...

The installation and interconnection of cryomagnets

by user

on
Category: Documents
10

views

Report

Comments

Transcript

The installation and interconnection of cryomagnets
Status of the LHC Project
L.Evans - C.Wyss
Riunione CSN1 INFN
Napoli, 21 Settembre 2005
AB/BT equipmentGeneral
in PS complex
situation
SPC
13:39  beam at the end of TI 8, some 2.5 km away, at first attempt
• length of newly tested part ~ 2.5 km
beam tests
23./24.10.04
6./7.11.04
• over 400 magnets
MQI
chamber
beam tests
8.9.03
TI 8
LHC
SPS
TI 2
TI 2 upstream part commissioning (w/o
beam) possible as of Q2/2005
TI 8 commissioning / V.Mertens / TCC, 29.10.2004
L.R. Evans – EDMS Document No. 521217
CERN L.Evans & C.Wyss
INFN CSN1 Napoli September 2005
3
2
Beam parameters obtained from the central frequency
measurements, averaged over the data obtained from the
horizontal and vertical planes.
CERN L.Evans & C.Wyss
INFN CSN1 Napoli September 2005
3
Results of TI8 test
CERN L.Evans & C.Wyss
INFN CSN1 Napoli September 2005
4
End of civil engineering works
in Point 5 (1st February 2005)
CERN L.Evans & C.Wyss
INFN CSN1 Napoli September 2005
5
Superconducting cable 1
CERN L.Evans & C.Wyss
INFN CSN1 Napoli September 2005
6
Superconducting cable 2
CERN L.Evans & C.Wyss
INFN CSN1 Napoli September 2005
7
Dipole cold masses
CERN L.Evans & C.Wyss
INFN CSN1 Napoli September 2005
8
230
220
210
200
190
180
170
160
150
140
130
120
110
100
90
80
70
60
50
40
30
20
10
0
02
03
n
o
tr
ea
c
h
ed
7
6
5
4
3
2
1
01
0
Number of cryo-dipoles
Number of quenches to reach 8,33 T
at the first cooldown (560 dipoles)
Num be r of que nche s to r e ach 8.33T
CERN L.Evans & C.Wyss
INFN CSN1 Napoli September 2005
9
LHC Dipoles: integrated field
Cold mass
Firm 1
Firm 2
Firm 3
40
upper limit for single magnet (3 sigma)
10.13
20
10.11
0
10.09
-20
Units
Int transf func (Tm/kA)
10.15
lower limit for single magnet (3 sigma)
10.07
-40
0
100
200
300
400
500
600
Magnet progressive number
CERN L.Evans & C.Wyss
INFN CSN1 Napoli September 2005
700
AT-MAS
10
Dipole field quality: average b3
b3 integral (units)
Cold mass
Firm 1
Firm 2
Firm 3
10
5
upper limit for systematic
0
lower limit for systematic
-5
Cross-section 2
-10
0
100
Cross-section 3
200
300
400
500
Magnet progressive number
CERN L.Evans & C.Wyss
INFN CSN1 Napoli September 2005
600
700
AT-MAS & MTM
11
Arc quadrupole cold masses
CERN L.Evans & C.Wyss
INFN CSN1 Napoli September 2005
12
MSCB sextupole dipole correctors
CERN L.Evans & C.Wyss
INFN CSN1 Napoli September 2005
13
Cryodipole overview
CERN L.Evans & C.Wyss
INFN CSN1 Napoli September 2005
14
SSS overview
CERN L.Evans & C.Wyss
INFN CSN1 Napoli September 2005
15
Magnet Installation
•
Installation is progressing in sectors 8-1 and 4-5. More than 100
superconducting magnets have been installed. The installation rate
must now ramp up to 20 magnets per week (16 dipoles and 4 SSSs) in
the next few weeks.
•
At the end of October, sector 7-8 will be liberated for magnetic
installation. From then on there will be no shortage of slots.
CERN L.Evans & C.Wyss
INFN CSN1 Napoli September 2005
16
First cryodipole lowered on 7 March 2005
CERN L.Evans & C.Wyss
INFN CSN1 Napoli September 2005
17
First SSS lowered on 19 April 2005
CERN L.Evans & C.Wyss
INFN CSN1 Napoli September 2005
18
Transport in the
tunnel with an
optical guided
vehicle
CERN L.Evans & C.Wyss
INFN CSN1 Napoli September 2005
19
Transfer on jacks
CERN L.Evans & C.Wyss
INFN CSN1 Napoli September 2005
20
Preparation of interconnect
CERN L.Evans & C.Wyss
INFN CSN1 Napoli September 2005
21
Interconnection of beam tubes
CERN L.Evans & C.Wyss
INFN CSN1 Napoli September 2005
22
Interconnect in sector 8-1: in progress in subsectors C and F
CERN L.Evans & C.Wyss
INFN CSN1 Napoli September 2005
23
Pre-assembly of first
low-beta triplet
(hall 181)
CERN L.Evans & C.Wyss
INFN CSN1 Napoli September 2005
24
CERN L.Evans & C.Wyss
INFN CSN1 Napoli September 2005
25
UA47: Quench protection & Power converters
CERN L.Evans & C.Wyss
INFN CSN1 Napoli September 2005
26
CERN L.Evans & C.Wyss
INFN CSN1 Napoli September 2005
27
Cryogenics overview
CERN L.Evans & C.Wyss
INFN CSN1 Napoli September 2005
28
2400 W @ 1,8 K in the UX85 cavern
1.8K refrigeration units
1st Pump-down in final LHC configuration
P8 - 7 April 2005
0.50
2500
0.40
Installed mode
2400 W @ 1.8 K
0.35
0.30
2000
1500
0.25
0.20
Suction Pressure
0.15
Set point
0.10
0.05
Pump-down
15 mbar
1.8K Cooling Power
0.00
7:12
1000
Cooling Power [W]
Suction Pressure [B]
0.45
500
0
8:24
9:36
10:48
12:00
Time
CERN L.Evans & C.Wyss
INFN CSN1 Napoli September 2005
29
Repair of QRL
modules
CERN L.Evans & C.Wyss
INFN CSN1 Napoli September 2005
30
Repair of special
QRL elements at
CERN
CERN L.Evans & C.Wyss
INFN CSN1 Napoli September 2005
31
Cryogenic distribution line
CERN L.Evans & C.Wyss
INFN CSN1 Napoli September 2005
32
QRL
CERN L.Evans & C.Wyss
INFN CSN1 Napoli September 2005
33
Reinstallation of QRL in 7-8
•
Sub-sectors A and B (600 m) have been cooled down on Wednesday
14th September.
•
After the cold tests, the inner triplet will be installed, cooled down and
powered whilst the rest of the line is being installed.
CERN L.Evans & C.Wyss
INFN CSN1 Napoli September 2005
34
First cooldown of 600 m cryogenic LHC line sector
13-14 September 2005
LHe
line
Th.screen
line
He in
He out
Pump. line
20 K line
Conclusions
•
•
•
•
•
•
•
Main objectives:
– terminate installation in February 2007
– first collisions in summer 2007
The industrial production of standard components is compatible with
this objective.
The ramping up of QRL activities and magnet installation is critical to
maintain this schedule.
Additional actions have been implemented to ensure proper QRL
production and installation rates.
The installation and interconnection of cryomagnets have started in the
tunnel.
The commissioning of technical systems will take place in two adjacent
sectors in parallel.
Main next actions:
– partial test of sector 7-8 in autumn 2005
– commissioning test of the two first sectors (7-8 and 8-1) in
summer 2006
– find external collaborators to help with commissioning.
=> many thanks to INFN for its support !
CERN L.Evans & C.Wyss
INFN CSN1 Napoli September 2005
36
Fly UP