Comments
Description
Transcript
INFN_ITS-upgrade_2012-11-06 - Indico
ITS upgrade Meeting Gruppi INFN V. Manzari – CERN, 6 Novembre 2012 Upgrades: status On September 27 after the third round of discussions with ALICE, the LHCC has endorsed our Upgrade LoI and ITS CDR. Minutes are not out yet, but there is a statement which we can quote issued by the LHCC chair: “There is an interest amongst the collider experiments (ALICE, ATLAS and CMS) for a continued heavy ion programme that gives access to rare final states. This programme will extend well into the 20ies assuming the current HI running mode of one month per year. The physics programmes of the two general purpose detectors and ALICE are complementary: while the former may focus on selected hard probes ALICE will be optimized for particle identification at low transverse momenta. The experiments are hence sensitive to different ”messenger“ signals and phases of the evolution of the quark gluon plasma. This increase in sensitivity for ALICE entails an upgrade of the rate capability of the TPC, a high resolution ITS, and a major upgrade of the online system and the read-out electronics. The LHCC commends this joint approach to heavy ion physics and endorses the upgrade plans of the ALICE collaboration. The committee is looking forward to the seeing detailed technical solutions presented in the respective TDRs..” Upgrades: next steps RRB 29 Oct -1 Nov o o Extension of the construction MoU General Endorsement of the Upgrade TDRs to be prepared in O(1 year) Will define the construction design o Will contain the specific commitments of the Institutions to the projects o Followed by MoU addendum (or addenda) o R&D Will have to continue vigorously throughout the process, with substantial funding, agreed within each project o Target date for ITS TDR August 2013 for submission to LHCC in September 2013 Running scenario after the upgrades • Pb–Pb • • • • int. luminosity per year 2.85 nb-1 (peak L = 7x1027 cm-2s-1) needed int. luminosity 10 nb-1, statistics 8x1010 events 3.5 month of running +1 month of special run at low field for dileptons • p–Pb • max event rate 200 kHz, flat (L = 1029 cm-2s-1) • needed int. luminosity 50 nb-1, statistics 1011 events • 0.5 month of dedicated p–Pb run • pp • max event rate 200 kHz, flat (L = 3x1030 cm-2s-1) • needed int. luminosity 6 pb-1, statistics 4x1011 events • 2 month of dedicated pp run, assumed in 1 year The list above fulfills the ALICE physics program as presented in the LoI. A run with lower mass nuclei (e.g. Ar) could be considered in addition, if a physics case for it would emerge. Upgrades: a possible running scheme • ALICE plans to run 6 years with upgraded detector, i.e. until 2026 (assuming start in 2019 and 2 years break of LS3) • Possible scenario: • 2019 – Pb–Pb 2.85 nb-1 • 2020 – Pb–Pb 2.85 nb-1 (low magnetic field) • 2021 – pp reference run • 2022 – LS3 • 2023 – LS3 • 2024 – Pb–Pb 2.85 nb-1 • 2025 – ½ Pb–Pb 1.42 nb-1 + ½ p–Pb 50 nb-1 • 2026 – Pb–Pb 2.85 nb-1 • This would not require pp running during high-luminosity runs, only a short time before a heavy-ion run for setting up and commissioning. Organization, Timeline and Cost Participating Institutes (subject to funding) • • • • • • • • • • • Upgrade Timeline 2012–2014 R&D • • 2012 2013 2014 evaluation of technologies & prototyp selection of technologies, eng. Design, TDR final design and validation • 2015-18 Construction and Installation • 2015-16 production, construction and test of detector modules assembly and pre-commissioning installaiton in the cavern • • Contribution of Institutes CERN to be defined within China (Wuhan, SINAP) the next 8 months Czech Republic (Prague) France IN2P3-CNRS (Strasbourg) Italy INFN (Bari, Cagliari, Catania, Frascati, Legnaro, Padova, Roma, Torino, Trieste) Korea (Yonsei University Seoul) Pakistan (Islamabad COMSATS) Russia (St. Petersburg) Already members of ITS project Slovakia (Kosice IEP) New members of ITS project UK STFC (Univ. of Birmingham, Daresbury Lab, RAL) Ukraine (Kharkov, Kiev) 2017 2018 Cost Estimate (Option A and B) (*) R&D 4 MCHF Option A (All pixels) 10 MCHF Option B (pixels + strips) 16 MCHF (*) detailed cost breakdown in Table 6.2 of CDR ITS Upgrade Breakdown of the CORE Cost Estimate Option 1: 7 layers of monolithic pixel detectors, which would provide excellent standalone tracking efficiency and pt resolution, but limited PID capability. Option 2: a combination of 3 innermost layers of hybrid pixel detectors and 4 outermost layers of strip detectors, which would provide better PID capability but worse standalone tracking efficiency and momentum resolution. V. Manzari - INFN Bari CSN III – 18 Settembre 2012 7 ITS Upgrade Timeline V. Manzari - INFN Bari CSN III – 18 Settembre 2012 8 ALICE Upgrade CORE Cost Estimates Overall cost estimate for the major upgrade projects Detector components and production costs Upgrade items and Common Project - ZDC included in “Trigger Detectors”, EMCal and HMPID require minor funds The Offline cost is the investment needed for the offline central services at CERN V. Manzari - INFN Bari CSN III – 18 Settembre 2012 9 ALICE Upgrade Spending Profile Memorandum of Understanding An Addendum for each Project to the ALICE MoU Addendum for the Common Projects including M&O A V. Manzari - INFN Bari CSN III – 18 Settembre 2012 10 Cost Estimate ALICE Upgrade INFN Estimated Contributions Overall cost estimate: ≈ 60 MCHF Italian Contribution: ≈ 10 MCHF V. Manzari - INFN Bari Detector Cost (KCHF) ITS 6000 VHMPID 1000 TOF 600 Muon 600 ZDC 100 CommonFunds 1000 CSN III – 20 Marzo 2012 11 Estimate ContributoCost INFN all’upgrade Partecipazione INFN in ALICE: “Scientist” 107/574 (19%) Costo Totale Upgrade ALICE: 36 - 42 MCHF 30 - 35 M€ Costo Totale Upgrade ITS: 10 - 16 MCHF (+ 4 MCHF per R&D) Contributo INFN per upgrade ITS: 4.7 - 6.7 MCHF (33%) 3.9 - 5.6 M€ Common Projects: 0.9 M€ TOF: 0.6 M€ Muon: 1.8 M€ x 0.2 0.4 M€ Stima finanziamento globale INFN per upgrade ALICE: 5.8 M€ spalmato su 5-6 anni Cost gruppi Estimate INFN Contributi Consultazione in corso con i vari gruppi che hanno espresso interesse a partecipare all’upgrade dell’ITS per definire contributi e responsabilità in base alle risorse disponibili (finanziarie, personale e infrastrutture) Discussione all’IB meeting durante la mini-week in Dicembre Come procediamo? Individuare attività/sotto-progetti di interesse comune Salvaguardare contributi, specificità e visibilità dei vari gruppi Leadership in alcuni sotto-progetti Sviluppi tecnologici Utilizzo delle infrastrutture esistenti Negoziazione delle risorse locali con i rispettivi Direttori di Sez/Lab: tecnici, tecnologi e servizi. List of activities Activities Development, design and production of front-end electronics Front-end wafer probing Sensor development and production (in case of hybrid pixels and/or μstrips) Wafer thinning &dicing Detector interconnect technologies (bump-, tab-, wire-bonding, BGA, other) Development and fabrication of test systems Characterization and mass production tests of individual detector components Power and Signal on-detector buses On-detector readout and interface electronics Radiation tests Design and production of the Stave mechanical support People Activities Design and production of the Integration and Installation mechanics On-detector cooling Cooling plant Stave assembly Barrel assembly and integration Power Supply System Detector Control and Interlock System Construction Database Off-detector readout electronics Power and Signal Connections Beam tests (hardware, software, analysis) Online software (monitoring, DAQ, HLT) Offline (MC, calibration and reconstruction) Physics performance studies People Backup V. Manzari - INFN Bari CSN III – 20 Marzo 2012 16 Link a Presentazioni Precedenti Riunione CSN3 28-29/03/2011 • R&D activities for the ALICE inner tracker upgrade http://agenda.infn.it/conferenceDisplay.py?confId=3202 Riunione CSN3 13-14/06/2011 • ALICE Inner Tracking System Upgrade http://agenda.infn.it/conferenceDisplay.py?confId=3203 Riunione CSN3 19-20/03/2012 • ALICE Upgrade http://agenda.infn.it/conferenceDisplay.py?confId=4296 Referee meeting 9/05/2012: • Novità ITS e R&D status http://agenda.infn.it/conferenceDisplay.py?confId=5002 Referee meeting 20/07/2012: • ITS upgrade: consuntivo e richieste http://agenda.infn.it/conferenceDisplay.py?confId=5291 V. Manzari - INFN Bari CSN III – 18 Settembre 2012 17 Link a Documenti su Upgrade Web pages: • Inner Tracking System http://aliceinfo.cern.ch/ITS/ • Inner Tracking System Upgrade http://aliceinfo.cern.ch/ITSUpgrade/ Conceptual Design Report for the Upgrade of the ALICE ITS – Version: CDR-0, CERN-LHCC-2012-05 / LHCC-G-159; March 6, 2012 https://aliceinfo.cern.ch/ITSUpgrade/sites/aliceinfo.cern.ch.ITSUpgrade/files/d ocuments/AliceITSupgrade-CDR-0_1.pdf Progress report on the Conceptual Design Report for the Upgrade of the ALICE ITS; June 18, 2012 https://aliceinfo.cern.ch/ITSUpgrade/sites/aliceinfo.cern.ch.ITSUpgrade/files/ documents/progress_report.pdf V. Manzari - INFN Bari CSN III – 18 Settembre 2012 18 Link a Documenti su Upgrade Upgrade of the ALICE Experiment – Letter of Intent; September 7, 2012 CERN-LHCC-2012-012 / LHCC-I-022 https://cdsweb.cer.ch/record/1475243/files/LHCC-I-022.pdf Upgrade of the ALICE Inner Tracking System – Conceptual Design Report; CERN-LHCC-2012-013 / LHCC-P-005; September 11, 2012 http://cdsweb.cern.ch/record/1475244/files/LHCC-P-005.pdf V. Manzari - INFN Bari CSN III – 18 Settembre 2012 19 Link alla Pagina Web ITS Upgrade V. Manzari - INFN Bari CSN III – 18 Settembre 2012 20 P.T. 2013-2015 (draft di piano finanziario, CSN3 30/1/2012) Upgrades : nostre previsioni presentata da Nico in CSN3 Nel 2011-12 per R&D (ITS, VHMPID) : 131, 194.5 K€ (77.5 +117 s.j.) Previsioni costo upgrades (MB e CB meetings del 12/1/2012): ITS : 14 MCHF (CERN, INFN, IN2P3, UK, COMSATS, BMBF, Ukraina, Russia, China, Slovakia, Czech Republic) 2012-2014 R&D e prototipi Contributo INFN old ITS 49.1% 2014-2016 Costruzione 2016-2017 Integrazione e commissioning in laboratorio 2017-2018 Installazione e commissioning VHMPID : 3 (- 4) MCHF (USA, INFN, India, Mexico, Korea, Brazil, Hungary) 2011-2012 R&D e prototipi 2013-2016 Costruzione e commissioning in lab./testbeam 2017-2018 Installazione e commissioning Contributo INFN old HMPID 57.4% Possibile contributo INFN (circa 16.7 %) : 500 KCHF tra 2013 e 2017 (100 KCHF nel 2013, 150 nel 2014, 150 nel 2015) Nuova strategia di upgrade del Central Barrel (MB e CB meetings del 12/1/2012): Stime approssimative dei costi per rivelatori con contributo INFN: TOF : 600 KCHF (100% INFN) → (72 schede DRM) 500 kEuro Muon Trigger : 604 KCHF (IN2P3, INFN) → 160 (rivel.) + 30 (sistema gas) = 190 kEuro Muon Tracking : 967 KCHF (IN2P3, INFN, India?, Russia?) → 200 – 250 kCHF ZDC 70 kEuro (100% INFN) Contributo INFN old MUON 9.2% …… 1 Marzo 2012 21