Activities Effective: July 23, 2002 Revision Date: November 21, 2008 recommendations, if any, to the PA within the 21 calendar days. The PA should take into consideration that the total review period is 21 calendar days and should allow sufficient time for others to review the QCP within that constraint. (C) State Materials Office Level Responsibilities The Director, Office of Materials shall publish a fee schedule that will be used to establish a credit on the monthly estimate for resolution tests performed by a Department’s laboratory that compare, in accordance with the Specifications, with the Department’s Verification test results. Such fee schedule shall be published annually, at the beginning of the fiscal year, for contracts let that fiscal year. 3.3.5.2 Disapproval The following conditions may result in the disapproval of the QCP, in part or all-inclusive: (A) 1. Failure to comply with the requirements of Specifications Section 105 and MM Section 5.6, such as failure to timely supply information. 2. Repeated failure of materials to meet specification requirements. 3. Failure to take immediate corrective action relative to deficiencies in the performance of the QC program. 4. Notification from the State Materials and/or District Materials Office in accordance with MM Section 5.6, such as certifying materials that are not produced under an approved Quality Control Program for use on Department projects. 5. Notification from the State Construction Office of disapproval of a QCM. Resident Level Responsibilities The RE or designee shall notify the Contractor, within two (2) working days of finding a condition or conditions warranting the disapproval of the QCP. Notification of such disapproval shall clearly state area(s) of concern and non-compliance with the Specifications and requirements of the Contract. If the Contractor has been given a verbal warning that all or part of his QC Plan is in non-conformance the PA will address this in his Daily Report of Construction or Daily Work Report. If after that point the Contractor does not correct this finding(s) then the PA shall issue a Deficiency Warning Letter (DWL). Contractor's Quality Control Plan 3-3-5 Topic No. 700-000-000 Construction Project Administration Manual Preconstruction Activities Effective: July 23, 2002 Revision Date: November 21, 2008 The PA shall issue a DWL to notify the Contractor of shortcomings/non-compliances with QC Plan. Prior to issuing a DWL, the Project Administrator should discuss the performance concerns with the Resident Engineer. A single DWL can be used to address concerns in more than one performance category. However, blatant violations or non-compliances may result in a Deficiency Letter (DL) being issued by the RE without a warning. Disapproval of the QCP could result in issuance of a DL by the RE if the Contractor ignores to correct his QC Plan or continues to perform outside of the QC Plan guidelines or Specifications. Refer to CPAM Section 13.1, Contractor’s Performance for processing DWL and DL. (B) Central Office Level Responsibilities In the event of repeated QCP disapprovals, the SCO or designee can disapprove a QCM. Should the SCO or designee disapprove a QCM, each PA will make the determination whether or not to disapprove each individual QCP that reference the QCM. Each QCP will be evaluated as a stand-alone document and will be considered on a case-by-case basis. The disapproval of a QCM will not automatically result in the disapproval of all QCPs that reference the QCM. 3.3.5.3 Addendum to QCP The Contractor’s QCP is often needed revising due to issues such as personnel changes, changes in design mixes, or plants, etc. Without the Contractor having to go through the revision process of these type changes, the Department will accept addendums to the already approved QCP. The Contractor will provide the proper information required to fulfill the changes/modifications of their QCP. These changes can be accepted and approved by the Project Administrator and will be added to the already approved QCP. These addendums may be received in writing or via E-mail from the Contractor or QC Manager. Contractor's Quality Control Plan 3-3-6 Topic No. 700-000-000 Construction Project Administration Manual Preconstruction Activities Effective: July 23, 2002 Revision Date: November 21, 2008 Attachment 3-3-1 What needs to be in the Contractor's Quality Control Manual? The Contractor should address the following items for all applicable materials, identified in Specifications Section 105-5, that would be used and for various scenarios that may be encountered. It is not the intent to address all possible scenarios but address as many as possible at the onset and amend later as others become evident. This checklist is to be used as a guide for review and should not be used for acceptance. The right hand column on the checklist identifies who’s responsible for describing information input into the QC Manual. Keep in mind, ultimately this Quality Control Manual is generated by the Prime Contractor, but may incorporate information from a known Sub-Contractor or Supplier. Quality Control Manual Review Checklist Company: __________________________________ Vendor#: ___________________ Address: _______________________________________________________________ City: _________________________________ State: _______ Zip Code:___________ FIN: _________________ Project Description: ________________________________ ______________________________________________________________________ Contact Person: ___________________________ Phone # _____________________ E-Mail Address: __________________________ Fax #: _______________________ QCP Received: ____________ QCP Dated: _________ Date Reviewed:___________ Evaluated By: __________________________________ Accepted (Y / N):__________ QCM Item Y/N QCM Page # Required By 105-5.2 Personnel Contractor / 105-5.2.1 – Qualifications QC Plan Not Applicable to QCM. 105-5.2.2 – Level of Responsibility Contractor / Not Applicable to QCM, however the Contractor QC Plan can define the line of responsibility with a generic organization chart. Does the QCM outline the QC Manager’s Contractor / responsibility? QC Plan 105-5.3 Raw Materials Raw Materials for the Contractor are defined as materials he receives to produce or construct the final product, for example a load of aggregates, asphalt, concrete, prestressed concrete products, metal and plastic pipes, timber, precast drainage structures or earthwork materials. Contractor / 105-5.3.1 – Sources (May include Does the QCM identify the sources of raw Contractor's Quality Control Plan 3-3-7 Topic No. 700-000-000 Construction Project Administration Manual Preconstruction Activities QCM Item materials including names, locations, plant or mine number and approved lists, when applicable? 105-5.3.2 – Certification Does the QCM detail how the verification of any raw materials would be handled? 105-5.3.3 – Disposition of Failing Materials Does the QCM describe detection methods for failing materials? Does the QCM describe preventative measures? Does it detail actions that the Contractor would take once failing materials was detected? Does it detail the process of notifying the Department of failing material? 105-5.4 – Storage Facilities for Raw Materials Does this section detail storage methods and site plan if the Contractor were to stockpile any raw materials (such as embankment material) on the project or off? Does it describe how segregation, contamination and degradation would be avoided? 105-5.5 – Production Equipment Does the QCM describe calibration frequencies, maintenance schedule and procedures for production equipment? 105-5.6 – Plant Requirements 105-5.6.1 – Plant Identification Not Applicable to QCM. 105-5.6.2 – Process Control System Not Applicable to QCM. 105-5.6.3 – Loading and Shipping Control Not Applicable to QCM. 105-5.6.4 – Types of Products Generated Not Applicable to QCM. 105-5.7 – Other Requirements 105-5.7.1 – Copy of Certifications Does the QCM provide examples of any certifications NOT already specified in the Specifications? 105-5.7.2 – Statement of Compliance Any general statements of compliance from the Contractor would be in this portion. 105-5.7.3 - Information on Approved Producer's Not Applicable to QCM. The QCM could identify plants. If so, Does the QCM provide detailed information about the plant, including FDOT Facility Number that will produce the Contractor's Quality Control Plan Effective: July 23, 2002 Revision Date: November 21, 2008 Y/N QCM Page # Required By Suppliers info) Contractor Contractor Contractor Contractor Contractor Producer/Sub (Potentially Contractor) Producer/Sub (Potentially Contractor) Producer/Sub Producer / Supplier Producer / Supplier Producer / Supplier Producer / Supplier Producer / Supplier Contractor Contractor / (May include Suppliers info) 3-3-8 Topic No. 700-000-000 Construction Project Administration Manual Preconstruction Activities Effective: July 23, 2002 Revision Date: November 21, 2008 QCM Item Y/N QCM Page # Required By required materials for the Contractor? 105-5.7.4 – Describing Documentation Procedure Does the QCM describe document-handling Contractor / processes for all documentation related to (May include quality control, including but not limited to the Suppliers / density logbook, control charts, inspection Sub info) reports and others? 105-5.8 – Final Manufactured Product – Plant Operations Producer / 105-5.8.1 – Storage Supplier Not Applicable to QCM. 105-5.8.2 – Disposition of Failing Materials Producer / Does the QCM describe detection methods for Supplier failing materials? Does the QCM describe preventative Producer / measures? Supplier Does it detail actions that the Contractor would Producer / take once failing materials was detected? Supplier Does it detail the process of notifying the Department of failing material? Contractor 105-5.9 – Final Manufacture Product – Field Operations for the Contractor are defined as methods he performs to construct the final placement of a product, for example how he will handle drainage pipe on the project and the installation to ensure proper procedures. Contractor / 105-5.9.1 – Transportation (May include Does the QCM describe specific loading and Suppliers / hauling operations, and/or trucking Sub info) operation/maintenance common to the product? 105-5.9.2 – Storage Does the QCM describe specific storage requirements/recommendations for all or Contractor specific materials? Are any specific additional (May include handling requirements or testing addressed? Is Supplier/Sub a maximum storage time listed for all/specific info) materials? 105-5.9.3 – Placement Does the QCM describe specific placement techniques common to the products being Contractor / placed? Has preparation and cleaning of Sub previous layers/substrates been addressed? 105-5.9.4 – Disposition of Failing Materials Does the QCM describe detection methods for Contractor failing materials? Does the QCM describe preventative measures? Contractor Does it detail actions that the Contractor would take once failing materials was detected? Contractor Does it detail the process of notifying the Department of failing material? Contractor 105-6 – Lab Qualification Program Not Applicable to QCM. If testing Laboratories are Contractor's Quality Control Plan 3-3-9 Topic No. 700-000-000 Construction Project Administration Manual Preconstruction Activities QCM Item known, they can be listed in the QCM. Contractor's Quality Control Plan Effective: July 23, 2002 Revision Date: November 21, 2008 Y/N QCM Page # Required By Contractor 3-3-10 Topic No. 700-000-000 Construction Project Administration Manual Preconstruction Activities Effective: July 23, 2002 Revision Date: November 21, 2008 Attachment 3-3-2 What needs to be in the Contractor's Quality Control Plan? The Contractor should address the following items for all materials, identified in Specifications Section 105, applicable to the Contract. For the purposes of this checklist, it is assumed that the Contractor has an approved Quality Control Manual. If the Contractor does not have an approved QCM, all information required on the QCM would need to be included in the QCP 1 . This checklist is to be used as a guide for review and should not be used for acceptance. There are some instances that the Prime Contractor may utilize a Sub-Contractor to perform certain operations where materials used are included in the QC Program. As an example the Prime may contract for a Sub-Contractor to perform concrete drain pipe installation. Section 105-5.9 Final Manufactured Product-Field Operations requires the Contractor to describe transportation, storage, placement and disposition of failing materials. The Prime Contractor may choose to incorporate certain parts of the SubContractor’s QC Plan for this operation. For example, the Sub-Contractor’s QC Plan may describe how the pipe will be transported to the project and how and what type equipment they will be using to offload the pipe, or how the pipe will be stored to prevent damage. The Sub-Contractor’s QC Plan would describe the installation of the pipe and how they would make sure its flow line is correct and pack the haunches uniformly to keep the pipe stationary while backfilling, as well as ensuring pipe joints and rubber gaskets are installed to specification. These are examples of what might be on the Sub-Contractor’s QC Plan that could be incorporated into the Prime Contractor’s QC Plan. However, it is the Prime Contractor’s responsibility to carry out these operations and he must describe them in his QC Plan. For example, what corrective measure will he take if the fill material is not suitable? Or what action will he take if the Sub-Contractor installs a cracked pipe? While the Prime Contractor may incorporate certain areas of Sub-Contractor’s QC Plans, keep in mind that the Prime Contractor is ultimately responsible for the Quality Control Operation on a project. So when using this checklist as a guide, make sure that the Prime Contractor has incorporated the proper details of what policies, methods and procedures he will use to insure the quality of the products. The right hand column on the checklist identifies who’s responsible for describing information input into the QC Plan. Ultimately, the Quality Control Plan is generated by the Prime Contractor, but may incorporate information from a Sub-Contractor or Supplier. 1 If the Contractor has not submitted a QCM, refer to Attachment 3-3-1 in order to ensure that the QCP information is complete. Contractor's Quality Control Plan 3-3-11 Topic No. 700-000-000 Construction Project Administration Manual Preconstruction Activities Effective: July 23, 2002 Revision Date: November 21, 2008 Quality Control Plan Review Checklist Company: __________________________________ Vendor#: ___________________ Address: _______________________________________________________________ City: _________________________________ State: _______ Zip Code:___________ FIN: _________________ Project Description: ________________________________ ______________________________________________________________________ Contact Person: ___________________________ Phone # _____________________ E-Mail Address: __________________________ Fax #: _______________________ QCP Received: ____________ QCP Dated: _________ Date Reviewed:___________ Evaluated By: __________________________________ Accepted (Y / N):__________ QCP Item 105-5.2 Personnel 105-5.2.1 - Qualifications Are all qualified personnel along with their level of qualifications and TIN listed? The PA should check the database on CTQP website for validation of qualifications on a random basis. 105-5.2.2 – Level of Responsibility Does the QCP incorporate this information from the QCM by reference 1 ? Does the QCP identify specific individuals to carry out these responsibilities? Does the QCP identify the QC Manager and their role and list the TIN? The PA should check the database on CTQP website for validation of qualification. Y/N QCP Page # Required By Contractor Contractor Contractor Contractor 1 If the Contractor has not submitted a QCM, refer to Attachment 3-3-1 in order to ensure that the QCP information is complete. Contractor's Quality Control Plan 3-3-12 Topic No. 700-000-000 Construction Project Administration Manual Preconstruction Activities Effective: July 23, 2002 Revision Date: November 21, 2008 QCP Item Y/N QCP Page # Required By 105-5.3 Raw Materials Raw Materials for the Contractor are defined as materials he receives to produce or construct the final product, for example a load of aggregates, asphalt, concrete, precast drainage products or earthwork materials. Contractor / 105-5.3.1 – Sources (May include Does the QCP identify the suppliers? The DME or Suppliers designee should verify whether the Suppliers listed info) are on the approved list. This information can be referenced from the QCM 1. 105-5.3.2 – Certification Does the QCP incorporate this information from Contractor the QCM by reference1? 105-5.3.3 - Disposition of Failing Materials Does the QCP incorporate this information from Contractor the QCM by reference1? 105-5.4 – Storage Facilities for Raw Materials Producer/Sub Does the QCP incorporate this information from the QCM (Potentially by reference1? Contractor) 105-5.5 – Production Equipment Does the QCP incorporate this information from the QCM by reference1? 105-5.6 – Plant Requirements 105-5.6.1 – Plant Identification Not applicable to the QCP. 105-5.6.2 – Process Control System Not applicable to the QCP. 105-5.6.3 – Loading and Shipping Control Not applicable to the QCP. 105-5.6.4 – Types of Products Generated Not applicable to the QCP. 105-5.7 – Other Requirements 105-5.7.1 – Copy of Certifications Does the QCP incorporate this information from the QCM by reference and does it identify the individual who would provide these certifications? 105-5.7.2 – Statement of Compliance Does the QCP incorporate this information from the QCM by reference and does the QCP identify the individual who would execute the Statement of Compliance? Producer/Sub Producer / Supplier Producer / Supplier Producer / Supplier Producer / Supplier Producer / Supplier Contractor 1 If the Contractor has not submitted a QCM, refer to Attachment 3-3-1 in order to ensure that the QCP information is complete. Contractor's Quality Control Plan 3-3-13 Topic No. 700-000-000 Construction Project Administration Manual Preconstruction Activities QCP Item 105-5.7.3 - Information on Approved Producer's Does the QCP incorporate Producer's QCP by listing the producers of 105-3 materials, including FDOT Facility Number? The DME or designee should verify whether the Producer is on the list of Producers with an Accepted QC Program. 105-5.7.4 – Describing Documentation Procedure Does the QCP incorporate this information from the QCM by reference1? 105-5.8 – Final Manufactured Product – Plant Operations 105-5.8.1 – Storage Not applicable to the QCP. 105-5.8.2 – Disposition of Failing Materials Not applicable to the QCP. Effective: July 23, 2002 Revision Date: November 21, 2008 Y/N QCP Page # Required By Contractor / (May include Suppliers info) Contractor / (May include Suppliers / Sub info) Producer / Supplier 105-5.9 – Final Manufacture Product – Field Operations for the Contractor are defined as methods he performs to construct the final placement of a product, for example how he will handle drainage pipe on the project and the installation to ensure proper procedures. Contractor / 105-5.9.1 – Transportation (May include Does the QCP incorporate this information from Suppliers / the QCM by reference 1 and provide any Sub info) supplementary information? 105-5.9.2 – Storage Contractor / Does the QCP incorporate this information from (May include the QCM by reference1 and provide any Supplier / supplementary information? Sub info) 105-5.9.3 – Placement Does the QCP incorporate this information from Contractor / the QCM by reference1 and provide any Sub supplementary information? 105-5.9.4 – Disposition of Failing Materials Does the QCP incorporate this information from the QCM by reference1 and provide any Contractor supplementary information? 105-6 – Lab Qualification Program Does the QCP identify all testing laboratories to be used on the contract or incorporate this information from the Contractor QCM by reference1? The DME or designee should verify whether the laboratory listed is qualified. 1 If the Contractor has not submitted a QCM, refer to Attachment 3-3-1 in order to ensure that the QCP information is complete. Contractor's Quality Control Plan 3-3-14 Topic No. 700-000-000 Construction Project Administration Manual Preconstruction Activities Effective: July 23, 2002 Revision Date: November 21, 2008 Guidance Document 3-3-A Sample letter for Receipt of a Quality Control Manual Date Contractor Name Contractor Address City State Zip RE: RECEIPT OF QUALITY CONTROL MANUAL Dear Sir or Madam: The Department is in receipt of your Contractor Quality Control Manual (QCM). The manual will be reviewed in accordance with Chapter 3, Section 3 of the Construction Project Administration Manual. Please note that the receipt of the Quality Control Manual does not relieve the Contractor of the responsibility to submit a contract specific Quality Control Plan (QCP) in accordance with Section 105 of the Specifications to the Project Administrator for review and approval. The Department will notify you of the outcome of the review within 50 calendar days of the receipt of this plan. If you have any questions, please feel free to contact <name of the person> at <telephone number>. Sincerely, David A. Sadler, P.E., Director, Office of Construction Contractor's Quality Control Plan 3-3-15 Topic No. 700-000-000 Construction Project Administration Manual Preconstruction Activities Effective: July 23, 2002 Revision Date: November 21, 2008 Guidance Document 3-3-B Sample letter for Approval of a Quality Control Manual Date Contractor Name Contractor Address City State Zip RE: APPROVAL OF QUALITY CONTROL MANUAL Dear Sir or Madam: The Department has reviewed and approved your Quality Control Manual (QCM). The information contained in the QCM can now be incorporated in the Contract Quality Control Plan by reference. Continued approval of the QCM is contingent upon the successful execution of Contractor Quality Control on specific construction contracts. The Contractor, in accordance with Section 105 of the Specifications, is still required to submit a contract specific Quality Control (QC) Plan to the Project Administrator for review and approval. Approval of the QCM does not constitute an approval to any deviations to the Contract, unless otherwise specifically authorized separately in writing by the Engineer. If you have any questions, please feel free to contact <name of the person> at <telephone number>. Sincerely, David A. Sadler, P.E., Director, Office of Construction cc: Director, Office of Materials District Construction Engineers District Materials Engineers Contractor's Quality Control Plan 3-3-16 Topic No. 700-000-000 Construction Project Administration Manual Preconstruction Activities Effective: July 23, 2002 Revision Date: November 21, 2008 Guidance Document 3-3-C Sample letter for Disapproval of a Quality Control Manual Date Contractor Name Contractor Address City State Zip RE: DISAPPROVAL OF QUALITY CONTROL MANUAL Dear Sir or Madam: The Department has reviewed your Quality Control Manual (QCM). Your QCM is hereby disapproved due to: Disapproval of the QCM could result in disapproval of any Contractor Quality Control Plans (QCP’s) that incorporate this QCM by reference. If you have any questions, please feel free to contact <name of the person> at <telephone number>. Sincerely, David A. Sadler, P.E., Director, Office of Construction cc: Director, Office of Materials District Construction Engineers District Materials Research Engineers Contractor's Quality Control Plan 3-3-17 Topic No. 700-000-000 Construction Project Administration Manual Preconstruction Activities Effective: July 23, 2002 Revision Date: November 21, 2008 Guidance Document 3-3-D Sample letter for Approval of a Quality Control Plan Date Contractor Name Contractor Address City State Zip RE: APPROVAL OF QUALITY CONTROL PLAN Dear Sir or Madam: The Department has reviewed and approved your Quality Control Plan (QCP). Continued approval of the QCP is contingent upon the successful execution of such plan. Approval of the QCP does not constitute an approval to any deviations to the Contract, unless otherwise specifically authorized separately in writing by the Engineer. If you have any questions, please feel free to call <Name of the Project Administrator> at<telephone number>. Sincerely, Resident Engineer cc: District Materials Research Engineer Contractor's Quality Control Plan 3-3-18 Topic No. 700-000-000 Construction Project Administration Manual Preconstruction Activities Effective: July 23, 2002 Revision Date: November 21, 2008 Guidance Document 3-3-E Sample letter for Disapproval of a Quality Control Plan Date Contractor Name Contractor Address City State Zip RE: DISAPPROVAL OF QUALITY CONTROL PLAN Dear Sir or Madam: The Department has disapproved your Quality Control Plan (QCP) due to: Furthermore, the Department directs the Contractor to cease the phase of work(s) covered under the QC Plan that has been deemed to be non-compliant, hence resulting in the disapproval of the QC Plan. Resumption of such phase of work(s) shall be dependent on the Contractor submitting a revised QC Plan and the Engineer’s review and approval of such plan. If you have any questions, please feel free to call <Name of the Project Administrator> at<telephone number>. Sincerely, Resident Engineer cc: District Materials Research Engineer Contractor's Quality Control Plan 3-3-19