WELDING PROCEDURE SPECIFICATION (WPS) PREQUALIFIED QUALIFIED BY TESTING
STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION
WELDING PROCEDURE SPECIFICATION (WPS)
675-070-10
MATERIALS
05/15
PREQUALIFIED
QUALIFIED BY TESTING
AWS D1.3 Sheet Steel
Contractor/Organization:
Welding Process(es):
Type: Manual
Mechanized
Tandem
Semiautomatic
Automatic
Parallel
JOINT DESIGN USED
Single
Double Weld
Backing:
Yes
Backing Mat’l:
Groove Welded From:
GAS
Shielding Gas:
Flow Rate:
Backing Gas: Yes
FILLER METAL
No
One side
Both Sides
Percent Mixture:
No
FLUX
PREHEAT
Preheat Temp Min.:
Preheat Temp Max:
Pass No.
Electrode
Size
TECHNIQUE
Welding Current
Amperes
Volts
Travel
Speed*
Melting
Rate
Identification :
Revision:
Date:
By:
Supporting PQR No. (s):
POSITION
Position of Groove:
Fillet:
Vertical Progression:
Up
Down
BASE METALS
Material Spec:
Type or Grade:
Support Steel:
Thickness Range:
Sheet Steel
Support Steel
Thickness:
Base Metal Prep:
COATING(S)
Type:
Thickness:
ELECTRICAL CHARACTERISTICS
Transfer Mode (GMAW):
Short-Circuiting
Globular
Spray
Current:
AC
DCEP
DCEN
Pulsed
Other:
Tungsten Electrode (GTAW)
Size:
Type:
FOR FDOT USE ONLY
Wire
Feed
Speed
*(or Weld Time for Arc Spot Welds)
FOR CERTIFIED WELDING INSPECTOR (CWI) USE ONLY
Signature
Date
JOINT DETAILS
FOR FDOT CONSULTANT USE ONLY
Comments:
Return this completed form to the FDOT State Materials Office Structural Materials Systems Field Operations Office.
Fly UP