Stakeholder Comment Matrix AESO AUTHORITATIVE DOCUMENT PROCESS Stakeholder Consultation Draft
Stakeholder Comment Matrix
AESO AUTHORITATIVE DOCUMENT PROCESS
Stakeholder Consultation Draft
2014-10-07
Consultation on Proposed Amendments to Existing Section 103.4 of the ISO Rules, Power Pool Financial Settlement (“Section 103.4”)
Date of Request for Comment [yyyy/mm/dd]:
Period of Consultation [yyyy/mm/dd]:
Comments From:
Capital Power
Date [yyyy/mm/dd]:
2014/10/21
2014/10/21
2014/10/07
through
2014/10/21
Contact:
Santi Churphongphun
Phone:
(403) 717-4639
E-mail:
[email protected]
Please refer back to the Consultation Letter under the “Attachments to Consultation Letter” section to view the actual content changes to the proposed amended ISO rules and new definition.
Please place your comments/reasons for position underneath (if any).
1. ISO Rules
a) Amended
The AESO is seeking comments from
stakeholders with regard to the
following matters:
1. Please provide your comments
relating to any technical
deficiencies identified within the
proposed amended Section 103.4.
Stakeholder Comments and/or Alternate Proposal
AESO Replies
th
In the context of the AESO’s Revised TCM Rule Implementation Paper published on July 8 , 2014 and
th
per the AESO’s request for comments relating to technical deficiencies as outlined in its October 7 ,
2014 Consultation Letter, Capital Power submits the comments below regarding the proposed
amendments to ISO Rule Section 103.4—Power Pool Financial Settlement. The fact that Capital Power
makes this submission and does not respond to other proposed changes herein should not be taken as
indicating Capital Power’s agreement with or support of the AESO’s proposed broader implementation
approach. Capital Power reiterates that modifications to several elements of the general transmission
constraint rebalancing mechanism are necessary to ensure an effective long term solution and
encourages the AESO to reconsider Capital Power’s comments submitted on August 1, 2014.
Capital Power submits that proposed subsection 7(1) of ISO Rule Section 103.4 requires clarification
specific to the energy volumes (as defined by terms “A”, “B” and “C”) used in calculating the payment of
Transmission Constraint Rebalancing. In particular, the energy volumes defined by proposed terms
“B” and “C” are unclear. Please provide clarification with respect to these two terms and an example
illustrating how the AESO intends on calculating Transmission Constraint Rebalancing payments.
Issued for Stakeholder Consultation: 2014-10-07