Comments
Description
Transcript
Document 1564649
DEPARTMENT OF ENVIRONMENTAL QUALITY City of Clio, Collection System Improvement Project State Revolving Fund/Strategic Water Quality Initiatives Fund Grant Environmental Assessment December 2015 I. II. PROJECT IDENTIFICATION Applicant Name: City of Clio Authorized Representative: Mr. Eric Wiederhold, City Administrator Applicant’s Address: 505 West Vienna Street Clio, Michigan 48420 Project Number: 9185-01 PROJECT SUMMARY The city of Clio obtained a State Revolving Fund/Strategic Water Quality Initiatives Fund (S2) grant for $153,283 in January 2012 to pay for planning costs for sewer system improvements in response to basement backups during storm events. With the S2 funding, the city of Clio conducted a sewer investigation, and prepared and submitted a State Revolving Fund (SRF) project plan. The submittal of an SRF project plan is a requirement of obtaining the S2 grant and is the basis for the information in this environmental assessment. It was known prior to the sewer investigation that the sewer system was at least 50 years old and had excessive infiltration and inflow (I/I), or clear water, during storm events. Infiltration is groundwater that enters the collection system from the soil through cracks, defects, and/or breaks in sewer pipes or manholes. Inflow is water that enters the system more directly through connected foundation/footing drains. Therefore, the purpose of the sewer study was to more precisely and accurately quantify the volumes and locations of the excess clear water. This was accomplished by isolating and examining 12 sections of the sewer system by the placement of meters. It was determined that 77 percent of the wastewater flow is due to I/I and that four of the districts, Districts 3, 6B, 7, and 10B, are responsible for 70 percent of the overall I/I flow (see Figure 1 for a map of the district locations). Clio is proposing to reduce the number of basement backups for storm events up to the 25-year, 24-hour design storm event with a sewer upgrade project. The proposed project consists of replacing approximately 1,200 feet of structurally deficient sewer in District 3 and 6B, replacing approximately 2,900 feet of undersized sewer in District 3, 7, and 10B, and installing a new 200-foot-long sewer to connect to the Genesee County Interceptor in District 6B (see Figure 2 for project locations). Construction is targeted to occur from May 2016 to September 2016. The project cost is estimated to be approximately $1,016,409 and is anticipated to be funded by a combined grant and loan from the United States Department of Agriculture’s Rural Development (USDA-RD) program. For a 20-year loan through the SRF Program at 2.5 percent interest, the impact to the monthly user charge would be expected to increase approximately $42 per year per residential equivalency unit (REU), or $3.50 per month; however, rates resulting from the USDA-RD loan/grant will differ. 1 II. PROJECT BACKGROUND A. Existing System Description The Clio collection system serves residents and businesses located within the city limits, which has an area of 1.1 square miles. The 2015 population is estimated to be 2,650, and there are 983 residential and commercial customers in the city. The collection system consists of 11.5 miles of gravity sewer, ranging in diameter from 8 inches to 18 inches, and one lift station, constructed in 1974. The collection system empties into an interceptor owned and operated by Genesee County Water and Wastewater Services (GCWWS). The GCWWS Interceptor is located on the east side of the city near Pine Creek. The city discharged 384.24 million gallons of wastewater into the GCWWS Interceptor in 2010. Recent flows have been similar. The city does not have a restricted limit with GCWWS and is charged $8.12 per 1,000 gallons of wastewater discharged into the GCWWS Interceptor. The collection system is a separated system that operates by gravity. The oldest sewers are approximately 50 years old or older. The collection system was evaluated in a February 2013 report, the “Summary Report Inflow and Infiltration Analysis and Sewer System Evaluation Survey.” The Sewer System Evaluation Survey (SSES) report also identified areas in the collection system where the existing pipes had insufficient capacities. B. Need for the Project The collection system is known to have excessive I/I. For example, in 2010, metered flows entering the GCWWS averaged 637 gallons per capita day (gpcd) for flows during high groundwater (March, April, May, September, October, and November), which far exceeds the state standard of 275 gpcd. The project need is to replace pipes that require immediate attention due to concerns of the structural integrity of the pipes and to reduce or eliminate basement backups. The pipes that need immediate replacement were determined to be structurally deficient by video inspection and are located on Bluff Street, M-57, and in a commercial area bounded by Pine Run Creek, M-57, East Young Street, and Railway Street. After it was determined that Districts 3, 6B, 7, and 10B contribute more than 70 percent of the I/I, further testing was focused on those four districts to determine why and how the I/I was entering the sewers. The most common factor for I/I was found to be from many small sources including sewer joints, service lead taps, small cracks, and a high water table. Based on the video inspection, it was found that approximately 11 percent of the sewer system in the four districts was in poor structural condition and another 49 percent was in need of maintenance. Smoke testing showed that there were negligible storm sewer cross-connections to the sanitary sewer system, which can often be a common source of inflow. The source of I/I was determined to be different in District 7 because many of the sewer pipes in this district and two districts that flow into District 7 were replaced recently. Therefore, the excessive I/I is likely the result of illicit footing drain connections from residences. Improper manhole covers and manhole rings are often a source of I/I in wet systems; however, in this case, manholes were not shown to be a significant source of I/I. In addition to sewers with immediate structural integrity needs and sewers with excessive I/I, there is a need to upgrade sewers that are undersized. Undersized sewers, especially when there is excessive I/I, can result in surcharging and basement backups. There were 36 recorded basement backups from 2003 to 2013, 35 of which occurred due to an event equal or less than a 25-year, 24-hour storm event. Simulation testing was performed using 2 Environmental Protection Program software and showed that 11 sections of pipe were surcharging under the design storm event. These 11 sections totaled 6,180 feet of sanitary sewer. C. Alternatives Considered Taking no action and examining a regional alternative are a required component of an SRF project plan. For this project, taking no action is not feasible because the problems will only get worse with the addition of time, resulting in more pollution events. Clio already belongs to the closest regional system, so regionalization is not a logical alternative. Even if a second regional system existed nearby, the city’s operational problems are due to the condition of the city’s sewer pipes, which a regionalization alternative would not address; therefore, regionalization is not a feasible alternative for addressing the project need. The alternatives for addressing the project need consist of first determining whether constructing additional capacity is more cost-effective than removing the excessive I/I. Because GCWWS does not have a discharge limit and because the operational problems are not originating from the connection to the county interceptor, additional capacity at the end point of the city collection system is not a factor. However, an inline retention basin is plausible and is, therefore, a component of the transportation and treatment calculation that was examined. A retention basin is a wastewater facility constructed to retain and equalize the flows between the extremes of the average daily flow. It holds the first flush of peak wet weather flows until the downstream portion of the system has the capacity to receive the basin’s contents. The capital cost of constructing a basin for each of the four districts is approximately $10,000,000. This becomes prohibitively expensive as an alternative and needs no further analysis. Because retention is not an alternative, the feasible alternatives are focused on how to cost-effectively remove the I/I and reduce capacity issues in ways other than a retention basin. Three principal alternatives were examined for removing the I/I from District 3, 6B, 7, and 10B with the elements of repairing the structurally deficient pipe, upsizing some pipes to increase capacity, and lining sections of pipe to eliminate I/I, common to all three options. Additional considerations are described below: • Footing drain disconnections, gutter, and downspout installation, service lateral repairs, and disconnection of footing drains from the service lateral. - Based on a study of 18 homes, it was assumed that 10 percent of the homes have footing drain connections. Gutters and downspouts would be added to buildings without them and those with roof drains connected to the sewer system would be redirected to the storm drains. Service laterals would be rehabilitated or replaced if needed. Missing or damaged cleanout caps would be repaired. • A new interceptor connection to GCWWS - An additional connection to the county interceptor would be placed at the east end of Johnson Street to reduce flows by redirecting some flows into the county interceptor before they cause capacity issues. Upon further review of the sewer televising data, it was determined that the cost to re-line sewer sections with excessive I/I would be greater than the cost to transport flow to the county. Therefore, the sewer lining work was removed from the scope of the project. 3 IV. DESCRIPTION OF THE PROPOSED PROJECT It is anticipated that addressing all of the needs in the project plan will cost approximately $1,016,409. The proposed project consists of replacing approximately 1,200 feet of structurally deficient sewer in District 3 and 6B, replacing approximately 2,900 feet of undersized sewer in District 3, 7, and 10B, and installing a new 200-foot-long sewer to connect to the GCWWS interceptor in District 6B. (See Figure 2). The system improvements are designed to ensure that this population’s wastewater reaches the GCWWS interceptor at all times and without surcharging and basement backups for all conditions up to and including a 25-year, 24-hour storm event. Once I/I has been removed from District 3, 6B, 7, and 10B, and the system is monitored, the city will be able to determine if any additional problems need to be addressed. Construction is targeted to occur from May 2016 to September 2016, contingent on receiving obligation through the USDA. V. IMPACTS OF PROPOSED LOCAL RELIEF PROJECT A. Direct Impacts Construction will primarily take place in existing sewers and will involve open trench construction. The proposed construction will cause temporary disruption to neighborhood residents through dust and noise, and potential alternate routing of traffic through neighborhoods. Underground utilities may be interrupted for short periods of time. The area is predominately residential, and there are no unique natural settings, sensitive ecosystems, or endangered species. A State Historic Preservation Officer has reviewed the proposed project for impacts on historical and archeological resources. It has been determined that there will be no impact on historical or archeological resources from the proposed project. The Native-American Tribal Historic Preservation Office contact for Genesee County was given the opportunity to comment on the project plan and will receive a copy of this document. The construction area of influence is mostly confined to residential streets where no suitable wildlife habitat is present for state and federal endangered, threatened, or special concern species. As such, it was determined that the project will have “no effect” on state and federally listed species. Examination of the Floodplain Insurance Rate Map indicated that the proposed new county interceptor connection is located in the 100-year floodplain of Pine Run Creek. However, proposed construction is at present grade levels and will not impact existing trees; therefore, it is not considered to have a significant impact. A Michigan Department of Environmental Quality (DEQ)/United States Army Corp of Engineers “Joint Permit Application” will be filed for all work proposed within the Pine Creek floodplain. This permit package covers permit requirements pursuant to state and federal rules and regulations for construction activities in areas referred to as the land/water interface. There is one location where Pine Creek will be crossed: between the west end of Jefferson and the county interceptor. This work will be completed by jacking and boring under the stream bed. This technique involves digging a bore pit and receiving pit at pre-determined depths. A boring machine placed in the initial bore pit pushes an auger and the pipe, generally called a casing, through the ground simultaneously while the machine turns a cutting head through the ground. The auger carries the debris back to the initial pit for 4 removal. This technique is used to minimize surface settling or heaving. The equipment can be loud and cause vibrations; however, this is standard for this method of construction. It was anticipated that a second crossing would be necessary at the Johnson Street interceptor connection; however, additional survey work in the area found the sewer interceptor to be on the west side of the creek, and no crossing would be required. Mitigation of short-term construction impacts to the area residents will entail standard construction procedures for traffic control and rerouting, safety issues, dust control, cleanup of area, and complete restoration of lawns, curbs, and streets. Soil erosion and sedimentation controls, and restoration requirements will be included in the contract specifications, which will ensure compliance. B. Indirect Impacts Sanitary sewers are available throughout the city, and capacity is not expected to increase through sewer expansion. The population within the project area is not anticipated to increase significantly over the 20-year planning period. The proposed sanitary improvements are expected to accommodate any anticipated increase. As a result of this proposed project, it is expected that the removal of excess I/I will benefit the GCWWS treatment process, thereby improving the quality of the regions’ water resources as a long-term, indirect benefit. C. Funding Information In December 2010, the DEQ passed legislation establishing the S2 grant program with the intention of spurring municipalities to increase wastewater infrastructure construction. In response to the creation of the S2 grant program, the city of Clio applied for an S2 grant, No. 9185-01, in the amount of $153,283 for the purpose of studying its sewer collection system in order to eliminate basement backups in residential basements. The project cost is estimated to be approximately $1,016,409, funded by a loan/grant from the USDA-RD. VI. PUBLIC PARTICIPATION A public hearing on the 2013 Project Plan was held on March 18, 2013, at the city of Clio’s office. A presentation outlining the alternatives and detailing the selected alternative was presented at the hearing. On April 15, 2013, after the project plan presentation and question-and-answer period was completed, the Clio City Commission passed a resolution adopting the recommended alternative and authorizing the project to proceed. No written comments were received from the public during the 30-day comment period. Comments and questions were received from the city commission and two citizens. A second public hearing was held on November 4, 2013, also at the city of Clio’s office, as the first hearing had not been advertised for a full 30 days. Again, after the project plan presentation and question-and-answer period was completed, the Clio City Commission passed a resolution adopting the recommended alternative and authorizing the project to proceed. VII. REASONS FOR A FINDING OF NO SIGNIFICANT IMPACT The project detailed in this environmental assessment involves the reduction of I/I by the replacement of sewers that lack structural integrity or are under-sized and the addition of another connection to the county interceptor. The short-term impacts of this construction to area residents will involve inconveniences such as noise, dust, erosion, and traffic congestion. 5 Mitigative measures for these short-term impacts include adequately marked construction areas, appropriate traffic control and rerouting through neighborhood areas, and restoration of disturbed areas, such as lawns, sidewalks, and road pavements. Any unexpected disruption of utility services will be restored in a timely manner. Adherence to contract specifications for mitigative measures and sound construction practices will minimize the construction impacts, and communication with residents directly impacted by the construction will be maintained. It is not expected that the proposed construction will impact any environmentally sensitive areas, wildlife habitat, wetlands, or cultural resources. It is not anticipated that there will be any long-term adverse impacts from the proposed construction project. The long-term benefits of removing clear water from the sewer system, and providing sufficient capacity in the sewer system to eliminate the potential for basement flooding and system bypasses to the area waterways during storm events up to the 25-year, 24-hour intensity level, can be accomplished with non-significant and temporary disruptions. Any questions or concerns about this Environmental Assessment can be directed to: Ms. Sonya T. Butler, Chief Revolving Loan Section Office of Drinking Water and Municipal Assistance Michigan Department of Environmental Quality P.O. Box 30241 Lansing, Michigan 48909-7741 Telephone: 517-284-5433 E-mail: [email protected] 6