Comments
Description
Transcript
0101 1 MOBILIZATION LS 23.220
Page 1 Florida Department of Transportation Maintenance Contract Cost Summary By Pay Item Number (SiteManager Data Only) 01/01/2012 - 12/31/2012 Statewide 2/12/2012 Pay Item Number Pay Item Description Unit of Measure 0101 1 0102 1 0102 14 0102 60 0102 71 11 0102 74 1 0102 74 1 0102 74 2 0102 76 0102 76 0102 77 0102 79 0102 99 0104 9 0104 10 3 0104 11 0104 12 0104 13 2 0104 18 0107 1 0110 1 1 0110 2 1 0110 3 0110 4 0120 1 0120 2 2 0120 6 0120 72 0120 73 0121 70 0125 1 0142 70 MOBILIZATION MAINTENANCE OF TRAFFIC TRAFFIC CONTROL OFFICER WORK ZONE SIGN BARRIER WALL, TEMPORARY, F&I, CONCRETE BARRICADE, TEMPORARY, TYPES I, II, DI, VP & DRUM TEMPORARY BARRICADE- TYPES I, II, DI, VP, DRUM, OR BARRICADE, TEMPORARY, TYPE III, 6' ADVANCE WARNING ARROW PANEL ARROW BOARD / ADVANCE WARNING ARROW PANEL HIGH INTENSITY FLASHING LIGHTS, TEMP, TYPE B LIGHTS,BARRIER WALL MOUNT,TEMP,TYPE C,STEADY BURN PORTABLE CHANGEABLE MESSAGE SIGN, TEMPORARY SEDIMENT BASIN / CONTAINMENT SYSTEM- CLEANOUT SEDIMENT BARRIER FLOATING TURBIDITY BARRIER STAKED TURBIDITY BARRIER- NYLON REINFORCED PVC STAKED SILT FENCE, TYPE IV INLET PROTECTION SYSTEM LITTER REMOVAL CLEARING & GRUBBING CLEARING & GRUBBING (PUSH BUTTON CONTRACT) REMOVAL OF EXISTING STRUCTURE REMOVAL OF EXISTING CONCRETE PAVEMENT REGULAR EXCAVATION BORROW EXCAVATION, TRUCK MEASURE EMBANKMENT GRAVEL FILL LIGHTWEIGHT AGGREGATE FILL FLOWABLE FILL EXCAVATION FOR STRUCTURES FILL SAND LS LS MH ED LF ED ED ED ED ED ED ED ED EA LF LF LF LF EA AC LS AC LS SY CY CY CY CY CY CY CY CY Total Quantity Total Cost Average Unit Cost 23.220 27.915 3,389.750 15,004.000 4,808.000 284.000 72,085.000 884.000 47.000 1,685.000 1,217.000 50.000 5,304.000 6.000 27,267.500 1,290.000 70.000 807.000 10.000 0.600 5.621 79.815 7.000 73,682.902 5,915.280 30,025.140 5,219.000 130.110 14.200 157.000 153.000 1,014.250 $418,626.35 $341,827.98 $177,795.44 $38,680.38 $72,011.20 $209.25 $49,412.01 $1,125.05 $464.00 $23,764.45 $2,551.10 $50.00 $147,287.90 $57,000.00 $27,015.00 $7,930.00 $300.00 $1,137.87 $816.00 $480.00 $169,339.82 $86,826.99 $3,500.00 $942,291.40 $92,969.82 $610,336.64 $75,054.90 $5,854.95 $568.00 $21,204.00 $1,854.60 $28,435.30 $18,028.70 $12,245.32 $52.45 $2.58 $14.98 $0.74 $0.69 $1.27 $9.87 $14.10 $2.10 $1.00 $27.77 $9,500.00 $0.99 $6.15 $4.29 $1.41 $81.60 $800.00 $30,126.28 $1,087.85 $500.00 $12.79 $15.72 $20.33 $14.38 $45.00 $40.00 $135.06 $12.12 $28.04 Page 2 Florida Department of Transportation Maintenance Contract Cost Summary By Pay Item Number (SiteManager Data Only) 01/01/2012 - 12/31/2012 Statewide 2/12/2012 Pay Item Number Pay Item Description Unit of Measure 0145 1 0145 2 0145 71 0160 3 0160 4 0162 1 11 0173 76 0173 77 1 0173 77 3 0210 1 1 0210 1 8 0210 2 0285701 0285704 0285709 0285711 0285713 0315 1 0327 70 1 0327 70 5 0327 70 6 0327 70 11 0327 70 13 0327 70 18 0327 70 19 0327 70 23 0334 1 13 0334 1 14 0334 1 23 0334 1 24 0334 1 43 0337 7 5 GEOSYNTHETIC REINFORCED SOIL SLOPE GEOSYNTHETIC REINFORCED FOUNDATION OVER SOFT SOIL REINFORCEMENT GRID FOR SOIL STABILIZATION COMMERCIAL STABILIZING MATERIAL TYPE B STABILIZATION PREPARED SOIL LAYER, FINISH SOIL LAYER, 6" GROUT PIPE INSTALLATION SUBSURFACE PRESSURE GROUTING, SAND CEMENT SUBSURFACE PRESSURE GROUTING, CEMENT SLURRY REWORKING LIMEROCK BASE, 6" REWORKING LIMEROCK BASE, 4" LIMEROCK-NEW MATERIAL FOR REWORKING BASE OPTIONAL BASE, BASE GROUP 01 OPTIONAL BASE, BASE GROUP 04 OPTIONAL BASE, BASE GROUP 09 OPTIONAL BASE, BASE GROUP 11 OPTIONAL BASE, BASE GROUP 13 STRESS ABSORBING MEMBRANE MILLING EXIST ASPH PAVT, 1" AVG DEPTH MILLING EXIST ASPH PAVT, 2" AVG DEPTH MILLING EXIST ASPH PAVT, 1 1/2" AVG DEPTH MILLING EXIST ASPH PAVT, 2 1/4" AVG DEPTH MILLING EXIST ASPH PAVT, 1 3/4" AVG DEPTH MILLING EXIST ASPH PAVT, 5 1/2" AVG DEPTH MILLING EXIST ASPH PAVT, 3/4" AVG DEPTH MILLING EXIST ASPH PAVT, 6" AVG DEPTH SUPERPAVE ASPHALTIC CONC, TRAFFIC C SUPERPAVE ASPHALTIC CONC, TRAFFIC D SUPERPAVE ASPH CONC, TRAFFIC C, PG76-22, PMA SUPERPAVE ASPH CONC, TRAFFIC D, PG76-22, PMA SUPERPAVE ASPH CONC, TRAFFIC LEVEL C, PG67-22 ASPHALT CONCRETE FRICTION COURSE- INC BIT/RUBBER, FC-5 SF SY SY CY SY SY LF CY CY SY SY CY SY SY SY SY SY SY SY SY SY SY SY SY SY SY TN TN TN TN TN TN Total Quantity Total Cost Average Unit Cost 4,336.000 410.222 903.000 24.970 446.000 127,421.820 576.000 18.600 15.000 832.760 0.000 1,265.160 4,001.000 25.000 3,512.660 1,276.000 247.000 109.000 45,108.940 52,783.982 96,922.600 17,815.430 416.670 548.000 47,318.030 433.623 7,913.813 794.140 1,310.370 2,192.530 218.990 3,217.310 $17,344.00 $2,051.11 $4,984.56 $249.81 $8,710.00 $127,682.98 $48,216.00 $6,231.00 $3,000.00 $39,860.40 $0.00 $75,897.51 $49,044.00 $1,017.50 $71,868.73 $22,827.64 $30,875.00 $3,978.50 $323,825.89 $285,896.85 $239,467.95 $171,387.44 $5,958.38 $7,885.72 $192,113.06 $3,403.94 $1,148,413.97 $117,985.30 $183,282.47 $301,086.47 $40,951.13 $539,497.57 $4.00 $5.00 $5.52 $10.00 $19.53 $1.00 $83.71 $335.00 $200.00 $47.87 $0.00 $59.99 $12.26 $40.70 $20.46 $17.89 $125.00 $36.50 $7.18 $5.42 $2.47 $9.62 $14.30 $14.39 $4.06 $7.85 $145.12 $148.57 $139.87 $137.32 $187.00 $167.69 Page 3 Florida Department of Transportation Maintenance Contract Cost Summary By Pay Item Number (SiteManager Data Only) 01/01/2012 - 12/31/2012 Statewide 2/12/2012 Pay Item Number Pay Item Description Unit of Measure 0337 7 22 0337 7 31 0337 7 32 0337 7 33 0337 7 35 0337 7 42 0337 7 43 0337 7 45 0337 7 63 0339 1 0350 72 0350 72 0350 78 0353 70 0400 1 1 0400 1 2 0400 1 11 0400 1 15 0400 1 25 0400 2 5 0400 4 4 0400143 0400145 0400153 0401 70 1 0401 70 5 0401 70 6 0401 71 11 0411 1 0411 2 0411 2 1 0413151 ASPHALT CONCRETE FRICTION COURSE, INC BIT, FC-5, ASPHALT CONCRETE FRICTION COURSE,TRAFFIC B, FC-12.5, ASPHALT CONCRETE FRICTION COURSE,TRAFFIC C, FC-9.5, ASPHALT CONCRETE FRICTION COURSE,TRAFFIC C, FC-12.5, ASPHALT CONCRETE FRICTION COURSE,TRAFFIC D, FC-12.5, ASPHALT CONCRETE FRICTION COURSE,TRAFFIC C, FC-9.5, ASPHALT CONCRETE FRICTION COURSE,TRAFFIC C, FC-12.5, ASPHALT CONCRETE FRICTION COURSE,TRAFFIC D, FC-12.5, ASPHALT CONCRETE FRICTION COURSE,TRAFFIC C, FC-4.75, MISCELLANEOUS ASPHALT PAVEMENT CLEANING & RESEALING JOINTS- CONCRETE PAVEMENT CLEANING & RESEALING JOINTS- EXISTING CONCRETE PAVEMENT: CLEANING & SEALING RANDOM CRACKS IN EXISTING CONCRETE CONCRETE PAVEMENT SLAB REPLACEMENT CONCRETE CLASS I, CULVERTS CONCRETE CLASS I, ENDWALLS CONCRETE CLASS I, RETAINING WALLS CONCRETE CLASS I, MISCELLANEOUS CONC CLASS I, MASS SUBSTRUCTURE CONCRETE CLASS II, SUBSTRUCTURE CONCRETE CLASS IV, SUPERSTRUCTURE CLEANING & COATING CONCRETE SURFACE, CLASS 5 CLEANING CONCRETE SURFACE NON SHRINK GROUT, F&I, MISCELLANEOUS- STRUCTURES RESTORE SPALLED AREAS, EPOXY RESTORE SPALLED AREAS, CONTRACTORS OPTION SPALLED AREAS RESTORE, THERMOSETTING POLYMER CONC RESTORE SPALLED AREAS- MAINTENANCE CONTRACTS ONLY, EPOXY MATERIAL FOR CRACK INJECTION- STRUCTURES REHAB CRACKS INJECT & SEAL- STRUCTURES REHAB INJECT AND SEAL CRACK- MAINTENANCE CONTRACTS ONLY, METHACRYLATE MONOMER TN TN TN TN TN TN TN TN TN TN LF LF LF CY CY CY CY CY CY CY CY SF SF CF CF CF CF CF GA LF LF GA Total Quantity Total Cost Average Unit Cost 1,352.460 112.340 1,347.020 2,846.900 442.500 1,778.810 299.740 730.300 283.560 2,266.187 1,690.000 9,897.000 3,669.000 599.860 32.620 66.450 20.000 21.000 2.000 1.250 6.000 2,179,553.000 1,503,431.000 265.000 126.500 42.000 102.000 9.000 4.150 1,137.200 790.000 24.000 $436,931.82 $16,938.63 $146,854.88 $365,922.11 $70,800.00 $222,827.40 $50,998.56 $216,168.80 $54,159.96 $476,209.12 $23,120.00 $267,464.00 $49,365.23 $244,032.81 $16,730.00 $47,837.50 $1,500.00 $4,725.00 $400.00 $1,250.00 $7,200.00 $408,688.69 $187,555.04 $7,073.00 $37,102.25 $6,300.00 $37,500.00 $5,400.00 $0.00 $38,680.80 $39,500.00 $12,000.00 $323.06 $150.78 $109.02 $128.53 $160.00 $125.27 $170.14 $296.00 $191.00 $210.14 $13.68 $27.02 $13.45 $406.82 $512.88 $719.90 $75.00 $225.00 $200.00 $1,000.00 $1,200.00 $0.19 $0.12 $26.69 $293.30 $150.00 $367.65 $600.00 $0.00 $34.01 $50.00 $500.00 Page 4 Florida Department of Transportation Maintenance Contract Cost Summary By Pay Item Number (SiteManager Data Only) 01/01/2012 - 12/31/2012 Statewide 2/12/2012 Pay Item Number Pay Item Description Unit of Measure 0413154 0415 1 6 0425 1351 0425 1361 0425 1411 0425 1521 0425 1541 0425 1545 0425 1551 0425 2 41 0425 2 42 0425 2110 0425 3 41 0425 5 0425 6 0425 11 0425 74 1 0425 74 2 0425 78 0425 82 0430 94 1 0430 94 2 0430 94 3 0430 94 4 0430 94 5 0430173118 0430174101 0430174102 0430174103 0430174112 0430174118 0430174124 CLEANING & SEALING CONCRETE SURFACES - PENETRANT REINFORCING STEEL- MISCELLANEOUS INLETS, CURB, TYPE P-5, <10' INLETS, CURB, TYPE P-6, <10' INLETS, CURB TYPE J-1, <10' INLETS, DT BOT, TYPE C,<10' INLETS, DT BOT, TYPE D, <10' INLETS, DITCH BOTTOM, TYPE D, PARTIAL INLETS, DT BOT, TYPE E, <10' MANHOLES, P-7, <10' MANHOLES, P-7, >10' MANHOLES, REPAIR JUNCTION BOX, DRAINAGE, P-7, <10' MANHOLE, ADJUST VALVE BOXES, ADJUST DRAINAGE STRUCTURE MODIFY MANHOLES & INLETS CLEANING & SEALING, <10' MANHOLES & INLETS CLEANING & SEALING, >10' INLET CAP, PRECAST REPLACE GRATE DESILTING PIPE, 0 - 24" DESILTING PIPE, 25 - 36" DESILTING PIPE, 37 - 48" DESILTING PIPE, 49 - 60" DESILTING PIPE, 61" OR GREATER PIPE CULVERT OPTIONAL MATERIAL, ROUND, 18", PIPE CULVERT, OPTIONAL MATERIAL, ROUND, 0-24"SD PIPE CULVERT, OPTIONAL MATERIAL, ROUND, 25-36"SD PIPE CULVERT, OPTIONAL MATERIAL, ROUND, 37-48"SD PIPE CULVERT, OPTIONAL MATERIAL, ROUND, 12"SD PIPE CULVERT, OPTIONAL MATERIAL, ROUND, 18"SD PIPE CULVERT, OPTIONAL MATERIAL, ROUND, 24"SD SF LB EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA LF LF LF LF LF LF LF LF LF LF LF LF Total Quantity Total Cost Average Unit Cost 1,840.000 1,194.540 11.000 2.000 1.000 10.000 1.000 1.000 2.000 1.000 2.000 1.000 1.000 46.000 3.000 3.000 41.000 26.000 56.000 7.000 991,345.700 427,212.400 181,341.600 56,381.650 6,663.800 25.000 190.000 90.000 144.000 153.000 554.000 535.000 $18,400.00 $3,655.77 $43,200.00 $9,000.00 $2,450.00 $21,400.00 $3,600.00 $1,000.00 $6,900.00 $3,400.00 $5,262.00 $1,200.00 $3,400.00 $13,140.00 $900.00 $2,000.00 $33,200.00 $17,400.00 $62,175.00 $3,547.60 $2,271,283.89 $1,142,022.95 $745,758.11 $372,016.27 $57,102.73 $1,000.00 $13,800.00 $6,750.00 $17,280.00 $6,058.80 $84,400.00 $68,680.00 $10.00 $3.06 $3,927.27 $4,500.00 $2,450.00 $2,140.00 $3,600.00 $1,000.00 $3,450.00 $3,400.00 $2,631.00 $1,200.00 $3,400.00 $285.65 $300.00 $666.67 $809.76 $669.23 $1,110.27 $506.80 $2.29 $2.67 $4.11 $6.60 $8.57 $40.00 $72.63 $75.00 $120.00 $39.60 $152.35 $128.37 Page 5 Florida Department of Transportation Maintenance Contract Cost Summary By Pay Item Number (SiteManager Data Only) 01/01/2012 - 12/31/2012 Statewide 2/12/2012 Pay Item Number Pay Item Description Unit of Measure 0430174130 0430174136 0430174142 0430174148 0430174160 0430174201 0430174202 0430174203 0430174236 0430175101 0430175115 0430175118 0430175124 0430175136 0430175148 0430950 0430982125 0430982129 0430984121 0430984123 0430984125 0430984129 0430984133 0430984138 0430984140 0430984141 0430984629 0430984638 0430984640 0430990 0430991 0431 1 1 PIPE CULVERT, OPTIONAL MATERIAL, ROUND, 30"SD PIPE CULVERT, OPTIONAL MATERIAL, ROUND, 36"SD PIPE CULVERT, OPTIONAL MATERIAL, ROUND, 42"SD PIPE CULVERT, OPTIONAL MATERIAL, ROUND, 48"SD PIPE CULVERT, OPTIONAL MATERIAL, ROUND, 60"SD PIPE CULVERT, OPTIONAL MATERIAL, OTHER - ELLIP/ARCH, PIPE CULVERT, OPTIONAL MATERIAL, OTHER - ELLIP/ARCH, PIPE CULVERT, OPTIONAL MATERIAL, OTHER - ELLIP/ARCH, PIPE CULVERT, OPTIONAL MATERIAL, OTHER SHAPE - ELLIP/ARCH, PIPE CULVERT,OPTIONAL MATERIAL,ROUND, 0-24"S/CD PIPE CULVERT,OPTIONAL MATERIAL,ROUND, 15"S/CD PIPE CULVERT,OPTIONAL MATERIAL,ROUND, 18"S/CD PIPE CULVERT,OPTIONAL MATERIAL,ROUND, 24"S/CD PIPE CULVERT, OPT MATERIAL, ROUND, 36"S/CD PIPE CULVERT, OPT MATERIAL, ROUND, 48"S/CD DESILTING CONCRETE BOX CULVERT, MITERED END SECTION, OPTIONAL ROUND, 18" CD MITERED END SECTION, OPTIONAL ROUND, 24" CD MITERED END SECTION, OPTIONAL ROUND, 12" SD MITERED END SECTION, OPTIONAL ROUND, 15" SD MITERED END SECTION, OPTIONAL ROUND, 18" SD MITERED END SECTION, OPTIONAL ROUND, 24" SD MITERED END SECTION , OPTIONAL ROUND, 30" SD MITERED END SECTION , OPTIONAL ROUND, 36" SIDE DRAIN MITERED END SECTION , OPTIONAL ROUND, 42" SD MITERED END SECTION , OPTIONAL ROUND, 48" SD MITERED END SECT, OPTIONAL - ELLIPTICAL / ARCH, 24" SD MITERED END SECT, OPTIONAL /ELLIP/ARCH, 36" SD MITERED END SECT, OPTIONAL /ELLIP/ARCH, 42" SD MITERED END SECT, REPLACE GRATE MITERED END SECT, REPLACE SLAB PIPE LINER, OPTIONAL MATERIAL, 0-24" LF LF LF LF LF LF LF LF LF LF LF LF LF LF LF CY EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA LF Total Quantity Total Cost Average Unit Cost 348.000 0.000 140.000 280.000 120.000 54.000 86.000 192.000 40.000 69.000 60.000 795.000 1,450.000 16.000 60.000 7,006.340 13.000 17.000 1.000 3.000 288.000 80.000 23.000 6.000 8.000 12.000 6.000 2.000 4.000 2.000 226.000 11,037.000 $16,440.00 $0.00 $8,120.00 $27,760.00 $14,400.00 $3,240.00 $7,310.00 $25,920.00 $2,000.00 $4,140.00 $4,080.00 $54,502.00 $92,560.00 $1,200.00 $6,000.00 $302,942.37 $11,600.00 $19,000.00 $748.00 $1,200.00 $219,750.00 $57,475.00 $26,600.00 $4,800.00 $10,800.00 $18,400.00 $4,500.00 $800.00 $5,200.00 $450.00 $102,350.00 $1,042,312.53 $47.24 $0.00 $58.00 $99.14 $120.00 $60.00 $85.00 $135.00 $50.00 $60.00 $68.00 $68.56 $63.83 $75.00 $100.00 $43.24 $892.31 $1,117.65 $748.00 $400.00 $763.02 $718.44 $1,156.52 $800.00 $1,350.00 $1,533.33 $750.00 $400.00 $1,300.00 $225.00 $452.88 $94.44 Page 6 Florida Department of Transportation Maintenance Contract Cost Summary By Pay Item Number (SiteManager Data Only) 01/01/2012 - 12/31/2012 Statewide 2/12/2012 Pay Item Number Pay Item Description Unit of Measure 0431 1 2 0431 1 3 0431 1 4 0433 1 0436 1 1 0440 1 20 0440 1 50 0440 73 3 0443 70 3 0450 82 0455 88 3 0455122 3 0457 70305 0457 70309 0458 1 21 0458 1 26 0460 1 13 0460 70 1 0460 70 2 0465 2122 0465 2152 0470 1 0471 1 1 0510 1 0514 71 1 0515 1 1 0515 1 2 0515 2201 0515 2202 0515 2301 0515 2302 0520 1 7 PIPE LINER, OPTIONAL MATERIAL, 25-36" PIPE LINER, OPTIONAL MATERIAL, 37-48" PIPE LINER, OPTIONAL MATERIAL, 49 - 60" CHEMICAL GROUT REPAIR, MANHOLE / INLET TRENCH DRAIN, STANDARD UNDERDRAIN, TYPE II UNDERDRAIN, TYPE V UNDERDRAIN OUTLET PIPE, 8" FRENCH DRAIN, 18" BEAMS REPAIR DRILLED SHAFT, 36" DIA EXCAVATION UNCLASSIFIED SHAFT, 36" DIA PILE JACKET INTEGRAL, CLASS III CONC FIL, 18" PILE JACKET INTEGRAL, CLASS III CONC FIL, 24" BRIDGE DECK EXPANSION JOINT, REHABILITATION, POURED BRIDGE DECK EXPANSION JOINT, REHABILITATION, OTHER STRUCTURAL STEEL REHAB- BOLTS, NUTS, WASHERS ALUMINUM BULLET RAILINGS, SINGLE RAIL ALUMINUM BULLET RAILINGS, DOUBLE RAIL MOVABLE BRIDGE MACHINERY AND CASTING-REHAB, F&I, MOVABLE BRIDGE MACHINERY AND CASTING-REHAB, F&I, TREATED TIMBER, STRUCTURAL FENDER SYSTEM,PLASTIC MARINE LUMBER,REINFORCED NAVIGATION LIGHTS- FIXED BRIDGE, SYSTEM PLASTIC FILTER FABRIC, SUBSURFACE PIPE HANDRAIL - GUIDERAIL, STEEL PIPE HANDRAIL - GUIDERAIL, ALUMINUM PEDESTRIAN/ BICYCLE RAILING, STEEL,42" PICKET RAIL PEDESTRIAN / BICYCLE RAILING, STEEL, 54" PICKET RAIL PEDESTRIAN/ BICYCLE RAILING, ALUMINUM ONLY,42" PICKET RAIL PEDESTRIAN/ BICYCLE RAILING, ALUMINUM ONLY,54" PICKET RAIL CONCRETE CURB & GUTTER, TYPE E LF LF LF EA LF LF LF LF LF LF LF LF LF LF LF LF LB LF LF EA EA MB MB LS SY LF LF LF LF LF LF LF Total Quantity Total Cost Average Unit Cost 10,731.700 6,705.200 506.800 29.000 97.000 315.000 415.000 20.000 190.000 1.000 54.000 54.000 27.000 161.000 4,060.500 11.000 156.000 97.000 232.500 2.000 0.330 0.230 0.300 1.000 26.000 254.000 3,123.500 99.000 28.000 698.500 382.000 855.950 $1,348,613.80 $1,344,077.65 $203,714.00 $29,000.00 $19,400.00 $13,541.85 $6,225.00 $500.00 $15,200.00 $180.00 $15,120.00 $4,320.00 $14,850.00 $96,600.00 $356,225.00 $1,375.00 $3,744.00 $1,345.00 $4,575.00 $14,000.00 $23,430.00 $920.00 $16,350.00 $555.00 $78.00 $9,352.00 $108,342.53 $4,950.00 $2,100.00 $26,048.04 $11,401.22 $24,340.13 $125.67 $200.45 $401.96 $1,000.00 $200.00 $42.99 $15.00 $25.00 $80.00 $180.00 $280.00 $80.00 $550.00 $600.00 $87.73 $125.00 $24.00 $13.87 $19.68 $7,000.00 $71,000.00 $4,000.00 $54,500.00 $555.00 $3.00 $36.82 $34.69 $50.00 $75.00 $37.29 $29.85 $28.44 Page 7 Florida Department of Transportation Maintenance Contract Cost Summary By Pay Item Number (SiteManager Data Only) 01/01/2012 - 12/31/2012 Statewide 2/12/2012 Pay Item Number Pay Item Description Unit of Measure 0520 1 8 0520 1 10 0520 2 4 0520 3 0521 1 0522 1 0522 2 0524 1 2 0524 1 4 0524 1 29 0524 1 49 0524 2 1 0524 2 2 0524 2 29 0527 1 0530 1 0530 3 3 0530 3 3 0530 3 4 0530 74 0530 76 2 0530 78 0536 1 1 0536 1 3 0536 1 5 0536 1 8 0536 1 9 0536 2 0536 7 0536 8 0536 8 6 0536 73 CONCRETE CURB & GUTTER, SPECIAL CONCRETE CURB & GUTTER, TYPE F CONCRETE CURB, TYPE D VALLEY GUTTER- CONCRETE MEDIAN CONCRETE BARRIER WALL SIDEWALK CONCRETE, 4" THICK SIDEWALK CONCRETE, 6" THICK CONCRETE DITCH PAVEMENT, NON REINFORCED, 4" CONCRETE DITCH PAVEMENT, NON REINFORCED, 6" CONCRETE DITCH PAVEMENT, 4", REINFORCED CONCRETE DITCH PAVEMENT, 6", REINFORCED CONCRETE SLOPE PAVEMENT,NON REINFORCED, 3" CONCRETE SLOPE PAVEMENT,NON REINFORCED, 4" CONCRETE SLOPE PAVEMENT, 4", REINFORCED DETECTABLE WARNING ON EXISTING WALKING SURFACE, RETROFIT RIPRAP, SAND-CEMENT RIPRAP, RUBBLE, BANK AND SHORE RIPRAP- RUBBLE, BANK AND SHORE RIPRAP, RUBBLE, F&I, DITCH LINING BEDDING STONE GABION MAT, 9" THICK RIPRAP - ARTICULATING BLOCK GUARDRAIL -ROADWAY GUARDRAIL- ROADWAY, DOUBLE FACE GUARDRAIL- ROADWAY, THRIE BEAM GUARDRAIL, ROADWAY, WITH RUB RAIL GUARDRAIL- ROADWAY, THRIE BEAM, DOUBLE FACE GUARDRAIL- SHOP-BENT PANELS SPECIAL GUARDRAIL POST GUARDRAIL- BRIDGE ANCHORAGE ASSEMBLY, GUARDRAIL, BRIDGE ANCHORAGE ASSEMBLY, REMOVE GUARDRAIL REMOVAL LF LF LF LF LF SY SY SY SY SY SY SY SY SY EA CY TN TN TN TN SY SY LF LF LF LF LF LF EA EA EA LF Total Quantity Total Cost Average Unit Cost 1,015.670 6,659.670 18.000 150.000 23.500 43,910.446 18,279.251 24,292.050 1,138.000 102.000 2,428.330 11.500 32.000 296.000 766.000 71.140 6.300 1,138.370 53.000 134.840 4,737.320 860.222 12,582.450 825.000 256.250 87.500 100.000 1,825.000 169.000 6.000 1.000 14,776.750 $18,188.57 $126,291.17 $339.00 $3,779.40 $3,525.00 $1,419,819.07 $631,126.20 $784,870.84 $70,590.00 $4,998.00 $105,486.66 $1,072.50 $1,733.00 $20,424.00 $349,651.33 $22,828.90 $781.20 $111,798.05 $1,865.00 $33,710.00 $307,925.80 $94,624.42 $255,405.14 $23,329.00 $5,796.00 $1,312.50 $3,125.00 $50,653.14 $12,577.00 $10,250.00 $450.00 $90,221.53 $17.91 $18.96 $18.83 $25.20 $150.00 $32.33 $34.53 $32.31 $62.03 $49.00 $43.44 $93.26 $54.16 $69.00 $456.46 $320.90 $124.00 $98.21 $35.19 $250.00 $65.00 $110.00 $20.30 $28.28 $22.62 $15.00 $31.25 $27.76 $74.42 $1,708.33 $450.00 $6.11 Page 8 Florida Department of Transportation Maintenance Contract Cost Summary By Pay Item Number (SiteManager Data Only) 01/01/2012 - 12/31/2012 Statewide 2/12/2012 Pay Item Number Pay Item Description Unit of Measure 0536 76 0536 82 0536 83 1 0536 85 22 0536 85 24 0536 85 25 0536 85 26 0538 1 0539 75113 0544 74 40 0544 75 23 0546 71 0547 70 1 0547 70 2 0550 10110 0550 10118 0550 10140 0550 10148 0550 10150 0550 10210 0550 10220 0550 10221 0550 10222 0550 10228 0550 10230 0550 10238 0550 10250 0550 10251 0550 10252 0550 10919 0550 15 11 0550 15 12 GUARDRAIL POST - SPECIAL LENGTH GUARDRAIL ANCHORAGE- CONCRETE BARRIER GUARDRAIL POST REPLACEMENT, REGULAR GUARDRAIL END ANCHORAGE ASSEMBLY- FLARED GUARDRAIL END ANCHORAGE ASSEMBLY- PARALLEL GUARDRAIL END ANCHORAGE ASSEMBLY- TYPE II GUARDRAIL END ANCHORAGE ASSEMBLY- TYPE CRT GUARDRAIL RESET GLARE SCREEN , F&I, MODULAR, 30" RELOCATE CRASH CUSHION CRASH CUSHION - SCI RUMBLE STRIPS RIPRAP FABRIC-FORMED CONCRETE, 8" FILTER POINTS RIPRAP FABRIC-FORMED CONCRETE, 10" FILTER POINTS FENCING, TYPE A, 0.0-5.0', STANDARD FENCING, TYPE A, 0.0-5.0', TYPE A STANDARD, RESET EXISTING FENCING, TYPE A, 7.1-8.0', STANDARD FENCING, TYPE A, 7.1-8.0', RESET EXISTING FENCING, TYPE A, 8.1-10.0', STANDARD FENCING, TYPE B, 0.0-5.0', STANDARD FEATURES FENCING, TYPE B, 5.1-6.0', STANDARD FENCING, TYPE B, 5.1-6.0', W/ BARB WIRE ATTMT FENCING, TYPE B, 5.1-6.0, W/ VINYL COATING FENCING, TYPE B, 5.1-6.0, RESET EXISTING FENCING, TYPE B, 6.1-7.0', STANDARD FENCING, TYPE B, 6.1-7.0, RESET EXISTING FENCING, TYPE B, 8.1-10.0', STANDARD FEATURES FENCING, TYPE B, 8.1-10.0', WITH BARBED WIRE ATTMT FENCING, TYPE B, 8.1-10.0', VINYL COATING FENCING, SPECIAL TYPE, 0.0-5.0', SPECIAL FEATURES FENCE REPAIR, TYPE A, CORNER POST ASSY FENCE REPAIR, TYPE A, LINE POST ASSY EA EA EA EA EA EA EA LF LF EA EA PS SY SY LF LF LF LF LF LF LF LF LF LF LF LF LF LF LF LF AS AS Total Quantity Total Cost Average Unit Cost 17.000 4.000 264.000 30.000 50.000 19.000 2.000 58,234.440 1,234.000 2.000 2.000 21.000 809.000 2,120.000 2,560.000 1,770.000 15,055.000 327.000 25.000 5,542.000 11,403.000 23,775.000 975.000 6,080.000 110.000 652.000 600.000 650.000 845.000 75.000 27.000 451.000 $3,157.50 $1,400.00 $14,415.00 $53,726.80 $99,282.55 $9,821.80 $2,113.40 $452,894.85 $55,530.00 $2.00 $46,800.00 $6,300.00 $48,540.00 $73,436.80 $19,130.10 $2,992.50 $150,550.00 $2,223.60 $75.75 $76,463.00 $130,196.65 $260,842.50 $10,902.50 $17,265.00 $2,173.60 $12,883.52 $10,500.00 $13,000.00 $12,615.85 $1,500.00 $2,754.00 $20,182.25 $185.74 $350.00 $54.60 $1,790.89 $1,985.65 $516.94 $1,056.70 $7.78 $45.00 $1.00 $23,400.00 $300.00 $60.00 $34.64 $7.47 $1.69 $10.00 $6.80 $3.03 $13.80 $11.42 $10.97 $11.18 $2.84 $19.76 $19.76 $17.50 $20.00 $14.93 $20.00 $102.00 $44.75 Page 9 Florida Department of Transportation Maintenance Contract Cost Summary By Pay Item Number (SiteManager Data Only) 01/01/2012 - 12/31/2012 Statewide 2/12/2012 Pay Item Number Pay Item Description Unit of Measure 0550 15 13 0550 60111 0550 60112 0550 60211 0550 60212 0550 60222 0550 60234 0570 1 1 0570 1 2 0571 1 11 0580 1 2 0630 1 11 0630 1 12 0630 1 14 0632 6 1 0632 7 1 0634 4152 0634 4153 0634 5 1 0635 1 11 0639 1 12 0639 1 22 0639 2 1 0641 2 12 0641 2 17 0643150 0650 51113 0650 51313 0650 51513 0653191 0653192 0659107 FENCE REPAIR, TYPE A, PULL POST ASSY FENCE GATE, TYPE A, SINGLE, 0-6.0' OPENING FENCE GATE, TYPE A, SINGLE, 6.1-12.0' OPENING FENCE GATE, TYPE B, SINGLE, 0- 6.0' OPENING FENCE GATE, TYPE B, SINGLE, 6.1 - 12.0' OPENING FENCE GATE, TYPE B, DOUBLE, 6.1-12.0' OPENING FENCE GATE, TYPE B, SLIDING/CANTILEVER, 18.1-20.0' OPENING PERFORMANCE TURF PERFORMANCE TURF, SOD PLASTIC EROSION MAT, TURF REINFORCED MAT, TYPE 1 LANDSCAPE COMPLETE- LARGE PLANTS CONDUIT, FURNISH & INSTALL, ABOVEGROUND CONDUIT, FURNISH & INSTALL, UNDERGROUND CONDUIT, F & I, UNDERGROUND -JACKED CABLE, FURNISH & INSTALL SIGNAL CABLE, FURNISH & INSTALL SPAN WIRE ASSEMBLY, F&I, TWO POINT, DIAGONAL SPAN WIRE ASSEMBLY, F&I, TWO POINT, BOX FIBERGLASS INSULATOR, FURNISH & INSTALL PULL & JUNCTION BOX, F&I, PULL BOX ELECTRICAL POWER SERVICE, OVERHEAD, ELECTRICAL POWER SERVICE, UNDERGROUND, ELECTRICAL SERVICE WIRE PRESTRESSED CONCRETE POLE, F&I, TYPE P-II SERVICE POLE PRESTRESSED CONCRETE POLE, F&I, TYPE P-VII STRAIN POLE, WOOD, F&I, 50' TRAFFIC SIGNAL, F&I, 1 SECTIONS, 1 WAY, SPECIAL TRAFFIC SIGNAL, F&I, 3 SECTIONS, 1 WAY, SPECIAL TRAFFIC SIGNAL, F&I, 5 SECTIONS, 1 WAY, SPECIAL PEDESTRIAN SIGNAL, F&I, LED - COUNT DOWN, 1 DIRECTION PEDESTRIAN SIGNAL, F&I, LED - COUNT DOWN, 2 DIRECTIONS SIGNAL HEAD AUXILIARIES, F&I, ALUMINUM PEDESTAL AS EA EA EA EA EA EA SY SY SY LS LF LF LF LF PI PI PI LF EA AS AS LF EA EA EA AS AS AS AS AS EA Total Quantity Total Cost Average Unit Cost 202.000 3.000 8.000 6.000 2.000 6.000 2.000 165,914.869 371,402.580 6,000.000 3.131 85.000 497.000 2,812.000 742.000 51.000 30.000 5.000 290.000 47.000 19.000 3.000 947.000 3.000 5.000 1.000 164.000 155.000 42.000 42.000 9.000 5.000 $20,604.00 $900.00 $4,800.00 $0.06 $1,454.10 $2,800.00 $3,000.00 $265,706.78 $817,221.92 $30,000.00 $985,286.85 $1,108.40 $4,110.19 $23,255.24 $3,220.28 $76,238.24 $27,230.70 $7,533.05 $5,327.30 $12,104.85 $20,184.84 $2,863.80 $1,268.98 $2,425.77 $27,217.45 $1,311.65 $67,389.24 $117,924.00 $46,936.68 $23,863.14 $8,963.46 $4,060.55 $102.00 $300.00 $600.00 $0.01 $727.05 $466.67 $1,500.00 $1.60 $2.20 $5.00 $314,687.59 $13.04 $8.27 $8.27 $4.34 $1,494.87 $907.69 $1,506.61 $18.37 $257.55 $1,062.36 $954.60 $1.34 $808.59 $5,443.49 $1,311.65 $410.91 $760.80 $1,117.54 $568.17 $995.94 $812.11 Page 10 Florida Department of Transportation Maintenance Contract Cost Summary By Pay Item Number (SiteManager Data Only) 01/01/2012 - 12/31/2012 Statewide 2/12/2012 Pay Item Number Pay Item Description Unit of Measure 0660 1110 0660 2101 0660 2102 0660 2106 0665 11 0670 4 1 0670 5111 0678 1109 0690 10 0690 20 0690 31 0690 32 1 0690 50 0690 70 0690 80 0690 90 0690100 0700 20 11 0700 20 12 0700 20 14 0700 20 15 0700 20 31 0700 20 32 0700 20 40 0700 20 60 0700 21 11 0700 21 12 0700 21 13 0700 21 14 0700 21 15 0700 21 16 0700 21 31 LOOP DETECTOR INDUCTIVE, F&I, TYPE 10 LOOP ASSEMBLY- F&I, TYPE A LOOP ASSEMBLY, F&I, TYPE B LOOP ASSEMBLY, F&I, TYPE F PEDESTRIAN DETECTOR, F&I, POLE OR CONTROLLER FLASHING BEACON CONTROLLER ASSEMBLY, F&I TRAFFIC CONTROLLER ASSEMBLY, F&I, NEMA, 1 PREEMPTION CONTROLLER ACCESSORIES, F&I, TYPE 3 TIME SWITCH SIGNAL HEAD TRAFFIC ASSEMBLY REMOVAL SIGNAL PEDESTRIAN ASSEMBLY REMOVAL SIGNAL PEDESTAL REMOVAL POLE REMOVAL, SHALLOW, DIRECT BURIAL CONTROLLER ASSEMBLY, REMOVE, COMPLETE ASSEMBLY DETECTOR PEDESTRIAN ASSEMBLY REMOVE SPAN WIRE ASSEMBLY, REMOVE CONDUIT & CABLING REMOVE SIGNAL EQUIPMENT MISCELLANOUS REMOVE SINGLE POST SIGN, F&I, LESS THAN 12 SF SINGLE POST SIGN, F&I, 12-20 SF SINGLE POST SIGN, F&I, 21-30 SF SINGLE POST SIGN, F&I, 31+ SF SINGLE POST SIGN, INSTALL, LESS THAN 12 SF SINGLE POST SIGN, INSTALL, 12-20 SF SINGLE POST SIGN, RELOCATE SINGLE POST SIGN, REMOVE MULTI- POST SIGN, F&I, 50 SF OR LESS MULTI- POST SIGN, F&I, 51 - 100 SF MULTI- POST SIGN, F&I, 101 - 150 SF MULTI- POST SIGN, F&I, 151 - 200 SF MULTI- POST SIGN, F&I, 201 - 250 SF MULTI- POST SIGN, F&I, 251 - 300 SF MULTI- POST SIGN, INSTALL, 50 SF OR LESS EA AS AS AS EA AS AS EA EA EA EA EA EA EA EA PI PI AS AS AS AS AS AS AS AS AS AS AS AS AS AS AS Total Quantity Total Cost Average Unit Cost 161.000 56.000 97.000 69.000 61.000 20.000 23.000 8.000 213.000 45.000 1.000 9.000 39.000 58.000 37.000 45.000 44.000 1,717.000 434.000 7.000 4.000 6.000 5.000 46.000 1,290.000 125.000 32.000 8.000 8.000 2.000 4.000 3.000 $25,407.41 $51,265.60 $71,962.62 $79,259.20 $5,457.06 $11,515.20 $334,091.56 $1,953.36 $4,656.18 $983.70 $349.70 $3,147.30 $10,228.92 $1,267.88 $6,469.45 $7,868.25 $7,693.40 $363,856.08 $299,332.44 $7,268.07 $3,772.28 $1,500.00 $3,250.00 $3,067.24 $15,387.14 $338,390.10 $83,200.00 $23,000.00 $40,220.00 $10,923.90 $22,641.68 $6,450.00 $157.81 $915.46 $741.88 $1,148.68 $89.46 $575.76 $14,525.72 $244.17 $21.86 $21.86 $349.70 $349.70 $262.28 $21.86 $174.85 $174.85 $174.85 $211.91 $689.71 $1,038.30 $943.07 $250.00 $650.00 $66.68 $11.93 $2,707.12 $2,600.00 $2,875.00 $5,027.50 $5,461.95 $5,660.42 $2,150.00 Page 11 Florida Department of Transportation Maintenance Contract Cost Summary By Pay Item Number (SiteManager Data Only) 01/01/2012 - 12/31/2012 Statewide 2/12/2012 Pay Item Number Pay Item Description Unit of Measure 0700 21 40 0700 21 60 0700 23123 0700 48 18 0700 48 19 0700 48 28 0700 48 39 0700 48 43 0700 48 52 0700 48 53 0700 48 58 0700 48 59 0700 48 60 0700 90 11 0700 90 31 0700 90 32 0701 11111 0701 11121 0701 11211 0705 10 1 0705 10 2 0705 11 1 0705 11 2 0705 11 3 0705 11 4 0706 3 0710 11111 0710 11122 0710 11123 0710 11124 0710 11125 0710 11131 MULTI- POST SIGN, RELOCATE MULTI- POST SIGN, REMOVE OVERHEAD TRUSS CANTILEVER SIGN, FURNISH & INSTALL, SIGN PANELS, F & I, 15 OR < SIGN PANELS, F & I, 16 - 100 SIGN PANELS, INSTALL, 15 OR LESS SIGN PANELS, OVERLAY, 16 - 100 SIGN PANELS, RELOCATE, 201 - 300 SIGN PANELS, REPLACE, 101 - 200 SIGN PANELS, REPLACE, 201 - 300 SIGN PANELS, REPLACE, 15 OR LESS SIGN PANELS, REPLACE, 16 - 100 SIGN PANELS, REMOVE SIGN FLASHING BEACON, F&I GROUND MOUNT SIGN FLASHING BEACON, REMOVE, GROUND MOUNT SIGN FLASHING BEACON, REMOVE, OVERHEAD MOUNT AUDIBLE & VIBRATORY PAVEMENT MARKING,STANDARD, AUDIBLE & VIBRATORY PAVEMENT MARKING,STANDARD, AUDIBLE & VIBRATORY PAVEMENT MARKING,STANDARD, OBJECT MARKER, TYPE 1 OBJECT MARKER, TYPE 2 DELINEATOR, FLEXIBLE TUBULAR DELINEATOR, NON-FLEXIBLE DELINEATOR, FLEXIBLE HIGH VISABILITY MEDIAN DELINEATOR, FLEXIBLE HIGH PERFORMANCE RETRO-REFLECTIVE PAVEMENT MARKERS PAINTED PAVEMENT MARKINGS, STANDARD, WHITE, SOLID, 6" PAINTED PAVEMENT MARKINGS, STANDARD, WHITE, SOLID, 8" PAINTED PAVEMENT MARKINGS, STANDARD, WHITE, SOLID, 12" PAINTED PAVEMENT MARKINGS, STANDARD, WHITE, SOLID, 18" PAINTED PAVEMENT MARKINGS, STANDARD, WHITE, SOLID, 24" PAINTED PAVEMENT MARKINGS, STANDARD, WHITE, SKIP, 6", AS AS AS EA EA EA EA EA EA EA EA EA EA AS AS AS NM GM NM EA EA EA EA EA EA EA NM LF LF LF LF GM Total Quantity Total Cost Average Unit Cost 1.000 151.000 1.000 228.000 33.000 2.000 8.000 2.000 23.000 1.000 34.000 56.000 80.000 3.000 17.000 30.000 312.515 0.000 108.003 11.000 140.000 931.000 56.000 12.000 33,550.000 116,072.000 803.263 778.000 1,396.000 619.000 329.500 624.753 $5.91 $23,445.08 $66,091.00 $45,446.19 $52,451.00 $100.00 $5,160.00 $1,920.00 $51,200.00 $2,500.00 $1,035.00 $106,450.00 $20,636.50 $6,011.87 $5,610.00 $9,900.00 $1,394,505.42 $0.00 $482,750.81 $427.00 $5,000.48 $46,466.00 $1,364.68 $960.00 $989,280.00 $289,153.90 $280,317.99 $359.20 $1,846.90 $1,067.85 $568.60 $82,490.09 $5.91 $155.27 $66,091.00 $199.33 $1,589.42 $50.00 $645.00 $960.00 $2,226.09 $2,500.00 $30.44 $1,900.89 $257.96 $2,003.96 $330.00 $330.00 $4,462.20 $0.00 $4,469.79 $38.82 $35.72 $49.91 $24.37 $80.00 $29.49 $2.49 $348.97 $0.46 $1.32 $1.73 $1.73 $132.04 Page 12 Florida Department of Transportation Maintenance Contract Cost Summary By Pay Item Number (SiteManager Data Only) 01/01/2012 - 12/31/2012 Statewide 2/12/2012 Pay Item Number Pay Item Description Unit of Measure 0710 11151 0710 11160 0710 11170 0710 11190 0710 11190 0710 11211 0710 11224 0710 11231 0710 11251 0710 11290 0710 11331 0711 11111 0711 11112 0711 11121 0711 11122 0711 11123 0711 11124 0711 11125 0711 11131 0711 11131 0711 11133 0711 11141 0711 11142 0711 11151 0711 11160 0711 11170 0711 11180 0711 11211 0711 11221 0711 11222 0711 11224 0711 11225 PAINTED PAVEMENT MARKINGS, STANDARD, WHITE, DOTTED / PAINTED PAVEMENT MARKINGS, STANDARD, WHITE, MESSAGE PAINTED PAVEMENT MARKINGS, STANDARD, WHITE, ARROWS PAINTED PAVEMENT MARKINGS, STANDARD, WHITE, PAINTED PAVEMENT MARKINGS,STANDARD,WHITE,ISLAND NOSE PAINTED PAVEMENT MARKINGS, STANDARD, YELLOW, SOLID, 6" PAINTED PAVEMENT MARKINGS, STANDARD, YELLOW, SOLID, 18" PAINTED PAVEMENT MARKINGS, STANDARD, YELLOW, SKIP, 6" PAINTED PAVEMENT MARKINGS, STANDARD, YELLOW, DOTTED/ PAINTED PAVEMENT MARKINGS, STANDARD, YELLOW, ISLAND PAINTED PAVEMENT MARKINGS, STANDARD,BLACK, SKIP, 6" THERMOPLASTIC, STANDARD, WHITE, SOLID, 6" THERMOPLASTIC, STANDARD, WHITE, SOLID, 8" THERMOPLASTIC, STANDARD, WHITE, SOLID, 6" THERMOPLASTIC, STANDARD, WHITE, SOLID, 8" THERMOPLASTIC, STANDARD, WHITE, SOLID, 12" THERMOPLASTIC, STANDARD, WHITE, SOLID, 18" THERMOPLASTIC, STANDARD, WHITE, SOLID, 24" THERMOPLASTIC, STANDARD, WHITE, SKIP, 6" THERMOPLASTIC, STANDARD, WHITE, SKIP, 6", THERMOPLASTIC, STANDARD, WHITE, SKIP, 12"- APPROACH TO THERMOPLASTIC, STANDARD, WHITE, SKIP, 6" THERMOPLASTIC, STANDARD, WHITE, SKIP, 8" THERMOPLASTIC, STANDARD, WHITE, DOTTED/GUIDELINE/ THERMOPLASTIC, STANDARD, WHITE, MESSAGE THERMOPLASTIC, STANDARD, WHITE, ARROW THERMOPLASTIC, STANDARD, WHITE, YIELD LINE THERMOPLASTIC, STANDARD,YELLOW, SOLID, 6" THERMOPLASTIC, STANDARD, YELLOW, SOLID, 6" THERMOPLASTIC, STANDARD, YELLOW, SOLID, 8" THERMOPLASTIC, STANDARD, YELLOW, SOLID, 18" THERMOPLASTIC, STANDARD, YELLOW, SOLID, 24" LF EA EA SF SF NM LF GM LF SF GM NM NM LF LF LF LF LF GM GM GM LF LF LF EA EA LF NM LF LF LF LF Total Quantity Total Cost Average Unit Cost 850.000 11.000 53.000 560.000 114.000 544.261 121.000 143.441 489.000 18,013.000 610.052 894.215 6,270.373 12,899.000 405,375.000 358,654.000 144,325.750 121,411.500 38.200 783.276 2.105 1,800.000 450.000 91,640.330 2,107.000 13,233.000 24.000 751.996 650.000 31,978.000 81,613.000 246.000 $1,016.50 $777.20 $1,752.60 $667.30 $57.00 $190,944.02 $132.80 $18,600.34 $417.45 $31,054.50 $66,220.23 $2,943,659.87 $68,075.01 $16,768.70 $569,791.28 $829,119.87 $360,135.48 $351,522.97 $7,896.00 $752,701.82 $4,661.28 $2,430.00 $563.10 $77,809.11 $161,293.49 $659,672.99 $171.72 $2,389,023.55 $845.00 $22,653.86 $193,211.20 $2.46 $1.20 $70.65 $33.07 $1.19 $0.50 $350.83 $1.10 $129.67 $0.85 $1.72 $108.55 $3,291.89 $10.86 $1.30 $1.41 $2.31 $2.50 $2.90 $206.70 $960.97 $2,214.38 $1.35 $1.25 $0.85 $76.55 $49.85 $7.16 $3,176.91 $1.30 $0.71 $2.37 $0.01 Page 13 Florida Department of Transportation Maintenance Contract Cost Summary By Pay Item Number (SiteManager Data Only) 01/01/2012 - 12/31/2012 Statewide 2/12/2012 Pay Item Number Pay Item Description Unit of Measure 0711 11231 0711 11251 0711 11421 0711 12111 0711 12121 0711 12122 0711 12123 0711 12124 0711 12125 0711 12131 0711 12151 0711 12160 0711 12170 0711 12211 0711 12221 0711 12222 0711 12224 0711 12231 0711 12241 0711 12251 0711 13111 0711 13122 0711 13131 0711 13151 0711 13211 0711 13222 0711 13231 0711 13251 0711 14123 0711 14160 0711 14170 0711 17 THERMOPLASTIC, STANDARD, YELLOW, SKIP, 6" THERMOPLASTIC, STANDARD, YELLOW, DOTTED / GUIDELINE THERMOPLASTIC, STANDARD, BLUE, SOLID,6" THERMOPLASTIC, REFURBISHMENT, WHITE, SOLID, 6" THERMOPLASTIC, REFURBISHMENT, WHITE, SOLID, 6" THERMOPLASTIC, REFURBISHMENT, WHITE, SOLID, 8" THERMOPLASTIC, REFURBISHMENT, WHITE, SOLID, 12" THERMOPLASTIC, REFURBISHMENT, WHITE, SOLID, 18" THERMOPLASTIC, REFURBISHMENT, WHITE, SOLID, 24" THERMOPLASTIC, REFURBISHMENT, WHITE, SKIP, 6" THERMOPLASTIC, REFURBISHMENT, WHITE, DOTTED/ GUIDELINE THERMOPLASTIC, REFURBISH, WHITE, MESSAGE THERMOPLASTIC, REFURBISH, WHITE, ARROWS THERMOPLASTIC, REFURBISHMENT, YELLOW, SOLID, 6" THERMOPLASTIC, REFURBISHMENT, YELLOW, SOLID, 6" THERMOPLASTIC, REFURBISHMENT, YELLOW, SOLID, 8" THERMOPLASTIC, REFURBISHMENT, YELLOW, SOLID, 18" THERMOPLASTIC, REFURBISHMENT, YELLOW, SKIP, 6" THERMOPLASTIC, REFURBISHMENT, YELLOW, SKIP, 6" THERMOPLASTIC, REFURBISHMENT, YELLOW THERMOPLASTIC, HOT SPRAY, WHITE, SOLID, 6" THERMOPLASTIC, HOT SPRAY, WHITE, SOLID, 8" THERMOPLASTIC, HOT SPRAY, WHITE, SKIP, 6" THERMOPLASTIC, HOT SPRAY, WHITE, DOTTED /GUIDELINE/ THERMOPLASTIC, HOT SPRAY, YELLOW, SOLID, 6" THERMOPLASTIC, HOT SPRAY, YELLOW, SOLID, 8" THERMOPLASTIC, HOT SPRAY, YELLOW, SKIP, 6" THERMOPLASTIC, HOT SPRAY, YELLOW, DOTTED / GUIDELINE/ THERMOPLASTIC, PREFORMED, WHITE, SOLID, 12" THERMOPLASTIC, PREFORMED, WHITE, MESSAGE THERMOPLASTIC, PREFORMED, WHITE, ARROWS THERMOPLASTIC, REMOVE GM LF LF NM LF LF LF LF LF GM LF EA EA NM LF LF LF GM LF LF NM LF GM LF NM LF GM LF LF EA EA SF Total Quantity Total Cost Average Unit Cost 172.403 55,968.000 68.000 210.774 59,882.000 83,497.000 137,120.000 29,026.000 36,864.000 130.440 12,233.000 590.000 2,931.000 143.161 63,310.000 2,801.000 10,044.000 29.900 474.000 9,661.000 173.051 72,688.000 139.970 814.000 134.743 6,151.000 30.216 8,364.000 6,563.000 855.000 325.000 196,636.500 $163,489.79 $42,386.44 $149.60 $434,526.55 $52,136.16 $71,360.80 $255,668.32 $56,915.10 $100,092.78 $72,109.84 $7,159.82 $26,384.00 $149,818.99 $282,724.13 $58,797.75 $1,739.33 $16,645.48 $17,882.76 $298.62 $7,670.65 $285,083.16 $34,163.36 $92,958.48 $284.90 $223,266.39 $2,890.97 $19,425.95 $2,927.40 $42,790.76 $147,600.71 $30,941.40 $26,893.53 $948.30 $0.76 $2.20 $2,061.58 $0.87 $0.85 $1.86 $1.96 $2.72 $552.82 $0.59 $44.72 $51.12 $1,974.87 $0.93 $0.62 $1.66 $598.09 $0.63 $0.79 $1,647.39 $0.47 $664.13 $0.35 $1,656.98 $0.47 $642.90 $0.35 $6.52 $172.63 $95.20 $0.14 Page 14 Florida Department of Transportation Maintenance Contract Cost Summary By Pay Item Number (SiteManager Data Only) 01/01/2012 - 12/31/2012 Statewide 2/12/2012 Pay Item Number Pay Item Description Unit of Measure 0711 17 0713101125 0713101160 0713101170 0713101560 0713102533 0715 1 11 0715 1 12 0715 1 13 0715 1 14 0715 1 15 0715 1 60 0715 2 11 0715 2 13 0715 5 50 0715 7 21 0715 7 41 0715 10 2 0715 10 3 0715 10 5 0715 11111 0715 11113 0715 11119 0715 11125 0715 11137 0715 11500 0715 14 11 0715 14 12 0715 14 14 0715 14 51 0715 14 71 0715 19 1 THERMOPLASTIC, REMOVE EXISTING THERMOPLASTIC PAVEMENT PREFORMED TAPE, STANDARD, WHITE, SOLID, 18" PREFORMED TAPE, STANDARD, WHITE, MESSAGE PREFORMED TAPE, STANDARD, WHITE, ARROWS PREFORMED TAPE, STANDARD, WHITE W/BLACK CONTRAST, PREFORMED TAPE, HIGH PERFORMANCE, LIGHTING CONDUCTORS, F&I, INSULATED, NO. 10 OR < LIGHTING CONDUCTORS, F&I, INSULATED, NO.8 - 6 LIGHTING CONDUCTORS, F&I, INSULATED, NO 4 TO NO 2 LIGHTING CONDUCTORS, F&I, INSULATED, NO 1 TO NO 0 LIGHTING CONDUCTORS, F&I, NO.1/0 - 3/0 (0 to 000) LIGHTING CONDUCTORS, REMOVE & DISPOSE, CONTRACTOR LIGHTING - CONDUIT, F&I, UNDERGROUND LIGHTING CONDUIT, F&I, SURFACE MOUNT LUMINAIRE & BRACKET ARM, REMOVE LOAD CENTER, REWORK, SECONDARY VOLTAGE LOAD CENTER, REMOVE, SECONDARY VOLTAGE LIGHT POLE FOUNDATION, F&I LIGHT POLE FOUNDATION, REPAIR LIGHT POLE FOUNDATION, REMOVE LUMINAIRE, F&I, ROADWAY, COBRA HEAD LUMINAIRE, F&I, ROADWAY, POLE TOP LUMINAIRE, F&I, ROADWAY SPECIAL LUMINAIRE, F&I, UNDER DECK, WALL MOUNT LUMINAIRE, F&I, SIGN, SIGN MOUNT LUMINAIRE, REMOVE LIGHTING - PULL BOX, F&I, ROADSIDE-MOULDED LIGHTING - PULL BOX, F&I, SIDEWALK LIGHTING - PULL BOX, F&I, SURFACE MOUNT LIGHTING - PULL BOX, REMOVE, ROADSIDE, MOULDED LIGHTING - PULL BOX, REPAIR, ROADSIDE-MOULDED LIGHTING - SURGE PROTECTOR, POLE BASE SF LF EA EA EA GM LF LF LF LF LF LF LF LF EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA Total Quantity Total Cost Average Unit Cost 1,786,283.460 1,005.000 2.000 3.000 10.000 0.692 9,826.000 52,192.000 7,327.000 673.000 600.000 2,890.000 260.000 929.000 0.000 1.000 1.000 8.000 68.000 10.000 101.000 6.000 12.000 2.000 4.000 22.000 46.000 13.000 19.000 2.000 204.000 177.000 $721,203.86 $5,025.00 $480.00 $150.00 $2,720.00 $4,509.40 $5,280.35 $63,502.25 $30,535.00 $5,930.00 $1,950.00 $28.90 $1,360.00 $6,479.40 $0.00 $18,584.00 $4,999.90 $10,224.64 $9,970.00 $2,435.65 $19,240.69 $6,000.00 $4,000.00 $150.00 $1,170.00 $550.00 $17,280.85 $4,825.00 $1,715.32 $100.00 $7,398.00 $1,463.00 $0.40 $5.00 $240.00 $50.00 $272.00 $6,516.47 $0.54 $1.22 $4.17 $8.81 $3.25 $0.01 $5.23 $6.97 $0.00 $18,584.00 $4,999.90 $1,278.08 $146.62 $243.57 $190.50 $1,000.00 $333.33 $75.00 $292.50 $25.00 $375.67 $371.15 $90.28 $50.00 $36.26 $8.27 Page 15 Florida Department of Transportation Maintenance Contract Cost Summary By Pay Item Number (SiteManager Data Only) 01/01/2012 - 12/31/2012 Statewide 2/12/2012 Pay Item Number Pay Item Description Unit of Measure 0715 26 1 0715 26 2 0715 36 12 0715 36 14 0715 36 62 0715511130 0715511135 0715511140 0715511145 0715511150 0715514145 0715516135 0715516145 0715550000 0715560000 0715576140 0744 70 12 0750 1 55 0750 1 59 0751 2 0904540 10 0905324 1 0999 2 0999 20 0999 25 1050 11223 9999 3 9999 4 9999 21 9999 22 E060 1 E099 1 QUICK DISCONNECT PLUG, SWITCH BOXING FOR SIGN QUICK DISCONNECT PLUG,PLUG POLE BASE, HIGH MAST LIGHT POLE, FRANGIBLE BASE, F&I, TRANSFORMER BASE LIGHT POLE, FRANGIBLE BASE, F&I, DOOR ASSEMBLY LIGHT POLE, FRANGIBLE BASE, REPLACE, TRANSFORMER BASE LIGHT POLE COMPLETE- SPECIAL DESIGN, F&I, LIGHT POLE COMPLETE- SPECIAL DESIGN, F&I, SINGLE ARM LIGHT POLE COMPLETE- SPECIAL DESIGN, F&I, SINGLE ARM LIGHT POLE COMPLETE- SPECIAL DESIGN, F&I, SINGLE ARM LIGHT POLE COMPLETE SPECIAL DESIGN , F&I, SINGLE ARM LIGHT POLE COMP- SPECIAL DESIGN, F&I, LIGHT POLE COMPLETE- SPECIAL DESIGN, F&I, LIGHT POLE COMPLETE- SPECIAL DESIGN, F&I, LIGHT POLE COMPLETE- SPECIAL DESIGN, REMOVE LIGHT POLE COMPLETE- SPECIAL DESIGN, REPAIR & REINSTALL LIGHT POLE COMPLETE- SPECIAL DESIGN, F&I INTERNAL VIBRATING TMS SOLAR POWER UNIT, F&I, EXISTING POLE ARCHITECTURAL, BUILDING, REHAB, OFFICE ARCHITECTURAL, BUILDING, REHAB, OTHER BUILDING ARCHITECTURAL - ELECTRICAL/POWER HIGH TENSION CABLE BARRIER SYSTEM - RELOCATE REWORKED ASPHALT CONCRETE LUMP SUM CONTRACT, ALTERNATIVE BIDDING DISPUTES REVIEW BOARD, DO NOT BID INITIAL CONTINGENCY AMOUNT, DO NOT BID UTILITY PIPE, F&I, PVC, WATER / SEWER, 5 - 7.9" GENERIC CONTRACT CHANGE(S/M ONLY) GENERIC CONTRACT CHANGE(S/M ONLY) CONTINGENCY SA (First) (SM Only) CONTINGENCY SA (Second) (SM Only) ASSET MANAGEMENT LUMP SUM EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA LS LS LS LF SY LS DA LS LF LS EA LS LS LS LS Total Quantity 1.000 12.000 46.000 3.000 54.000 7.000 1.000 13.000 5.000 3.000 1.000 2.000 1.000 51.000 24.000 1.000 2.000 5.077 8.920 3.000 989.000 45,435.100 24.330 2.000 5.180 17.000 3.000 388.500 0.669 1.000 23.952 85.628 Total Cost Average Unit Cost $262.18 $262.18 $370.00 $30.83 $15,225.00 $330.98 $3.00 $1.00 $67,500.00 $1,250.00 $19,801.65 $2,828.81 $1,500.00 $1,500.00 $32,553.32 $2,504.10 $17,012.12 $3,402.42 $7,441.29 $2,480.43 $1,500.00 $1,500.00 $4,000.00 $2,000.00 $3,500.00 $3,500.00 $14,300.00 $280.39 $8,000.00 $333.33 $4,000.00 $4,000.00 $6,000.00 $3,000.00 $678,638.86 $133,669.27 $1,348,764.31 $151,206.76 $86,400.00 $28,800.00 $9,395.50 $9.50 $354,393.78 $7.80 $5,676,916.17 $233,329.89 $16,000.00 $8,000.00 $35,902.00 $6,930.89 $2,805.00 $165.00 $258,401.87 $86,133.96 $1,180.95 $3.04 $1,681.87 $2,514.01 $1,200.00 $1,200.00 $86,741,452.07 $3,621,470.11 $19,477,909.82 $227,471.27 Page 16 Florida Department of Transportation Maintenance Contract Cost Summary By Pay Item Number (SiteManager Data Only) 01/01/2012 - 12/31/2012 Statewide 2/12/2012 Pay Item Number Pay Item Description Unit of Measure E099 2 E101 1 1 E101 72 E102 1 2 E102 1 3 E102 1 4 E102 10 E102 11 1 E102 20 E102 74 9 E102 97 1 E102 97 2 E102 99 1 E102100 12 E102100 13 E102100 16 E104 4 1 E104 4 2 E104 4 3 E104 4 4 E104 41 E104 50 E104 50 E106 22 1 E106 22 2 E106 22 5 E110 2 E110 30 E110 31 E110 32 1 E110 70 E120 10 1 PERIODIC PAYMENTS OF LUMP SUM MOBILIZATION MOBILIZATION (EMERGENCY RESPONSE) MAINTENANCE OF TRAFFIC MAINTENANCE OF TRAFFIC MAINTENANCE OF TRAFFIC (NIGHT WORK) OFF-DUTY LAW ENFORCEMENT OFFICER SERVICE PATROL PORTABLE LIGHTING UNIT (MAST MOUNTED) TRAFFIC CONES TRUCK MOUNTED ATTENUATOR (TEMPORARY) TRUCK MOUNTED ATTENUATOR (WITH OPERATOR) SIGN VARIABLE MESSAGE (FURNISH ONLY) NECESSARY MAINTENANCE SERVICE (STRAIGHT TIME) NECESSARY MAINT SERVICE (OVERTIME SUNDAY/HOLIDAY) NECESSARY MAINT SERVICE (ROUND TRIP EXPENSE) MOWING (REGULAR/LARGE MACHINE) MOWING (SLOPE) MOWING (SMALL MACHINE) MOWING (INTERMEDIATE MACHINE) MOWING (PERFORMANCE) WEED CONTROL MANUAL Weed Control-Manual REM & DISPOSAL OF DEAD ANIMALS (0 - 100 LBS) REM & DISPOSAL OF DEAD ANIMALS (> 100 LBS) REMOVAL & DISPOSAL MATERIALS CLEARING & GRUBBING LITTER REMOVAL SWEEPING (MECHANICAL) EDGING AND SWEEPING REMOVAL OF FLEXIBLE PAVEMENT CLEAN AND RESHAPE DITCH (SPREAD) EA LO EA DA LO LO MH EA ED ED ED HR ED HR HR EA AC AC AC AC LS AC AC EA EA CY AC AC PM PM SY LF Total Quantity Total Cost Average Unit Cost 424.035 1,121.000 175.000 638.000 459.000 26.000 4,224.750 756.000 41.000 77,057.000 553.000 1,139.350 137.000 5,133.000 88.500 353.000 382,379.240 22,614.807 30,563.634 24,883.901 5.305 257.402 0.800 49.000 27.000 228.000 501.685 981,772.332 115,067.293 24,310.799 107.186 18,330.000 $39,610,453.59 $1,354,909.83 $125,490.00 $543,171.80 $161,544.40 $17,391.69 $199,917.15 $447,097.80 $1,585.00 $70,142.35 $228,370.00 $56,971.04 $6,165.00 $209,410.75 $3,540.00 $76,645.00 $5,074,345.85 $1,335,183.71 $1,982,885.57 $1,167,153.50 $857,852.27 $70,078.95 $323.12 $7,300.00 $1,080.00 $10,872.50 $785,894.49 $6,531,067.63 $3,490,895.96 $3,114,800.87 $16,747.60 $45,759.00 $93,413.17 $1,208.66 $717.09 $851.37 $351.95 $668.91 $47.32 $591.40 $38.66 $0.91 $412.97 $50.00 $45.00 $40.80 $40.00 $217.12 $13.27 $59.04 $64.88 $46.90 $161,706.37 $272.25 $403.90 $148.98 $40.00 $47.69 $1,566.51 $6.65 $30.34 $128.12 $156.25 $2.50 Page 17 Florida Department of Transportation Maintenance Contract Cost Summary By Pay Item Number (SiteManager Data Only) 01/01/2012 - 12/31/2012 Statewide 2/12/2012 Pay Item Number Pay Item Description Unit of Measure E120 10 2 E120 10 4 E120 10 5 E327 73 E339 2 E350 72 1 E350 74 6 E350 74 8 E354 72 E400 90 E400 92 E400144 E400403 E425 73 1 E425 73 2 E425 73 3 E425 73 4 E425 73 5 E425 73 7 E430 17 99 E430 82 11 E430 82 12 E430 82 13 E430 82 14 E430 82 15 E432 4 E448 2 E460 19 1 E460 20 1 E460 20 2 E460 20 14 E460 82 CLEAN AND RESHAPE DITCH (HAUL) CLEAN AND RESHAPE CANAL (3.5' TO 7.0' DEPTH) CLEAN AND RESHAPE CANAL (> 7.0' DEPTH) MILLING EXISTING ASPHALT PAVEMENT ASPHALTIC CONCRETE (COLD PATCH) CLEANING & RESEALING JOINTS(EXPANSION) PAVEMENT JOINT (HOT POURED > 3/4") PAVEMENT JOINT (SILICON) SUBSURFACE POLYURETHANE INJECTION DEWATERING DEWATERING DRAINAGE STRUCTURES CLEANING & PAINTING CONCRETE SURFACES CONCRETE REMOVAL CLEANING MANHOLES AND INLETS (MECHANICAL) REPAIR LEAKS IN MANHOLES AND INLETS FRAME AND GRATE (F&I) RESET EXISTING FRAME AND GRATE CLEANING MANHOLES AND INLETS (MANUAL) MANHOLE FRAME & COVER PIPE REMOVAL CLEAN & SEAL EXISTING PIPE JOINT, 0-24" CLEAN & SEAL EXISTING PIPE JOINT, 25-36" CLEAN & SEAL EXISTING PIPE JOINT, 37-48" CLEAN & SEAL EXISTING PIPE JOINT, 49-60" CLEAN & SEAL EXISTING PIPE JOINT, 61" OR GREATER STORM SEWER INSPECTION (VIDEO CAMERA) WATER LEVEL FLOOD CONTROL PUMPING ARMOR ANGLE (REMOVE) POLYMER JOINT REPLACEMENT POLYMER CONCRETE HEADER REPAIR ELASTOMERIC STRUCT JOINT SEAL REPLACE BOLT TIGHTENING LF LF LF TN TN LF LF LF LB LS SY SF SF EA EA EA EA EA EA LF EA EA EA EA EA LF DA LF CF CF LF EA Total Quantity Total Cost Average Unit Cost 497,129.220 13,747.000 45,512.000 1,746.420 29.018 1,579.000 2,450.000 40,896.000 4,754.000 2.380 14,397.990 1,104,604.000 18,505.140 7,079.000 3.000 24.000 9.000 185.000 1.000 2,907.000 241.000 250.000 162.000 105.000 474.000 1,168,850.160 183.000 115.000 236.500 27.690 2,417.500 6.000 $764,685.56 $51,551.25 $96,702.00 $41,765.25 $5,882.65 $47,370.00 $11,515.00 $186,495.00 $45,508.00 $22,800.00 $349,723.75 $237,652.59 $65,659.89 $249,687.23 $3,100.00 $13,225.00 $3,800.00 $5,826.00 $450.00 $100,761.60 $41,795.00 $48,625.00 $49,500.00 $54,300.00 $20,100.00 $942,866.92 $80,154.00 $6,725.00 $95,450.00 $13,390.91 $89,985.00 $354.00 $1.54 $3.75 $2.12 $23.91 $202.72 $30.00 $4.70 $4.56 $9.57 $9,579.83 $24.29 $0.22 $3.55 $35.27 $1,033.33 $551.04 $422.22 $31.49 $450.00 $34.66 $173.42 $194.50 $305.56 $517.14 $42.41 $0.81 $438.00 $58.48 $403.59 $483.60 $37.22 $59.00 Page 18 Florida Department of Transportation Maintenance Contract Cost Summary By Pay Item Number (SiteManager Data Only) 01/01/2012 - 12/31/2012 Statewide 2/12/2012 Pay Item Number Pay Item Description Unit of Measure E470 1 1 E470 1 2 E470 1 3 E499 1 1 E500 72 E521 1 E522 74 E524 1 1 E534 72 1 E536 3122 E536 3131 E536 3132 E536 3133 E536 3134 E536 3140 E536 3141 E536 3142 E536 3143 E536 3144 E536 3232 E536 3240 E536 3242 E536 3342 E536 3432 E536 3532 E536 3540 E536 3642 E536 3643 E536 3644 E536 5 1 E536 5 2 E536 5 3 BOARDWALK, REMOVE AND REPLACE BOARDWALK MAINTENANCE BOARDWALK BOLT TIGHTENING MANUAL RAKING FOR FLOOD CONTROL HANDRAIL ALUMINUM (REMOVE & REINSTALL) CONCRETE BARRIER WALL REPAIR CURB RAMP (RETROFIT) CONCRETE DITCH PAVEMENT REPAIR SOUND/NOISE BARRIER PANELS, F&I, REPLACE GUARDRAIL PANELS (INSTALL) (0' - 50') GUARDRAIL STANDARD PANEL (F&I) (SHOP BENT) GUARDRAIL STANDARD PANEL (F&I)( 0.' - 50') GUARDRAIL STANDARD PANEL (F&I)(51' - 200') GUARDRAIL STANDARD PANEL (F&I)(> 200') GUARDRAIL STANDARD PANEL (REPLACE) GUARDRAIL STANDARD PANEL (REPLACE) (SHOP BENT) GUARDRAIL STANDARD PANEL (REPLACE) (0' - 50') GUARDRAIL STANDARD PANEL (REPLACE) (51' - 200') GUARDRAIL STANDARD PANEL (REPLACE) (> 200') GUARDRAIL THRIE BEAM (F&I) (0' - 50') GUARDRAIL THRIE BEAM (REPLACE) GUARDRAIL THRIE BEAM (REPLACE) (0' - 50') GUARDRAIL BOX BEAM (REPLACE) (0' - 50') GUARDRAIL RUB RAIL (F&I) (0' - 50') GUARDRAIL (PIPE RAIL SAFETY) (F&I) (0' - 50') GUARDRAIL (PIPE RAIL SAFETY) (REPLACE) GUARDRAIL DOUBLE FACE (REPLACE) (0' - 50') GUARDRAIL DOUBLE FACE (REPLACE) (51' - 200') GUARDRAIL DOUBLE FACE (REPLACE) (> 200') THRIE BEAM (TERMINAL CONNECTOR) THRIE BEAM (RAIL SPLICE) THRIE BEAM (TRANSITION SECTION) BF BF LO AC LF CY EA CY SF LF LF LF LF LF LF LF LF LF LF LF LF LF LF LF LF LF LF LF LF EA EA EA Total Quantity Total Cost Average Unit Cost 22,027.970 144.640 415.000 10.980 112.500 24.850 493.000 80.690 1,006.000 17,925.000 12.500 9,350.000 1,900.000 1,750.000 48,215.500 1,226.000 22,668.800 7,350.000 950.000 600.000 237.500 75.500 72.000 250.000 25.000 62.000 7,125.000 4,450.000 1,412.500 2.000 3.000 24.000 $146,830.57 $1,229.44 $10,375.00 $549.00 $4,831.63 $7,665.90 $272,700.00 $16,138.00 $13,912.98 $348,950.00 $187.50 $166,196.98 $46,187.50 $8,750.00 $582,253.75 $15,340.00 $279,969.30 $94,250.00 $4,750.00 $14,112.50 $6,087.50 $755.00 $3,600.00 $2,225.00 $375.00 $510.00 $250,800.00 $155,562.50 $48,000.00 $200.00 $781.20 $3,502.40 $6.67 $8.50 $25.00 $50.00 $42.95 $308.49 $553.14 $200.00 $13.83 $19.47 $15.00 $17.78 $24.31 $5.00 $12.08 $12.51 $12.35 $12.82 $5.00 $23.52 $25.63 $10.00 $50.00 $8.90 $15.00 $8.23 $35.20 $34.96 $33.98 $100.00 $260.40 $145.93 Page 19 Florida Department of Transportation Maintenance Contract Cost Summary By Pay Item Number (SiteManager Data Only) 01/01/2012 - 12/31/2012 Statewide 2/12/2012 Pay Item Number Pay Item Description Unit of Measure E536 5 4 E536 6 45 E536 6 48 E536 6 61 E536 6414 E536 6422 E536 6424 E536 12305 E536 12311 E536 12601 E536 12602 E536 12603 E536 12604 E536 12605 E536 12606 E536 12608 E536 12609 E536 12611 E536 12613 E536 12615 E536 12616 E536 12617 E536 12619 E536 12620 E536 14 1 E536 14 2 E536 15 E536 21 501 E536 21 503 E536 65 E536301501 E536301502 THRIE BEAM (MODIFIED OFFSET BLOCK) END ANCHORAGE ASSEM (REPLACE) (TYPE ET 2000) END ANCHORAGE ASSEM (REPLACE) (TYPE SRT-350) END ANCHORAGE ASSEM (F&I) (TYPE II) END ANCHORAGE ASSEM (REPLACE) (TYPE SRT-350/8) END ANCHORAGE ASSEM (REPLACE) (FLARED) END ANCHORAGE ASSEM (REPLACE) (PARALLEL) GUARDRAIL REPAIRS (F&I) (STEEL POST IN ASPHALT) GUARDRAIL REPAIRS (F&I) (REFLECTORS) GUARDRAIL REPAIRS (REPLACE) (METAL BLOCK) GUARDRAIL REPAIRS (REPLACE) (WOOD BLOCK) GUARDRAIL REPAIRS (REPL) (PLASTIC BLOCK) GUARDRAIL REPAIRS (REPLACE) (STEEL POST IN CONC.) GUARDRAIL REPAIRS (REPLACE) (STEEL POST IN ASPH.) GUARDRAIL REPAIRS (REPLACE) (STEEL POST IN SOIL) GUARDRAIL REPAIRS (REPLACE) (WOOD POST IN ASPH.) GUARDRAIL REPAIRS (REPLACE) (WOOD POST IN SOIL) GUARDRAIL REPAIRS (REPLACE) (REFLECTORS) GUARDRAIL REPAIRS (REPLACE) (RUB RAIL) GUARDRAIL REPAIRS (REPLACE) (FILLER BLOCKS) GUARDRAIL REPAIRS(REPLACE)(OFFSET BLOCK) GUARDRAIL REPAIRS(REPLACE)(PANEL, 12-1/2') GUARDRAIL REPAIRS (REPLACE) (TRIE-BEAM PANEL, 12-1/2') GUARDRAIL REPAIRS (REPLACE) (TRIE-BEAM PANEL, 25') GUARDRAIL ALIGNMENT (DOUBLE FACE) GUARDRAIL ALIGNMENT (SINGLE FACE) MISCELLANEOUS GUARDRAIL MAINTENANCE END ANCHORAGE ASSEMBLY FLEAT SP (F&I) FIRST POST UPPER END ANCHORAGE ASSEMBLY FLEAT SP (F&I) SECOND POST END ANCHORAGE ASSEM (REMOVE) END ANCHOR ASSEM TYPE II (REPL FLARED END SECT) END ANCHOR ASSEM TYPE II (REPL ROUND END SECT) EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA LF LF LF EA EA EA EA EA Total Quantity Total Cost Average Unit Cost 127.000 10.000 32.000 57.000 25.000 42.000 42.000 5.000 18.000 6.000 12,796.000 4,259.000 59.000 3,865.000 1,416.000 2,339.000 739.000 6,955.000 458.500 1,147.000 2,620.000 887.000 1.000 1.000 1,214.500 17,157.250 145,882.600 4.000 1.000 1.000 43.000 28.000 $22,117.55 $23,314.16 $52,324.25 $34,774.00 $33,990.88 $68,060.00 $68,150.00 $200.00 $180.00 $256.00 $175,588.00 $44,851.60 $2,605.00 $295,975.51 $103,121.60 $168,643.54 $36,147.30 $48,455.47 $36,269.79 $13,771.00 $45,274.00 $163,937.50 $135.00 $250.00 $17,398.43 $52,429.59 $203,427.38 $574.00 $315.00 $50.00 $3,638.00 $1,721.49 $174.15 $2,331.42 $1,635.13 $610.07 $1,359.64 $1,620.48 $1,622.62 $40.00 $10.00 $42.67 $13.72 $10.53 $44.15 $76.58 $72.83 $72.10 $48.91 $6.97 $79.11 $12.01 $17.28 $184.82 $135.00 $250.00 $14.33 $3.06 $1.39 $143.50 $315.00 $50.00 $84.60 $61.48 Page 20 Florida Department of Transportation Maintenance Contract Cost Summary By Pay Item Number (SiteManager Data Only) 01/01/2012 - 12/31/2012 Statewide 2/12/2012 Pay Item Number Pay Item Description Unit of Measure E536301503 E536301506 E536301508 E536302503 E536302504 E536302505 E536302506 E536302508 E536303508 E536304503 E536304505 E536304507 E536304510 E536304511 E536305501 E536305503 E536305504 E536305505 E536305506 E536305507 E536305508 E536306501 E536306503 E536306509 E536308213 E536308501 E536308502 E536308503 E536308504 E536308505 E536308506 E536308507 END ANCHOR ASSEM TYPE II (REPL BUFFER END SECT) END ANCHOR ASSEM TYPE II (REPL GUARDRAIL BEAM) END ANCHOR ASSEM TYPE II (REPL TIMBER BREAK POST) END ANCHOR ASSEM TYPE IV (REPL BUFFER END SECT) END ANCHOR ASSEM TYPE IV (REPL ANCHOR PANEL SECT) END ANCHOR ASSEM TYPE IV (REPL CABLE ASSEMBLY) END ANCHOR ASSEM TYPE IV (REPL STEEL TUBE & POST) END ANCHOR ASSEM TYPE IV (REPL TIMBER BREAK POST) END ANCHOR ASSEM CRT (REPL TIMBER BREAK POST) END ANCHOR ASSEM MELT (REPL AMBER REFL SHEET) END ANCHOR ASSEM MELT (REPL SHORT TMBR BRK POST) END ANCHOR ASSEM MELT (REPL BUFFER END SECTION) END ANCHOR ASSEM MELT (REPL TMBR BRK LINE POST) END ANCHOR ASSEM MELT (REPL GUARDRAIL BEAM) END ANCHOR ASSEM ET-2000 (REPL TIMBER BRK POST) END ANCHOR ASSEM ET-2000 (REPL CABLE ANCHOR) END ANCHOR ASSEM ET-2000 (REPL OFFSET STRUT) END ANCHOR ASSEM ET-2000 (REPL BEARING PLATE) END ANCHOR ASSEM ET-2000 (REPL G-RAIL EXTRUDER) END ANCHOR ASSEM ET-2000 (REPL STEEL TUBE/POST) END ANCHOR ASSEM ET-2000 (REPL GUARDRAIL BEAM) END ANCHOR ASSEM BRIDGE (REPL SPECIAL END SHOE) END ANCHOR ASSEM BRIDGE (REPL TIMBER FILL BLOCK) END ANCHOR ASSEM BRIDGE (REPL ANCHOR PANEL SECT) END ANCHOR ASSEM SRT-350 (INSTALL END SHOE) END ANCHOR ASSEM SRT-350 (REPL CABLE ASSEMBLY) END ANCHOR ASSEM SRT-350 (REPL DIAPHRAM PLATE) END ANCHOR ASSEM SRT-350 (REPL AMBER REFL SHEET) END ANCHOR ASSEM SRT-350 (REPL BEARING PLATE) END ANCHOR ASSEM SRT-350 (REPL TIMBER BREAK POST) END ANCHOR ASSEM SRT-350 (REPL STEEL TUBE/PLATE) END ANCHOR ASSEM SRT-350 (REPL BUFFER END SECT) EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA Total Quantity Total Cost Average Unit Cost 35.000 12.000 4.000 5.000 2.000 1.000 2.000 5.000 24.000 1.000 5.000 12.000 23.000 1.000 34.000 3.000 1.000 2.000 9.000 6.000 23.000 5.000 16.000 75.000 8.000 7.000 1.000 61.000 8.000 70.000 3.000 74.000 $4,450.96 $2,450.00 $250.00 $401.28 $825.00 $103.72 $160.00 $555.00 $2,590.00 $40.00 $800.00 $1,000.00 $1,280.00 $215.00 $2,853.89 $191.40 $2.57 $76.16 $1,045.18 $183.30 $7,365.96 $426.00 $3,200.00 $12,177.57 $351.00 $3,693.56 $5.50 $2,452.88 $40.20 $5,549.23 $114.00 $6,960.00 $127.17 $204.17 $62.50 $80.26 $412.50 $103.72 $80.00 $111.00 $107.92 $40.00 $160.00 $83.33 $55.65 $215.00 $83.94 $63.80 $2.57 $38.08 $116.13 $30.55 $320.26 $85.20 $200.00 $162.37 $43.88 $527.65 $5.50 $40.21 $5.03 $79.27 $38.00 $94.05 Page 21 Florida Department of Transportation Maintenance Contract Cost Summary By Pay Item Number (SiteManager Data Only) 01/01/2012 - 12/31/2012 Statewide 2/12/2012 Pay Item Number Pay Item Description Unit of Measure E536308508 E536308509 E536308510 E536308511 E536308514 E536308517 E536312501 E536313508 E536313509 E536313514 E536314501 E536314503 E536314504 E536314505 E536314506 E536314507 E536314509 E536314510 E536314511 E536315503 E536316501 E536316503 E536316504 E536316508 E536316514 E536317511 E536322501 E536322502 E536322503 E536322506 E536322508 E536322515 END ANCHOR ASSEM SRT-350 (REPL SHELF ANGLE) END ANCHOR ASSEM SRT-350 (REPL STRUT & YOKE ASSM) END ANCHOR ASSEM SRT-350 (REPL TIMBER LINE POST) END ANCHOR ASSEM SRT-350 (REPL GUARDRAIL BEAM) END ANCHOR ASSEM SRT-350 (REPL SLOT GUARD) END ANCHOR ASSEM SRT-350 (REPL BRK TRM POST SLV) END ANCHOR ASSEM LET (REPL TIMBER BREAK POST) END ANCHOR ASSEMBLY SKT-350 (REPL GUARDRAIL BEAM) END ANCHOR ASSEMBLY SKT-350 (REPL MISC HARDWARE) END ANCHOR ASSEMBLY SKT-350 (REPL IMPACT HEAD) END ANCHOR ASSEM SRT-350/8 (REPL CABLE ASSEMBLY) END ANCHOR ASSEM SRT-350/8 (REPL AMBER REFL SHT) END ANCHOR ASSEM SRT-350/8 (REPL BEARING PLATE) END ANCHOR ASSEM SRT-350/8 (REPL TIMBER BRK POST) END ANCHOR ASSEM SRT-350/8 (REPL STEEL TUBE/PLT) END ANCHOR ASSEM SRT-350/8 (REPL BUFFER END SECT) END ANCHOR ASSEM SRT-350/8 (REPL STRUT/YOKE ASSM) END ANCHOR ASSEM SRT-350/8 (REPL TMBR LINE POST) END ANCHOR ASSEM SRT-350/8 (REPL GUARDRAIL BEAM) END ANCHOR ASSEM REGENT (REPL AMBER REFL SHEET) END ANCHOR ASSEMBLY FLEAT-350 (REPL TMBER BRKWAY POST) END ANCHOR ASSEMBLY FLEAT-350 (REPL CABLE ANCHOR ASSY) END ANCHOR ASSEMBLY FLEAT-350 (REPL GROUND STRUT) END ANCHOR ASSEMBLY FLEAT-350 (REPL GUARDRAIL BEAM) END ANCHOR ASSEMBLY FLEAT-350 (REPL IMPACT HEAD) END ANCHORAGE ASSEMBLY (REGENT C) GUARDRAIL BEAM END ANCHOR ASSEM FLARED (REPL FLARED END SECT) END ANCHOR ASSEM FLARED (REPL ROUND END SECT) END ANCHOR ASSEM FLARED (REPL BUFFER END SECT) END ANCHOR ASSEM FLARED (REPL GUARDRAIL BEAM) END ANCHOR ASSEM FLARED (REPL TIMBER BREAK POST) END ANCHOR ASSEM FLARED (REPL AMBER REFLECT SHEET) EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA Total Quantity Total Cost Average Unit Cost 0.000 2.000 8.000 32.000 17.000 3.000 9.000 2.000 1.000 1.000 5.000 63.000 2.000 47.000 2.000 20.000 1.000 89.000 37.000 1.000 14.000 5.000 1.000 10.000 5.000 9.000 2.000 3.000 6.000 20.000 15.000 8.000 $0.00 $60.00 $1,140.00 $34,233.42 $40.04 $162.00 $405.00 $217.81 $150.00 $425.00 $213.16 $2,355.31 $10.00 $4,775.00 $21.86 $2,300.00 $10.00 $9,780.00 $15,600.00 $40.00 $1,422.75 $160.00 $2.55 $7,750.00 $2,001.00 $810.00 $45.00 $270.00 $535.00 $3,930.00 $1,080.00 $135.00 $0.00 $30.00 $142.50 $1,069.79 $2.36 $54.00 $45.00 $108.91 $150.00 $425.00 $42.63 $37.39 $5.00 $101.60 $10.93 $115.00 $10.00 $109.89 $421.62 $40.00 $101.63 $32.00 $2.55 $775.00 $400.20 $90.00 $22.50 $90.00 $89.17 $196.50 $72.00 $16.88 Page 22 Florida Department of Transportation Maintenance Contract Cost Summary By Pay Item Number (SiteManager Data Only) 01/01/2012 - 12/31/2012 Statewide 2/12/2012 Pay Item Number Pay Item Description Unit of Measure Total Quantity Total Cost Average Unit Cost E536322517 E540 0 0 E540 0 23 E540 0 24 E540 0 25 E540 0 26 E540 3 1 E540 3 11 E540 3 2 E540 3 3 E540 1 01 E540 1 02 E540 2 01 E540 2 02 E540 2 07 E540 2 08 E540 3 01 E540 3 02 E544 76 1 E544 76 1 E544 76 2 E544 76 2 E544031001 E544031020 E544031026 E544031027 E544031039 E544031040 E544031046 E544031047 E544041020 E544041040 END ANCHOR ASSEM FLARED (REPL SHORT TIMBR BREAK POST) CABLE BARRIER INSPECTION CABLE BARRIER LINE POST, INC ALL INCIDENTALS CABLE BARRIER TRANS TERMN POST REPAIR, INC INCIDENTALS END ANCHOR REPAIR/REPLACE INCLUDES ALL INCIDENTALS CABLE BARRIER HAIRPIN AND LOCKPLATE ASSEMBLY GIBRALTAR TL 3 LINE POST REP INCL HAIRPIN & LOCKPLATE GIBRALTAR TL 3 LINE POST REP >4 INCL HAIRPIN & LOCKPLATE GIBRALTAR TERMINAL POST REP (INCL 1, 2, 3 & 4) GIBRALTAR ANCHOR POST REPLACEMENT CABLE SAFETY BARRIER (BRIFEN) STANDARD POST REPLACEMENT CABLE SAFETY BARRIER (BRIFEN) STANDARD POST REPLACEMENT > 4 CABLE SAFETY BARRIER (CASS) STANDARD POST REPLACEMENT CABLE SAFETY BARRIER (CASS) STANDARD POST REPLACEMENT >4 POS CABLE SAFETY BARRIER (CASS) END POST REPLACEMENT (CABLE SAFETY BARRIER) (CASS) EYE POST REPLACEMENT CABLE SAFETY BARRIER (SAFENCE) STANDARD POST REPLACEMENT CABLE SAFETY BARRIER (SAFENCE) STANDARD POST REPLACEMENT > 4 CRASH CUSHION (RESET) VEHICULAR IMPACT ATTENUATOR (RESET) CRASH CUSHION (CLEAN & INSPECT) VEHICULAR IMPACT ATTENUATOR (CLEAN & INSPECT) ATTENUATOR (QUADGUARD) F&I (FENDER PANEL) ATTENUATOR (QUADGUARD) F&I (DIAPHRAM) ATTENUATOR (QUADGUARD) F&I (SIDE PANEL CONC CON) ATTENUATOR (QUADGRARD) F&I (HAZARD RFLT-9 BUTTON) ATTENUATOR (QUADGUARD) F&I (CARTRIDGE ASSEMBLY) ATTENUATOR (QUADGUARD) F&I (NOSE ASSEMBLY) ATTENUATOR (QUADGUARD) F&I (MONORAIL, 3 BAY) ATTENUATOR (QUADGUARD) F&I (MUSHROOM BOLT ASSM) ATTENUATOR (QUADGUARD HIGH SPEED) F&I (DIAPHRAM) ATTENUATOR (QUADGUARD HIGH SPEED) F&I (NOSE ASSEMBLY) EA LS EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA 4.000 2.000 308.000 10.000 6.000 322.000 131.000 441.000 11.000 8.000 8.000 38.000 7.000 146.000 12.000 1.000 9.000 130.000 71.000 56.000 291.000 844.000 22.000 22.000 1.000 21.000 212.000 62.000 1.000 1.000 5.000 1.000 $300.00 $43,000.00 $53,900.00 $750.00 $600.00 $24,150.00 $11,595.00 $36,470.00 $1,470.00 $3,750.00 $600.00 $2,660.00 $70.00 $10,220.00 $4,800.00 $10.00 $855.00 $9,825.00 $91,300.00 $26,725.00 $24,270.00 $7,530.00 $11,230.00 $19,900.00 $1.00 $1,810.00 $206,200.00 $59,575.00 $10.00 $200.00 $7,500.00 $75.00 $75.00 $21,500.00 $175.00 $75.00 $100.00 $75.00 $88.51 $82.70 $133.64 $468.75 $75.00 $70.00 $10.00 $70.00 $400.00 $10.00 $95.00 $75.58 $1,285.92 $477.23 $83.40 $8.92 $510.45 $904.55 $1.00 $86.19 $972.64 $960.89 $10.00 $200.00 $1,500.00 $75.00 Page 23 Florida Department of Transportation Maintenance Contract Cost Summary By Pay Item Number (SiteManager Data Only) 01/01/2012 - 12/31/2012 Statewide 2/12/2012 Pay Item Number Pay Item Description Unit of Measure E544051001 E544051003 E544051007 E544051020 E544051022 E544051025 E544051026 E544051027 E544051050 E544061004 E544061005 E544061006 E544101040 E550 1 1 E550 6112 E550 6114 E550 6212 E550 6222 E550 6232 E550 6422 E550 7111 E550 7112 E550 7212 E550 7221 E550 7222 E550 7412 E550 7422 E550 9 E550 22 30 E550 22 31 E550 31 10 E550 32 30 ATTENUATOR (GREAT) F&I (FENDER PANEL) ATTENUATOR (GREAT) F&I (HEX FOAM CART, TYPE 51) ATTENUATOR (GREAT) F&I (HEX FOAM BRACKET/DIAPH) ATTENUATOR (GREAT) F&I (DIAPHRAM) ATTENUATOR (GREAT) F&I (UNIVERSAL NOSE CONE) ATTENUATOR (GREAT) F&I (ANCHOR CHAIN RAIL ASSM) ATTENUATOR (GREAT) F&I (S PANEL CONC CONNECTOR) ATTENUATOR (GREAT) F&I (HAZARD REFL - 9 BUTTON) ATTENUATOR (GREAT) F&I (DEFLCT ASSM, CONC BACKUP) ATTENUATOR (HEX FOAM) F&I (HEX FOAM CART,TYPE 80) ATTENUATOR (HEX FOAM) F&I (HEX FOAM CART,TYPE 81) ATTENUATOR (HEX FOAM) F&I (HEX FOAM CART,TYPE 82) ATTENUATOR (TRACC) F&I (NOSE PIECE) FENCING (TYPE A) (4') FENCE POST LINE (TYPE A) (4') FENCE POST PULL (TYPE A) (4') FENCE POST LINE (TYPE B) (4') FENCE POST LINE (TYPE B) (6') FENCE POST LINE (TYPE B) (10') FENCE POST, LINE(TYP B, PVC COAT) (6') FENCE MAINT (TYPE A) (BARBED WIRE) (4') FENCE MAINTENANCE (TYPE A) (FENCE FABRIC) (4') FENCE MAINTENANCE (TYPE B) (FENCE FABRIC) (4') FENCE MAINTENANCE (TYPE B) (BARBED WIRE) (6') FENCE MAINTENANCE (TYPE B) (FENCE FABRIC) (6') FENCE MAINTENANCE (TYPE B) (FENCE FABRIC, PVC) (4') FENCE MAINTENANCE (TYPE B) (FENCE FABRIC, PVC COAT) (6') FENCE REMOVAL FENCE, TYP B (PVC COAT) (6') FENCE, TYP B (W/BARB WIRE ATTACH) (6') CORNER POST ASSEM (TYPE A) (4') FENCE, CORNER POST ASSEMBLY (TYPE B) (6') EA EA EA EA EA EA EA EA EA EA EA EA EA LF EA EA EA EA EA EA LF LF LF LF LF LF LF LF LF LF EA EA Total Quantity Total Cost Average Unit Cost 22.000 161.000 3.000 17.000 21.000 1.000 1.000 33.000 1.000 27.000 7.000 4.000 1.000 18,273.000 218.000 1.000 9.000 340.000 25.000 32.000 5,390.000 1,305.000 960.000 10,281.000 7,334.000 25.000 11,162.000 21,563.000 1,740.000 2,464.000 3.000 45.000 $4,011.13 $169,515.00 $7.20 $3,702.00 $17,356.73 $250.00 $1.00 $2,510.00 $1.00 $18,900.00 $4,900.00 $1,200.00 $100.00 $98,801.00 $7,050.00 $30.00 $270.00 $13,185.00 $1,362.50 $3,529.95 $3,585.00 $23,490.00 $21,120.00 $14,770.25 $144,763.00 $300.00 $112,163.71 $37,687.05 $25,222.00 $12,320.00 $110.00 $3,842.12 $182.32 $1,052.89 $2.40 $217.76 $826.51 $250.00 $1.00 $76.06 $1.00 $700.00 $700.00 $300.00 $100.00 $5.41 $32.34 $30.00 $30.00 $38.78 $54.50 $110.31 $0.67 $18.00 $22.00 $1.44 $19.74 $12.00 $10.05 $1.75 $14.50 $5.00 $36.67 $85.38 Page 24 Florida Department of Transportation Maintenance Contract Cost Summary By Pay Item Number (SiteManager Data Only) 01/01/2012 - 12/31/2012 Statewide 2/12/2012 Pay Item Number Pay Item Description Unit of Measure E550 32 31 E550 33 30 E550 51 10 E550 51 30 E550 52 30 E550 53 11 E550 61 10 E550 61 30 E550 61 40 E550 62 30 E550 80 E560 1 E563 99 E570 1 3 E570 2 E570 5 E570 6 E570 9 1 E573 1 E575 1 E575 1 2 E575 1 4 E575 1 6 E577 70 E577 70 1 E577 70 2 E580 3 1 E580 3 2 E580173 E580301 1 E580326 4 E580332 20 FENCE, CORNER POST ASSEM (TYP B, W/BARB WIRE ATTACH) (6') FENCE, CORNER POST ASSEMBLY (TYPE B, PVC COAT) (6') FENCE, PULL POST ASSEMBLY (TYPE B, ZINC COAT) (4') FENCE, PULL POST ASSEMBLY (TYPE B, ZINC COAT) (6') FENCE, PULL POST ASSEMBLY (TYPE B, PVC COAT) (6') FENCE, PULL POST ASSEMBLY (TYPE A, BARB WIRE ATTACH) (4') FENCE, END POST ASM (TYP B, ZINC) (4') FENCE, END POST ASM (TYP B, ZINC) (6') FENCE, END POST ASM (TYP B, ZINC) (8') FENCE, END POST ASM (TYP B, PVC) (6') FENCE GATE (REPAIR) PAINT STRUCTURAL STEEL GRAFFITI REMOVAL TURF MANAGEMENT (PERFORMANCE) SEED & MULCH FERTILIZER FERTILIZER (SLOW RELEASE) WATER FOR GRASS & PLANTS HYDRO-SEEDING - APPLICATION OF SLURRY INCLUDING SODDING SODDING (CENTIPEDE) SODDING (ST AUGUSTINE) SODDING (BERMUDA) SHOULDER REWORK REWORKING SHOULDERS (SPOT REPAIRS) REWORKING UTILITY STRIPS LANDSCAPE MAINTENANCE (WEED REMOVAL, MANUAL) LANDSCAPE MAINTENANCE (ACRE) BED PREPARATION & MULCHING STAKING & GUYING (TREES) MULCH WOOD CHIPS TREE REMOVAL (LESS THAN 4") EA EA EA EA EA EA EA EA EA EA EA SF SF LS SY TN TN MG SY SY SY SY SY SY SY SY SF AC SY EA SY EA Total Quantity Total Cost Average Unit Cost 12.000 2.000 1.000 20.000 5.000 3.000 1.000 64.000 3.000 2.000 11.000 443.000 186,602.000 0.996 438,791.170 192.070 0.500 8,782.117 41,363.000 1,109,913.017 2,632.000 3,964.800 152,631.950 888,091.080 633,732.050 1,100.280 1,986,857.586 2,008.572 68,417.330 7.000 147,050.250 3,249.000 $12.00 $632.70 $350.00 $3,155.00 $1,304.25 $3.00 $150.00 $1,656.00 $62.00 $377.40 $4,701.00 $3,101.00 $36,040.48 $2,490.00 $396,507.88 $110,783.11 $150.00 $51,007.61 $15,889.48 $2,209,620.41 $10,896.48 $10,173.60 $337,078.32 $910,625.45 $737,744.37 $5,501.40 $136,909.79 $777,573.98 $155,120.53 $350.00 $104,862.90 $66,924.96 $1.00 $316.35 $350.00 $157.75 $260.85 $1.00 $150.00 $25.88 $20.67 $188.70 $427.36 $7.00 $0.19 $2,500.00 $0.90 $576.79 $300.00 $5.81 $0.38 $1.99 $4.14 $2.57 $2.21 $1.03 $1.16 $5.00 $0.07 $387.13 $2.27 $50.00 $0.71 $20.60 Page 25 Florida Department of Transportation Maintenance Contract Cost Summary By Pay Item Number (SiteManager Data Only) 01/01/2012 - 12/31/2012 Statewide 2/12/2012 Pay Item Number Pay Item Description Unit of Measure E580332 21 E580332 22 E580332 23 E580332 24 E580332 25 E580332 97 E580332 98 E580332 99 E580333 1 E580333 2 E580333 3 E580334 1 E580334 2 E580334 3 E580335 1 E580336 E580336 1 E580336 2 E580336 4 E580336 5 E580336 6 E580336 12 E580336 12 E580336 13 E580336 14 E580337 2 E580337 3 E580337 4 E580337 6 E580337 8 E580337 11 E581 2 TREE REMOVAL (4" TO 12") TREE REMOVAL (13" TO 24") TREE REMOVAL (25" TO 36") TREE REMOVAL (37" TO 48") TREE REMOVAL (> 48") TREE TRIMMING TREE AND BRUSH REMOVAL TREE AND BRUSH REMOVAL STUMP REMOVAL (4" TO 24") STUMP REMOVAL (25" TO 48") STUMP REMOVAL (> 48") STUMP GRINDING (4" TO 24") STUMP GRINDING (25" TO 48") STUMP GRINDING (> 48") PESTICIDE (INSECTICIDE) PRUNING AND TRIMMING (LESS THAN 4") PRUNING AND TRIMMING (4" TO 24") PRUNING AND TRIMMING (> 24") PRUNING AND TRIMMING (TREES AND SHRUBS) PRUNING AND TRIMMING (TREES AND SHRUBS) CROWN REDUCTION (4" TO 24") POWER SHEARING (0-15' WIDTH)(0-20' HEIGHT) POWER SHEARING >0' TO 15' WIDTH AND 20' HEIGHT POWER SHEARING >0' TO 15' WIDTH GREATER THAN 20' HEIGHT PRUNING AND TRIMMING (PALMS) HERBICIDE (STRIP APPLICATION) HERBICIDE (SPOT APPLICATION < 100 SF) HERBICIDE (STRIP APPLICATION)(AQUATIC) HERBICIDE (HAND APPLICATION) HERBICIDE (MOWER APPLICATION) HERBICIDE (MANUAL APPLICATION) GROUND COVER (10" TO 18" HEIGHT OR SPREAD) EA EA EA EA EA EA PM AC EA EA EA EA EA EA GA EA EA EA PM SF EA LF LF LF EA AC SF AC AC AC GA PL Total Quantity Total Cost Average Unit Cost 12,287.000 7,248.000 603.000 193.000 131.000 1,350.000 1.000 325.935 246.000 69.000 56.000 8,651.000 571.000 31.000 250.000 4,280.000 19,558.000 5,976.000 696.803 1,020,794.500 1.000 176,904.000 342,163.660 608,600.110 9,379.000 7,500.284 12,479,597.080 2,377.609 780.504 19,452.514 31,087.686 130.000 $885,094.22 $942,089.36 $150,520.32 $73,345.62 $117,120.00 $68,122.00 $11,500.00 $470,661.93 $11,920.00 $3,310.00 $6,850.00 $113,227.34 $15,229.03 $2,225.00 $2,000.00 $98,969.45 $734,816.52 $392,804.65 $550,628.54 $357,020.85 $60.00 $58,961.03 $91,756.92 $122,911.96 $257,157.70 $399,993.82 $419,020.90 $141,651.39 $34,483.23 $731,256.07 $113,190.23 $832.00 $72.04 $129.98 $249.62 $380.03 $894.05 $50.46 $11,500.00 $1,444.04 $48.46 $47.97 $122.32 $13.09 $26.67 $71.77 $8.00 $23.12 $37.57 $65.73 $790.22 $0.35 $60.00 $0.33 $0.27 $0.20 $27.42 $53.33 $0.03 $59.58 $44.18 $37.59 $3.64 $6.40 Page 26 Florida Department of Transportation Maintenance Contract Cost Summary By Pay Item Number (SiteManager Data Only) 01/01/2012 - 12/31/2012 Statewide 2/12/2012 Pay Item Number Pay Item Description Unit of Measure E582 2 E582 3 E583 3 E583 4 E583 5 E584 4 E700 40 3 E700 41 5 E700 46 31 E700 46 32 E700 46 33 E700 46110 E700 46120 E700 46210 E700 46320 E700 481E1 E700 481E2 E700 481E3 E700 482E1 E700 482E2 E700 483E1 E700 483E2 E700 483E3 E700 48400 E700 485E1 E700 485E2 E700 485E3 E700 485E5 E700 486E1 E700 486E2 E700 486E3 E700 487E1 SHRUBS ( 10" TO 18" HEIGHT OR SPREAD) SHRUBS (19" TO 7' HEIGHT OR SPREAD) TREE (19" TO 7' HEIGHT OR SPREAD) TREE (8' TO 20' HEIGHT OR CLEAR TRUNK) TREE (21' OR MORE HEIGHT OR CLEAR TRUNK) PALM SINGLE TRUNK (8' TO 20' HEIGHT OR CLEAR TRUNK) SIGN SINGLE POST (PER SQUARE FEET) SIGN MULTI POST (PER SQUARE FEET) REPAIR EXISTING SIGN (SINGLE POST) REPAIR EXISTING SIGN (MULTI POST) REPAIR EXISTING SIGN (OVHD TRUSS) SIGN REMOVE EXIST (SINGLE POST) SIGN REMOVE EXIST (MULTI POST) SIGN RELOCATE EXIST(SINGLE POST) SIGN REPAIR EXIST (MULTI POST) SIGN PANELS (F&I)(SINGLE POST) SIGN PANELS (F&I) (MULTI POST) SIGN PANELS (F&I) (OVERHEAD) SIGN PANELS (INSTALL) (SINGLE POST) SIGN PANELS (INSTALL) (MULTI POST) SIGN PANELS(OVERLAY) (SINGLE POST) SIGN PANELS(OVERLAY) (MULTI POST) SIGN PANELS(OVERLAY) (OVERHEAD) SIGN PANELS(OVERLAY) (MEASURE EXISTING) SIGN PANELS(REPLACE) (SINGLE POST) SIGN PANELS(REPLACE) (MULTI POST) SIGN PANELS(REPLACE) (OVERHEAD) SIGN PANELS(REPLACE) (BRIDGE MOUNT) SIGN PANELS (REMOVE) (SINGLE POST) SIGN PANELS (REMOVE) (MULTI POST) SIGN PANELS (REMOVE) (OVER HEAD) SIGN PANELS (WASH) (SINGLE POST) PL PL PL PL PL PL SF SF AS AS AS SF SF SF SF SF SF SF SF SF SF SF SF EA SF SF SF SF SF SF SF SF Total Quantity Total Cost Average Unit Cost 8,573.330 2,500.000 305.000 424.000 54.000 87.000 2,923.281 2,222.030 329.000 89.000 38.000 823.153 2,276.978 7.000 80.000 1,063.342 1,341.728 1,354.500 726.160 738.149 18.000 984.230 1,591.070 11.000 1,102.331 708.500 5,286.750 928.930 394.243 1,090.649 325.750 16,977.000 $83,858.30 $17,250.00 $20,874.00 $61,604.00 $17,952.30 $14,165.00 $95,704.78 $224,562.65 $18,515.00 $16,370.00 $17,750.00 $1,464.45 $31,093.38 $42.01 $12.00 $17,284.05 $24,067.93 $68,300.10 $2,214.39 $6,167.66 $198.00 $18,558.36 $32,204.00 $2,423.08 $19,023.49 $12,685.50 $105,735.00 $18,578.60 $985.63 $10,209.89 $4,154.25 $25,465.50 $9.78 $6.90 $68.44 $145.29 $332.45 $162.82 $32.74 $101.06 $56.28 $183.93 $467.11 $1.78 $13.66 $6.00 $0.15 $16.25 $17.94 $50.42 $3.05 $8.36 $11.00 $18.86 $20.24 $220.28 $17.26 $17.90 $20.00 $20.00 $2.50 $9.36 $12.75 $1.50 Page 27 Florida Department of Transportation Maintenance Contract Cost Summary By Pay Item Number (SiteManager Data Only) 01/01/2012 - 12/31/2012 Statewide 2/12/2012 Pay Item Number Pay Item Description Unit of Measure E700 487E2 E700 94 1 E700 94 2 E700 96 1 E700 96 2 E700 98 E700 99 E706 1 32 E706 1 42 E710 11121 E710 11141 E710 11221 E710 11241 E711 3 1 E711 4 1 E711 11121 E711 11141 E711 11221 E711 11241 E713102121 E713102160 E713102221 E714 1 99 E715 1900 E715 14 71 E715 15110 E715 15120 E715 15160 E715 15180 E715 16 2 E715 17 1 E715 17 2 SIGN PANELS (WASH) (MULTI POST) BREAKAWAY SIGN SUPPORT FOUNDATION (F&I) BREAKAWAY SIGN SUPPORT FOUNDATION (REMOVE) SIGN SUPPORT REPAIRS (ALUMINUM) SIGN SUPPORT REPAIRS (STEEL) SIGN INSPECTION (SINGLE/MULTI POST GROUND MOUNT) SIGN MAINTENANCE (PERFORMANCE) REFLECTIVE PAVEMENT MARKER (REMOVE)(CLASS B) REFLECTIVE PAVEMENT MARKER(REM AND REPL)(CLASS B) PAINTED PAVEMENT MARKINGS, STANDARD, WHITE, SOLID, 6" PAINTED PAVEMENT MARKINGS, STANDARD, WHITE, SKIP, 6" PAINTED PAVEMENT MARKINGS, STANDARD, YELLOW, SOLID, 6" PAINTED PAVEMENT MARKINGS, STANDARD, YELLOW, SKIP, 6" PAVEMENT MESSAGES (THERMOPLASTIC) DIRECTIONAL ARROWS THERMOPLASTIC THERMOPLASTIC, STANDARD, WHITE, SOLID, 6" THERMOPLASTIC, STANDARD, WHITE, SKIP, 6" THERMOPLASTIC, STANDARD, YELLOW, SOLID, 6" THERMOPLASTIC, STANDARD, YELLOW, SKIP, 6" PREFORMED TAPE, HIGH PERFORMANCE, WHITE, SOLID, 6" PREFORMED TAPE, HIGH PERFORMANCE, WHITE, MESSAGES PREFORMED TAPE, HIGH PERFORMANCE, YELLOW, SOLID, 6" MOTORIST AID CALL BOX MAINTENANCE CONDUCTOR (LOCATE & MARK LOCATION ONLY) PULL BOX (REPAIR)(ROADSIDE MOULDED) HIGH MAST PARTS (F&I)(LOWERING CABLE) HIGH MAST PARTS (F&I)(POWER CABLE) HIGH MAST PARTS (F&I)(COMPLETE LOWERING ASSEMBLY) HIGH MAST PARTS (F&I) (BALLAST ASSEMBLY) BALLAST ASSEMBLY (F&I) LAMP (HPS) LAMP (MERCURY VAPOR) SF EA EA LB LB EA LS EA EA LF LF LF LF SF SF LF LF LF LF LF EA LF LS LF EA EA EA EA EA AS EA EA Total Quantity Total Cost Average Unit Cost 928.000 78.000 25.000 3,533.901 7,498.500 964.000 2.586 16,038.000 923,968.000 670,732.000 37,616.000 411,201.000 82,478.000 3,043.500 15,672.000 149,207.067 15,946.000 103,956.000 3,067.000 3,786.000 124.000 3,786.000 1.000 9,209.000 326.000 5.000 2.000 1.000 89.000 326.000 1,562.000 76.000 $1,856.00 $29,100.00 $3,430.00 $21,564.02 $71,608.62 $2,250.00 $146,822.40 $226.50 $1,882,782.21 $101,794.93 $6,473.90 $64,273.01 $12,378.30 $8,601.90 $119,830.95 $162,120.60 $15,343.62 $124,012.30 $2,814.53 $18,441.30 $24,800.00 $18,441.30 $49,778.80 $9,062.00 $7,235.00 $2,545.00 $1,050.00 $600.00 $8,370.00 $26,554.20 $99,449.50 $8,080.00 $2.00 $373.08 $137.20 $6.10 $9.55 $2.33 $56,775.87 $0.01 $2.04 $0.15 $0.17 $0.16 $0.15 $2.83 $7.65 $1.09 $0.96 $1.19 $0.92 $4.87 $200.00 $4.87 $49,778.80 $0.98 $22.19 $509.00 $525.00 $600.00 $94.04 $81.45 $63.67 $106.32 Page 28 Florida Department of Transportation Maintenance Contract Cost Summary By Pay Item Number (SiteManager Data Only) 01/01/2012 - 12/31/2012 Statewide 2/12/2012 Pay Item Number Pay Item Description Unit of Measure E715 17 3 E715 17 7 E715 18101 E715 18102 E715 18104 E715 18105 E715 18106 E715 18107 E715 18108 E715 18112 E715 18113 E715 19 99 E715 22 1 E715 23 1 E715 24 1 E715 24 4 E715 25 1 E715 25 2 E715 27 E715 31 7 E715 32 1 E715 32 2 E715 32 4 E715 32 5 E715 32 6 E715 32 7 E715 32 8 E715 32 9 E715 32 10 E715 32 11 E715 32 12 E715 32 13 LAMP (METAL HALIDE) LAMP (HPS HIGH MAST) LOAD CENTER PART (F&I) (SGL POLE BREAKER) LOAD CENTER PART (F&I) (DBL POLE BREAKER) LOAD CENTER PART (F&I)(BREAKER PANEL & ENCLOSURE) LOAD CENTER PART (F&I) (CONTACTOR) LOAD CENTER PART (F&I)(PHOTOCELL CONTR TRANSFORM) LOAD CENTER PART (F&I) (PHOTOCELL) LOAD CENTER PART (F&I) (PHOTOCELL SOCKET) LOAD CENTER PART (F&I) (CIRCUIT FUSE) LOAD CENTER PART (F&I) (MAIN FUSE) LIGHTING - CABLE REMOVAL DETERRENT SYSTEM GROUND ROD REFRACTER (F&I) (STANDARD COBRA HEAD) FUSE (F&I) (POLE BASE) DUMMY SLUG (F&I) (POLE BASE) FUSE HOLDER (F&I) (POLE BASE) FUSE HOLDER / DISCONNECT PLUG (F&I) EMERGENCY WORK ROUTINE LIGHTING MAINT (LOAD CENTER) DIAGNOSTIC WORK (SHOULDER SINGLE ARM) DIAGNOSTIC WORK (SHOLDER DOUBLE ARM) DIAGNOSTIC WORK (MED DBL ARM WALL MTD) DIAGNOSTIC WORK (BRIDGE MTD) DIAGNOSTIC WORK (UNDERDECK) DIAGNOSTIC WORK (LOAD CENTER) DIAGNOSTIC WORK(HIGH MAST) (W/LOWERING DEVICE) DIAGNOSTIC WORK(OVERHEAD)(SIGN ASSEMBLY) DIAGNOSTIC WORK (CIRCUIT) DIAGNOSTIC WORK (HIGH MAST, GROUND) DIAGNOSTIC WORK (HIGH MAST, AERIAL) DIAGNOSTIC WORK (TOP MOUNT) EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA EA LO LO LO LO LO LO LO LO LO LO LO LO LO LO Total Quantity Total Cost Average Unit Cost 19.000 257.000 1.000 7.000 4.000 2.000 1.000 18.000 4.000 16.000 2.000 108.000 5.000 2.000 1,680.000 53.000 210.000 238.000 140.000 4.000 1,254.000 25.000 73.000 29.000 97.000 197.000 18.000 130.000 318.000 114.000 6.000 657.000 $1,140.00 $25,471.76 $33.27 $2,550.00 $14,108.14 $500.00 $5.00 $1,716.42 $20.00 $826.00 $2.00 $23,220.00 $293.35 $6.00 $76,575.24 $90.02 $1,267.22 $1,384.00 $22,484.60 $4.00 $37,599.93 $1,070.00 $16,300.00 $1,364.80 $5,637.40 $25,329.76 $9,173.70 $5,700.74 $16,330.00 $15,100.00 $1,820.00 $94,980.00 $60.00 $99.11 $33.27 $364.29 $3,527.04 $250.00 $5.00 $95.36 $5.00 $51.63 $1.00 $215.00 $58.67 $3.00 $45.58 $1.70 $6.03 $5.82 $160.60 $1.00 $29.98 $42.80 $223.29 $47.06 $58.12 $128.58 $509.65 $43.85 $51.35 $132.46 $303.33 $144.57 Page 29 Florida Department of Transportation Maintenance Contract Cost Summary By Pay Item Number (SiteManager Data Only) 01/01/2012 - 12/31/2012 Statewide 2/12/2012 Pay Item Number Pay Item Description Unit of Measure E715 35 1 E715 50220 E715 99 E715561100 E735 74 11 E735 74 22 E735 74 23 E735 74 24 E735 74 25 E735 74 26 E737 70 11 E770 51 14 E770 51 15 E770 55 8 E942 2 E999 1 1 E999 1 2 E999 1 4 E999 2 1 E999 2 2 E999 2 3 E999 2 5 E999 2 17 E999 3 1 E999 3 2 E999 30 E999 30 E999 40 MAST ARM (FURNISH & INSTALL)) TRANSFORMER (F&I)(PAD MOUNT) HIGHWAY LIGHTING SYSTEM MAINTENANCE (PERFORMANCE) LIGHT POLE (REP&REINST)(SGL ARM SHLD MNT ALUM) TOLL PLAZA (CLEAN) (DEBRIS, LITTER, SAND/GRAVEL) TOLL PLAZA (PRESSURE CLEAN) (TRAFFIC LANE) TOLL PLAZA (PRESSURE CLEAN) (CANOPY) TOLL PLAZA (PRESSURE CLEAN) (TRAF LANE) (REMOVE TAR/ASPHALT) TOLL PLAZA (PRESSURE CLEAN) (BUILDING, SIDEWALK, PAD, PATIO) TOLL PLAZA (PRESSURE CLEAN) (CONCRETE APRON) UTILITY LOCATE (DOT OWNED) (UNDERGROUND) LABOR, PROFFESIONAL (ENGINEERING TECHNICIAN) LABOR, PROFFESIONAL (CONSTRUCTION INSPECTOR) REST AREA SECURITY SERVICES ROADWAY CHARACTERISTICS INVENTORY SERVICES LABOR (REGULAR TIME) SKILLED LABOR (REGULAR TIME) SKILLED LABOR (SPECIAL TIME) TRUCK PICKUP (3/4 TON OR LESS)(INCLUDES OPERATOR) TRUCK FLATBED (2 TON OR LESS)(INCLUDES OPERATOR) TRUCK DUMP BODY (INCLUDES OPERATOR) LOADER FRONT END (INCLUDES OPERATOR) LOADER SKID STEER (INCLUDES OPERATOR) HYDRAULIC PUMP (4") HYDRAULIC PUMP (6") TRAFFIC OPERATIONS (NO BID ITEM) (WORK ORDER) TRAFFIC OPERATIONS - DO NOT BID UTILITIES - DO NOT BID EA EA LS EA SF SF SF SF SF SF EA HR HR MO HR HR HR HR HR HR HR HR HR HR HR LS LS LS Total Quantity 27.000 1.000 7.000 19.000 366,127.063 2,361,592.000 1,199,264.000 147,308.000 2,947,425.000 1,672,490.000 1,912.000 2,056.000 7,273.000 5.860 2,527.500 47,003.610 8,748.250 182.500 72.000 8.000 887.500 14.000 29.000 156.000 454.000 0.019 0.095 1.144 Total Cost Average Unit Cost $7,600.00 $281.48 $55.53 $55.53 $3,062,599.53 $437,514.22 $8,728.71 $459.41 $13,224.32 $0.04 $135,544.74 $0.06 $54,941.26 $0.05 $10,569.56 $0.07 $168,685.08 $0.06 $50,419.20 $0.03 $70,190.00 $36.71 $130,453.20 $63.45 $358,922.55 $49.35 $1,237,110.46 $211,111.00 $118,792.50 $47.00 $930,314.97 $19.79 $244,554.95 $27.95 $6,197.50 $33.96 $5,400.00 $75.00 $360.00 $45.00 $56,900.74 $64.11 $910.00 $65.00 $3,585.00 $123.62 $3,900.00 $25.00 $10,537.50 $23.21 $5,700.00 $300,000.00 $2,375.00 $25,000.00 $1,213,700.00 $1,060,926.57 $267,727,697.99